CN218643907U - Handling system suitable for super high-rise building curtain unit plate - Google Patents

Handling system suitable for super high-rise building curtain unit plate Download PDF

Info

Publication number
CN218643907U
CN218643907U CN202222153636.2U CN202222153636U CN218643907U CN 218643907 U CN218643907 U CN 218643907U CN 202222153636 U CN202222153636 U CN 202222153636U CN 218643907 U CN218643907 U CN 218643907U
Authority
CN
China
Prior art keywords
steel
unit plate
curtain wall
frames
wall unit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222153636.2U
Other languages
Chinese (zh)
Inventor
张桂先
王旭辉
李永宝
方建鹏
王志勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhuhai Sanxin Technology Development Co ltd
Shenzhen Sanxin Technology Development Co ltd
Original Assignee
Zhuhai Sanxin Technology Development Co ltd
Shenzhen Sanxin Technology Development Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhuhai Sanxin Technology Development Co ltd, Shenzhen Sanxin Technology Development Co ltd filed Critical Zhuhai Sanxin Technology Development Co ltd
Priority to CN202222153636.2U priority Critical patent/CN218643907U/en
Application granted granted Critical
Publication of CN218643907U publication Critical patent/CN218643907U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Load-Bearing And Curtain Walls (AREA)

Abstract

The utility model belongs to the technical field of building curtain, specifically disclose a handling system suitable for super high-rise building curtain unit plate, include: the steel frames are arranged on the main body structure in a rectangular array mode and comprise fixed frames which are vertically arranged and fixedly connected with the main body structure and connecting frames which are horizontally arranged at the upper ends of the fixed frames; the sliding rail devices are vertically arranged on each column of connecting frames which are longitudinally distributed, and the curtain wall unit plate is arranged between the adjacent sliding rail devices; the curtain wall unit plate is connected with the slide rail device through the steel truss; the construction efficiency of curtain unit plate handling can be promoted.

Description

Handling system suitable for super high-rise building curtain unit plate
Technical Field
The utility model belongs to the technical field of building curtain, concretely relates to handling system suitable for super high-rise building curtain unit plate.
Background
In recent years, with the development of society and the continuous breakthrough of science and technology, various super high-rise buildings and buildings with complex shapes emerge endlessly, unit plates of the curtain wall tend to be in an ultra-large and ultra-heavy design, and great challenge is brought to the construction design of maintaining the curtain wall on the outer vertical surface; and along with the great improvement of the requirements of labor cost and quality safety, higher requirements are provided for the construction efficiency and quality of the external curtain wall of the super high-rise building of each curtain wall construction design enterprise; the system for hoisting and conveying the unit plates of the ultra-large curtain wall is reliable and efficient, and vertical hoisting and installation of the unit plates of the ultra-large curtain wall are achieved, so that the construction efficiency is improved, and the project quality is guaranteed.
SUMMERY OF THE UTILITY MODEL
The utility model aims at providing a handling system suitable for super high-rise building curtain unit plate can promote the efficiency of construction of curtain unit plate handling.
In order to solve the technical problem, the purpose of the utility model is realized through following technical scheme: the utility model provides a handling system suitable for super high-rise building curtain unit plate installs on the major structure of curtain, includes:
the steel frames are arranged on the main body structure in a rectangular array mode and comprise fixed frames which are vertically arranged and fixedly connected with the main body structure and connecting frames which are horizontally arranged at the upper ends of the fixed frames;
the curtain wall unit plates are arranged between the adjacent sliding rail devices;
and the steel truss is arranged on the sliding rail device in a sliding manner, and the curtain wall unit plate is connected with the sliding rail device through the steel truss.
Furthermore, the quantity of mount and link is two, two the link sets up in opposite directions, slide rail device locates two between the link.
Furthermore, a plurality of embedded parts are arranged on the main body structure, and the fixing frame is fixedly connected with the embedded parts through the stiffening parts.
Further, the handling system suitable for super high-rise building curtain unit plate still includes the connecting rod, the connecting rod is vertical to be set up two between the link, the slide rail device is fixed to be set up on the connecting rod.
Furthermore, the slide rail device is formed by combining two C-shaped rails with openings facing outwards.
Further, the C-shaped track is C-shaped steel, the connecting rod is a steel square tube, and the C-shaped track is fixed on the connecting rod in a welding mode.
Furthermore, a sliding device is arranged in the C-shaped track in a sliding mode, and the steel truss is fixedly connected with the sliding device.
Further, the hoisting system suitable for the curtain wall unit plate of the super high-rise building further comprises a back attachment steel frame, the curtain wall unit plate is fixedly arranged on the outer side of the back attachment steel frame, and the back attachment steel frame is fixedly connected with the steel truss.
Furthermore, a connecting steel plate is arranged at the position where the steel truss is connected with the back-attached steel frame, the back-attached steel frame is arranged on the outer side of the connecting steel plate and penetrates through the connecting steel plate and the steel truss through a bolt assembly.
Furthermore, the fixing frame, the connecting frame and the steel truss are steel square pipes.
The utility model discloses following beneficial effect has:
the utility model discloses at first set up a plurality of steelframes on the major structure of curtain with the mode of rectangle array, slide rail device sets up on the steelframe, thereby whole atress performance has been promoted, the steel truss slides and sets up on slide rail device, curtain unit plate is located between the adjacent slide rail device, and curtain unit plate passes through the steel truss and is connected with slide rail device, reciprocate along slide rail device through the steel truss, alright reciprocate along slide rail device with driving curtain unit plate, the vertical handling and the installation work of curtain unit plate have been realized, whole system installation is convenient and reliable and stable, great promotion the efficiency of construction.
Drawings
In order to more clearly illustrate the technical solution of the embodiments of the present invention, the drawings required to be used in the description of the embodiments are briefly introduced below, and it is obvious that the drawings in the description below are some embodiments of the present invention, and it is obvious for those skilled in the art to obtain other drawings without creative efforts.
Fig. 1 is a transverse cross-sectional view of a hoisting system suitable for a curtain wall unit plate of a super high-rise building provided by the embodiment of the utility model;
FIG. 2 is an enlarged view of portion A of FIG. 1;
FIG. 3 is an enlarged view of portion B of FIG. 1;
fig. 4 is a longitudinal section view of the lifting system suitable for the curtain wall unit plate of the super high-rise building provided by the embodiment of the utility model.
The labels in the figures illustrate:
1-main structure, 2-steel frame, 3-slide rail device, 4-steel truss, 10-curtain wall unit plate, 11-structural column, 12-embedded part, 13, back attached steel frame; 21-fixed frame, 22-connecting frame, 23-stiffening member, 24-connecting rod, 31-C type track, 32-sliding device, 41-connecting steel plate and 42-bolt assembly.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are some, not all embodiments of the present invention. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative efforts all belong to the protection scope of the present invention.
It will be understood that the terms "comprises" and/or "comprising," when used in this specification and the appended claims, specify the presence of stated features, integers, steps, operations, elements, and/or components, but do not preclude the presence or addition of one or more other features, integers, steps, operations, elements, components, and/or groups thereof.
It is also to be understood that the terminology used in the description of the invention herein is for the purpose of describing particular embodiments only and is not intended to be limiting of the invention. As used in the specification and the appended claims, the singular forms "a", "an", and "the" are intended to include the plural forms as well, unless the context clearly indicates otherwise.
It should be further understood that the term "and/or" as used in the specification and the appended claims refers to any and all possible combinations of one or more of the associated listed items and includes such combinations.
Examples
Referring to fig. 1-4, a lifting system for curtain wall unit plates 10 according to an embodiment of the present invention is installed on a main structure 1 of a curtain wall, including:
the steel frames 2 are arranged on the main body structure 1 in a rectangular array mode, and each steel frame 2 comprises a fixing frame 21 which is vertically arranged and fixedly connected with the main body structure 1 and a connecting frame 22 which is horizontally arranged at the upper end of the fixing frame 21;
the sliding rail devices 3 are vertically arranged on each row of connecting frames 22 which are longitudinally distributed, and the curtain wall unit plate blocks 10 are arranged between the adjacent sliding rail devices 3;
and the steel truss 4 is arranged on the slide rail device 3 in a sliding manner, and the curtain wall unit plate 10 is connected with the slide rail device 3 through the steel truss 4.
Through the structure, in practical application, adopt the utility model discloses a handling system suitable for super high-rise building curtain unit plate, at first set up a plurality of steelframes 2 on the major structure 1 of curtain with the mode of rectangle array, mount 21 and major structure 1 fixed connection, each row link 22 of longitudinal distribution all is equipped with slide rail device 3, so that each row link 22 of longitudinal distribution is equant apart from the interval setting on the slide rail device 3 that corresponds, also make a plurality of slide rail device 3 equidistance intervals set up on major structure 1 simultaneously, thereby whole atress performance has been promoted, steel truss 4 slides and sets up on slide rail device 3, curtain unit plate 10 is located between the adjacent slide rail device 3, and curtain unit plate 10 passes through steel truss 4 and is connected with slide rail device 3, reciprocate along slide rail device 3 through steel truss 4, alright with driving curtain unit plate 10 and reciprocate along slide rail device 3, the perpendicular handling and the installation work of curtain unit plate 10 have been realized, whole system simple to operate is reliable and stable, construction efficiency has been promoted.
Specifically, the main body structure 1 comprises a plurality of structure columns 11 arranged at equal intervals, embedded parts 12 are arranged on two sides of each layer of the main body structure 1, which are positioned on the structure columns 11, each steel frame 2 comprises two fixing frames 21 and two connecting frames 22, the fixing frames 21 are fixedly connected with the embedded parts 12 through stiffening parts 23, the two connecting frames 22 are arranged oppositely, and the slide rail devices 3 are arranged between the two connecting frames 22; mount 21 passes through stiffener 23 and the built-in fitting 12 fixed connection of structure post 11 both sides, can make the connection between major structure 1 and the steelframe 2 more stable, and slide rail device 3 sets up and can guarantee that link 22 atress is stable between two links 22 to guarantee that slide rail device 3's connection is more stable.
As a preferred embodiment, referring to fig. 2, in this embodiment, the hoisting system suitable for the curtain wall unit plate of the super high-rise building further includes a connecting rod 24, the connecting rod 24 is vertically disposed on each row of steel frames 2 longitudinally distributed and located between two connecting frames 22, the sliding rail device 3 is fixedly disposed on the connecting rod 24, the sliding rail device 3 is fixed on the connecting frame 22 through the connecting rod 24, the stability of the sliding rail device 3 can be increased, and when the steel truss 4 drives the curtain wall unit plate 10 to slide on the sliding rail device 3, the stress performance of the sliding rail device 3 is improved.
Specifically, the slide rail device 3 is formed by combining two C-shaped rails 31 with openings facing outwards, the C-shaped rails 31 are C-shaped steel, the connecting rods 24 are steel square tubes, the C-shaped rails 31 are fixed on the connecting rods 24 in a welding mode, sliding devices 32 are arranged in the C-shaped rails 31 in a sliding mode, and the steel truss 4 is fixedly connected with the sliding devices 32; c shape steel and steel side's pipe all have intensity height, the good and high characteristics of operational reliability of toughness, make the connection between C type track 31 and the connecting rod 24 more stable through the welded mode, slider 32 slides in C type track 31 to stretch out the back through the opening of C type track 31 to outside and steel truss 4 fixed connection, thereby make equal sliding connection steel truss 4 in both sides of a slide rail device 3, the compactness of having guaranteed the structure and the homogeneity of slide rail device 3 atress.
In this embodiment, the hoisting system suitable for the curtain wall unit plate of the super high-rise building further comprises a back attachment steel frame 13, the curtain wall unit plate 10 is fixedly arranged on the outer side of the back attachment steel frame 13, the back attachment steel frame 13 is fixedly connected with the steel truss 4, and the back attachment steel frame 13 is beneficial to connection and fixation of the curtain wall unit plate 10 and provides rigid support for the curtain wall unit plate 10 so as to be conveniently and fixedly connected with the steel truss 4.
Further, in order to increase the rigidity of the position where the steel truss 4 is connected with the back attachment steel frame 13, a connecting steel plate 41 is arranged at the position where the steel truss 4 is connected with the back attachment steel frame 13, the back attachment steel frame 13 is arranged on the outer side of the connecting steel plate 41 and is fixedly connected with the connecting steel plate 41 through a bolt assembly 42, the bolt assembly 42 sequentially penetrates through the back attachment steel frame 13, the connecting steel plate 41 and the steel truss 4 and fixes the three together, and the rigidity of the position where the steel truss 4 is connected with the back attachment steel frame 13 is increased due to the existence of the connecting steel plate 41, so that the connecting structure is more stable.
As a preferable implementation manner, in this embodiment, the fixing frame 21, the connecting frame 22 and the steel truss 4 are all steel square pipes, so that the fixing frame 21, the connecting frame 22 and the steel truss 4 have the advantages of high strength, good toughness and high operational reliability.
The above description is only for the specific embodiments of the present invention, but the scope of the present invention is not limited thereto, and any person skilled in the art can easily think of various equivalent modifications or substitutions within the technical scope of the present invention, and these modifications or substitutions should be covered within the scope of the present invention. Therefore, the protection scope of the present invention shall be subject to the protection scope of the claims.

Claims (10)

1. The utility model provides a handling system suitable for super high-rise building curtain unit plate installs on the major structure of curtain, its characterized in that includes:
the steel frames are arranged on the main body structure in a rectangular array mode and comprise fixed frames which are vertically arranged and fixedly connected with the main body structure and connecting frames which are horizontally arranged at the upper ends of the fixed frames;
the curtain wall unit plates are arranged between the adjacent sliding rail devices;
and the steel truss is arranged on the sliding rail device in a sliding manner, and the curtain wall unit plate is connected with the sliding rail device through the steel truss.
2. The hoisting system suitable for the curtain wall unit plate of the super high-rise building as claimed in claim 1, wherein the number of the fixing frames and the connecting frames is two, the two connecting frames are oppositely arranged, and the sliding rail device is arranged between the two connecting frames.
3. The system as claimed in claim 2, wherein the main structure is provided with a plurality of embedded parts, and the fixing frame is fixedly connected to the embedded parts through the stiffeners.
4. The system of claim 3, further comprising a connecting rod vertically disposed between the two connecting frames, wherein the sliding rail device is fixedly disposed on the connecting rod.
5. The hoisting system suitable for the curtain wall unit plate block of the super high-rise building as claimed in claim 4, wherein the slide rail device is formed by combining two C-shaped rails with the openings facing outwards.
6. The hoisting system suitable for the curtain wall unit plate of the super high-rise building as claimed in claim 5, wherein the C-shaped rail is C-shaped steel, the connecting rod is a steel square tube, and the C-shaped rail is fixed on the connecting rod in a welding manner.
7. The hoisting system suitable for the curtain wall unit plate of the super high-rise building as claimed in claim 6, wherein a sliding device is slidably arranged in the C-shaped rail, and the steel truss is fixedly connected with the sliding device.
8. The system of any one of claims 1 to 7, further comprising a back attachment steel frame, wherein the curtain wall unit panels are fixedly arranged on the outer side of the back attachment steel frame, and the back attachment steel frame is fixedly connected with the steel truss.
9. The hoisting system suitable for the curtain wall unit plate of the super high-rise building as claimed in claim 8, wherein a connecting steel plate is arranged at the connecting position of the steel truss and the back attachment steel frame, and the back attachment steel frame is arranged on the outer side of the connecting steel plate and fixedly connected with the steel truss by penetrating through the connecting steel plate through a bolt assembly.
10. The hoisting system suitable for the curtain wall unit plate of the super high-rise building as claimed in claim 1, wherein the fixing frame, the connecting frame and the steel truss are square steel tubes.
CN202222153636.2U 2022-08-16 2022-08-16 Handling system suitable for super high-rise building curtain unit plate Active CN218643907U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222153636.2U CN218643907U (en) 2022-08-16 2022-08-16 Handling system suitable for super high-rise building curtain unit plate

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222153636.2U CN218643907U (en) 2022-08-16 2022-08-16 Handling system suitable for super high-rise building curtain unit plate

Publications (1)

Publication Number Publication Date
CN218643907U true CN218643907U (en) 2023-03-17

Family

ID=85491859

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222153636.2U Active CN218643907U (en) 2022-08-16 2022-08-16 Handling system suitable for super high-rise building curtain unit plate

Country Status (1)

Country Link
CN (1) CN218643907U (en)

Similar Documents

Publication Publication Date Title
CN107816223B (en) Safe and stable type station canopy station house and installation method thereof
CN115977407B (en) Prestressed large-span truss string slipping construction system and construction method thereof
CN218643907U (en) Handling system suitable for super high-rise building curtain unit plate
CN201024677Y (en) Super high sliding assembly jig
CN215291322U (en) Integrally assembled attached scaffold
CN214738851U (en) Beam column node connecting device
CN109162437B (en) Integral steel platform for multi-cylinder steel plate shear wall and construction method thereof
CN218373365U (en) Folding tie rod arch continuous beam curve beam bottom bracket device
CN215858499U (en) Large-span assembled prestressed purlin-free fish belly roof support system
CN214565293U (en) Modular platform door
CN115637810A (en) Large-space special-shaped honeycomb aluminum plate ceiling structure and construction method
CN212866772U (en) Large-span scaffold with moving platform
CN211735104U (en) Prefabricated rain-proof sunshade shed frame of festival section case roof beam
CN210263577U (en) High strength building carrier plate
CN111734115A (en) Guide rail frame for adhesion type construction platform
CN219809017U (en) Shield constructs contact passageway section of jurisdiction support frame and braced system
CN220726312U (en) Underground limited space movable two lining buckles arch mould
CN216922123U (en) Detachable walkway plate support for shield tunnel
CN212296417U (en) Arch structure and arch support device
CN211256673U (en) Steel truss installation attached construction platform
CN214330650U (en) Tunnel supporting device
CN213597445U (en) Lower section track of lifting scaffold
CN214316438U (en) Swift high-efficient type is a thin film greenhouse even
CN219945064U (en) Cross steel column processing strutting arrangement
CN215520024U (en) Segmented sliding structure of string steel truss

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant