CN218597163U - Anchor rope drill way section auxiliary device that is in milk - Google Patents

Anchor rope drill way section auxiliary device that is in milk Download PDF

Info

Publication number
CN218597163U
CN218597163U CN202222882704.9U CN202222882704U CN218597163U CN 218597163 U CN218597163 U CN 218597163U CN 202222882704 U CN202222882704 U CN 202222882704U CN 218597163 U CN218597163 U CN 218597163U
Authority
CN
China
Prior art keywords
pipe
anchor
grouting
steel pipe
grout
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222882704.9U
Other languages
Chinese (zh)
Inventor
易湘华
陈萌
王涛
肖传勇
康子民
许文涛
杨健
周文斌
刘大海
佟岚
武才斌
聂向洲
卢耀民
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Gezhouba Group Three Gorges Construction Engineering Co Ltd
Original Assignee
China Gezhouba Group Three Gorges Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Gezhouba Group Three Gorges Construction Engineering Co Ltd filed Critical China Gezhouba Group Three Gorges Construction Engineering Co Ltd
Priority to CN202222882704.9U priority Critical patent/CN218597163U/en
Application granted granted Critical
Publication of CN218597163U publication Critical patent/CN218597163U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model provides an anchor cable orifice section grouting auxiliary device, which comprises an anchor cable guide steel pipe, wherein the anchor cable guide steel pipe is fixed on the outer wall of a steel backing plate, two groups of grouting holes which are arranged in parallel are processed on the anchor cable guide pipe, small steel pipes are correspondingly fixed at the positions of the grouting holes, and flexible grouting pipes are sleeved and fixed on the small steel pipes; the small steel pipe is positioned inside the reinforced concrete anchor pier; one of the flexible grouting pipes is used as a grouting pipe, and the other flexible grouting pipe is used as a grout return pipe. The device is through the seamless and unobstructed grout pipe of modified to and anchor rope self protection steel casing, stop the thick liquid package, wait that the mud return pipe is bent and is ligatured after the thick liquid returns in the grout process for the drill way section forms a withstand voltage obturator, ensures to promote to the anchor rope drill way section grout of design requirement and screen thick liquid pressure, makes the grout closely knit, guarantees anchor rope drill way section grout quality.

Description

Anchor rope drill way section auxiliary device that is in milk
Technical Field
The utility model relates to an anchor rope drill way section auxiliary device that is in milk belongs to the anchor rope construction engineering field in plain hole and the hole of bowing.
Background
The anchor cable is widely applied to deep support of side slopes, grottos and the like, and after the construction of the anchor cable is finished, anti-sliding resistance can be generated on a sliding surface, so that the displacement of soil bodies and rock bodies is effectively controlled, the stability of the soil bodies and the rock bodies is promoted, and the purposes of regulating bedding, landslides and dangerous rocks are achieved. The grouting of the anchor cable orifice section is a key procedure of anchor cable construction, and if the grouting of the anchor cable orifice section is not compact or fails, the anchor head steel strand and the anchor clamping piece are easily corroded by underground water or oxidized by contacting air, so that the risk of late loss of locking prestress of the anchor cable is increased, and the service life of the anchor cable is shortened.
Traditional anchor rope orifice section grout directly adopts the PE grout pipe, in the entry that direction steel pipe is close to the steel backing plate and sets up is inserted to grout return pipe (outlet duct), there is the gap between the entry on PE pipe and the direction steel pipe, easily get into the direction steel pipe through this gap during anchor pier concrete placement, block up the grout pipe, the grout return pipe mouth of pipe, the steel strand wires of densely covered in the direction steel pipe in addition, perhaps lead to the PE pipe to buckle in the PE pipe disect insertion direction steel pipe, warp, the flat PE pipe of straight crowded because of the steel strand wires atress among the anchor rope stretch-draw process, and then make anchor rope orifice section grout passageway not smooth or direct stifled dead pipeline. Therefore, the traditional anchor cable orifice section grouting method has various defects, the grouting of the orifice section is not compact or fails due to slight improper operation, the risk of late loss of locking prestress of the anchor cable is increased, and the service life of the anchor cable is shortened.
SUMMERY OF THE UTILITY MODEL
For solving above technical problem, the utility model provides a closely knit device of anchor rope drill way section grout, the device is through the seamless and unobstructed grout pipeline of modified to and the protection steel casing of anchor rope self, the grout stopping package, treat that grout in-process grout returning pipe returns the thick liquid back bend and ligature this pipe, make the drill way section form a pressure-resistant obturator, ensure to promote to the anchor rope drill way section grout of designing requirement and shield thick liquid pressure, it is closely knit to make the grout, guarantee anchor rope drill way section grout quality.
In order to realize the technical characteristics, the purpose of the utility model is realized as follows: an anchor cable orifice section grouting auxiliary device comprises an anchor cable guide steel pipe, wherein the anchor cable guide steel pipe is fixed on the outer wall of a steel base plate, two groups of grouting holes which are arranged in parallel are processed on the anchor cable guide pipe, small steel pipes are correspondingly fixed at positions of the grouting holes, and flexible grouting pipes are fixedly sleeved on the small steel pipes; the small steel pipe is positioned inside the reinforced concrete anchor pier; one of the flexible grouting pipes is used as a grouting pipe, and the other flexible grouting pipe is used as a grout return pipe.
The small steel pipe is made of galvanized steel pipe materials, and the length value of the small steel pipe is as follows: 10 cm-15 cm.
The flexible grouting pipe adopts a PE pipe, and the flexible grouting pipe is sleeved on the small steel pipe, so that the length value of the flexible grouting pipe is as follows: 8 cm-10 cm.
The outer end of the flexible grouting pipe extends out of the outer surface of the reinforced concrete anchor pier and is not less than 50cm.
The steel backing plate is provided with anchor sealing concrete on the side far away from the small steel pipe, and an anchorage device is arranged in the anchor sealing concrete.
And a concrete spray layer is arranged on the outer wall of the reinforced concrete anchor pier.
The anchor rope guide steel pipe is characterized in that a steel hinge line is arranged inside the anchor rope guide steel pipe, the steel hinge line penetrates through an anchor plate and a supporting plate which are arranged inside the anchor rope guide steel pipe, a grouting pipe is arranged at the center of the anchor rope guide steel pipe, a guide cap is arranged at the end of the grouting pipe, and a grout stopping bag is arranged outside the steel hinge line and inside the anchor rope guide steel pipe.
The utility model discloses there is following beneficial effect:
1. the utility model discloses the device is through the seamless and unobstructed grout pipeline of modified to and the protection steel casing of anchor rope self, only the thick liquid package, treat grout return pipe in-process and turn back the thick liquid back bend and ligature this pipe, make the drill way section form a withstand voltage obturator, ensure to promote to the anchor rope drill way section grout of designing requirement and screen thick liquid pressure, make the grout closely knit, guarantee anchor rope drill way section grout quality.
2. Device can guarantee anchor rope orifice segment grout quality and anchor rope design life, reduces the locking prestressing force later stage loss risk of anchor rope.
3. The small steel pipe made of the material has enough structural strength, can bear the lateral pressure of anchor pier concrete, and avoids the phenomena of grouting pipe deformation, grouting channel blockage, blockage and the like.
4. Through the slurry return pipe of the small steel pipe and the flexible grouting pipe, the internal pressure of a grouting area during grouting of a large opening section can be increased, and the grouting and screen grouting pressures meeting design requirements are achieved, so that grouting is compact, and the grouting quality is ensured.
Drawings
The present invention will be further explained with reference to the drawings and examples.
Fig. 1 is the whole structure diagram of the utility model.
Fig. 2 is a three-dimensional view of the present invention.
In the figure: the anchor comprises a reinforced concrete anchor pier 1, a steel backing plate 2, an anchorage device 3, anchor sealing concrete 4, a flexible grouting pipe 5, a small steel pipe 6, a concrete spraying layer 7, an anchor rope guide pipe 8, a steel strand 9, an anchor plate 10, a supporting plate 11, a grouting pipe 12, a guide cap 13 and a grout stopping bag 14.
Detailed Description
The following describes embodiments of the present invention with reference to the drawings.
Example 1:
referring to fig. 1-2, an anchor cable orifice section grouting auxiliary device includes an anchor cable guide steel pipe 8, the anchor cable guide steel pipe 8 is fixed on the outer wall of a steel backing plate 2, two groups of grouting holes arranged in parallel are processed on the anchor cable guide pipe 8, a small steel pipe 6 is correspondingly fixed at the position of the grouting hole, and a flexible grouting pipe 5 is sleeved and fixed on the small steel pipe 6; the small steel pipe 6 is positioned inside the reinforced concrete anchor pier 1; one of the flexible grouting pipes 5 is used as a grouting pipe, and the other flexible grouting pipe 5 is used as a grout return pipe. By adopting the grouting auxiliary device, the grouting quality of the orifice section of the anchor cable and the design service life of the anchor cable can be guaranteed, and the risk of later loss of the locking prestress of the anchor cable is reduced.
Further, the small steel pipe 6 is made of a galvanized steel pipe material, and the length of the small steel pipe 6 is as follows: 10 cm-15 cm. The small steel pipe 6 made of the material has enough structural strength, can bear the lateral pressure of anchor pier concrete, and avoids the phenomena of grouting pipe deformation, grouting channel blockage, blockage and the like.
Further, flexible grout pipe 5 adopts the PE pipe, and flexible grout pipe 5 embolias the length value on little steel pipe 6 and does: 8 cm-10 cm. Through adopting the PE pipe to be flexible structure, guaranteed that it can buckle and then conveniently carry out the shutoff to it.
Furthermore, the outer end of the flexible grouting pipe 5 extends out of the outer surface of the reinforced concrete anchor pier 1 by more than or equal to 50cm. The flexible grouting pipe 5 is convenient to be connected with grouting equipment, and accordingly corresponding sealing grouting is achieved.
Further, the steel backing plate 2 is provided with anchor sealing concrete 4 on the side far away from the small steel pipe 6, and an anchorage device 3 is arranged in the anchor sealing concrete 4. The anchorage device 3 can be used for connecting and fixing the steel strand 9.
Further, a concrete spray layer 7 is arranged on the outer wall of the reinforced concrete anchor pier 1. The concrete spraying layer 7 can be used for spraying the outside of the reinforced concrete anchor pier 1.
Further, a steel hinge line 9 is arranged inside the anchor rope guide steel pipe 8, the steel hinge line 9 penetrates through an anchor plate 10 and a supporting plate 11 which are arranged inside the anchor rope guide steel pipe 8, a grouting pipe 12 is arranged at the center of the anchor rope guide steel pipe 8, a guide cap 13 is arranged at the end of the grouting pipe 12, and a grout stopping bag 14 is arranged outside the steel hinge line 9 and inside the anchor rope guide steel pipe 8.
Anchor rope drill way section grout auxiliary device's construction steps:
step 1: two grouting holes with the diameter of 20mm are formed in the anchor cable guide steel pipe 8.
Step 2: and welding small galvanized steel pipes 6 with the same inner diameter of 20mm on the two grouting holes, wherein the length of the small steel pipes 6 is controlled below the surface of the reinforced concrete anchor pier 1 and is about 10-15 cm.
And step 3: the small steel pipe 6 is tightly sleeved with a PE flexible grouting pipe 5, the inner diameter of the PE flexible grouting pipe 5 is the outer diameter of the steel pipe, the length of the PE flexible grouting pipe 5 sleeved into the small steel pipe is 8 cm-10 cm, the firm sleeving connection is ensured, the outer end of the PE flexible grouting pipe 5 needs to extend out of the outer surface of anchor pier concrete to be more than or equal to 50cm, the PE flexible grouting pipe 5 is conveniently bent and bound during grout shielding, the grouting pressure of the anchor cable hole section is improved, the galvanized small steel pipe and the PE pipe sleeved on the galvanized small steel pipe jointly form a grouting pipeline of the anchor cable hole section, one of the galvanized small steel pipe and the PE pipe are used as grouting pipes, and the other of the galvanized small steel pipe and the PE pipe are used as grout return pipes.

Claims (7)

1. The utility model provides an anchor rope drill way section auxiliary device that is in milk which characterized in that: the anchor cable guide steel pipe grouting device comprises an anchor cable guide steel pipe (8), wherein the anchor cable guide steel pipe (8) is fixed on the outer wall of a steel base plate (2), two groups of grouting holes which are arranged in parallel are processed on the anchor cable guide steel pipe (8), a small steel pipe (6) is correspondingly fixed at the position of each grouting hole, and a flexible grouting pipe (5) is fixedly sleeved on each small steel pipe (6); the small steel pipe (6) is positioned inside the reinforced concrete anchor pier (1); one flexible grouting pipe (5) is used as a grouting pipe, and the other flexible grouting pipe (5) is used as a grout return pipe.
2. The anchor line orifice section grouting aid of claim 1, wherein: the small steel pipe (6) is made of galvanized steel pipe materials, and the length of the small steel pipe (6) is as follows: 10 cm-15 cm.
3. The anchor line orifice section grouting aid of claim 1, wherein: flexible grout pipe (5) adopt the PE pipe, just flexible grout pipe (5) embolia the length value on little steel pipe (6) and do: 8 cm-10 cm.
4. The anchor cable orifice section grouting aid of claim 3, wherein: the outer end of the flexible grouting pipe (5) extends out of the outer surface of the reinforced concrete anchor pier (1) and is not less than 50cm.
5. The anchor line orifice section grouting aid of claim 1, wherein: the steel backing plate (2) is provided with anchor sealing concrete (4) at the side far away from the small steel pipe (6), and an anchorage device (3) is arranged in the anchor sealing concrete (4).
6. The anchor line orifice section grouting aid of claim 1, wherein: and a concrete spray layer (7) is arranged on the outer wall of the reinforced concrete anchor pier (1).
7. The anchor line orifice section grouting aid of claim 1, wherein: the anchor rope guide steel pipe is characterized in that a steel hinge line (9) is arranged inside the anchor rope guide steel pipe (8), the steel hinge line (9) penetrates through an anchor plate (10) and a supporting plate (11) which are arranged inside the anchor rope guide steel pipe (8), a grouting pipe (12) is arranged at the center of the anchor rope guide steel pipe (8), a guide cap (13) is arranged at the end of the grouting pipe (12), and a grout stopping bag (14) is arranged outside the steel hinge line (9) and inside the anchor rope guide steel pipe (8).
CN202222882704.9U 2022-10-31 2022-10-31 Anchor rope drill way section auxiliary device that is in milk Active CN218597163U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222882704.9U CN218597163U (en) 2022-10-31 2022-10-31 Anchor rope drill way section auxiliary device that is in milk

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222882704.9U CN218597163U (en) 2022-10-31 2022-10-31 Anchor rope drill way section auxiliary device that is in milk

Publications (1)

Publication Number Publication Date
CN218597163U true CN218597163U (en) 2023-03-10

Family

ID=85405533

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222882704.9U Active CN218597163U (en) 2022-10-31 2022-10-31 Anchor rope drill way section auxiliary device that is in milk

Country Status (1)

Country Link
CN (1) CN218597163U (en)

Similar Documents

Publication Publication Date Title
CN106320346B (en) Campshed adds anchor cable grouting behind shaft or drift lining deep foundation pit supporting construction method
JP2024505110A (en) Anchor cable for grouting with large deformation, constant resistance and support function
CN218597163U (en) Anchor rope drill way section auxiliary device that is in milk
CN106838463A (en) The fastener inserts and usage of longitudinal integral rigidity after raising rectangular top plumber
CN107542086B (en) Anchor cable construction method for filling slope
CN115262537A (en) Karst development area cast-in-situ bored pile forming device and construction method
CN206467661U (en) The resistance to compression attachment structure of secondary splitting grouting
CN206521773U (en) Tapered end leak plugging structure after a kind of prestressed anchor cable stretching
CN110629792A (en) Splicing construction method for corrugated steel pipe gallery
CN206626283U (en) A kind of new concrete push pipe
CN113446039A (en) Grouting type variable cross-section anchor pipe and soft rock tunnel surrounding rock grouting reinforcement construction method
CN211816216U (en) Anchor rod device for tertiary grouting
CN210766913U (en) High-pressure rotary spraying anchor cable structure for resisting floating of building
JP5725470B2 (en) Joint opening size limiting device and joint opening size limiting method
CN214738024U (en) Component for realizing reaming anchor rod
CN216405402U (en) Plugging structure applied to leakage stoppage of anchor cable
CN213086803U (en) Integrated grouting device for pile side grouting of long spiral bored pile
CN215444104U (en) Slip casting type variable cross-section anchor pipe
CN215406098U (en) Water stopping device and grouting anchor cable water stopping system
CN220551096U (en) Grouting pipe with well wall reinforcing structure
CN213572033U (en) Retaining wall supporting construction
CN213233473U (en) Anchor cable body for deep foundation pit pouring slope protection pile and anchor cable support construction
CN217439540U (en) Hydraulic climbing formwork climbing cone reinforcing device
CN218757457U (en) Prestressed anchor cable structure
CN216518044U (en) Water-rich tunnel outside solution cavity block structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant