CN218566269U CN202221306678.9U CN202221306678U CN218566269U CN 218566269 U CN218566269 U CN 218566269U CN 202221306678 U CN202221306678 U CN 202221306678U CN 218566269 U CN218566269 U CN 218566269U
Authority
CN
China
Prior art keywords
suspension rod
suspension
water collector
clamping piece
packing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202221306678.9U
Other languages
Chinese (zh)
Inventor
张强
王秋艳
高翔
宋建功
张国亮
张全相
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Lanxiang Environmental Technology Co ltd
Original Assignee
Shandong Lanxiang Environmental Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Lanxiang Environmental Technology Co ltd filed Critical Shandong Lanxiang Environmental Technology Co ltd
Priority to CN202221306678.9U priority Critical patent/CN218566269U/en
Application granted granted Critical
Publication of CN218566269U publication Critical patent/CN218566269U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Heat-Exchange Devices With Radiators And Conduit Assemblies (AREA)

Abstract

The utility model discloses a filler suspension structure for a cooling tower, belonging to the technical field of cooling towers, comprising a plurality of water collector beams which are arranged in parallel at intervals, wherein two ends of each water collector beam are fixed on the tower wall of the cooling tower; a plurality of suspension rod assemblies which are uniformly arranged at intervals are arranged on both sides of each water collector beam; the suspension rod assembly comprises a clamping piece arranged on a cross beam of the water collector, and a suspension rod is arranged on the clamping piece; the utility model discloses can be stable suspend filler in midair, can avoid the setting of filler bottom bearing crossbeam, increase the area of contact of cold air and cooling water, improve cooling efficiency, reduce pressure head loss, reduce the fan energy consumption.

Description

Packing suspension structure for cooling tower
Technical Field
The utility model relates to a filler suspended structure for cooling tower belongs to cooling tower technical field.
Background
The filler is the core part of the cooling tower, the heat exchange efficiency of the whole tower is related to the distance between the filler structure and the filler sheets, and for the filler sheets with the oblique wave structure, the heat exchange efficiency is also related to the oblique wave angle. The heat exchange efficiency of the heat exchanger is also greatly related to the contact area between the filler and the cold air, and the heat exchange is mainly performed between the cold air and the water to be cooled.
However, the load-bearing cross beams are arranged below the fillers of the counter-flow cooling tower applied in the industry at present, the height of the cross beams of a general large tower can reach 900-1000mm, and the cross beams in contact with the fillers are dead air areas, so that the heat exchange area of the fillers is reduced, and the pressure head loss of the tower is increased. For the fan, the resistance of the fan is increased, so that the energy consumption of a fan motor is increased.
In view of the foregoing, it is apparent that the prior art has inconvenience and disadvantages in practical use, and thus, needs to be improved.
SUMMERY OF THE UTILITY MODEL
The to-be-solved technical problem of the utility model is to above not enough, provide a filler suspended structure for cooling tower, can be stable suspend in midair the filler, can avoid the setting of filler bottom bearing crossbeam, increase the area of contact of cold air and cooling water, improved cooling efficiency, reduce the loss of pressure head, reduce the fan energy consumption.
For solving the technical problem, the utility model discloses a following technical scheme: a packing suspension structure for a cooling tower comprises a plurality of water collector beams which are arranged in parallel at intervals, wherein two ends of each water collector beam are fixed on the tower wall of the cooling tower; a plurality of suspension rod assemblies which are uniformly arranged at intervals are arranged on both sides of each water collector beam; the suspension rod assembly comprises a clamping piece arranged on a cross beam of the water collector, and a suspension rod is arranged on the clamping piece.
Furthermore, the suspension rod assemblies on two sides of the water collector beam are arranged in a staggered manner; the suspension rod components on the adjacent sides of the two adjacent water collector beams are arranged in a staggered mode.
Furthermore, it is the rectangle steel pipe to receive the hydrophone crossbeam, chucking spare is U type structure, chucking spare card cover is on receiving the hydrophone crossbeam, just the blind end and the laminating of receiving the hydrophone crossbeam of chucking spare, chucking spare open-ended inside wall and the laminating of receiving the hydrophone crossbeam about side wall mutually.
Further, the suspension rod is arranged at the opening end of the clamping piece; the suspension rod is vertically arranged; the cross section of the suspension rod is circular.
Furthermore, the suspension rod is screwed with two fixing nuts, and the two fixing nuts are respectively arranged at the connecting parts of the upper side surface and the lower side surface of the clamping piece and the suspension rod; the fixing nut fixes the suspension rod and the clamping piece together.
Further, all be equipped with the through-hole on the both sides wall of chucking spare open end, the coaxial setting of through-hole on the chucking spare, the through-hole cooperatees with the suspension rod.
Furthermore, the suspension rod is made of stainless steel.
The utility model adopts the above technical scheme after, compare with prior art, have following advantage:
the utility model discloses can be stable suspend filler in midair, can avoid the setting of filler bottom bearing crossbeam, increase the area of contact of cold air and cooling water, improve cooling efficiency, reduce pressure head loss, reduce the fan energy consumption.
The utility model discloses the range setting that staggers each other of suspension pole is in receiving hydrophone crossbeam both sides for it is even to receive hydrophone bearing crossbeam atress, has also ensured to suspend in midair the stability that the pole suspends in midair to the filler.
The present invention will be described in detail with reference to the accompanying drawings and examples.
Drawings
FIG. 1 is a schematic view of the present invention;
FIG. 2 is a schematic structural view of a suspension bar assembly;
in the figure, the position of the first and second end faces,
1-a water collector beam, 2-a clamping piece, 3-a suspension rod and 4-a fixing nut.
Detailed Description
In order to clearly understand the technical features, objects, and effects of the present invention, embodiments of the present invention will be described with reference to the accompanying drawings.
Example 1
As shown in fig. 1-2, the utility model provides a filler suspension structure for cooling tower, comprising a plurality of water collector beams 1 arranged in parallel at intervals, wherein both ends of the water collector beams 1 are fixed on the tower wall of the cooling tower; the water collector crossbeam 1 is a rectangular steel pipe, a plurality of suspension rod assemblies which are uniformly arranged at intervals are arranged on two sides of each water collector crossbeam 1, and the suspension rod assemblies on the two sides of the water collector crossbeam 1 are arranged in a staggered manner; the suspension rod assembly is used for suspending the filler.
Further, the suspension rod assemblies on the adjacent sides of the two adjacent water collector beams 1 are arranged in a staggered manner.
Each suspension rod component comprises a clamping piece 2 fixed on the water collector beam 1 and a suspension rod 3 fixed on the clamping piece 2, the clamping piece 2 is of a U-shaped structure, the clamping piece 2 is clamped on the water collector beam 1, the closed end of the clamping piece 2 is attached to the water collector beam 1, and the inner side wall of the opening of the clamping piece 2 is attached to the upper side wall and the lower side wall of the water collector beam 1; a suspension rod 3 is arranged at the opening end of the clamping piece 2, the suspension rod 3 is vertically arranged, the cross section of the suspension rod 3 is circular, two fixing nuts 4 are screwed on the suspension rod 3, and the two fixing nuts 4 are respectively arranged at the connecting parts of the upper side surface and the lower side surface of the clamping piece 2 and the suspension rod 3; the fixing nut 4 fixes the suspension rod 3 and the clamping member 2 together.
Further, all be equipped with the through-hole on the both sides wall of 2 open ends of chucking spare, the coaxial setting of through-hole on the chucking spare 2, the through-hole cooperatees with hanging in midair pole 3.
Further, the suspension rod 3 is made of a metal material having an anti-corrosion effect, such as stainless steel, and the suspension rod 3 has high strength.
The utility model discloses during the use, adopt chucking spare card cover on receiving the hydrophone crossbeam, will suspend the pole in midair through fixation nut and fix on chucking spare, will pack through this structure and suspend in midair on receiving the hydrophone crossbeam to avoided setting up the bearing crossbeam below packing, can avoid the setting of packing bottom bearing crossbeam, the area of contact of increase cold air and cooling water has improved cooling efficiency, reduces the pressure head loss, reduces the fan energy consumption.
The above description is illustrative of the best mode contemplated for carrying out the present invention and the details not specifically mentioned are within the common general knowledge of those skilled in the art. The protection scope of the present invention is subject to the content of the claims, and any equivalent transformation based on the technical teaching of the present invention is also within the protection scope of the present invention.

Claims (7)

1. A packing suspension structure for a cooling tower comprises a plurality of water collector beams (1) which are arranged in parallel at intervals, wherein two ends of each water collector beam (1) are fixed on the tower wall of the cooling tower; the method is characterized in that: a plurality of suspension rod assemblies which are uniformly arranged at intervals are arranged on both sides of each water collector beam (1); the suspension rod assembly comprises a clamping piece (2) arranged on a water collector beam (1), and a suspension rod (3) is arranged on the clamping piece (2).
2. A packing suspension for a cooling tower as claimed in claim 1, wherein: the suspension rod assemblies on two sides of the water collector beam (1) are arranged in a staggered manner; the suspension rod components on the adjacent sides of the two adjacent water collector beams (1) are arranged in a staggered manner.
3. A packing suspension for cooling towers according to claim 1, wherein: receive hydrophone crossbeam (1) and be the rectangle steel pipe, chucking spare (2) are U type structure, chucking spare (2) card cover is on receiving hydrophone crossbeam (1), just the blind end and the laminating of receiving hydrophone crossbeam (1) of chucking spare (2), chucking spare (2) open-ended inside wall and receive hydrophone crossbeam (1) about lateral wall laminate mutually.
4. A packing suspension for cooling towers according to claim 1, wherein: the suspension rod (3) is arranged at the opening end of the clamping piece (2); the suspension rod (3) is vertically arranged; the cross section of the suspension rod (3) is circular.
5. A packing suspension for cooling towers according to claim 1, wherein: the suspension rod (3) is in threaded connection with two fixing nuts (4), and the two fixing nuts (4) are respectively arranged at the connecting parts of the upper side surface and the lower side surface of the clamping piece (2) and the suspension rod (3); the fixing nut (4) fixes the suspension rod (3) and the clamping piece (2) together.
6. A packing suspension for cooling towers according to claim 4, wherein: all be equipped with the through-hole on the both sides wall of chucking spare (2) open end, the coaxial setting of through-hole on chucking spare (2), the through-hole cooperatees with hanging in midair pole (3).
7. A packing suspension for cooling towers according to claim 1, wherein: the suspension rod (3) is made of stainless steel.
CN202221306678.9U 2022-05-28 2022-05-28 Packing suspension structure for cooling tower Active CN218566269U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221306678.9U CN218566269U (en) 2022-05-28 2022-05-28 Packing suspension structure for cooling tower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221306678.9U CN218566269U (en) 2022-05-28 2022-05-28 Packing suspension structure for cooling tower

Publications (1)

Publication Number Publication Date
CN218566269U true CN218566269U (en) 2023-03-03

Family

ID=85302495

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221306678.9U Active CN218566269U (en) 2022-05-28 2022-05-28 Packing suspension structure for cooling tower

Country Status (1)

Country Link
CN (1) CN218566269U (en)

Similar Documents

Publication Publication Date Title
TW201911735A (en) Three-in-one coupling insertion-pull type water surface photovoltaic power generation unit and power generation system thereof
CN218566269U (en) Packing suspension structure for cooling tower
CN207183365U (en) A kind of circulation cooling type lithium battery group
CN104511371A (en) Cooling water tower electrostatic demisting water recovery device
CN213124585U (en) Power battery pack and electric vehicle
CN104138804A (en) Demountable nonmetallic FRP electrostatic dust collection device suitable for automatic production
CN207834395U (en) A kind of novel battery lodge body bottom surface structure
CN207624760U (en) A kind of Battery case for preventing drawing crack from destroying
CN211551847U (en) Outdoor unit frame
CN209461448U (en) A kind of press mounting structure of rectifier diode
CN209386627U (en) A kind of U-tube dry evaporator effectively to radiate
CN205808174U (en) Energy storage titanium electrolyte cooler
CN217082739U (en) Heat exchanger
CN206288207U (en) The supporting construction of photovoltaic plant waterborne
CN207558555U (en) A kind of water cooling three-phase alternating current reactance device
CN221403989U (en) Corrosion-proof insulating efficient heat exchanger for electrolyte
CN204429489U (en) Cooling tower electrostatic demist apparatus for recovering
CN212778832U (en) All-steel cooling tower for three-dimensional bent 3D panel
CN220439378U (en) Copper-aluminum transition structure and transformer
CN220853221U (en) Microchannel heat exchanger
CN109458770A (en) A kind of U-tube dry evaporator effectively to radiate
CN217584655U (en) Heat exchange device and air conditioner
CN213691680U (en) Protective cover for radiator, radiator structure and combined transformer
CN214365286U (en) Anti-overturning high-voltage transmission line iron tower
CN220965352U (en) Water-cooling energy station machine room