CN218540793U - Measuring tool for cast-in-place pile Kong Jiaozhu standard height - Google Patents

Measuring tool for cast-in-place pile Kong Jiaozhu standard height Download PDF

Info

Publication number
CN218540793U
CN218540793U CN202221975625.6U CN202221975625U CN218540793U CN 218540793 U CN218540793 U CN 218540793U CN 202221975625 U CN202221975625 U CN 202221975625U CN 218540793 U CN218540793 U CN 218540793U
Authority
CN
China
Prior art keywords
gangbar
jiaozhu
kong
measuring tool
reel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202221975625.6U
Other languages
Chinese (zh)
Inventor
徐源鹏
韦晓明
陈超
楼洺强
包佳鑫
吴琦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Fifth Engineering Bureau Co Ltd
Huadong Building Co Ltd of China Construction Fifth Engineering Bureau Co Ltd
Original Assignee
China Construction Fifth Engineering Bureau Co Ltd
Huadong Building Co Ltd of China Construction Fifth Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Fifth Engineering Bureau Co Ltd, Huadong Building Co Ltd of China Construction Fifth Engineering Bureau Co Ltd filed Critical China Construction Fifth Engineering Bureau Co Ltd
Priority to CN202221975625.6U priority Critical patent/CN218540793U/en
Application granted granted Critical
Publication of CN218540793U publication Critical patent/CN218540793U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses a bored concrete pile Kong Jiaozhu standard height measuring tool, including being used for placing the subaerial support body in external world, be provided with the gangbar on the support body, the activity is provided with the take-up reel on the gangbar, twine on the take-up reel and be equipped with the depth measurement rope, depth measurement rope one end is connected with the collection piece that is arranged in putting into external bored concrete pile hole and takes out the concrete, be provided with the mounting that is used for fixed take-up reel on the gangbar, the utility model provides a lack a problem with low costs, convenient operation, simple structure and detection efficiency efficient concrete face elevation measuring tool among the prior art.

Description

Measuring tool for cast-in-place pile Kong Jiaozhu standard height
Technical Field
The utility model relates to an elevation measuring device technical field is pour to the bored concrete pile, specifically is a bored concrete pile Kong Jiaozhu standard height measuring tool.
Background
Need detect bored concrete pile concrete face elevation after the completion of bored concrete pile concrete placement among the prior art to this detects whether concrete face elevation accords with the standard, but the instrument structure that is used for detecting concrete face elevation among the prior art is complicated and complex operation, very big influence detection efficiency and construction process, the construction site is dirty indiscriminate poor simultaneously, influence placing and using of instrument, and instrument cost is expensive, whole construction site may only be equipped with one, and then influence the construction process.
SUMMERY OF THE UTILITY MODEL
Not enough to prior art, the utility model provides a bored concrete pile Kong Jiaozhu elevation measuring tool lacks a problem with low costs, convenient operation, simple structure and detection efficiency efficient concrete face elevation measuring tool among the solution prior art.
In order to achieve the purpose, the utility model provides a bored concrete pile Kong Jiaozhu elevation measuring tool, including being used for placing the subaerial support body in external world, be provided with the gangbar on the support body, the activity is provided with the take-up reel on the gangbar, it is equipped with the depth sounding rope to twine on the take-up reel, depth sounding rope one end is connected with and is arranged in putting into external bored concrete pile hole and takes out the collection piece of concrete, be provided with the mounting that is used for fixed take-up reel on the gangbar.
The technical scheme is adopted, and the method has the advantages that: an operator places a frame body on the outside ground, moves the frame body to enable a collecting block to be aligned to the center of an outside cast-in-place pile hole, the top end face of the collecting block and an opening of the cast-in-place pile hole are located on the same horizontal plane, at the moment, the operator records a scale mark on a depth measuring rope, the scale mark is a primary scale mark of the primary pile hole, then the operator rotates a take-up reel to enable the depth measuring rope to extend out of the take-up reel for increasing, the collecting block gradually moves towards the cast-in-place pile hole until the collecting block is contacted with concrete fluid, the operator continuously rotates the take-up reel to enable the collecting block to be completely immersed into the concrete, at the moment, the operator records a scale mark on the depth measuring rope, the scale mark is a stretched scale mark, the length between the stretched scale mark and the primary scale mark is the length of the measuring rope, and the elevation of the concrete surface is the length subtracted from the height of the cast-in-place pile hole; the setting of above-mentioned technique can accurately detect out concrete face elevation, and whole testing process convenient and fast has reduced check-out time simultaneously, has improved detection efficiency.
The utility model discloses further set up: the collecting block is conical, a containing groove for containing concrete stone blocks in the pile hole of the external cast-in-place pile is formed in the top surface of the collecting block, an outlet hole for flowing out of external concrete fluid is formed in the peripheral wall of the collecting block, and the outlet hole is communicated with the containing groove.
The technical scheme is adopted, and the method has the advantages that: when collecting the piece and entering into in the concrete in solid such as stone and fluid such as grout can flow to holding the groove, and the setting of porose is then in order to ensure that concrete fluid can flow out and hold the groove, ensures to hold and only collects solid such as stone in the groove for operating personnel can observe solid such as stone and judge whether to enter into the concrete, ensures that the detection of concrete face elevation can not receive the influence.
The utility model discloses further set up: the mounting includes and slides the axle of inserting of setting on the gangbar along gangbar length direction, the first rack of hoop arrangement on the axle periphery wall of inserting, set up on the take-up reel outer wall and supply the inserted jack of inserting, the second rack of hoop arrangement on the internal perisporium of jack, first rack sets up with the meshing of second rack, the draw-in groove has been seted up along its length direction on the gangbar, the protruding complex fixture block that is used for pegging graft with the draw-in groove on the internal perisporium of inserting, the fixture block slides and sets up in the draw-in groove.
The technical scheme is adopted, and the method has the advantages that: when the collecting block enters the concrete, an operator needs to fix the take-up reel to make the take-up reel incapable of rotating, and further ensures that the depth measuring rope cannot continuously move to a pile hole of the cast-in-place pile, so that the operator can check scale marks on the depth measuring rope, and further calculates the elevation of the concrete surface.
The utility model discloses further set up: be provided with the locating lever on the gangbar, the locating lever is located the gangbar below and sets up perpendicularly mutually with the gangbar, be provided with the holding ring on the locating lever outer wall, it has the perforation that supplies the sounding rope to wear to establish to run through on the holding ring.
The technical scheme is adopted, and the method has the advantages that: the retaining ring and the perforated extension that can effectual guide depth measurement rope ensure that the depth measurement rope can not drive the collection piece and rock at the stake downthehole, and then avoid collection piece and the downthehole wall of stake to bump phenomenon.
The utility model discloses further set up: the sounding rope is provided with a floating plate, and the floating plate is made of foam materials.
The technical scheme is adopted, and the method has the advantages that: the kickboard supports by foam in the above-mentioned technique, and the kickboard can float to the concrete face because of its material reason when the kickboard contacts with the concrete face gradually for operating personnel can look over outside the stake hole, and then judges that the collection piece has entered into the concrete, makes things convenient for operating personnel to detect the length of measuring rope this moment.
Drawings
FIG. 1 is a three-dimensional view of the present invention;
fig. 2 is a sectional view of the connection state of the middle clamping block and the clamping groove.
Detailed Description
The utility model provides a bored concrete pile Kong Jiaozhu standard height measuring tool, which comprises a frame body 1 for placing on the outside ground, wherein a linkage rod 2 is arranged on the frame body 1, a take-up reel 21 is movably arranged on the linkage rod 2, a depth measuring rope 22 is wound on the take-up reel 21, one end of the depth measuring rope 22 is connected with a collecting block 3 for placing in an outside bored concrete pile hole and taking out concrete, a fixing part for fixing the take-up reel 21 is arranged on the linkage rod 2, the collecting block 3 is conical, a containing groove 31 for containing concrete stones in the outside bored concrete pile hole is arranged on the top surface of the collecting block 3, an outlet 32 for flowing out of outside concrete fluid is arranged on the peripheral wall of the collecting block 3, the outlet 32 is communicated with the containing groove 31, the fixing part comprises an inserting shaft 23 which slides along the length direction of the linkage rod 2 and is arranged on the linkage rod 2, insert 23 periphery wall and go up the first rack 231 of annular arrangement, offer on the take-up reel 21 outer wall and supply 23 male jacks of inserting, the second rack 211 of annular arrangement on the jack internal perisporium, first rack 231 meshes the setting with second rack 211, draw-in groove 241 has been seted up along its length direction on the gangbar 2, the protruding has the complex fixture block 24 that is used for pegging graft with draw-in groove 241 on the 23 internal perisporium of inserting, fixture block 24 slides and sets up in draw-in groove 241, be provided with locating lever 11 on the gangbar 2, locating lever 11 lies in 2 below of gangbar and sets up perpendicularly mutually with gangbar 2, be provided with holding ring 12 on the 11 outer walls of locating lever, it has the perforation 13 that supplies sounding rope 22 to wear to establish to run through on holding ring 12, be provided with kickboard 4 on the sounding rope 22, kickboard 4 is made by the foam material.
The basic principles and main features of the present invention and the advantages of the present invention have been shown and described above, and it should be understood by those skilled in the art that the present invention is not limited by the above embodiments, but only by the principle of the present invention, and the present invention can be modified without departing from the spirit and scope of the present invention, and all of the modifications and improvements fall within the scope of the present invention.

Claims (5)

1. The utility model provides a bored concrete pile Kong Jiaozhu standard height measuring tool which characterized in that: including being used for placing the subaerial support body in external world, be provided with the gangbar on the support body, the activity is provided with the take-up reel on the gangbar, it is equipped with the depth measurement rope to twine on the take-up reel, depth measurement rope one end is connected with and is arranged in putting into external bored concrete pile stake hole and takes out the collection piece of concrete, be provided with the mounting that is used for fixed take-up reel on the gangbar.
2. The cast-in-place pile Kong Jiaozhu elevation measuring tool of claim 1, wherein: the collecting block is conical, a containing groove for containing concrete stone blocks in the pile hole of the external cast-in-place pile is formed in the top surface of the collecting block, an outlet hole for flowing out of external concrete fluid is formed in the peripheral wall of the collecting block, and the outlet hole is communicated with the containing groove.
3. The cast-in-place pile Kong Jiaozhu elevation measuring tool of claim 1, wherein: the mounting includes and slides the axle of inserting of setting on the gangbar along gangbar length direction, the first rack of hoop arrangement on the axle periphery wall of inserting, set up on the take-up reel outer wall and supply the inserted jack of inserting, the second rack of hoop arrangement on the internal perisporium of jack, first rack sets up with the meshing of second rack, the draw-in groove has been seted up along its length direction on the gangbar, the protruding complex fixture block that is used for pegging graft with the draw-in groove on the internal perisporium of inserting, the fixture block slides and sets up in the draw-in groove.
4. The cast-in-place pile Kong Jiaozhu elevation measuring tool of claim 1, wherein: be provided with the locating lever on the gangbar, the locating lever is located the gangbar below and sets up perpendicularly mutually with the gangbar, be provided with the holding ring on the locating lever outer wall, it has the perforation that supplies the sounding rope to wear to establish to run through on the holding ring.
5. The cast-in-place pile Kong Jiaozhu elevation measuring tool of claim 1, wherein: the sounding rope is provided with a floating plate, and the floating plate is made of foam materials.
CN202221975625.6U 2022-07-28 2022-07-28 Measuring tool for cast-in-place pile Kong Jiaozhu standard height Active CN218540793U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221975625.6U CN218540793U (en) 2022-07-28 2022-07-28 Measuring tool for cast-in-place pile Kong Jiaozhu standard height

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221975625.6U CN218540793U (en) 2022-07-28 2022-07-28 Measuring tool for cast-in-place pile Kong Jiaozhu standard height

Publications (1)

Publication Number Publication Date
CN218540793U true CN218540793U (en) 2023-02-28

Family

ID=85268784

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221975625.6U Active CN218540793U (en) 2022-07-28 2022-07-28 Measuring tool for cast-in-place pile Kong Jiaozhu standard height

Country Status (1)

Country Link
CN (1) CN218540793U (en)

Similar Documents

Publication Publication Date Title
CN112393998A (en) Accurate detection device of steel sheet hardness water level for construction
CN218540793U (en) Measuring tool for cast-in-place pile Kong Jiaozhu standard height
CN210104704U (en) Detection apparatus for ground power sounding
CN212742660U (en) Pile hole sediment detection device
CN212452814U (en) Bored concrete pile pore-forming sediment thickness measurement device
CN212159771U (en) Surface water detects uses sample thief
CN206721943U (en) A kind of pile foundation displacement auxiliary detection device
CN206515333U (en) A kind of soil sample dilatancy measurement apparatus
CN213455252U (en) Detection apparatus for foundation construction sediment thickness
CN212622605U (en) Concrete slump tester
CN110872851B (en) Construction method for controlling elevation of concrete slurry surface of hollow pile section engineering pile
CN219284719U (en) Highway road surface engineering compactness test detection device
CN214521156U (en) Concrete core drilling machine
CN216898840U (en) Automatic sandstone thickness detector
CN215064442U (en) Drilling depth detection device for geotechnical engineering pile foundation construction
CN214794362U (en) A water permeability detection device for concrete
CN213090642U (en) Simple concrete pouring thickness detection rod
CN218296988U (en) Bored concrete pile sediment thickness detection device
CN110616703A (en) Drill rod detection device
CN217896595U (en) Sand filling device for detecting compaction degree
CN220084430U (en) Powder taking device for testing chloride ion content of reinforced concrete
CN204740185U (en) PVC manages simple and easy mud proportion detector
CN212742653U (en) Composite foundation bearing capacity detection device for cement mixing pile for building
CN212612668U (en) Bored pile sediment thickness detection device
CN113832946B (en) Compactness check out test set that foundation ditch was backfilled for building engineering

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant