CN218493045U - High-altitude operation hanging frame - Google Patents
High-altitude operation hanging frame Download PDFInfo
- Publication number
- CN218493045U CN218493045U CN202222188599.9U CN202222188599U CN218493045U CN 218493045 U CN218493045 U CN 218493045U CN 202222188599 U CN202222188599 U CN 202222188599U CN 218493045 U CN218493045 U CN 218493045U
- Authority
- CN
- China
- Prior art keywords
- guardrail
- frame
- baffle
- hanging
- seted
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)
Abstract
The utility model discloses an aerial working hangs frame, including hanging the frame, it is the hollow structure of front end and top non-facial to hang the frame, and the dead slot has been seted up in the front end of hanging the frame, hang the top of frame and set up the multiunit locating hole with the dead slot intercommunication, be provided with the guardrail in the dead slot, the fixed orifices has been seted up on the top of guardrail, the dead slot has been seted up to the front end bottom of guardrail, the dead slot has the baffle through hinge swing joint, be provided with positioning bolt in the locating hole, in the device, through hanging frame and the guardrail structure that sets up, the user can pull out the guardrail to suitable length, and fix with positioning bolt, open the baffle structure in the guardrail, and to die the hinge lock of being connected with the guardrail, during operation, operating personnel can put debris in the guardrail. When the guardrail falls to the ground, the bolt of the baffle at the bottom of the guardrail is opened, the hanging frame falls, and sundries in the hanging frame automatically slide out.
Description
Technical Field
The utility model relates to a hang frame device field, especially relate to a high altitude construction hangs frame.
Background
The city for reforming old town districts relates to civil engineering of personal interests of common people, development engineering and civil engineering of promoting the index of citizens in the city. Adding insulation to the outer wall is part of the reconstruction of old communities. At present, window covers are arranged outside most old residential quarter windows, if the window covers are not detached, heat insulation at the windows cannot be constructed, the heat insulation construction quality of an outer wall is affected, cold bridges and water leakage phenomena are easy to generate, and the image of the outer vertical face of a modified building body is affected.
And in the window cover demolishs the in-process, resident's window cover debris are more, and the working face is less in the operation car hangs the frame, because of debris are forbidden high throwing strictly, need the big arm of oscilaltion many times, seriously influence the construction progress, and the window cover is inconsistent in size, if when demolising great window covers such as balcony, the operation car need adjust many times and hang the frame position, and careless a little will touch glass or air conditioner, brings very big inconvenience for the construction, influences resident's normal life.
SUMMERY OF THE UTILITY MODEL
In order to overcome the defects of the prior art, the utility model provides a high altitude construction hangs frame through the frame and the guardrail structure that hang that set up, the user can pull out the guardrail to suitable length to it is fixed with positioning bolt, open the baffle structure in the guardrail, and will die with the hinge lock that the guardrail is connected, during the operation, operating personnel can put debris in the guardrail. When the guardrail falls to the ground, the bolt of the baffle at the bottom of the guardrail is opened, the hanging frame falls, and sundries in the hanging frame automatically slide out.
In order to solve the technical problem, the utility model provides a following technical scheme: the utility model provides a high altitude construction hangs frame, includes and hangs the frame, it is the hollow structure of front end and top non-facies to hang the frame, just hang and to have seted up the dead slot in the front end of frame, hang the top of frame and set up the multiunit locating hole with the dead slot intercommunication, be provided with the guardrail in the dead slot, the fixed orifices has been seted up on the top of guardrail, the kerve has been seted up to the front end bottom of guardrail, the kerve has the baffle through hinge swing joint, be provided with positioning bolt in the locating hole.
As an optimal technical scheme of the utility model, locating hole and fixed orifices are with the screw hole structure of size, and its size and positioning bolt's size looks adaptation.
As an optimal technical scheme of the utility model, the front end of baffle is the sieve structure, the front end of sieve is the steel sheet structure, just the biggest contained angle between baffle and the guardrail is 30 degrees.
As an optimized technical scheme of the utility model, the length of guardrail is less than the length of hanging the frame.
As an optimized technical scheme of the utility model, the rear end of hanging the frame and the front end of guardrail all are provided with the universal wheel structure.
As a preferred technical scheme of the utility model, the baffle size is not more than the size of kerve.
As a preferred technical scheme of the utility model, the one end of baffle carries out fixed connection because the bolt is passed through to the one end of guardrail.
Compared with the prior art, the utility model discloses the beneficial effect that can reach is:
1. in the device, through the arranged hanging frame and the guardrail structure, a user can pull out the guardrail to a proper length, fix the guardrail by using the positioning bolt, open the baffle structure in the guardrail and lock the hinge connected with the guardrail, and during operation, an operator can put sundries in the guardrail. When the guardrail falls to the ground, the bolt of the baffle at the bottom of the guardrail is opened, the hanging frame falls, and sundries in the hanging frame automatically slide out.
2. The utility model discloses adjustable hanging frame can prevent debris, aerial work can placement tool and material when demolising the window cover, increases the usage space that hangs the frame, need not the frequent big arm of lift of high altitude construction car, has prolonged mechanical life, improves work efficiency, reduction of erection time.
Drawings
Fig. 1 is a schematic structural view of the present invention;
fig. 2 is one of the structural schematic diagrams of the hanging frame and the guardrail of the present invention;
fig. 3 is one of the structural schematic diagrams of the hanging frame and the guardrail of the present invention;
fig. 4 is a top view of the present invention.
Wherein: 1. hanging a frame; 11. an empty groove; 12. positioning holes; 2. a guardrail; 21. a fixing hole; 22. a bottom groove; 3. a baffle plate; 31. a sieve plate; 4. positioning the bolt; 5. and (4) a bolt.
Detailed Description
In order to make the technical means, creation features, achievement objects and functions of the present invention easy to understand, the present invention will be further explained with reference to the following embodiments, however, the following embodiments are only preferred embodiments of the present invention, and not all embodiments are included. Based on the embodiments in the implementation, other embodiments obtained by those skilled in the art without any creative work belong to the protection scope of the present invention. The experimental methods in the following examples are conventional methods unless otherwise specified, and materials, reagents and the like used in the following examples are commercially available unless otherwise specified.
Example (b):
as shown in fig. 1-4, the utility model provides an aerial work hangs frame, including hanging frame 1, hang frame 1 and be the hollow structure of front end and top non-facies, and offered dead slot 11 in the front end of hanging frame 1, hang the top of frame 1 and offer the multiunit locating hole 12 with dead slot 11 intercommunication, be provided with guardrail 2 in the dead slot 11, fixed orifices 21 has been seted up on the top of guardrail 2, and kerve 22 has been seted up to the front end bottom of guardrail 2, and kerve 22 has baffle 3 through hinge swing joint, is provided with positioning bolt 4 in the locating hole 12.
In other embodiments, the positioning hole 12 and the fixing hole 21 are both threaded hole structures with the same size, and the size of the threaded hole structures is matched with that of the positioning bolt 4; the front end of baffle 3 is sieve 31 structure, and the front end of sieve 31 is the steel sheet structure, and the biggest contained angle between baffle 3 and guardrail 2 is 30 degrees. Through the hanging frame 1 and the 2 structures of guardrail that set up, the user can pull out 2 with guardrail to suitable length to fixed with positioning bolt 4, open 3 structures of baffle in 2 guardrails, and will die with the hinge lock of 2 being connected of guardrail, during the operation, operating personnel can put debris in 2 guardrails. When the guardrail 2 falls to the ground, the bolt 5 of the baffle 3 at the bottom of the guardrail 2 is opened, the hanging frame 1 falls, and sundries in the hanging frame 1 automatically slide out.
In other embodiments, the length of the guard rail 2 is less than the length of the hanger frame 1.
In other embodiments, the rear end of the hanging frame 1 and the front end of the guardrail 2 are both provided with universal wheel structures.
In other embodiments, the size of the baffle 3 is not greater than the size of the bottom slot 22; one end of the baffle 3 is fixedly connected with one end of the guardrail 2 through a bolt 5. The bolt 5 structure can be when not using baffle 3 structure, fixed baffle 3 structure and 2 structures of guardrail, when using, cancels bolt 5 structure, puts down baffle 3 downwards, slides down debris.
In the present disclosure, unless expressly stated or limited otherwise, the first feature "on" or "under" the second feature may comprise direct contact between the first and second features, or may comprise contact between the first and second features not directly. Also, the first feature "on," "above" and "over" the second feature may include the first feature being directly above and obliquely above the second feature, or simply indicating that the first feature is at a higher level than the second feature. A first feature being "under," "below," and "beneath" a second feature includes the first feature being directly under and obliquely below the second feature, or simply meaning that the first feature is at a lesser elevation than the second feature.
The foregoing shows and describes the basic principles, essential features, and advantages of the invention. It should be understood by those skilled in the art that the present invention is not limited by the above embodiments, and the description in the above embodiments and the description is only preferred examples of the present invention, and is not intended to limit the present invention, and that the present invention can have various changes and modifications without departing from the spirit and scope of the present invention, and these changes and modifications all fall into the scope of the claimed invention. The scope of the invention is defined by the appended claims and equivalents thereof.
Claims (7)
1. The utility model provides a high altitude construction hangs frame which characterized in that: including hanging frame (1), hang frame (1) and be the hollow structure of front end and top no face, just empty groove (11) have been seted up in the front end of hanging frame (1), multiunit locating hole (12) with empty groove (11) intercommunication are seted up on the top of hanging frame (1), be provided with guardrail (2) in empty groove (11), fixed orifices (21) have been seted up on the top of guardrail (2), kerve (22) have been seted up to the front end bottom of guardrail (2), kerve (22) have baffle (3) through hinge swing joint, be provided with positioning bolt (4) in locating hole (12).
2. The aerial work lifting frame of claim 1, wherein: the positioning hole (12) and the fixing hole (21) are both threaded hole structures with the same size, and the size of the positioning hole structures is matched with that of the positioning bolt (4).
3. The aerial work hanging frame as claimed in claim 1, wherein: the front end of baffle (3) is sieve (31) structure, the front end of sieve (31) is the steel sheet structure, just the biggest contained angle between baffle (3) and guardrail (2) is 30 degrees.
4. The aerial work lifting frame of claim 1, wherein: the length of the guardrail (2) is less than that of the hanging frame (1).
5. The aerial work lifting frame of claim 1, wherein: the rear end of the hanging frame (1) and the front end of the guardrail (2) are both provided with universal wheel structures.
6. The aerial work lifting frame of claim 1, wherein: the size of the baffle (3) is not larger than that of the bottom groove (22).
7. The aerial work lifting frame of claim 1, wherein: one end of the baffle (3) is fixedly connected with one end of the guardrail (2) through a bolt (5).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202222188599.9U CN218493045U (en) | 2022-08-19 | 2022-08-19 | High-altitude operation hanging frame |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202222188599.9U CN218493045U (en) | 2022-08-19 | 2022-08-19 | High-altitude operation hanging frame |
Publications (1)
Publication Number | Publication Date |
---|---|
CN218493045U true CN218493045U (en) | 2023-02-17 |
Family
ID=85188863
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202222188599.9U Active CN218493045U (en) | 2022-08-19 | 2022-08-19 | High-altitude operation hanging frame |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN218493045U (en) |
-
2022
- 2022-08-19 CN CN202222188599.9U patent/CN218493045U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN218493045U (en) | High-altitude operation hanging frame | |
CN214464829U (en) | Pump station protection device | |
CN205977020U (en) | During using, endures building door and window structure with hidden drainage structures | |
CN210564056U (en) | Self-regulating metal door and window | |
CN207974742U (en) | Hide draining internal-open and inner tilt window | |
CN207813366U (en) | One kind can wireless control solar energy intelligent window | |
CN210598087U (en) | Decoration hanging flower basket for building | |
CN201137407Y (en) | Multifunctional sliding window | |
CN207974719U (en) | Internal-open and inner tilt swinging-out casement window | |
CN207063808U (en) | A kind of integral window aluminum section door | |
CN213115120U (en) | Building curtain wall windproof device | |
CN205894632U (en) | Spiral arm over -and -under type mobile scaffold | |
CN214697518U (en) | Detachable movable convex window with strong bearing capacity | |
CN217924107U (en) | Movable board house with escape function | |
CN216949018U (en) | Slope roof overhauling structure | |
CN214885743U (en) | Adjustable combined building flat net | |
CN217505285U (en) | Quantitative water sample collection device for sewage treatment | |
CN205918301U (en) | Push -and -pull integral type window frame constructs | |
CN108487829A (en) | A kind of intelligent electric-controlled window of fall arrest | |
CN213955486U (en) | Sun-proof prefabricated air conditioner board | |
CN213449580U (en) | Ground safety device for building engineering | |
CN205135338U (en) | Prevent strong wind rain water leakage window | |
CN211257952U (en) | Novel ticket business workstation | |
CN215563606U (en) | Energy-saving building curtain wall | |
CN214330011U (en) | Entrance to a cave protection strutting arrangement |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |