CN218466280U - Highway engineering bridge construction bridge face concrete curing means - Google Patents

Highway engineering bridge construction bridge face concrete curing means Download PDF

Info

Publication number
CN218466280U
CN218466280U CN202221859302.0U CN202221859302U CN218466280U CN 218466280 U CN218466280 U CN 218466280U CN 202221859302 U CN202221859302 U CN 202221859302U CN 218466280 U CN218466280 U CN 218466280U
Authority
CN
China
Prior art keywords
fixedly connected
highway engineering
fixed mounting
concrete curing
block
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202221859302.0U
Other languages
Chinese (zh)
Inventor
徐志野
张磊
龚图华
李冬梅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Jilin Investment And Construction Co ltd
Original Assignee
China Railway North Jilin Investment And Construction Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway North Jilin Investment And Construction Co ltd filed Critical China Railway North Jilin Investment And Construction Co ltd
Priority to CN202221859302.0U priority Critical patent/CN218466280U/en
Application granted granted Critical
Publication of CN218466280U publication Critical patent/CN218466280U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A20/00Water conservation; Efficient water supply; Efficient water use
    • Y02A20/108Rainwater harvesting

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model relates to a highway engineering technology field especially relates to a highway engineering bridge construction bridge deck concrete curing means. The technical scheme comprises the following steps: the bottom plate, bearing block and connecting block, bottom plate top fixed mounting has the regulating box, bottom plate top fixedly connected with storage water tank, storage water tank both sides fixedly connected with transmission pipe, transmission pipe both sides fixed mounting has the shower nozzle, a plurality of shower nozzles of shower nozzle one side fixedly connected with, fixed mounting has the water pump with transmission pipe intercommunication in the storage water tank, regulating box opposite side fixed mounting has the motor, motor one side fixedly connected with lead screw, the peripheral threaded connection of lead screw has the screw thread piece, screw thread piece bottom fixedly connected with connecting plate, connecting plate bottom fixedly connected with brush of dredging water. The utility model discloses a shower nozzle and shower nozzle carry out the watering maintenance to the bridge floor, and the hydrophobic brush cleans the bridge floor, outwards promotes ponding on the road surface, has increased the practicality of device.

Description

Highway engineering bridge construction bridge face concrete curing means
Technical Field
The utility model relates to a highway engineering technology field specifically is a highway engineering bridge construction bridge floor concrete curing means.
Background
After the concrete bridge deck is poured, in order to ensure that the concrete can be normally hardened, water needs to be sprayed on the surface of the concrete, and the concrete is maintained.
Through retrieval, patent publication No. CN213896676U discloses a concrete structure maintenance device for road and bridge construction, comprising a base, a water tank fixedly connected to the upper surface of the base, a water pump arranged at the inner bottom of the water tank, a connecting pipe fixedly connected to the output end of the water pump, a connecting cover connected to one end of the connecting pipe through the cover by screw thread, a water spray plate fixedly connected to the lower surface of the connecting cover, a nozzle arranged at one side of the water spray plate, and a rotating frame connected to the upper surface of the base by screw thread; in the prior art, CN213896676U can spray water on the concrete pavement, but the accumulated water on the concrete pavement cannot be cleaned, so that the maintenance effect of the device is poor.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a highway engineering bridge construction bridge face concrete curing means to solve the problem that proposes in the above-mentioned background art.
In order to achieve the above purpose, the utility model provides a following technical scheme: the utility model provides a highway engineering bridge construction bridge face concrete curing means, includes bottom plate, bearing block and connecting block, bottom plate top fixed mounting has the regulating box, bottom plate top fixedly connected with storage water tank, storage water tank both sides fixedly connected with transmission pipe, transmission pipe both sides fixed mounting has the spray pipe, a plurality of shower nozzles of spray pipe one side fixedly connected with, fixed mounting has the water pump with transmission pipe intercommunication in the storage water tank, regulating box opposite side fixed mounting has the motor, motor one side fixedly connected with lead screw, the peripheral threaded connection of lead screw has the screw thread piece, screw thread piece bottom fixedly connected with connecting plate, connecting plate bottom fixedly connected with brush of dispelling water.
The utility model provides a highway engineering bridge construction bridge floor concrete curing means, when the device is used, the staff's accessible carries out the water injection to the storage water tank, simultaneously when carrying out the maintenance to the bridge floor, transmit through the transmission pipe, carry out the watering maintenance to the bridge floor through spray line and shower nozzle simultaneously, the convenience that the device used has been promoted, the practicality of device has been increased simultaneously, when the device is used, but staff's starter motor drives the lead screw and rotates, accessible lead screw drive threaded block removes in the lead screw periphery this moment, accessible connecting plate cleans with the ponding department of hydrophobic brush on the bridge floor this moment, make ponding can outside even spread on the road surface on every side, the maintenance effect of device has been promoted, the practicality of device has been increased simultaneously.
As an alternative of this application technical scheme, bottom plate bottom fixedly connected with bearing block, bearing block bottom fixed mounting has the backup pad, and backup pad bottom fixed mounting has the universal wheel. When the device uses, staff's accessible backup pad removes with universal wheel pair device, has promoted the convenience that the device used.
As an alternative scheme of this application technical scheme, bottom plate top fixedly connected with connecting block, connecting block top fixed mounting has the connecting rod, connecting rod top fixedly connected with holding rod. When the device carries out the use, the staff accessible is held the holding rod and is promoted connecting rod and connecting block drive arrangement forward and remove, has promoted the convenience that the device used.
As an alternative of this application technical scheme, regulating box top fixedly connected with operation panel installs operating button on the operation panel, the display screen is installed to the operation panel, operation panel and motor electric connection, water pump electric connection in operation panel and the storage water tank. When the device carries out the use, staff's accessible display screen debugs device internal efficiency with operating button, has promoted the convenience that the device used.
As an alternative scheme of this application technical scheme, the observation window has been seted up to storage water tank one end, inlay in the observation window and install the glass window, be equipped with the scale mark on the glass window. When the device used, staff's accessible observation window and glass window observed the inside water yield of device, had promoted the convenience that the device used.
As an alternative scheme of this application technical scheme, the slide rail has been seted up to regulating box inside, the inside sliding connection of slide rail has the slider, the slider is connected fixedly with the screw thread piece. When the thread block moves on the periphery of the screw rod, the sliding block arranged at the top of the thread block slides inside the sliding rail, so that the using fluency of the device is improved.
Compared with the prior art, the beneficial effects of the utility model are that:
through there being the regulating box at bottom plate top fixed mounting, when the device is used, the staff accessible carries out the water injection to the storage water tank, simultaneously when carrying out the maintenance to the bridge floor, transmit through the transmission pipe, simultaneously carry out the watering maintenance to the bridge floor through spray pipe and shower nozzle, and simultaneously, still starter motor of staff drives the lead screw and rotates, accessible lead screw this moment drives the fillet at the lead screw periphery and removes, accessible connecting plate and hydrophobic brush clean the bridge floor this moment, outwards promote ponding on the road surface, the maintenance effect of device has been promoted, the practicality of device has been increased simultaneously.
Drawings
Fig. 1 is a perspective view of the present invention;
fig. 2 is a side view of the present invention;
FIG. 3 is a schematic view of a partial structure of the water storage tank of the present invention;
fig. 4 is a schematic view of the local structure of the screw rod of the present invention.
In the figure: 1. a base plate; 101. an adjusting box; 2. a bearing block; 201. a support plate; 202. a universal wheel; 3. connecting blocks; 301. a connecting rod; 302. a holding rod; 4. an operation table; 401. a display screen; 402. an operation button; 5. a water storage tank; 501. a conveying pipe; 502. an observation window; 503. scale marks; 504. a glass window; 505. a spray head; 506. a spray tube; 6. a motor; 601. a slider; 602. a slide rail; 603. a screw rod; 604. a thread block; 605. a connecting plate; 606. a hydrophobic brush.
Detailed Description
The technical solution of the present invention will be further explained with reference to the accompanying drawings and specific embodiments.
Example one
As shown in fig. 3 and 4, the utility model provides a highway engineering bridge construction bridge deck concrete curing means, comprising a base plate 1, bearing block 2 and connecting block 3, 1 top fixed mounting of bottom plate has regulating box 101, 1 top fixedly connected with storage water tank 5 of bottom plate, 5 both sides fixedly connected with transmission pipe 501 of storage water tank, transmission pipe 501 both sides fixed mounting has spray pipe 506, a plurality of shower nozzles 505 of spray pipe 506 one side fixedly connected with, fixed mounting has the water pump with transmission pipe 501 intercommunication in the storage water tank 5, regulating box 101 opposite side fixed mounting has motor 6, motor 6 one side fixedly connected with lead screw 603, the peripheral threaded connection of lead screw 603 has thread piece 604, thread piece 604 bottom fixedly connected with connecting plate 605, connecting plate 605 bottom fixedly connected with brush 606 that dredges water.
In some technical schemes, as shown in fig. 1, fig. 3 and fig. 4, when the device is used, staff's accessible 507 carries out the water injection to storage water tank 5, simultaneously when maintaining the bridge floor, transmit through transmission pipe 501, simultaneously carry out the maintenance of watering through spray pipe 506 and shower nozzle 505 to the bridge floor, the convenience of device use has been promoted, the practicality of device has been increased simultaneously, when the device is used, staff's starter motor 6 drives lead screw 603 and rotates, accessible lead screw 603 drives screw block 604 and removes in lead screw 603 periphery this moment, accessible connecting plate 605 is right with hydrophobic brush 606 this moment, outwards promote ponding on the road surface, the maintenance effect of device has been promoted, the practicality of device has been increased simultaneously.
In some technical solutions, as shown in fig. 2, fig. 3 and fig. 4, the present embodiment further includes: bottom plate 1 bottom fixedly connected with bearing block 2, 2 bottom fixed mounting of bearing block have backup pad 201, and backup pad 201 bottom fixed mounting has universal wheel 202. 1 top fixedly connected with connecting block 3 of bottom plate, 3 top fixed mounting of connecting block have connecting rod 301, and connecting rod 301 top fixedly connected with holding rod 302. Regulating box 101 top fixedly connected with operation panel 4 installs operating button 402 on the operation panel 4, and display screen 401 is installed to operation panel 4, operation panel 4 and motor 6 electric connection, operation panel 4 and the water pump electric connection in the storage water tank 5. An observation window 502 is arranged at one end of the water storage tank 5, a glass window 504 is embedded in the observation window 502, and scale marks 503 are arranged on the glass window 504. A sliding rail 602 is arranged inside the adjusting box 101, a sliding block 601 is connected inside the sliding rail 602 in a sliding manner, and the sliding block 601 is fixedly connected with a thread block 604.
In some technical solutions, as shown in fig. 2, fig. 3 and fig. 4, a worker can move the device through the support plate 201 and the universal wheel 202, convenience of use of the device is improved, when the device is used, the worker can hold the holding rod 302 to push the connecting rod 301 and the connecting block 3 forward to drive the device to move, convenience of use of the device is improved, when the device is used, the worker can debug internal efficiency of the device through the display screen 401 and the operating button 402, convenience of use of the device is improved, when the device is used, the worker can observe water inside the device through the observation window 502 and the glass window 504, convenience of use of the device is improved, when the thread block 604 moves on the periphery of the lead screw 603, the sliding block 601 installed at the top of the thread block 604 slides inside the sliding rail 602, and smoothness of use of the device is improved.
The above embodiments are merely some preferred embodiments of the present invention, and many alternative modifications and combinations can be made to the above embodiments by those skilled in the art based on the technical solution of the present invention and the related teachings of the above embodiments.

Claims (6)

1. The utility model provides a highway engineering bridge construction bridge face concrete curing means, includes bottom plate (1), bearing block (2) and connecting block (3), its characterized in that: the water pump type water storage tank is characterized in that an adjusting box (101) is fixedly mounted at the top of the base plate (1), a water storage tank (5) is fixedly connected to the top of the base plate (1), transmission pipes (501) are fixedly connected to two sides of the water storage tank (5), sprinkling pipes (506) are fixedly mounted to two sides of the transmission pipes (501), a plurality of spray heads (505) are fixedly connected to one side of each sprinkling pipe (506), a water pump communicated with the transmission pipes (501) is fixedly mounted in the water storage tank (5), a motor (6) is fixedly mounted to the other side of the adjusting box (101), a lead screw (603) is fixedly connected to one side of the motor (6), a thread block (604) is in threaded connection with the periphery of the lead screw (603), a connecting plate (605) is fixedly connected to the bottom of the thread block (604), and a drainage brush (606) is fixedly connected to the bottom of the connecting plate (605).
2. The highway engineering bridge construction bridge deck concrete curing device of claim 1, characterized in that: bottom plate (1) bottom fixedly connected with bearing block (2), bearing block (2) bottom fixed mounting has backup pad (201), and backup pad (201) bottom fixed mounting has universal wheel (202).
3. The highway engineering bridge construction bridge deck concrete curing device of claim 1, characterized in that: bottom plate (1) top fixedly connected with connecting block (3), connecting block (3) top fixed mounting has connecting rod (301), connecting rod (301) top fixedly connected with holding rod (302).
4. The highway engineering bridge construction bridge deck concrete curing device of claim 1, characterized in that: adjusting box (101) top fixedly connected with operation panel (4), install operating button (402) on operation panel (4), display screen (401) are installed in operation panel (4), operation panel (4) and motor (6) electric connection, operation panel (4) and the water pump electric connection in storage water tank (5).
5. The highway engineering bridge construction bridge deck concrete curing device of claim 1, characterized in that: an observation window (502) is arranged at one end of the water storage tank (5), a glass window (504) is embedded in the observation window (502), and scale marks (503) are arranged on the glass window (504).
6. The highway engineering bridge construction bridge deck concrete curing device of claim 1, characterized in that: slide rail (602) have been seted up to regulating box (101) inside, slide rail (602) inside sliding connection has slider (601), slider (601) are connected fixedly with screw block (604).
CN202221859302.0U 2022-07-19 2022-07-19 Highway engineering bridge construction bridge face concrete curing means Active CN218466280U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221859302.0U CN218466280U (en) 2022-07-19 2022-07-19 Highway engineering bridge construction bridge face concrete curing means

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221859302.0U CN218466280U (en) 2022-07-19 2022-07-19 Highway engineering bridge construction bridge face concrete curing means

Publications (1)

Publication Number Publication Date
CN218466280U true CN218466280U (en) 2023-02-10

Family

ID=85136824

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221859302.0U Active CN218466280U (en) 2022-07-19 2022-07-19 Highway engineering bridge construction bridge face concrete curing means

Country Status (1)

Country Link
CN (1) CN218466280U (en)

Similar Documents

Publication Publication Date Title
CN218466280U (en) Highway engineering bridge construction bridge face concrete curing means
CN215051805U (en) Fog seal construction equipment of bituminous paving preventive maintenance
CN110331691A (en) A kind of cleaning device for track
CN211947846U (en) Marking clearing device for highway construction
CN113328690A (en) Accurate timely belt cleaning device of photovoltaic power plant photovoltaic module
CN212200723U (en) Ditch wall cleaning device
CN208513182U (en) A kind of photovoltaic module automatic flushing device
CN208965378U (en) A kind of highway communication engineering graticule removing vehicle
CN114472280B (en) Surface cleaning system for photovoltaic panel and cleaning method thereof
CN214363229U (en) Dust fall equipment for portable construction
CN214638872U (en) Rotary lifting brushing mechanism
CN213194303U (en) Rubber wheel oil brushing device for rubber wheel of road roller
CN202238708U (en) Automatic cleaning machine
CN221133344U (en) Three-rail cover cleaning device and railway cleaning system
CN208245294U (en) A kind of construction wallboard cleaning device
CN221029828U (en) Driving type sweeping vehicle with cleaning brush cleaning structure
CN211898080U (en) Highway rail guard curing means
CN216217149U (en) Construction management monitoring device based on BIM
CN216833568U (en) Old and useless train cleaning equipment
CN220202379U (en) Mud scraping road roller
CN213345521U (en) High-rise glass outer wall cleaning device
CN220635481U (en) Supervisory equipment fixer for building engineering
CN214832125U (en) Highway engineering warning sign
CN219010899U (en) Water stabilizing layer maintenance watering cart
CN221118190U (en) Road and bridge maintenance device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 130,000 Building 1, Yongchang Community, Nanguan District, Changchun City, Jilin Province

Patentee after: China Railway Jilin Investment and Construction Co.,Ltd.

Address before: 130,000 Building 1, Yongchang Community, Nanguan District, Changchun City, Jilin Province

Patentee before: China Railway North Jilin Investment and Construction Co.,Ltd.