CN218453702U - Integrated central feeding machine - Google Patents

Integrated central feeding machine Download PDF

Info

Publication number
CN218453702U
CN218453702U CN202222889662.1U CN202222889662U CN218453702U CN 218453702 U CN218453702 U CN 218453702U CN 202222889662 U CN202222889662 U CN 202222889662U CN 218453702 U CN218453702 U CN 218453702U
Authority
CN
China
Prior art keywords
hopper
conveyor
auger
integrated central
inclined plane
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222889662.1U
Other languages
Chinese (zh)
Inventor
万红涛
郭建鑫
万红彬
陈延刚
陈国芳
万鑫博
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Puyang City Hongyu Pressure Vessel Co ltd
Original Assignee
Puyang City Hongyu Pressure Vessel Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Puyang City Hongyu Pressure Vessel Co ltd filed Critical Puyang City Hongyu Pressure Vessel Co ltd
Priority to CN202222889662.1U priority Critical patent/CN218453702U/en
Application granted granted Critical
Publication of CN218453702U publication Critical patent/CN218453702U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Filling Or Emptying Of Bunkers, Hoppers, And Tanks (AREA)
  • Screw Conveyors (AREA)

Abstract

The utility model discloses an integrated central batcher, including setting up the hopper that connects in raw coal bunker bottom, the bottom that connects the hopper is provided with two conveyor, connect the hopper in two be provided with ascending bellying between the conveyor, the bellying is the inclined plane in two conveyor's a side, be provided with to the first auger that connects hopper bottom pay-off on the inclined plane, the buggy is carried to screw conveyer's feed end to first auger, and dropping of buggy accelerates prevents to appear blockking up because buggy knot arch phenomenon, guarantees feed rate, promotes production.

Description

Integrated central feeding machine
Technical Field
The utility model relates to a batcher technical field especially relates to a central batcher that conjointly used.
Background
The feeder is used for continuously and uniformly feeding processed or unprocessed materials from various equipment (hoppers, storage bins and the like) into receiving equipment or a conveying machine. Some places are also called feeders, and the essence is the same. The coal feeder type is various, and the coal powder feeder among the prior art is impeller type and spiral mostly, and its basic structure is: the outer shell and the impeller assembled in the shell through the shaft form a cavity for filling coal powder, the impeller and the shaft are assembled in a synchronous rotating mode, and two ends of the shaft are fixed on end covers at two ends of the outer shell transversely penetrating through the cavity through bearings. When the impeller rotates, the pulverized coal on the upper part of the feeder fills a cavity formed by the shell and the impeller, and falls down when the pulverized coal in the cavity rotates to the discharge hole, so that the feeding function is realized.
The continuous and long-distance feeding process of the pulverized coal often uses the screw feeder, the receiving hopper of the existing screw conveyor is mostly directly arranged at the lower part of a raw coal bin, and the pulverized coal can fall into the receiving hopper of the screw conveyor under the action of gravity when in use. In order to improve conveying efficiency, some manufacturers can install two or even a plurality of spiral conveyors at the lower part of a large raw coal bunker, and can feed a plurality of using ends simultaneously when in use. But the buggy is when entering into the hopper that connects of spiral number conveyer from the raw coal storehouse in, because the effect of moisture in the buggy, can form the caking phenomenon on the upper portion of screw conveyer in the hopper that connects, when a plurality of screw conveyer used simultaneously, the bottom that connects the hopper can shrink the volume and be convenient for carry especially, and the caking phenomenon is especially serious, very big reduction feed rate, influence production.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to overcome can form between raw coal bunker and the hopper that connects and become the knot and encircle the not enough that the phenomenon reduces defeated pay-off rate among the prior art when the buggy feed, provide an disjunctor formula center batcher.
The utility model discloses a realize through following technical scheme: the utility model provides an integrated central batcher, is including setting up the hopper that connects in raw coal bunker bottom, the bottom that connects the hopper is provided with two conveyor, connect the hopper two be provided with ascending bellying between the conveyor, the bellying is the inclined plane in two conveyor's a side, be provided with on the inclined plane to connect the first auger of hopper bottom pay-off.
Furthermore, the first auger is obliquely arranged, and a rotating shaft of the first auger is vertical to the inclined plane.
Further, the conveying device is a screw conveyor.
Furthermore, the two spiral conveyors are arranged at the bottom of the receiving hopper in an inverted splayed shape.
Furthermore, a mounting seat is arranged on the side wall of the receiving hopper, and a vibrator is arranged on the mounting seat.
Furthermore, a base plate is arranged in the middle of the mounting seat, and the vibrator is an air vibrator.
The beneficial effects of the utility model reside in that: two screw conveyer are the setting of falling the splayed in connecing hopper bottom, and two screw conveyer can carry the different directions from the buggy in the raw coal storehouse when using, increase conveying efficiency, improve economic benefits. Connect the hopper two be provided with ascending bellying between conveyor, the bellying is the inclined plane in two conveyor's a side, be provided with the first auger to connect hopper bottom pay-off on the inclined plane, first auger slope sets up and the pivot of first auger is perpendicular with the inclined plane, first auger sets up on the route that the buggy dropped when using, when first auger rotates, it drops to drive the buggy of joint between former bunker bottom and screw conveyer, the rotatory clear stifled ware below of installing on nearly former bunker in the upper portion of first auger, the whereabouts of how dividing can accelerate when using, nearly screw conveyer one side is installed on the inclined plane to the other end of first auger simultaneously, guarantee the whereabouts speed rate of buggy in the very big degree when using, guarantee production effect.
Drawings
Fig. 1 is a schematic view of the overall internal top structure of the present invention;
fig. 2 is a schematic view of the overall structure of the receiving hopper of the present invention;
wherein: 1. a screw conveyor; 2. a receiving hopper; 201. a bevel; 3. a mounting base; 301. a first auger; 302. a backing plate.
Detailed Description
In the description of the present invention, it should also be noted that, unless otherwise explicitly specified or limited, the terms "disposed," "mounted," "connected," and "connected" are to be construed broadly, e.g., as meaning either a fixed connection, a removable connection, or an integral connection; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meaning of the above terms in the present invention can be understood in specific cases to those skilled in the art.
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Example 1
As shown in fig. 1-2: the utility model provides an integrated central batcher, is including setting up the hopper 2 that connects in raw coal bunker bottom, and the inside buggy in raw coal bunker can fall into and connect hopper 2 under the effect of gravity, is provided with two conveyor in the bottom that connects hopper 2, and the buggy that falls into and connects in the hopper 2 can pass through conveyor and carry the use position. Wherein conveyor is screw conveyer 1, and two screw conveyer 1 are the setting of falling the eight characters in the 2 bottoms of hopper that connect, and two screw conveyer 1 can carry the different directions from the buggy in the raw coal bunker when using, increase conveying efficiency, improve economic benefits.
An upward bulge is arranged between the two conveying devices in the material receiving hopper 2, one side of each bulge on each conveying device is an inclined surface 201, and the inclined surfaces 201 of the bulges can convey the coal dust falling from the raw coal bunker above to the conveying machines when in use. Be provided with the first hank dragon 301 to the 2 bottom pay-off of hopper that connects on inclined plane 201, first hank dragon 301 slope sets up and first hank dragon 301's pivot is perpendicular with inclined plane 201, first hank dragon 301 sets up on the route that the buggy dropped when using, when first auger 301 rotates, it drops to drive the buggy of joint between former bunker bottom and screw conveyer 1, the clear stifled ware below of rotation of installing on nearly former bunker on the upper portion of first hank dragon 301, the whereabouts of dividing can accelerate when using, nearly screw conveyer 1 one side on inclined plane 201 is installed to the other end of first auger 301 simultaneously, guarantee the whereabouts fast rate of buggy in the very big degree when using, guarantee the production effect.
The side wall of the receiving hopper 2 is provided with a mounting seat 3, and the mounting seat 3 is provided with a vibrator. The middle position of the mounting seat 3 is provided with a backing plate 302, and the rapping device is an air rapping device. The vibrator uses a pneumatic vibrator (brand: DIYI, model: AH-SK-ZC-SX 30), uses the compressed air as a drive, has reliable and durable drive structure and low failure rate, and improves the production effect. The rapping device is connected with the receiving hopper 2 through the mounting seat 3, the middle position of the mounting seat 3 is provided with the backing plate 302, and the working part of the rapping device acts on the backing plate 302, so that the damage to the raw coal bunker is reduced, and the use stability is ensured. Rapping apparatus and 3 bolt joints of mount pad to mount pad 3 sets up along the outer wall that connects hopper 2, and installs a plurality ofly, can form a vibrations scope at the lateral wall that connects hopper 2 when using, will block up connecing 2 tops of hopper and the adhesion pulverized coal that connect on the 2 lateral walls of hopper to shake and fall, and very big reduction blocks up the probability, improves the pay-off effect.
The working principle is as follows: when the coal bunker feeding device is used, the first packing auger is started firstly, and when a raw coal bunker feeds materials, the first packing auger conveys coal dust to the feeding end of the spiral conveyor, so that the falling of the coal dust is accelerated, the blockage caused by the arching phenomenon of the coal dust is prevented, the feeding speed is ensured, and the production is promoted.
Finally, it should be noted that: although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications and variations can be made in the embodiments or in part of the technical features of the embodiments without departing from the spirit and the scope of the invention.

Claims (6)

1. The utility model provides an integrated central batcher, is including setting up the hopper that connects in raw coal bunker bottom, its characterized in that: connect the bottom of hopper to be provided with two conveyor, connect the hopper two be provided with ascending bellying between the conveyor, the bellying is the inclined plane in two conveyor's a side, be provided with the first auger to connect the hopper bottom pay-off on the inclined plane.
2. An integrated central feeder according to claim 1, wherein: the first auger is obliquely arranged, and a rotating shaft of the first auger is perpendicular to the inclined plane.
3. An integrated central feeder according to claim 1, wherein: the conveying device is a screw conveyor.
4. An integrated central feeder according to claim 3, wherein: the two screw conveyors are arranged at the bottom of the receiving hopper in an inverted splayed shape.
5. An integrated central feeder according to claim 1, wherein: the side wall of the receiving hopper is provided with a mounting seat, and the mounting seat is provided with a vibrator.
6. An integrated central feeder according to claim 5, wherein: the middle position of the mounting seat is provided with a base plate, and the vibrator is an air vibrator.
CN202222889662.1U 2022-10-31 2022-10-31 Integrated central feeding machine Active CN218453702U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222889662.1U CN218453702U (en) 2022-10-31 2022-10-31 Integrated central feeding machine

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222889662.1U CN218453702U (en) 2022-10-31 2022-10-31 Integrated central feeding machine

Publications (1)

Publication Number Publication Date
CN218453702U true CN218453702U (en) 2023-02-07

Family

ID=85125785

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222889662.1U Active CN218453702U (en) 2022-10-31 2022-10-31 Integrated central feeding machine

Country Status (1)

Country Link
CN (1) CN218453702U (en)

Similar Documents

Publication Publication Date Title
CN218453702U (en) Integrated central feeding machine
CN206645472U (en) A kind of automatic feeding of material
CN218369908U (en) Automatic feeder of coal pulverizer
CN201351056Y (en) Omni-sealing pneumatic continuous mode material-handling pump
CN207016084U (en) A kind of impacting type automatic blanking machine
CN206485939U (en) A kind of sandstone conveying device
CN210635320U (en) Screw machine feeder for industrial production
CN216444376U (en) Scraper conveyor chain with anti-blocking device
CN211687144U (en) Scraper type coal feeding device
CN210943977U (en) Novel high-efficient coal feeder
CN206050562U (en) Material conveying device under a kind of ejection concussion
CN210140242U (en) Conveying device for coal mine
CN207861481U (en) A kind of powder material automatic feeding system
CN206886275U (en) A kind of anti-blocking flat material device of light industry scrapper conveyor
CN219751015U (en) Prevent screen grain mouth scraper machine of long-pending material
CN216188797U (en) Sand conveyor for mining placer
CN201721967U (en) Transporting and feeding device for firework tube
CN210286020U (en) A conveying equipment for soft white sugar material
CN213737634U (en) Powder bin
CN211033232U (en) Automatic feeding device for packaging machine
CN214778143U (en) Prevent blockking up powdered ore packing plant
CN213325677U (en) Ammonium sulfate unloader
CN210619074U (en) Dry-mixed mortar mobile silo
CN216996748U (en) Mining feeder
CN208775659U (en) The vibration lifting apparatus of anti-spillage material

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant