CN218449190U - Auxiliary erecting tool for power transmission line - Google Patents

Auxiliary erecting tool for power transmission line Download PDF

Info

Publication number
CN218449190U
CN218449190U CN202222656656.1U CN202222656656U CN218449190U CN 218449190 U CN218449190 U CN 218449190U CN 202222656656 U CN202222656656 U CN 202222656656U CN 218449190 U CN218449190 U CN 218449190U
Authority
CN
China
Prior art keywords
sets
mounting bracket
adjustable shelf
groove
ratchet
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202222656656.1U
Other languages
Chinese (zh)
Inventor
陶毅哲
李冉
罗全恒
杨勇
武晓贵
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202222656656.1U priority Critical patent/CN218449190U/en
Application granted granted Critical
Publication of CN218449190U publication Critical patent/CN218449190U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Electric Cable Installation (AREA)

Abstract

The utility model discloses a supplementary instrument of erectting of transmission line, which comprises a mounting bracket, the adjustable shelf and hang and establish the subassembly, logical groove has been seted up on the mounting bracket, it is provided with the adjustable shelf to lead to the inslot, all be provided with the pulley on mounting bracket and the adjustable shelf, all be provided with the ratchet on two sets of pulleys, two sets of ratchets revolve to opposite, all be provided with the protection casing on mounting bracket and the adjustable shelf, all be provided with the fixed axle on mounting bracket and the adjustable shelf, the equal activity of two sets of fixed axles is provided with the jack catch, two sets of jack catches block respectively and establish on two sets of ratchet, all the cover is equipped with the torsional spring on two sets of fixed axles, two sets of torsional springs set up respectively on two sets of jack catches, the mounting bracket top is provided with to hang and establishes the subassembly on being provided with the hanging shaft, it includes the bearing block to hang and establish the subassembly. The utility model provides a current in-process cable of acting as go-between drops from the swiveling wheel easily, and the cable quality is heavier, and when the grip was not enough, can fall down because of self gravity, influences the construction progress, injures constructor's problem by a crashing object even.

Description

Auxiliary erecting tool for power transmission line
Technical Field
The utility model relates to a transmission line erects instrument technical field, more specifically says, in particular to supplementary instrument of erectting of transmission line.
Background
The power transmission line erection is to install a cable between two adjacent iron towers, and in the erection process, in order to avoid the contact between a power transmission lead and the ground or between two iron towers and crossed obstacles such as charged bodies, crops, trees and the like, a corresponding erection tool is needed for auxiliary erection.
For example, the utility model patent No. cn201220373630.X discloses a paying-off tool for erecting a power transmission line, which is characterized in that in the use process, an openable and closable U-shaped ring on a paying-off ring is opened, a paid-off wire is put in the U-shaped ring, then the openable and closable U-shaped ring is closed to perform paying-off work, and the paid-off wire is adjusted along with the 360-degree angle of a rotating wheel; after the paying-off is finished, the U-shaped ring which can be opened and closed on the paying-off ring is opened, the electric wire can be taken out, and the telescopic rod can be adjusted according to the height of the barrier. However, traditional unwrapping wire instrument of erectting can prevent that the corner from acting as go-between by the emergence of card phenomenon, but traditional supplementary erects instrument simple structure, and the function is single, and the cable drops from the swiveling wheel easily in the in-process of acting as go-between, leads to losing original effect, and the practicality is not high.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a supplementary instrument of erectting of transmission line aims at solving current supplementary instrument of erectting simple structure, and the function is single, and the cable comes off from the swiveling wheel easily in the in-process of acting as go-between, leads to losing original effect, and cable self quality is heavier, and when the grip was not enough, the cable can fall because of self gravity, influences the construction progress, falls to injure constructor's technical problem by a crashing object even.
The utility model discloses a realize like this:
the utility model provides a supplementary instrument of erectting of transmission line, includes mounting bracket, adjustable shelf and hangs and establish the subassembly, logical groove has been seted up on the mounting bracket, it is provided with the adjustable shelf to lead to the inslot, the mounting bracket with all be provided with the pulley on the adjustable shelf, it is two sets of all be provided with the ratchet on the pulley, it is two sets of ratchet revolves to opposite, the mounting bracket with all be provided with the protection casing on the adjustable shelf, it is two sets of the ratchet sets up respectively in two sets of in the protection casing, the mounting bracket with all be provided with the fixed axle on the adjustable shelf, it is two sets of all the activity is provided with the jack catch on the fixed axle, and is two sets of the jack catch blocks respectively and establishes on two sets of the ratchet, it is two sets of all the cover is equipped with the torsional spring on the fixed axle, the mounting bracket top is provided with the hanging on the hanging axle and establishes the subassembly, it includes the bearing seat to hang and establish the subassembly.
As the utility model discloses a preferred technical scheme, the counter bore has been seted up on the bearing seat, be provided with the bearing in the counter bore, the bearing sets up hang epaxial, the rectangular channel has been seted up on the bearing seat, hang epaxial threaded connection and have fixing bolt, fixing bolt one end is provided with the fixed block, be provided with the stopper on the fixed block, the spacing groove has been seted up in the rectangular channel, the stopper sets up the spacing inslot.
As the utility model discloses a preferred technical scheme, it is provided with the guide rail to lead to the inslot, the stroke groove has been seted up to the last setting of adjustable shelf, the guide rail sets up the stroke inslot, threaded connection has the adjusting screw bolt on the mounting bracket, adjusting screw bolt one end activity sets up on the adjustable shelf, the adjusting screw bolt other end is provided with the carousel.
As the utility model discloses a preferred technical scheme, be provided with locking Assembly on the mounting bracket, locking Assembly includes the fixed clamp splice, the activity is provided with movable clamp splice on the fixed clamp splice, be provided with the buckle on the fixed clamp splice, be provided with the latch on the movable clamp splice, the buckle card is established on the latch, the adjusting stud is located the fixed clamp splice with between the movable clamp splice.
As the utility model discloses an it is preferred technical scheme, two sets of all be provided with the driving lever on the jack catch, two sets of all be provided with the circular arc groove on the protector, two sets of the driving lever sets up respectively in the circular arc inslot.
As the utility model discloses an optimal technical scheme, it is two sets of all be provided with the rubber circle on the pulley.
Compared with the prior art, the beneficial effects of the utility model are that:
1. under the setting of two sets of pulleys, wear to establish the cable that will erect between two sets of pulleys, by the restriction of two sets of pulleys, outside cable roll-off pulley can not appear at the in-process of acting as go-between, thereby the influence is used, the operation effect of acting as go-between again, reduce frictional force, the work efficiency is improved, under the setting of ratchet and jack catch, prevent the pulley reversal, can avoid transmission cable to retrieve and drop, if effectively avoid sliding because of erectting personnel's error hand, when the grip is not enough, the cable can fall because of self gravity, influence the construction progress, fall to injure constructor by a crashing object even.
2. Under the arrangement of the bearing, when the power transmission lead is not perpendicular to the central axis of the pulley, the movable frame can rotate and adjust automatically, the power transmission lead is guaranteed to be perpendicular to the central axis of the pulley, resistance is reduced, the fixing bolt and the fixing block are used for fixing the mounting frame at a corresponding position, and the fixing bolt is rotated to drive the fixing block to firmly fix the mounting frame, so that the mounting frame cannot fall off after being stressed; under the arrangement of the guide rail and the travel groove, the movable frame can move in the mounting frame, so that the distance between the two groups of pulleys is adjusted, and power transmission conductors with different diameters can be clamped.
Drawings
Fig. 1 is a schematic perspective view of an auxiliary erecting tool for a power transmission line of the present invention;
fig. 2 is an exploded view of the auxiliary erecting tool for power transmission lines according to the present invention;
fig. 3 is a schematic structural view of a locking assembly in the auxiliary erecting tool for power transmission lines according to the present invention;
fig. 4 is a schematic structural view of a locking assembly in the auxiliary erecting tool for power transmission lines according to the present invention;
the corresponding relation between the names of the attachments and the numbers of the attached figures in the figure:
101. a mounting frame; 102. a protective cover; 103. a through groove; 104. a turntable; 105. a load bearing seat; 106. a stroke slot; 107. fixing the bolt; 108. a fixed block; 109. a hanging shaft; 110. a pulley; 111. a rubber ring; 112. a ratchet wheel; 113. an arc groove; 114. a deflector rod; 115. a jaw; 116. a torsion spring; 117. a guide rail; 118. fixing the clamping block; 119. buckling; 120. a movable clamping block; 121. clamping teeth; 122. adjusting the stud; 123. a limiting block; 124. a limiting groove; 125. a counter bore; 126. a bearing; 127. a rectangular groove; 128. a movable frame; 129. and fixing the shaft.
Detailed Description
In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the drawings in the embodiments of the present invention will be combined below to clearly and completely describe the technical solutions in the embodiments of the present invention.
The embodiment is as follows:
referring to fig. 1 and 2: the utility model provides a supplementary instrument of erectting of transmission line, including mounting bracket 101, the adjustable shelf 128 and hang and establish the subassembly, logical groove 103 has been seted up on mounting bracket 101, it is provided with adjustable shelf 128 in logical groove 103, all be provided with pulley 110 on mounting bracket 101 and the adjustable shelf 128, all be provided with ratchet 112 on two sets of pulley 110, two sets of ratchet 112 revolve to opposite, all be provided with protection casing 102 on mounting bracket 101 and the adjustable shelf 128, two sets of ratchet 112 set up respectively in two sets of protection casings 102, all be provided with fixed axle 129 on mounting bracket 101 and the adjustable shelf 128, all the activity is provided with jack catch 115 on two sets of fixed axle 129, two sets of jack catch 115 block respectively establishes on two sets of ratchet 112, all the cover is equipped with torsional spring 116 on two sets of fixed axle 129, two sets of torsional spring 116 set up respectively on two sets of jack catch 115, mounting bracket 101 top is provided with on hanging axle 109 and hangs and establishes the subassembly, it includes bearing seat 105 to hang and establish the subassembly.
In the process of line erection, the transmission conductor is prevented from contacting the ground or crossed obstacles such as charged bodies, crops, trees, buildings and the like between two iron towers, and the conductor needs to be tensioned by equipment; however, the currently used wire hanging device has no moving mechanism, so that the working difficulty is increased due to too large friction force during wire pulling operation, and even the transmission conductor is abraded due to friction, under the arrangement of the two groups of pulleys 110, the cable to be erected is arranged between the two groups of pulleys 110 in a penetrating manner, and then the wire pulling operation is performed, so that the friction force is reduced, and the working efficiency is improved; because the cable is erect the high altitude construction, the cable is often thicker, and its quality is heavier, if because of erect personnel's error hand smooth, when the grip is not enough, the cable can fall because of self gravity, influences the construction progress, falls to injure constructor by a crashing object even, and owing to wear to establish transmission of electricity cable and lean on pulley 110 rotatory transmission cable between two sets of pulleys 110, under ratchet 112 and jack catch 115's setting, prevent pulley 110 reversal, can avoid transmission of electricity cable to retrieve and drop.
During the use, establish the subassembly through hanging and fix this instrument in required position, pass the cable again between group's pulley 110, carry out the work of acting as go-between again, easy operation, convenient to use.
Referring to fig. 2, a counter bore 125 is formed in the bearing seat 105, a bearing 126 is disposed in the counter bore 125, the bearing 126 is disposed on the hanging shaft 109, a rectangular groove 127 is formed in the bearing seat 105, a fixing bolt 107 is threadedly connected to the hanging shaft 109, a fixing block 108 is disposed at one end of the fixing bolt 107, a limit block 123 is disposed on the fixing block 108, a limit groove 124 is formed in the rectangular groove 127, and the limit block 123 is disposed in the limit groove 124.
The transmission line is under pulley 110's traction, will remove between two adjacent iron towers, if pulley 110 can not the automatic adjustment direction, when transmission line and pulley 110 axis out of plumb appear, it is big to act as go-between this moment also can appear frictional force, lead to acting as go-between the difficulty, under bearing 126's setting, when transmission line and pulley 110 axis out of plumb appear, the adjustable shelf 128 can rotate the adjustment by oneself, guarantee that transmission line is perpendicular with pulley 110 axis, the resistance is reduced, fixing bolt 107 and fixing block 108's effect is fixed mounting bracket 101 in corresponding position, rotatory fixing bolt 107 drives fixing block 108 and firmly fixes mounting bracket 101, make it can not drop after the atress.
Referring to fig. 2, a guide rail 117 is disposed in the through groove 103, a stroke groove 106 is disposed on the movable frame 128, the guide rail 117 is disposed in the stroke groove 106, an adjusting stud 122 is connected to the mounting frame 101 by a thread, one end of the adjusting stud 122 is movably disposed on the movable frame 128, and a turntable 104 is disposed at the other end of the adjusting stud 122.
In order to meet the installation of power transmission conductors with different diameters, the guide rails 117 and the travel slots 106 are arranged so that the movable frame 128 can move in the mounting frame 101 to adjust the distance between the two sets of pulleys 110, thereby clamping power transmission conductors with different diameters. The specific operation is that the turntable 104 is rotated to increase the distance between the two groups of pulleys 110, the power transmission conductor penetrates between the two groups of pulleys 110, and then the turntable 104 is rotated to control the movable frame 128 to be close to the mounting frame 101, so that the distance between every two groups of pulleys 110 is gradually reduced until the power transmission conductor is clamped.
Referring to fig. 2, a locking assembly is disposed on the mounting frame 101, the locking assembly includes a fixed clamping block 118, a movable clamping block 120 is movably disposed on the fixed clamping block 118, a buckle 119 is disposed on the fixed clamping block 118, a latch 121 is disposed on the movable clamping block 120, the buckle 119 is clamped on the latch 121, and an adjusting stud 122 is disposed between the fixed clamping block 118 and the movable clamping block 120. The locking assembly is used for preventing the adjusting stud 122 from loosening and rotating due to larger stress of the movable frame 128 in the process of erecting the stay wire, if the movable frame 128 loosens, the clamping force of the two groups of pulleys 110 is reduced, and at the moment, after the movable frame 128 loosens the hand, the power transmission conductor can fall due to self-gravity. When needing to adjust, open locking Assembly for adjust the double-screw bolt 122 can rotate, thereby adjust, after adjusting corresponding position, establish buckle 119 card on latch 121, locking Assembly will adjust double-screw bolt 122 this moment and hug closely, adjust double-screw bolt 122 just can not be rotatory by oneself.
Referring to fig. 2, the two sets of jaws 115 are provided with a shift lever 114, the two sets of protective covers 102 are provided with arc grooves 113, and the two sets of shift levers 114 are respectively disposed in the arc grooves 113. The arrangement of the shift lever 114 and the arc groove 113 enables the shift lever 114 to move in the arc groove 113 of the arc groove 113, thereby controlling the pawl 115 to disengage from the ratchet wheel 112, and enabling the ratchet wheel 112 to rotate reversely.
In some embodiments, referring to fig. 2, two sets of pulleys 110 are provided with rubber rings 111. The rubber ring 111 serves to increase the friction of the pulley 110 while avoiding direct hard contact of the power conductor with the pulley 110.
The utility model discloses an operating procedure does:
firstly, the hanging component fixes the tool at a required position, the rotating turntable 104 is adjusted to increase the distance between two groups of pulleys 110, then a power transmission wire penetrates between the two groups of pulleys 110, and then the rotating turntable 104 is rotated to control the movable frame 128 to be close to the mounting frame 101, so that the distance between the two groups of pulleys 110 is gradually reduced until the power transmission wire is clamped.
The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention, and various modifications and changes may be made by those skilled in the art. Any modification, equivalent replacement, or improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (6)

1. The utility model provides an auxiliary erection tool of transmission line, includes mounting bracket (101), adjustable shelf (128) and hangs and establishes the subassembly, its characterized in that: logical groove (103) have been seted up on mounting bracket (101), be provided with adjustable shelf (128) in logical groove (103), mounting bracket (101) with all be provided with pulley (110), two sets of on adjustable shelf (128) all be provided with ratchet (112), two sets of ratchet (112) revolve to opposite, mounting bracket (101) with all be provided with protection casing (102), two sets of on adjustable shelf (128) ratchet (112) set up respectively two sets of in protection casing (102), mounting bracket (101) with all be provided with fixed axle (129) on adjustable shelf (128), two sets of all the activity is provided with jack catch (115) on fixed axle (129), two sets of jack catch (115) are blocked respectively and are established two sets of on ratchet (112), two sets of all the cover is equipped with torsional spring (116) on fixed axle (129), two sets up respectively on jack catch (115), mounting bracket (101) top is provided with hanger shaft (109) be provided with on hanger shaft (109) and hang and establish the subassembly, it includes bearing seat (105) to hang the subassembly.
2. The auxiliary erection tool for power transmission lines of claim 1, wherein: the bearing device is characterized in that a counter bore (125) is formed in the bearing seat (105), a bearing (126) is arranged in the counter bore (125), the bearing (126) is arranged on the hanging shaft (109), a rectangular groove (127) is formed in the bearing seat (105), a fixing bolt (107) is connected to the hanging shaft (109) through threads, a fixing block (108) is arranged at one end of the fixing bolt (107), a limiting block (123) is arranged on the fixing block (108), a limiting groove (124) is formed in the rectangular groove (127), and the limiting block (123) is arranged in the limiting groove (124).
3. The auxiliary erection tool for power transmission lines of claim 1, wherein: the improved structure is characterized in that a guide rail (117) is arranged in the through groove (103), a stroke groove (106) is formed in the movable frame (128), the guide rail (117) is arranged in the stroke groove (106), an adjusting stud (122) is connected to the mounting frame (101) in a threaded manner, one end of the adjusting stud (122) is movably arranged on the movable frame (128), and a turntable (104) is arranged at the other end of the adjusting stud (122).
4. Auxiliary erection tool of transmission line according to claim 3, characterized in that: be provided with locking Assembly on mounting bracket (101), locking Assembly includes fixed clamp splice (118), the activity is provided with movable clamp splice (120) on fixed clamp splice (118), be provided with buckle (119) on fixed clamp splice (118), be provided with latch (121) on movable clamp splice (120), buckle (119) card is established on latch (121), adjust double-screw bolt (122) and be located fixed clamp splice (118) with between movable clamp splice (120).
5. The auxiliary erection tool for power transmission lines of claim 1, wherein: the two groups of clamping jaws (115) are respectively provided with a deflector rod (114), the two groups of protective covers (102) are respectively provided with an arc groove (113), and the two groups of deflector rods (114) are respectively arranged in the arc grooves (113).
6. The auxiliary erection tool for power transmission lines of claim 1, wherein: rubber rings (111) are arranged on the two groups of pulleys (110).
CN202222656656.1U 2022-10-10 2022-10-10 Auxiliary erecting tool for power transmission line Expired - Fee Related CN218449190U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222656656.1U CN218449190U (en) 2022-10-10 2022-10-10 Auxiliary erecting tool for power transmission line

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222656656.1U CN218449190U (en) 2022-10-10 2022-10-10 Auxiliary erecting tool for power transmission line

Publications (1)

Publication Number Publication Date
CN218449190U true CN218449190U (en) 2023-02-03

Family

ID=85085452

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222656656.1U Expired - Fee Related CN218449190U (en) 2022-10-10 2022-10-10 Auxiliary erecting tool for power transmission line

Country Status (1)

Country Link
CN (1) CN218449190U (en)

Similar Documents

Publication Publication Date Title
CN110797801B (en) Electric power construction tensioner bullwheel
CN220830274U (en) Be used for municipal works circuit to reform transform support
CN218449190U (en) Auxiliary erecting tool for power transmission line
CN114104848A (en) Lightning protection detection automatic take-up device for construction engineering
CN116613676B (en) Tightening device for installation of electric wires and cables
CN113363865B (en) Insulating operation fixing device of line pole tower tablet
CN210680463U (en) Clamping line type contact net elastic sling installation device
CN112909828B (en) Cable tensioning device for electric power paying-off
CN214590228U (en) Cable laying draw gear that cable construction used
DE10033517B4 (en) Cable laying machine
CN113156286A (en) Adjustable enclasping device of strain insulator string detection robot
CN209621201U (en) A kind of electric power overhead insulating ladder with antiskid function
CN208274952U (en) Pole climber
CN110706872A (en) Electric power insulator convenient to installation
CN221787961U (en) Be arranged in steel construction lifeline fixing device
CN220223157U (en) Tensioning structure
LU500204B1 (en) bike holder
CN220543654U (en) Automatic ground wire picking device for high-speed cable bundles
CN221552676U (en) Auxiliary erection tool for power transmission line
CN214337363U (en) Cable body positioning device for high-voltage cable outdoor terminal
CN220245145U (en) Cable winding device
CN221688126U (en) Electric overhead transmission line overhauling device
CN118343590B (en) Auxiliary lifting device for electric power angle steel tower
CN215067066U (en) Adjustable enclasping device of strain insulator string detection robot
CN219394230U (en) Electrical and intelligent circuit laying device for building

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20230203