CN218438139U - Overhanging scaffold on steel beam - Google Patents

Overhanging scaffold on steel beam Download PDF

Info

Publication number
CN218438139U
CN218438139U CN202222237969.3U CN202222237969U CN218438139U CN 218438139 U CN218438139 U CN 218438139U CN 202222237969 U CN202222237969 U CN 202222237969U CN 218438139 U CN218438139 U CN 218438139U
Authority
CN
China
Prior art keywords
scaffold
length
cantilever
rods
welded
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222237969.3U
Other languages
Chinese (zh)
Inventor
崔建军
崔大楷
安冬
杨超凡
李丽
韩广帅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Shougang Construction Group Co Ltd
Original Assignee
Beijing Shougang Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Shougang Construction Group Co Ltd filed Critical Beijing Shougang Construction Group Co Ltd
Priority to CN202222237969.3U priority Critical patent/CN218438139U/en
Application granted granted Critical
Publication of CN218438139U publication Critical patent/CN218438139U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A40/00Adaptation technologies in agriculture, forestry, livestock or agroalimentary production
    • Y02A40/10Adaptation technologies in agriculture, forestry, livestock or agroalimentary production in agriculture
    • Y02A40/25Greenhouse technology, e.g. cooling systems therefor

Landscapes

  • Movable Scaffolding (AREA)

Abstract

A cantilever scaffold on a steel beam belongs to the field of frame structure construction and comprises a cantilever rod 1, upright rods, bolts, supporting rods, screws, transverse plates and vertical plates, wherein the two upright rods and the cantilever rod are fixed through the two bolts, bolt holes are arranged at intervals of 300mm in the vertical direction of the upright rods, and the distance between 2 of the two upright rods is 500mm; two ends of the supporting rod are welded with the bottom ends of the two vertical rods; the vertical plate is welded with the tail end of the cantilever rod; the transverse plate is welded with the vertical plate; the screw passes through the transverse plate to be fixed. The advantage lies in. The equipment is simple, convenient operation, and simple and practical has avoided the use of a large amount of scaffold pipes and manpower, and convenient and fast has reduced construction cost.

Description

Overhanging scaffold on steel beam
Technical Field
The utility model belongs to the technical field of the frame construction, especially, a scaffold frame of encorbelmenting on girder steel is provided.
Background
When a frame structure is constructed, for the construction of a secondary structure under a frame steel beam, the operation construction is generally carried out in a mode of erecting through long through high scaffolds from two sides of a secondary structure wall, and the defects of the mode include that firstly, a large number of scaffold pipes are needed for erecting the scaffolds, and a large amount of manpower is consumed; secondly, a large amount of manpower is needed to remove the scaffold after the scaffold is used, and the overall construction cost is high.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a scaffold frame of encorbelmenting on girder steel has overcome and has used a large amount of scaffold pipes, consumes a large amount of manpowers, the higher scheduling problem of overall construction cost.
The utility model discloses to encorbelment scaffold frame and frame girder steel pass through the fix with screw on the diaphragm. Every 3m sets up a set of scaffold that encorbelments, later places the springboard on the die-pin of scaffold that encorbelments and fix. And then an operator stands on the springboard to carry out masonry construction on the secondary structure below the frame steel beam. When the scaffold frame of encorbelmenting is moved to needs, only need not hard up screw, can make the scaffold frame of encorbelmenting remove about, satisfy the operation construction demand.
The utility model comprises a cantilever rod 1, upright rods 2, bolts 3, a supporting rod 4, screws 5, a transverse plate 6 and a vertical plate 7 which are combined for use, wherein the two upright rods 2 and the cantilever rod 1 are fixed by the two bolts 3, bolt holes are arranged at intervals of 300mm in the vertical direction of the upright rods 2, and the distance between the two upright rods 2 is 500mm; two ends of the supporting rod 4 are welded with the bottom ends of the two upright rods 2; the vertical plate 7 is welded with the tail end of the cantilever rod 1; the transverse plate 6 is welded with the vertical plate 7; the screw 5 is fixed through the transverse plate (see fig. 1, 2).
When the cantilever scaffold is used, the cantilever scaffold and the frame steel beam 9 are fixed through the screws 5 on the transverse plate 6. Every 3m is provided with a group of overhanging scaffolds, and then the springboard 8 is placed on the support rod 4 of the overhanging scaffold and fixed. The operator then stands on the gangway 8 to masonry the secondary structure 10 under the frame steel beams. When the scaffold frame of encorbelmenting is moved to needs, only need not hard up screw 5, can make the scaffold frame of encorbelmenting remove about, satisfy the operation construction demand. After construction is finished, the dismantled cantilever scaffold can be repeatedly recycled (fig. 3 and 4).
This scaffold frame of encorbelmenting assembles simply, convenient operation, and simple and practical has avoided the use of a large amount of scaffold pipes and manpower, and convenient and fast has reduced construction cost, has obtained good economic benefits for the company.
Drawings
Fig. 1 is a front view of the overhanging scaffold.
Fig. 2 is a side view of the overhanging scaffold.
Fig. 3 is a front view of the cantilever scaffold.
Fig. 4 is a side view of the use of the overhanging scaffold.
In the figure, a cantilever rod 1, a vertical rod 2, a bolt 3, a supporting rod 4, a screw 5, a transverse plate 6, a vertical plate 7, a springboard 8, a frame steel beam 9 and a secondary structure 10.
Detailed Description
Fig. 1-4 show a specific embodiment of the present invention. The present invention will be further explained with reference to the accompanying drawings.
The utility model comprises a cantilever rod 1, upright rods 2, bolts 3, a supporting rod 4, screws 5, a transverse plate 6 and a vertical plate 7 which are combined for use, wherein the two upright rods 2 and the cantilever rod 1 are fixed by the two bolts 3, bolt holes are arranged at intervals of 300mm in the vertical direction of the upright rods 2, and the distance between the two upright rods 2 is 500mm; two ends of the supporting rod 4 are welded with the bottom ends of the two upright rods 2; the vertical plate 7 is welded with the tail end of the cantilever rod 1; the transverse plate 6 is welded with the vertical plate 7; the screw 5 is fixed through the transverse plate.
Wherein, the cantilever bar 1 is formed by processing a square tube with the cross section size (length and width) of 120 and 120mm and the length is 1000mm; the upright rod 2 is formed by processing a square tube with the cross section size (length and width) of 100 x 100mm, and the length is 3000mm; the diameter of the bolt 3 is 20mm, and the length of the bolt is 240mm; the supporting rod 4 is formed by processing a square tube with the cross section size (length and width) of 80 and 80mm, and the length is 500mm; the diameter of the screw 5 is 16mm, and the length is 60mm; the transverse plate 6 is formed by processing a 20mm thick steel plate, and the size is 200 x 200mm (length x width); the vertical plate 7 is machined from a 20mm thick steel plate and has a dimension (length and width) of 200 × 180mm.
When the cantilever scaffold is used, the cantilever scaffold and the frame steel beam 9 are fixed through the screws 5 on the transverse plate 6. Every 3m sets up a set of scaffold that encorbelments, later places springboard 8 on the die-pin 4 of scaffold that encorbelments and fix. The operator then stands on the gangway 8 to masonry the secondary structure 10 under the frame steel beams. When the scaffold frame of encorbelmenting is moved to needs, only need not hard up screw 5, can make the scaffold frame of encorbelmenting remove about, satisfy the operation construction demand. After the construction is finished, the dismantled cantilever scaffold can be repeatedly recycled.
When office building frame construction constructs, to the secondary structure wall construction under the frame girder steel, the scaffold of encorbelmenting on having taken a girder steel carries out the operation construction, has gained better effect. The cantilever scaffold is used in a combined manner, two upright rods and a cantilever rod are fixed through two bolts, bolt holes are arranged every 300mm in the vertical direction of the upright rods, and the distance between the two upright rods is 500mm; two ends of the supporting rod are welded with the bottom ends of the two vertical rods; the vertical plate is welded with the tail end of the cantilever rod; the transverse plate is welded with the vertical plate; the screw passes through the transverse plate to be fixed. During the use, will encorbelment scaffold frame and frame girder steel and pass through the fix with screw on the diaphragm. Every 3m sets up a set of scaffold that encorbelments, later places the springboard on the die-pin of scaffold that encorbelments and fix. And then an operator stands on the springboard to carry out masonry construction on the secondary structure below the frame steel beam. When the scaffold frame of encorbelmenting is moved to needs, only need not hard up screw, can make the scaffold frame of encorbelmenting remove about, satisfy the operation construction demand. After the construction is finished, the dismantled cantilever scaffold can be repeatedly recycled. This scaffold frame of encorbelmenting assembles simply, convenient operation, and simple and practical has avoided the use of a large amount of scaffold pipes and manpower, and convenient and fast has reduced construction cost.

Claims (2)

1. A cantilever scaffold on a steel beam is characterized by comprising cantilever rods (1), upright rods (2), bolts (3), support rods (4), screws (5), transverse plates (6) and vertical plates (7), wherein the two upright rods (2) and the cantilever rods (1) are fixed through the two bolts (3), bolt holes are arranged in the vertical direction of the upright rods (2) at intervals of 300mm, and the distance between the two upright rods (2) is 500mm; two ends of the supporting rod (4) are welded with the bottom ends of the two upright rods (2); the vertical plate (7) is welded with the tail end of the cantilever rod (1); the transverse plate (6) is welded with the vertical plate (7); the screw (5) passes through the transverse plate for fixing.
2. The overhanging scaffold on steel beam according to claim 1, characterized in that the overhanging pole (1) is made of square tube with cross section size length 120 x 120mm wide, length 1000mm; the upright rod (2) is formed by processing a square tube with the cross section size of 100X 100mm in length and width, and the length is 3000mm; the diameter of the bolt (3) is 20mm, and the length of the bolt is 240mm; the support rod (4) is formed by processing a square tube with the cross section size of 80X 80mm in length and width, and the length is 500mm; the diameter of the screw (5) is 16mm, and the length of the screw is 60mm; the transverse plate (6) is formed by processing a 20mm thick steel plate, and the length and the width of the transverse plate are 200 and 200mm; the vertical plate (7) is machined from a steel plate with the thickness of 20mm, and the length and the width of the vertical plate are 200 and 180mm.
CN202222237969.3U 2022-08-24 2022-08-24 Overhanging scaffold on steel beam Active CN218438139U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222237969.3U CN218438139U (en) 2022-08-24 2022-08-24 Overhanging scaffold on steel beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222237969.3U CN218438139U (en) 2022-08-24 2022-08-24 Overhanging scaffold on steel beam

Publications (1)

Publication Number Publication Date
CN218438139U true CN218438139U (en) 2023-02-03

Family

ID=85096331

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222237969.3U Active CN218438139U (en) 2022-08-24 2022-08-24 Overhanging scaffold on steel beam

Country Status (1)

Country Link
CN (1) CN218438139U (en)

Similar Documents

Publication Publication Date Title
CN101974974A (en) Support device for template for construction of steel structure concrete floor slab
CN201943344U (en) Supporting device of template used in the construction of steel structure concrete floor
CN218438139U (en) Overhanging scaffold on steel beam
CN215858982U (en) Follow-on corner support of encorbelmenting
CN214658788U (en) Retractable's concrete floor formwork structure
CN213538700U (en) Supporting structure for concrete construction of cantilever end of steel-concrete composite beam bridge
CN211846865U (en) Device for hoisting corrugated pipe
CN216587631U (en) Fixing support of platform edge horizontal safety net
CN209741674U (en) Civil engineering cement pouring device
CN218440997U (en) Temporary fixing support for combined installation of stand pipes
CN217431951U (en) Wet electrode special for flue gas of flame cleaning machine
CN214658657U (en) Operation outrigger on girder steel
CN219157937U (en) Steel construction support column convenient to dismantle
CN209585608U (en) Quick-release and quick-support structure for truss floor support plate
CN220622974U (en) Concrete pump pipe fixing device
CN215716332U (en) Building curtain wall with strong wind resistance level capability
CN220565773U (en) Device for improving overall safety of steel pipe fastener
CN215516468U (en) Hoisting support on frame beam
CN219684334U (en) Bracket for dragging welding handle line on frame steel beam
CN218467099U (en) Post-cast strip template jacking device for supporting system
CN218970616U (en) Assembled steel bar truss template
CN220202466U (en) Assembled bent cap limb protection device
CN216583969U (en) Top iron of pipe jacking
CN214301272U (en) Simple jack mounting and dismounting frame used in prestress tensioning
CN215053284U (en) Novel independent support of post-cast strip for bearing stress by using original structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant