CN218437066U - Positioning device is pour to power transmission and transformation circuit shaft tower basis - Google Patents

Positioning device is pour to power transmission and transformation circuit shaft tower basis Download PDF

Info

Publication number
CN218437066U
CN218437066U CN202222576803.4U CN202222576803U CN218437066U CN 218437066 U CN218437066 U CN 218437066U CN 202222576803 U CN202222576803 U CN 202222576803U CN 218437066 U CN218437066 U CN 218437066U
Authority
CN
China
Prior art keywords
plate
arc
lower support
power transmission
displacement frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222576803.4U
Other languages
Chinese (zh)
Inventor
毛佳琦
贾生普
李浩飞
方宽
曹晓海
王顺阳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Henan Engineering Co Ltd
Original Assignee
PowerChina Henan Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Henan Engineering Co Ltd filed Critical PowerChina Henan Engineering Co Ltd
Priority to CN202222576803.4U priority Critical patent/CN218437066U/en
Application granted granted Critical
Publication of CN218437066U publication Critical patent/CN218437066U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The utility model discloses a positioner is pour to power transmission and transformation circuit shaft tower basis, including cardboard and bottom plate, be connected with the cardboard perpendicularly at the bottom plate left end, be provided with the arc connecting plate in the cardboard outside, and be provided with the first subassembly that compresses tightly at arc connecting plate top, be provided with the locating plate at the bottom plate right-hand member, and rotate at locating plate top and be connected with the displacement frame, and the displacement frame supports through the ejector pin, is provided with the second at displacement frame top and compresses tightly the subassembly, and the bottom plate all is in the same place through location borer and ground fixed connection with the locating plate. The utility model discloses a set up the arc connecting plate in the cardboard outside to set up the first subassembly that compresses tightly at arc connecting plate top, the pipeline of being convenient for is together fixed with basic formwork, has improved holistic stability, is favorable to going on smoothly of concrete placement construction.

Description

Positioning device is pour to power transmission and transformation circuit shaft tower basis
The technical field is as follows:
the utility model relates to a pipeline positioner, in particular to positioner is pour to power transmission and transformation circuit tower basis.
Background art:
when the tower foundation pouring construction is carried out in a region with higher terrain, large machines cannot directly reach construction points due to the influence of the terrain, so that workers can set up chutes or pouring pipes to carry out concrete pouring construction; when the local situation is in a climbing state, the concrete at the lower part needs to be transported to the higher part, so that the pouring construction can be carried out only by laying the pouring pipe, and during the period, when the pouring construction is carried out by using the pouring pipe, the front end (upper end) of the pouring pipe is easy to slide and is not easy to be fixed, thereby influencing the smooth operation of the concrete pouring construction.
The utility model has the following contents:
the utility model discloses the technical problem that will solve is: overcome prior art's not enough, provide a power transmission and transformation circuit shaft tower foundation and pour positioner, can be with the front end of pouring the pipe near construction point, the going on smoothly of the concrete placement construction of being convenient for.
The technical scheme that this practicality was adopted for solving technical problem is:
the utility model provides a positioner is pour to power transmission and transformation circuit tower basis, includes cardboard and bottom plate, the left end of bottom plate is connected with the cardboard perpendicularly, the outer wall of cardboard is provided with the screw rod to be connected with the arc connecting plate on the screw rod, the top of arc connecting plate is provided with the first subassembly that compresses tightly, the right-hand member of bottom plate is provided with the locating plate, it is connected with the displacement frame to rotate on the locating plate to fix through the bolt, the top of displacement frame is provided with the second and compresses tightly the subassembly, the right side of displacement frame is provided with the ejector pin, and the ejector pin inserts and establish in the sleeve to fix through the bolt, the sleeve sets up on the bottom plate perpendicularly.
The clamping plate is of a U-shaped structure and is matched with the radian of the basic formwork.
The bottom plate is fixedly connected with the ground through a positioning drill rod, and the positioning plate stretches across the bottom plate and is fixedly connected with the ground through the positioning drill rod.
And a groove is dug in the right side surface of the displacement frame and corresponds to the position of the ejector rod.
The two screws are vertically distributed, and the arc-shaped connecting plate is sleeved on the screws, so that the inner wall of the arc-shaped connecting plate is tightly attached to the outer wall of the clamping plate and is fixed by the matched nuts; the top end of the arc-shaped connecting plate is positioned above the top of the clamping plate.
The first compression assembly is composed of a first upper pressing plate and a first lower support plate, the first lower support plate is arranged at the top of the arc-shaped connecting plate, first supporting columns are arranged at two ends of the top of the first lower support plate, the first upper pressing plate is arranged above the first lower support plate, two ends of the first upper pressing plate are sleeved on the first supporting columns and fixed through matched nuts, and the bottom surface of the first lower support plate and the top surface of the first upper pressing plate are distributed in an arc-shaped groove shape.
The second pressing assembly is composed of a second lower support plate and a second upper pressing plate, the second upper pressing plate is located above the second lower support plate, the bottom surface of the second upper pressing plate and the top surface of the second lower support plate are distributed in an arc groove shape, two ends of the second lower support plate are fixedly connected with the inner wall of the displacement frame, second support columns are arranged at two ends of the top surface of the second lower support plate, two ends of the second upper pressing plate are sleeved on the second support columns and fixed through nuts matched with the second support columns.
The utility model discloses an actively beneficial effect is:
1. the utility model discloses an outside at the cardboard sets up the arc connecting plate to set up the first subassembly that compresses tightly at arc connecting plate top, can fix the tip of concrete placement pipe, when avoiding pouring the construction, pour the condition that the landing appears in the pipe.
2. The utility model discloses a set up the displacement frame at the bottom plate right-hand member to set up the second at displacement frame top and compress tightly the subassembly, can provide a transition region for when pouring on the half slope manage to the horizontal ground crooked, improved holistic stability, convenient to use, easy operation.
Description of the drawings:
FIG. 1 is a schematic view of the present invention;
FIG. 2 is a schematic structural view of the bottom plate and the clamping plate of the present invention;
FIG. 3 is a schematic structural view of the positioning plate of the present invention;
FIG. 4 is a schematic structural view of the positioning pin of the present invention;
wherein: the device comprises a clamping plate 1, a bottom plate 2, a positioning drill 3, a screw rod 4, an arc-shaped connecting plate 5, a first lower support plate 6, a first support 601, a first upper pressing plate 7, a positioning plate 8, a displacement frame 9, a groove 901, a second lower support plate 10, a second upper pressing plate 11, a second support 101, an ejector rod 12, a sleeve 13 and a basic formwork A.
The specific implementation mode is as follows:
the invention will be further explained and explained with reference to the drawings:
an embodiment, refer to fig. 1-4, a positioner is pour to power transmission and transformation circuit tower foundation, including cardboard 1 and bottom plate 2, be connected with cardboard 1 perpendicularly at the left end of bottom plate 2, be provided with screw rod 4 at the outer wall of cardboard 1, and be connected with arc connecting plate 5 on screw rod 4, be provided with the first subassembly that compresses tightly at the top of arc connecting plate 5, right-hand member at bottom plate 2 is provided with locating plate 8, it is connected with displacement frame 9 to rotate on locating plate 8, and fix through the bolt, be provided with the second at the top of displacement frame 9 and compress tightly the subassembly, be provided with ejector pin 12 on displacement frame 9's right side, and ejector pin 12 inserts and establishes in sleeve 13, and fix through the bolt, sleeve 13 sets up perpendicularly on bottom plate 2.
In the above description, the middle part of the positioning plate is provided with the support block, the displacement frame is rotatably connected with the support block, and the outside of the support block is provided with the bolt for fixing the displacement frame; when the clamping plate is inserted on the basic formwork A, the bottom plate is tightly attached to the horizontal ground and is fixedly connected with the ground through the positioning drill rod.
The clamping plate 1 is of a U-shaped structure and is matched with the radian of the basic formwork A.
The bottom plate 2 is fixedly connected with the ground through the positioning drill rod 3, and the positioning plate 8 stretches across the bottom plate 2 and is fixedly connected with the ground through the positioning drill rod 3.
A groove 901 is dug on the right side surface of the displacement frame 9, and the groove 901 corresponds to the position of the mandril 12.
The two screws 4 are vertically distributed, the arc-shaped connecting plate 5 is sleeved on the screws 4, so that the inner wall of the arc-shaped connecting plate 5 is tightly attached to the outer wall of the clamping plate 1 and is fixed through matched nuts; the top end of the arc-shaped connecting plate 5 is positioned above the top of the clamping plate 1.
The first compressing assembly is composed of a first upper pressing plate 7 and a first lower supporting plate 6, the first lower supporting plate 6 is arranged at the top of the arc-shaped connecting plate 5, first supporting columns 601 are arranged at two ends of the top of the first lower supporting plate 6, the first upper pressing plate 7 is arranged above the first lower supporting plate 6, two ends of the first upper pressing plate 7 are sleeved on the first supporting columns 601 and are fixed through matched nuts, and the bottom surface of the first lower supporting plate 6 and the top surface of the first upper pressing plate 7 are distributed in an arc-shaped groove shape.
The second compresses tightly the subassembly and comprises extension board 10 and second top board 11 under the second, and second top board 11 is located extension board 10's under the second top board, and the bottom surface of second top board 11 all is arc recess form with extension board 10's top surface and distributes under the second, and extension board 10's both ends and displacement frame 9's inner wall fixed connection are in the same place under the second to be provided with second pillar 101 at the both ends of extension board 10 top surface under the second, and the both ends cover of second top board 11 is established on second pillar 101, and fix through the assorted nut.
In the above description, the card 1 is inserted on the base formwork a, so that the distance between the inner walls of the card 1 satisfies: can be inserted on the basic formwork A.
In the above description, the end portions of the positioning plate and the bottom plate are respectively provided with through holes, and the positioning drill rod is inserted into the through holes, so that the bottom plate and the ground, and the positioning plate and the ground can be fixed on the ground.
In the above description, the lower ends of the positioning pins are distributed in a tapered shape.
In the above description, the push rod provides a strong support for the displacement frame in the inclined state, and the overall stability is improved, so that the extension height of the push rod can be determined according to the construction condition, and the push rod is fixed through the bolt outside the sleeve.
In the above description, the groove on the right side face of the displacement frame satisfies: the ejector rod can be propped in the groove.
In the above description, the right end of the bottom plate is located at a junction between the slope-shaped area and the ground level, and the pouring pipe is located at a junction between the climbing area and the flat ground, so that the pipe can be bent, and the pouring pipe can be transited when being bent towards the horizontal ground by adjusting the inclination angle of the displacement frame, so that the pouring pipe can be more stably installed at the first pressing assembly.
In the above description, the middle part of the bottom surface of the positioning plate is dug with a groove at a position corresponding to the bottom plate, so that when the positioning plate stretches across the bottom plate, two ends of the positioning plate are clung to the ground, and the middle part of the positioning plate is clung to the bottom plate.
The working principle is as follows:
before pouring, inserting the clamping plate on the foundation formwork A, fixing the bottom plate on the ground through a positioning drill rod, and then installing a positioning plate on the bottom plate;
the positioning plate is arranged on the bottom plate, two ends of the positioning plate are fixed with the ground through the positioning drill rods, the inclination angle of the displacement frame is adjusted, the casting pipe is prevented from being bent excessively, then the displacement frame is fixedly connected with the positioning plate through bolts outside the positioning plate, and meanwhile, the height of the ejector rod is adjusted to enable the ejector rod to be located in a groove in the right side face of the displacement frame, so that powerful support is provided for the displacement frame;
and the front end of the pouring pipe is sequentially fixed on the second pressing component and the first pressing component, then the arc-shaped connecting plate is sleeved on the screw rod and is fixed through the bolt, and at the moment, the pouring pipe is fixed with the foundation formwork.
After the steps are set, concrete pouring construction can be carried out.
The utility model discloses a set up the displacement frame, can provide a transition district when crooked to level ground according to domatic pipeline, through setting up the arc connecting plate in the cardboard outside to set up the first subassembly that compresses tightly at arc connecting plate top, the pipeline of being convenient for is together fixed with basic formwork, has improved holistic stability, convenient to use, and easy operation is favorable to going on smoothly of concrete placement construction.

Claims (7)

1. The utility model provides a positioner is pour to power transmission and transformation circuit tower basis, includes cardboard (1) and bottom plate (2), its characterized in that: the left end of bottom plate (2) is connected with cardboard (1) perpendicularly, the outer wall of cardboard (1) is provided with screw rod (4) to be connected with arc connecting plate (5) on screw rod (4), the top of arc connecting plate (5) is provided with the first subassembly that compresses tightly, the right-hand member of bottom plate (2) is provided with locating plate (8), it is connected with displacement frame (9) to rotate on locating plate (8) to fix through the bolt, the top of displacement frame (9) is provided with the second and compresses tightly the subassembly, the right side of displacement frame (9) is provided with ejector pin (12), and ejector pin (12) insert and establish in sleeve (13) to fix through the bolt, sleeve (13) set up perpendicularly on bottom plate (2).
2. The power transmission and transformation line tower foundation pouring positioning device as claimed in claim 1, wherein: the clamping plate (1) is of a U-shaped structure and is matched with the radian of the basic formwork (A).
3. The power transmission and transformation line tower foundation pouring positioning device of claim 1, wherein: the bottom plate (2) is fixedly connected with the ground through a positioning drill rod (3), and the positioning plate (8) stretches across the bottom plate (2) and is fixedly connected with the ground through the positioning drill rod (3).
4. The power transmission and transformation line tower foundation pouring positioning device of claim 1, wherein: a groove (901) is dug in the right side face of the displacement frame (9), and the groove (901) corresponds to the position of the ejector rod (12).
5. The power transmission and transformation line tower foundation pouring positioning device of claim 1, wherein: the two screw rods (4) are vertically distributed, the arc-shaped connecting plate (5) is sleeved on the screw rods (4), so that the inner wall of the arc-shaped connecting plate (5) is tightly attached to the outer wall of the clamping plate (1) and is fixed through matched nuts; the top end of the arc-shaped connecting plate (5) is positioned above the top of the clamping plate (1).
6. The power transmission and transformation line tower foundation pouring positioning device of claim 1, wherein: the first pressing assembly is composed of a first upper pressing plate (7) and a first lower support plate (6), the first lower support plate (6) is arranged at the top of the arc-shaped connecting plate (5), first support columns (601) are arranged at two ends of the top of the first lower support plate (6), the first upper pressing plate (7) is arranged above the first lower support plate (6), two ends of the first upper pressing plate (7) are sleeved on the first support columns (601) and are fixed through matched nuts, and the bottom surface of the first lower support plate (6) and the top surface of the first upper pressing plate (7) are distributed in an arc-shaped groove shape.
7. The power transmission and transformation line tower foundation pouring positioning device of claim 1, wherein: the second pressing component is composed of a second lower support plate (10) and a second upper pressing plate (11), the second upper pressing plate (11) is located above the second lower support plate (10), the bottom surface of the second upper pressing plate (11) and the top surface of the second lower support plate (10) are distributed in an arc groove shape, two ends of the second lower support plate (10) are fixedly connected with the inner wall of the displacement frame (9), second supporting columns (101) are arranged at two ends of the top surface of the second lower support plate (10), two ends of the second upper pressing plate (11) are sleeved on the second supporting columns (101) and are fixed through matched nuts.
CN202222576803.4U 2022-09-28 2022-09-28 Positioning device is pour to power transmission and transformation circuit shaft tower basis Active CN218437066U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222576803.4U CN218437066U (en) 2022-09-28 2022-09-28 Positioning device is pour to power transmission and transformation circuit shaft tower basis

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222576803.4U CN218437066U (en) 2022-09-28 2022-09-28 Positioning device is pour to power transmission and transformation circuit shaft tower basis

Publications (1)

Publication Number Publication Date
CN218437066U true CN218437066U (en) 2023-02-03

Family

ID=85084482

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222576803.4U Active CN218437066U (en) 2022-09-28 2022-09-28 Positioning device is pour to power transmission and transformation circuit shaft tower basis

Country Status (1)

Country Link
CN (1) CN218437066U (en)

Similar Documents

Publication Publication Date Title
CN218437066U (en) Positioning device is pour to power transmission and transformation circuit shaft tower basis
CN218292823U (en) Building engineering template fixing assembly
CN216428331U (en) Assembled piping lane mid-board positioner
CN215564386U (en) Assembled structure of building main body engineering
CN214144112U (en) Accurate positioning and connecting device for beam column PC component
CN206859658U (en) A kind of adjustable slab form support system
CN110005249A (en) A kind of electric pole installation perfusion power construction mechanism based on high wind weather
CN212866363U (en) Portable inclined strut embedded part for prefabricated part with assembled structure
CN201610510U (en) Stepless fine-tuning template of plate-type ballastless track base concrete
CN212534119U (en) Road and bridge construction foundation ditch patching device
CN209040174U (en) The fixed device of pile body of indoor pile-soil model test
CN206752474U (en) A kind of foundation pit steel support bracket pre-embedded device
CN207484981U (en) Secondary structure vertical member concrete construction pours device
CN215107413U (en) Concrete pouring mould
CN221034293U (en) Pipeline connection supporting device
CN210529886U (en) Water supply and drainage engineering pipeline laying fixing device
CN214531162U (en) Concrete foundation embedded part pouring fixing device
CN215943301U (en) Prefabricated inspection well template
CN211693763U (en) Detachable push bench
CN219060848U (en) Inclined support structure for stable scaffold
CN110439273A (en) A kind of mold and installation method of telescopic production slope monitoring clump pedestal
CN216766527U (en) Building wall column base quick connecting device
CN220539322U (en) Combined supporting device
CN221030225U (en) Auxiliary device capable of improving grooving quality of diaphragm wall under complex round gravel stratum
CN216921332U (en) Combined aluminum alloy template for concrete composite foundation

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant