CN218434621U - Wallboard hoisting construction equipment - Google Patents

Wallboard hoisting construction equipment Download PDF

Info

Publication number
CN218434621U
CN218434621U CN202222814398.5U CN202222814398U CN218434621U CN 218434621 U CN218434621 U CN 218434621U CN 202222814398 U CN202222814398 U CN 202222814398U CN 218434621 U CN218434621 U CN 218434621U
Authority
CN
China
Prior art keywords
construction equipment
triangular
wallboard
lifting
triangular frames
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222814398.5U
Other languages
Chinese (zh)
Inventor
董健
吴丰波
付夏炜
崔羽
马进福
屈智伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction First Group Corp Ltd
Original Assignee
China Construction First Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction First Group Corp Ltd filed Critical China Construction First Group Corp Ltd
Priority to CN202222814398.5U priority Critical patent/CN218434621U/en
Application granted granted Critical
Publication of CN218434621U publication Critical patent/CN218434621U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses a wallboard hoist and mount construction equipment relates to construction technical field to solve the integrative design of current hoist and mount construction equipment, inconvenient carrying, and highly unable regulation can not adapt to the problem of different floor heights. A wallboard hoisting construction equipment comprises: the device comprises a support frame, a lifting traction device, a power lifting device, a traction rope and an operation platform; the supporting frame comprises two triangular frames which are arranged side by side at intervals, a first cross rod which detachably connects the top ends of the two triangular frames, and a second cross rod which detachably connects the bottom ends of the two triangular frames, and each triangular frame can be detachably connected; the power lifting device is connected with the lifting traction device in a sliding manner through a traction rope; the lifting traction device, the power lifting device and the operating platform are all arranged between the two triangular frames. The utility model provides a wallboard hoist and mount construction equipment all parts all can be dismantled, the turnover of being convenient for, but the different floor height of height-adjusting adaptation.

Description

Wallboard hoisting construction equipment
Technical Field
The utility model relates to a construction technical field especially relates to a wallboard hoist and mount construction equipment.
Background
Along with the development of social economy, more and more partition boards, external wall boards, roof boards and other functional boards mostly adopt AAC boards, but AAC boards are large in size and heavy in weight, so that the AAC boards are difficult to carry and hoist manually, and safety cannot be guaranteed. The existing hoisting construction equipment is generally designed integrally, cannot be disassembled and is inconvenient to carry. And because the diversification of building, the floor height of building also often is different, and current hoist and mount construction equipment can only adapt to the floor of a height, if need adapt to the floor of co-altitude not support frame of co-altitude still need be changed, increase construction cost.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a wallboard hoist and mount construction equipment for solve current hoist and mount construction equipment body design, inconvenient carrying, and highly unable regulation can not adapt to the problem of different floor heights.
In order to achieve the above object, the present invention provides the following technical solutions:
a wallboard hoisting construction equipment comprises: the device comprises a support frame, a lifting traction device, a power lifting device, a traction rope and an operation platform;
the supporting frame comprises two triangular frames which are arranged side by side at intervals, a first cross rod which detachably connects the top ends of the two triangular frames, and a second cross rod which detachably connects the bottom ends of the two triangular frames, and each triangular frame can be detachably connected;
the power lifting device is connected with the lifting traction device in a sliding manner through the traction rope; the lifting traction device and the power lifting device are arranged between the two triangular frames, and the height of the lifting traction device is higher than that of the first cross rod;
the operation platform is fixedly connected between the two triangular frames.
Optionally, a plurality of support rods are transversely detachably connected in any one of the triangular frames, and the distance between every two adjacent support rods is the same.
Optionally, a plurality of connecting rods can be detachably connected between the triangular frames, and the connecting rods are arranged in parallel between the first cross rod and the second cross rod and are adjacent to each other, so that the distance between the connecting rods is the same.
Optionally, a plurality of connecting rods can be detachably connected between the triangular frames, and the connecting rods are arranged in parallel between the first cross rod and the second cross rod and are adjacent to each other, so that the distance between the connecting rods is the same.
Optionally, the support frame further comprises a first support rod and a second support rod, and for any one triangular frame, the support rod is longitudinally detachably connected to one end of the bottom of the triangular frame; four universal wheels are installed to the support frame bottom, wherein two the universal wheels respectively with first bracing piece with the second bracing piece links to each other.
Optionally, the support frame is detachably connected through a cross fastener.
Optionally, the power lifting device is an electric winch, the traction rope is wound on the electric winch, one end of the traction rope bypasses a pulley of the lifting traction device, and a hook is installed at the end of the traction rope.
Optionally, a U-shaped clamping plate is mounted on a wheel shaft of the pulley.
Optionally, the first cross rod, the second cross rod and the triangular frame are all steel pipes.
Compared with the prior art, the utility model provides a wallboard hoist and mount construction equipment, include: the device comprises a support frame, a lifting traction device, a power lifting device, a traction rope and an operation platform; the supporting frame comprises two triangular frames which are arranged side by side at intervals, a first cross rod which detachably connects the top ends of the two triangular frames and a second cross rod which detachably connects the bottom ends of the two triangular frames, and each triangular frame can be detachably connected; the power lifting device is connected with the lifting traction device in a sliding manner through a traction rope; the lifting traction device and the power lifting device are arranged between the two triangular frames, and the height of the lifting traction device is higher than that of the first cross rod; the operation platform is fixedly connected between the two triangular frames. The detachable triangular frames are arranged side by side at intervals through the support frame, the first cross rods detachably connecting the top ends of the two triangular frames and the second cross rods detachably connecting the bottom ends of the two triangular frames enable the support frame to be detachably connected, so that all parts of the wallboard hoisting construction equipment can be detached, and the turnover of the wallboard hoisting construction equipment is facilitated; simultaneously because two triangle frames can dismantle the connection, can increase or reduce the height of triangle frame in order to adjust whole wallboard hoist and mount construction equipment through the mode of dismantling to adapt to the floor of co-altitude not. The lifting traction device and the power lifting device are arranged to realize the lifting work of the wallboard in the floor, the lifting height can be adjusted, and the operation platform is arranged to facilitate the operation of workers on the operation platform.
Drawings
The accompanying drawings, which are described herein, serve to provide a further understanding of the invention and constitute a part of this specification, and the exemplary embodiments and descriptions thereof are provided for explaining the invention without unduly limiting it. In the drawings:
figure 1 is now the utility model provides a pair of wallboard hoist and mount construction equipment's structure chart.
Reference numerals:
1-a support frame, 2-a lifting traction device, 3-a power lifting device, 4-a traction rope, 5-an operation platform, 11-a first triangular frame, 12-a second triangular frame, 13-a first cross rod, 14-a second cross rod, 15-a support rod, 16-a connecting rod, 17-a first support rod, 18-a second support rod, 19-a universal wheel, 20-a mounting frame and 21-a placing frame.
Detailed Description
In order to make the technical problem, technical solution and advantageous effects to be solved by the present invention more clearly understood, the following description is given in conjunction with the accompanying drawings and embodiments to illustrate the present invention in further detail. It should be understood that the specific embodiments described herein are merely illustrative of the invention and are not intended to limit the invention.
It will be understood that when an element is referred to as being "secured to" or "disposed on" another element, it can be directly on the other element or be indirectly on the other element. When an element is referred to as being "connected to" another element, it can be directly connected to the other element or be indirectly connected to the other element.
Furthermore, the terms "first", "second" and "first" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of that feature. In the description of the present invention, "a plurality" means two or more unless specifically limited otherwise. The meaning of "a number" is one or more unless specifically limited otherwise.
In the description of the present invention, it should be understood that the terms "upper", "lower", "front", "rear", "left", "right", and the like indicate orientations or positional relationships based on orientations or positional relationships shown in the drawings, and are only for convenience of description and simplification of description, but do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and thus should not be construed as limiting the present invention.
In the description of the present invention, it is to be noted that, unless otherwise explicitly specified or limited, the terms "mounted," "connected," and "connected" are to be construed broadly, and may be, for example, fixedly connected, detachably connected, or integrally connected; can be mechanically or electrically connected; either directly or indirectly through intervening media, either internally or in any other relationship. The specific meaning of the above terms in the present invention can be understood according to specific situations by those skilled in the art.
In the house construction process, partition plate, the side fascia, roof boarding and other functional panel adopt ACC panel more, but ACC panel is bulky, the quality is heavy, need adopt wallboard hoist and mount construction equipment to hoist, current wallboard hoist and mount construction equipment is often integrative, can not dismantle, portable not, and because construction environment's change, often need adapt to different floor height, however current wallboard hoist and mount construction equipment's highly unable regulation, need to change not floor height that co-altitude's support frame adapts to co-altitude, increase construction cost.
In order to solve the problem, the utility model provides a wallboard hoist and mount construction equipment through the setting that can dismantle the support frame, realizes dismantling the turnover of equipment, can adjust each floor height of different high adaptation simultaneously. The following description is made with reference to the drawings.
Referring to fig. 1, an embodiment of the present invention provides a wallboard hoisting construction equipment, including: the device comprises a support frame 1, a lifting traction device 2, a power lifting device 3, a traction rope 4 and an operation platform 5; the support frame 1 comprises two triangular frames which are arranged side by side at intervals, a first cross rod 13 which detachably connects the top ends of the two triangular frames, and a second cross rod 14 which detachably connects the bottom ends of the two triangular frames, and each triangular frame can be detachably connected; the power lifting device 3 is connected with the lifting traction device 2 in a sliding way through a traction rope 4; the lifting traction device 2 and the power lifting device 3 are both arranged between the two triangular frames, and the height of the lifting traction device 2 is higher than that of the first cross rod 13; operation platform 5 sets up in the middle of two triangle frames, and operation platform 5 can dismantle with support frame 1 and be connected. The support frame 1 can be formed by steel pipes, and the steel pipes are detachably connected through cross fasteners. The bottom of the support frame 1 is connected with four universal wheels 19.
The hauling cable 4 can be a rope made of metal materials such as a steel wire rope, a hard alloy rope and the like.
The two triangular frames are in the shape of a right triangle, such as a first triangular frame 11 and a second triangular frame 12 shown in fig. 1, three sides of the two triangular frames can be composed of three steel pipes, and the three steel pipes can be detachably connected.
In the concrete implementation process, two triangle frames in support frame 1 all can be dismantled to the steel pipe that differs in length, first horizontal pole 13 between two triangle frames also can be dismantled with second horizontal pole 14, promote draw gear 2 simultaneously, power hoisting device 3, the universal wheel 19 of operation platform 5 and bottom all can be dismantled and install from support frame 1, only need install support frame 1 when using, will promote draw gear 2 simultaneously, power hoisting device 3, the universal wheel 19 of operation platform 5 and bottom is installed and can be used in support frame 1 suitable position, will promote draw gear 2 after finishing using, power hoisting device 3, the universal wheel 19 of operation platform 5 and bottom is dismantled, support frame 1 also dismantles, support frame 1 dismantles the back portable. If the height of different floors needs to be adapted in the using process, the height of the whole equipment can be increased only by increasing the heights of the two triangular frames when the height needs to be increased; and when the height needs to be reduced, the heights of the two triangular frames are reduced. When the height is increased or decreased, the distance between the two triangular frames and the length of the bottom edge of the triangular frame need to be adjusted properly. It should be understood that increasing or decreasing the height of the constituent triangular frames does not mean replacing longer or shorter steel pipes, but increases or decreases the distance between the junctions of the three steel pipes constituting the triangular frames.
According to the structure and the specific implementation mode, the wall plate hoisting construction equipment provided by the utility model has the advantages that the detachable triangular frames are arranged side by side at two intervals through the support frame 1, the first cross rod 13 detachably connecting the top ends of the two triangular frames and the second cross rod 14 detachably connecting the bottom ends of the two triangular frames enable the support frame 1 to realize detachable connection, so that all parts of the wall plate hoisting construction equipment can be detached, and the carrying and turnover of the wall plate hoisting construction equipment are convenient; simultaneously because two triangle frames can dismantle the connection, can increase or reduce the height of two triangle frames in order to adjust the height of whole wallboard hoist and mount construction equipment through the mode of dismantling to adapt to the floor of co-altitude not. The lifting traction device 2 and the power lifting device 3 are arranged to realize lifting work of the wallboard, the lifting height can be adjusted, and the operation platform 5 is arranged to facilitate operation of workers on the operation platform 5. Through four universal wheels 19 that set up in support frame 1 bottom, make whole wallboard hoist and mount construction equipment possess the mobility.
Specifically, all transversely can dismantle in the arbitrary triangle frame in the above-mentioned wallboard hoist and mount construction equipment and be connected with a plurality of vaulting poles 15, the distance between two adjacent vaulting poles 15 is the same, and the distance value can be established to 50CM, and vaulting pole 15 is used for maintaining the stability of triangle frame. When the triangular frame is increased or decreased in height, the number of the struts 15 is correspondingly increased or decreased.
Specifically, can dismantle between two triangle frames among the above-mentioned wallboard hoist and mount construction equipment and be connected with a plurality of connecting rods 16, a plurality of connecting rods 16 parallel arrangement are between first horizontal pole 13 and second horizontal pole 14, and the distance is the same between two adjacent connecting rods 16, and the distance value can be established to 50CM, and a plurality of connecting rods 16, first horizontal pole 13 and second horizontal pole 14's length homogeneous phase is the same. The connecting rod 16, the first cross bar 13 and the second cross bar 14 are used for maintaining the stability between the two triangular frames. When the triangular frame is increased or decreased in height, the number of the connecting rods 16 is correspondingly increased or decreased.
Specifically, the support frame 1 in the wallboard hoisting construction equipment further comprises a first support rod 17 and a second support rod 18, the first support rod 17 is longitudinally detachably connected to one end of the bottom of the first triangular frame 11, as shown in fig. 1, the first support rod 17 is longitudinally arranged and located on one side of the first triangular frame 11, and meanwhile, two ends of the first support rod 17 are respectively detachably connected with the two support rods at the bottom of the first triangular frame 11; the second support bar 18 is vertically detachably connected to one end of the bottom of the second triangular frame 12, as shown in fig. 1, the second support bar 18 is vertically disposed and located on one side of the second triangular frame 12, and meanwhile, two ends of the second support bar 18 are detachably connected to two support bars of the bottom of the second triangular frame 12 respectively. The bottoms of the first supporting rod 17 and the second supporting rod 18 are respectively provided with a universal wheel 19, and the other two universal wheels 19 are arranged at the bottoms of the two steel pipes with the triangular frames and vertical edges.
Specifically, among the above-mentioned wallboard hoist and mount construction equipment, 1 top of support frame is provided with the mounting bracket 20 that is used for installing and promotes draw gear 2, as shown in fig. 1, this mounting bracket 20 comprises three steel pipe, and two long steel pipe demountable installation are on the inclined plane of support frame 1, and a short steel pipe can be dismantled and connected on the top of two long steel pipes, promote draw gear 2 and install on this short steel pipe. The lifting traction device 2 may comprise a pulley, a U-shaped clamp plate, the U-shaped clamp plate being mounted on the axle of the pulley.
Specifically, the rack 21 of power hoisting device 3 is arranged at the bottom of support frame 1 in the wallboard hoisting construction equipment, as shown in fig. 1, this rack 21 is composed of two steel pipes, one end of two steel pipes can be dismantled with one of them vaulting pole 15 of first triangular frame 11 and be connected, the other end of two steel pipes can be dismantled with one of them vaulting pole 15 of second triangular frame 12 and be connected, two vaulting poles 15 of connection are in same water flat line, wherein can select the position of placing that power hoisting device 3 was adjusted to the height of connecting vaulting pole 15 as required. The power lifting device 3 can be an electric winch, a traction rope 4 is wound on the electric winch, one end of the traction rope 4 bypasses a pulley of the lifting traction device 2, and a hook is installed at the end part.
The utility model provides a wallboard hoist and mount construction equipment breaks the limitation of traditional wallboard transportation, and is portable, can dismantle, and is adjustable, and is nimble convenient, and the place is free, adaptable not co-altitude floor, economy is suitable for, can use repeatedly, practices thrift the cost.
In the foregoing description of embodiments, the particular features, structures, materials, or characteristics may be combined in any suitable manner in any one or more embodiments or examples.
The above description is only for the specific embodiments of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art can easily think of the changes or substitutions within the technical scope of the present invention, and all should be covered within the protection scope of the present invention. Therefore, the protection scope of the present invention shall be subject to the protection scope of the claims.

Claims (8)

1. The utility model provides a wallboard hoist and mount construction equipment which characterized in that includes:
the device comprises a support frame, a lifting traction device, a power lifting device, a traction rope and an operation platform;
the support frame comprises two triangular frames which are arranged side by side at intervals, a first cross rod which detachably connects the top ends of the two triangular frames and a second cross rod which detachably connects the bottom ends of the two triangular frames, and each triangular frame can be detachably connected;
the power lifting device is connected with the lifting traction device in a sliding manner through the traction rope; the lifting traction device and the power lifting device are arranged between the two triangular frames, and the height of the lifting traction device is higher than that of the first cross rod;
the operating platform is arranged between the two triangular frames.
2. The wall panel hoisting construction equipment according to claim 1, wherein a plurality of support rods are transversely detachably connected in any one of the triangular frames, and the distance between every two adjacent support rods is the same.
3. The wallboard hoisting construction equipment of claim 1, wherein a plurality of connecting rods are detachably connected between two triangular frames, the connecting rods are arranged between the first cross rod and the second cross rod in parallel, and the distance between two adjacent connecting rods is the same.
4. The wall panel hoisting construction equipment according to claim 1, wherein the support frame further comprises a first support rod and a second support rod, and the support rods are longitudinally and detachably connected to one end of the bottom of the triangular frame aiming at any one triangular frame; four universal wheels are installed to the support frame bottom, wherein two the universal wheels respectively with first bracing piece with the second bracing piece links to each other.
5. The wallboard hoisting construction equipment of claim 1, wherein the support frame is detachably connected by a cross fastener.
6. The wallboard hoisting construction equipment of claim 1, wherein the power lifting device is an electric winch, the traction rope is wound on the electric winch, one end of the traction rope bypasses a pulley of the lifting traction device, and a hook is installed at the end of the traction rope.
7. The wall panel hoisting construction equipment according to claim 6, wherein a U-shaped clamping plate is mounted on a wheel shaft of the pulley.
8. The wallboard hoisting construction equipment of claim 1, wherein the first cross bar, the second cross bar and the triangular frame are steel pipes.
CN202222814398.5U 2022-10-25 2022-10-25 Wallboard hoisting construction equipment Active CN218434621U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222814398.5U CN218434621U (en) 2022-10-25 2022-10-25 Wallboard hoisting construction equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222814398.5U CN218434621U (en) 2022-10-25 2022-10-25 Wallboard hoisting construction equipment

Publications (1)

Publication Number Publication Date
CN218434621U true CN218434621U (en) 2023-02-03

Family

ID=85070107

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222814398.5U Active CN218434621U (en) 2022-10-25 2022-10-25 Wallboard hoisting construction equipment

Country Status (1)

Country Link
CN (1) CN218434621U (en)

Similar Documents

Publication Publication Date Title
CN202202558U (en) Girder-riding weight basket hanging mechanism arranged on high-rise roof frame girder
CN111668757A (en) Convenient support is used in cable erection convenient to adjustment cable interval
CN210032533U (en) Construction equipment scaffold
CN218434621U (en) Wallboard hoisting construction equipment
CN114436134A (en) Glass vertical hoisting in-place tool capable of being flexibly adjusted and displaced in multiple directions and use method
CN215631489U (en) Building templates operation platform
CN105152052A (en) Glass curtain wall component lifting device and glass curtain wall component installing method
CN210759347U (en) Mounting equipment
CN210140393U (en) Curtain wall suspension hoisting gun carriage
CN210530363U (en) Gradual change formula triangle-shaped curtain skeleton construction operation platform
CN210260897U (en) Hoisting device for prefabricated part
CN202899720U (en) Steel pole provided with foot treadles and used for high-tension transmission line iron tower
CN113202281A (en) Building templates operation platform
CN220376215U (en) Electric hoist device
CN218842877U (en) Strutting arrangement with adjustable bridge construction is used
CN214589208U (en) Pole holding device for mobile communication base station
CN215160352U (en) Single-double-beam dual-purpose hanging bracket
CN213894920U (en) Portable adjustable cable drum unwrapping wire support
CN110054104B (en) Transport and hoist integrated detachable multipurpose movable support
CN219929468U (en) Hoisting tool used in narrow space
CN219469634U (en) Simple and easy convenient many pipe fittings automatic lifting device
CN214531787U (en) Height-adjustable's scaffold frame
CN211902280U (en) Inverter dismounting mechanism
CN217458499U (en) Movable lifting machine
CN218592182U (en) Welding robot mobile device capable of being supported in stretching mode

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant