Pre-buried auxiliary device of pipeline for electric power engineering construction Download PDFInfo
- Publication number
- CN218415650U CN218415650U CN202222381568.5U CN202222381568U CN218415650U CN 218415650 U CN218415650 U CN 218415650U CN 202222381568 U CN202222381568 U CN 202222381568U CN 218415650 U CN218415650 U CN 218415650U
- Authority
- CN
- China
- Prior art keywords
- pipeline
- block
- fixedly connected
- electric power
- engineering construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Laying Of Electric Cables Or Lines Outside (AREA)
Abstract
The utility model discloses a pipeline pre-embedding auxiliary device for electric power engineering construction, relating to the technical field of pipeline auxiliary pre-embedding; the utility model comprises a pipeline placing plate, and both sides of the pipeline placing plate are fixedly connected with mounting blocks; during the use, need to peg graft the toper piece subaerial, in order to place the pipeline the board and fix in the pre-buried position of pipeline, later place the pipeline on the board is placed to the pipeline, rotate the installation rotating rod again, it moves to one side that is close to the pipeline together with the rubber block to make it drive the pipe of pegging graft, thereby make one side of rubber block extrude the surface of pipeline, continue to rotate the installation rotating rod afterwards, make it rotate and continue to promote the rubber block on the grafting ring, make the rubber block continue to extrude the pipeline, the air in the mounting hole on the later rubber block will be extruded, thereby make the rubber block adsorb on the pipeline, and then fix the pipeline, prevent that the pipeline is because of removing when pre-buried and skew pre-buried position.
Description
Technical Field
The utility model relates to a supplementary pre-buried technical field of pipeline specifically is a pre-buried auxiliary device of pipeline for electric power engineering construction.
Background
In the engineering of electric power engineering construction, need to use the pre-buried auxiliary device of pipeline to assist constructor to bury the pipeline in advance. When the existing pipeline embedding auxiliary device for electric power engineering construction is used, the operation is simple and easy, the device is convenient for personnel to carry, and the device is convenient for the personnel to use when the pipeline is embedded, but the problem of inconvenience still exists;
the pre-buried auxiliary device of pipeline is used in present electric power engineering construction, because most all are not provided with the mechanism of consolidating the pipeline on it when using, so when the pre-buried pipeline of assistant personnel, be difficult to with the pipeline fixed to be difficult to prevent the skew pre-buried position of pipeline, and then brought certain inconvenience for personnel when pre-buried pipeline.
In order to solve the above problems, the inventor proposes a pipe embedding auxiliary device for electric power engineering construction.
SUMMERY OF THE UTILITY MODEL
The pipeline pre-embedding auxiliary device aims to solve the problems that when the existing pipeline pre-embedding auxiliary device for electric power engineering construction is used, as most of the auxiliary device is not provided with a pipeline reinforcing mechanism, when an assistant person pre-embeds a pipeline, the pipeline is difficult to fix, so that the pipeline is difficult to prevent from deviating from the pre-embedding position, and further certain inconvenience is brought to the person when the pipeline is pre-embedded; an object of the utility model is to provide a pre-buried auxiliary device of pipeline is used in electric power engineering construction.
In order to solve the technical problem, the utility model adopts the following technical scheme: a pipeline pre-embedding auxiliary device for electric power engineering construction comprises a pipeline placing plate, a pipeline can be positioned by the pipeline placing plate, mounting blocks are fixedly connected to two sides of the pipeline placing plate, an adjusting fixing frame is fixedly connected to the top of each mounting block, an adjusting groove is formed in the top of the adjusting fixing frame, a positive charge magnetic block is fixedly connected to the inner wall of the adjusting groove, a negative charge magnetic block is fixedly connected to two sides of each limiting block, the positive charge magnetic block can be adsorbed to the negative charge magnetic block, so that the stability of the plugging moving block in the adjusting groove is improved, a plugging moving block is plugged in the adjusting groove, the plugging moving block can be limited after being plugged in the plugging groove, the rotation auxiliary block is prevented from driving the rotation of the plugging moving block, a limiting block is movably connected to the bottom of the plugging moving block, a butting groove is formed in the top of each limiting block, a mounting threaded hole is formed in the surface of each mounting block, a mounting rotating rod is connected to the surface of the mounting hole in a rotating manner, the rotating rod is capable of driving the rubber block to move towards one side far away from the pipeline, and the mounting hole is formed in the rotating ring, and the plugging connecting hole is formed in the rotating rod, and the plugging connecting hole, and the rotating rod is capable of preventing the plugging connecting ring from being plugged in the mounting hole from being conveniently connected to be plugged in the rotating groove, the one end fixedly connected with block rubber of grafting pipe, the back is extruded to the air in the mounting hole on the block rubber, and the block rubber will adsorb on the pipeline, and the mounting hole has been seted up to one side of block rubber, and the bottom fixedly connected with grafting conical block of board is placed to the pipeline, pegs graft the conical block of pegging graft behind underground, can place the pipeline that the board is fixed.
Preferably, the length and the width in butt joint groove all are greater than the length and the width of grafting movable block, because the length and the width in butt joint groove all are greater than the length and the width of grafting movable block, so the grafting movable block of being convenient for enters into the inside in butt joint groove, one side of stopper with rotate supplementary piece fixed connection, the top fixedly connected with pull rectangular block of grafting movable block utilizes the pull rectangular block, the personnel of being convenient for stimulate the grafting movable block, the surface of pull rectangular block is provided with the supplementary line of pull, utilize the supplementary line of pull, the personnel of being convenient for hold the pull rectangular block tightly.
Preferably, the bottom of pull rectangular block and the top swing joint of adjusting the mount, because the bottom of pull rectangular block and the top swing joint of adjusting the mount, so be convenient for the removal of pull rectangular block, rotate supplementary piece and installation piece swing joint, because rotate supplementary piece and installation piece swing joint, so be convenient for rotate supplementary piece and to keeping away from or be close to the one side removal of installation piece.
Compared with the prior art, the beneficial effects of the utility model reside in that:
during the use, need to peg graft the toper piece subaerial, in order to place the pipeline the board and fix in the pre-buried position of pipeline, later place the pipeline on the board is placed to the pipeline, rotate the installation rolling rod again, make it drive the pipe of pegging graft and the same one side that is close to the pipeline of rubber block and remove, thereby make one side extrusion pipeline's of rubber block surface, continue to rotate the installation rolling rod afterwards, make it rotate and continue to promote the rubber block on the grafting ring, make the rubber block continue to extrude the pipeline, later the air in the mounting hole on the rubber block will be extruded, thereby make the rubber block adsorb on the pipeline, and then fix the pipeline, prevent that the pipeline is because of removing skew pre-buried position when pre-buried.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, it is obvious that the drawings in the following description are only some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to these drawings without creative efforts.
Fig. 1 is a schematic view of the overall structure of the present invention.
Fig. 2 is the structure schematic diagram of the mounting threaded hole of the present invention.
Fig. 3 is a schematic structural diagram of the middle rotation auxiliary block of the present invention.
Fig. 4 is a partially enlarged schematic structural view of a portion a in fig. 1 according to the present invention.
Fig. 5 is a schematic view of the present invention at a part B enlarged in fig. 2.
Fig. 6 is a schematic diagram of the present invention at a part C of fig. 2.
Fig. 7 is a schematic diagram of the present invention at a part D in fig. 2.
In the figure: 1. a pipe-placing plate; 2. mounting blocks; 3. installing a threaded hole; 4. installing a rotating rod; 5. inserting holes; 6. inserting a tube; 7. a plug-in ring; 8. a rotary groove is inserted; 9. a rubber block; 10. inserting a conical block; 11. rotating the auxiliary block; 12. adjusting the fixing frame; 13. an adjustment groove; 14. inserting a moving block; 15. a limiting block; 16. a butt joint groove; 17. a ball bearing; 18. a positively charged magnetic block; 19. a negatively charged magnetic block; 20. the rectangular block is pulled.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative efforts all belong to the protection scope of the present invention.
The first embodiment is as follows: as shown in fig. 1-7, the utility model provides a pre-buried auxiliary device of pipeline for electric power engineering construction, place board 1 including the pipeline, it can fix a position the pipeline to utilize the pipeline to place board 1, the equal fixedly connected with installation piece 2 in both sides of board 1 is placed to the pipeline, installation screw hole 3 has been seted up on the surface of installation piece 2, the inside threaded connection of installation screw hole 3 has installation rotating rod 4, rotate installation rotating rod 4, it will drive rubber piece 9 and remove to one side of keeping away from or being close to the pipeline, spliced eye 5 has been seted up to the one end of installation rotating rod 4, spliced eye 5's inside is pegged graft and is had spliced pipe 6, spliced pipe 6's fixed surface is connected with grafting ring 7, grafting ring 7 can prevent installation rotating rod 4 and spliced pipe 6 separation, set up the grafting rotation groove 8 with grafting ring 7 looks adaptation on spliced eye 5's the inner wall, spliced pipe 6's one end fixedly connected with rubber piece 9, after the air in the mounting hole on the rubber piece 9 is extruded, rubber piece 9 will adsorb on the pipeline, the mounting hole has been seted up to one side of rubber piece 9, the bottom fixedly connected with tapered piece 10 of board 1, the fixed tapered piece 10 after the grafting, the pipeline is placed 1, the pipeline can be pegged graft.
The other end of the installation rotating rod 4 is fixedly connected with a rotation auxiliary block 11, and friction grains are arranged on the surface of the rotation auxiliary block 11.
Through adopting above-mentioned technical scheme, utilize and rotate supplementary piece 11, the personnel of being convenient for rotate installation and rotate stick 4, utilize friction line, the personnel of being convenient for hold and rotate supplementary piece 11.
The top fixedly connected with of installation piece 2 adjusts mount 12, and the adjustment tank 13 has been seted up at the top of adjusting mount 12, and the inside grafting of adjustment tank 13 has grafting movable block 14, and the bottom swing joint of grafting movable block 14 has stopper 15, and butt joint groove 16 has been seted up at stopper 15's top.
By adopting the technical scheme, after the splicing moving block 14 is spliced in the butt joint groove 16, the limiting block 15 can be limited, and the rotation auxiliary block 11 is prevented from driving the splicing moving block to rotate by three hundred and sixty degrees.
The length and the width of the butt joint groove 16 are both larger than those of the plugging moving block 14, and one side of the limiting block 15 is fixedly connected with the rotation auxiliary block 11.
By adopting the technical scheme, the length and the width of the butt joint groove 16 are both larger than those of the plugging moving block 14, so that the plugging moving block 14 can conveniently enter the butt joint groove 16.
The top of the plugging moving block 14 is fixedly connected with a drawing rectangular block 20, and the surface of the drawing rectangular block 20 is provided with drawing auxiliary lines.
Through adopting above-mentioned technical scheme, utilize pull rectangular block 20, the personnel of being convenient for pull grafting movable block 14, utilize the supplementary line of pull, the personnel of being convenient for grasp pull rectangular block 20.
The bottom of the drawing rectangular block 20 is movably connected with the top of the adjusting fixing frame 12, and the rotation auxiliary block 11 is movably connected with the mounting block 2.
By adopting the technical scheme, the bottom of the drawing rectangular block 20 is movably connected with the top of the adjusting fixing frame 12, so that the drawing rectangular block 20 is convenient to move, and the rotation auxiliary block 11 is movably connected with the mounting block 2, so that the rotation auxiliary block 11 is convenient to move to one side far away from or close to the mounting block 2.
The surface of the inserting ring 7 is provided with an inserting rotating hole, and the inside of the inserting rotating hole is movably connected with a ball 17.
Through adopting above-mentioned technical scheme, utilize ball 17, be convenient for install and rotate stick 4 and rotate on grafting ring 7.
The inner wall of the adjusting groove 13 is fixedly connected with a positive charge magnetic block 18, and both sides of the limiting block 15 are fixedly connected with negative charge magnetic blocks 19.
By adopting the technical scheme, the positive charge magnetic blocks 18 and the negative charge magnetic blocks 19 can be adsorbed together, so that the stability of the plugging moving block 14 in the adjusting groove 13 is improved.
The working principle is as follows: during operation, need to peg graft toper piece 10 subaerial, place board 1 with the pipeline and fix in the pre-buried position of pipeline, later place the pipeline on board 1 is placed to the pipeline, rotate installation rotating rod 4 again, make it drive plug tube 6 and rubber block 9 together to the one side that is close to the pipeline removal, thereby make one side of rubber block 9 extrude the surface of pipeline, later continue to rotate installation rotating rod 4, make it rotate on grafting ring 7 and continue to promote rubber block 9, make rubber block 9 continue to extrude the pipeline, later the air in the mounting hole on the rubber block 9 will be extruded, thereby make rubber block 9 adsorb on the pipeline, and then fix the pipeline, prevent that the pipeline is skew pre-buried position because of moving when pre-buried, at last peg graft movable block 14 in butt joint groove 16, with stopper 15 is fixed, and then it is fixed to rotate auxiliary block 11, prevent to rotate auxiliary block 11 and rotate.
It will be apparent to those skilled in the art that various changes and modifications may be made without departing from the spirit and scope of the invention. Thus, if such modifications and variations of the present invention fall within the scope of the claims of the present invention and their equivalents, the present invention is also intended to include such modifications and variations.
Claims (8)
1. The utility model provides a pre-buried auxiliary device of pipeline for electric power engineering construction, places board (1), its characterized in that including the pipeline: the pipeline placing plate comprises a pipeline placing plate body (1), wherein mounting blocks (2) are fixedly connected to the two sides of the pipeline placing plate body (1), mounting threaded holes (3) are formed in the surface of the mounting blocks (2), mounting rotating rods (4) are connected to internal threads of the mounting threaded holes (3), inserting holes (5) are formed in one ends of the mounting rotating rods (4), inserting pipes (6) are inserted into the inserting holes (5), inserting rings (7) are fixedly connected to the surfaces of the inserting pipes (6), inserting rotating grooves (8) matched with the inserting rings (7) are formed in the inner wall of the inserting holes (5), one ends of the inserting pipes (6) are fixedly connected with rubber blocks (9), mounting holes are formed in one sides of the rubber blocks (9), and bottom portions of the pipeline placing plate body (1) are fixedly connected with inserting conical blocks (10).
2. The auxiliary device for embedding the pipeline for the electric power engineering construction as claimed in claim 1, wherein the other end of the installation rotating rod (4) is fixedly connected with an auxiliary rotating block (11), and friction lines are arranged on the surface of the auxiliary rotating block (11).
3. The auxiliary device for embedding the pipeline for the electric power engineering construction as claimed in claim 2, wherein an adjusting fixing frame (12) is fixedly connected to the top of the mounting block (2), an adjusting groove (13) is formed in the top of the adjusting fixing frame (12), an inserting moving block (14) is inserted into the adjusting groove (13), a limiting block (15) is movably connected to the bottom of the inserting moving block (14), and a butt-joint groove (16) is formed in the top of the limiting block (15).
4. The auxiliary device for embedding pipelines in electric power engineering construction as claimed in claim 3, wherein the length and width of the butt-joint groove (16) are both greater than those of the insertion moving block (14), and one side of the limiting block (15) is fixedly connected with the auxiliary rotating block (11).
5. The pipe embedding auxiliary device for the electric power engineering construction as claimed in claim 4, wherein a drawing rectangular block (20) is fixedly connected to the top of the plugging moving block (14), and drawing auxiliary lines are arranged on the surface of the drawing rectangular block (20).
6. The pipe embedding auxiliary device for the electric power engineering construction as claimed in claim 5, wherein the bottom of the drawing rectangular block (20) is movably connected with the top of the adjusting fixing frame (12), and the rotating auxiliary block (11) is movably connected with the mounting block (2).
7. The auxiliary device for embedding the pipeline for the electric power engineering construction as claimed in claim 6, wherein the surface of the inserting ring (7) is provided with an inserting rotating hole, and the inside of the inserting rotating hole is movably connected with a ball (17).
8. The auxiliary device for embedding pipelines in electric power engineering construction as claimed in claim 7, wherein the inner wall of the adjusting groove (13) is fixedly connected with positive charge magnetic blocks (18), and both sides of the limiting block (15) are fixedly connected with negative charge magnetic blocks (19).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202222381568.5U CN218415650U (en) | 2022-09-08 | 2022-09-08 | Pre-buried auxiliary device of pipeline for electric power engineering construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202222381568.5U CN218415650U (en) | 2022-09-08 | 2022-09-08 | Pre-buried auxiliary device of pipeline for electric power engineering construction |
Publications (1)
Publication Number | Publication Date |
---|---|
CN218415650U true CN218415650U (en) | 2023-01-31 |
Family
ID=85030921
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202222381568.5U Active CN218415650U (en) | 2022-09-08 | 2022-09-08 | Pre-buried auxiliary device of pipeline for electric power engineering construction |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN218415650U (en) |
-
2022
- 2022-09-08 CN CN202222381568.5U patent/CN218415650U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN218415650U (en) | Pre-buried auxiliary device of pipeline for electric power engineering construction | |
CN113638951A (en) | Composite pipe with quick-connecting pipe head | |
CN117353230B (en) | Pre-twisted double suspension clamp | |
CN205070335U (en) | Structure is laid to circuit line pipe suitable for corner | |
CN218867802U (en) | A device for pipeline wiring for electric power construction | |
CN217402013U (en) | Pipe joint convenient for connecting air pipes | |
CN214368348U (en) | Municipal works water pipe leak protection device | |
CN212427430U (en) | Heavy-calibre pipeline mouth of pipe socket joint auxiliary device | |
CN218719479U (en) | High leakproofness pipeline connection structure | |
CN218732965U (en) | Anti-seismic support convenient to install | |
CN220787641U (en) | Novel cable conveying traction device | |
CN218182631U (en) | Waterproof cable connector for servo motor encoder | |
CN216042691U (en) | Concrete grouting machine | |
CN214668214U (en) | Building detects with rearmounted anti-pulling strength detection device that buries | |
CN218449260U (en) | Detachable CPVC cable protection pipe | |
CN217811747U (en) | Steel-concrete structure building energy-saving wall | |
CN217679042U (en) | Uplift pile splicing connection node convenient for pile sinking | |
CN220582327U (en) | Fan ceiling lamp convenient to installation | |
CN218976178U (en) | Electric power transmission device capable of adjusting supporting direction and angle | |
CN218822462U (en) | Instrument for monitoring outdoor environment | |
CN211908314U (en) | Pipeline mechanical expansion type plugging device | |
CN218895101U (en) | Sewer pipe assembly | |
CN221609085U (en) | Light steel villa fossil fragments | |
CN219992523U (en) | Novel large-span deep basal pit precipitation device | |
CN221097705U (en) | Sewage pipeline laying device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |