CN218403309U - Lifting equipment for constructional engineering for preventing landing - Google Patents

Lifting equipment for constructional engineering for preventing landing Download PDF

Info

Publication number
CN218403309U
CN218403309U CN202221743895.4U CN202221743895U CN218403309U CN 218403309 U CN218403309 U CN 218403309U CN 202221743895 U CN202221743895 U CN 202221743895U CN 218403309 U CN218403309 U CN 218403309U
Authority
CN
China
Prior art keywords
rope
support
lifting
hanger
bundled
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202221743895.4U
Other languages
Chinese (zh)
Inventor
赵安林
郭鹏
严始军
张永军
董勇
孙泰胜
努尔古丽·阿不都热合曼
尤琳燕
周学生
刘大伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kashgar Construction Engineering Group Co ltd
Original Assignee
Kashgar Construction Engineering Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kashgar Construction Engineering Group Co ltd filed Critical Kashgar Construction Engineering Group Co ltd
Priority to CN202221743895.4U priority Critical patent/CN218403309U/en
Application granted granted Critical
Publication of CN218403309U publication Critical patent/CN218403309U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses a prevent lifting devices for building engineering of landing, including tying up rope and hanger, it establishes to two and suit respectively in bundled building material's both ends to tie up the rope, the hanger erects in bundled building material top and is connected with two tying up ropes, the hanger includes bracing piece and spacing subassembly, spacing subassembly is established to two and installs respectively in the top of two tying up ropes, the bracing piece erects between two spacing subassemblies, spacing subassembly runs through in the tip of bracing piece and through nut and the bracing piece fixed connection that is located spacing subassembly both sides, the utility model relates to a building engineering technical field. This lifting means for building engineering who prevents landing through two ligatures rope in bundling reinforcing bar or steel both ends respectively, and the hanger of cooperation installation on two ligatures rope can ensure that two ligatures rope fastens the winding to bundling reinforcing bar or steel to avoid building material to take place the landing, ensured the handling safety.

Description

Lifting equipment for constructional engineering for preventing landing
Technical Field
The utility model relates to a building engineering technical field specifically is a lifting devices for building engineering who prevents landing.
Background
In the building engineering, it is often necessary to hoist bundles of steel bars or steel materials by means of ropes in conjunction with hoisting equipment.
When existing bundles of steel bars or steel products are hung on a lifting hook, a steel wire rope is usually wound on the bundles of steel bars or steel products for a circle, a rope sleeve at one end of the steel wire rope is buckled on the steel wire rope through a hanging ring buckle, a rope sleeve at the other end of the steel wire rope is hung on the lifting hook, the self weight of the bundles of steel bars or steel products is utilized to realize the winding of the steel wire rope outside the bundles of steel bars or steel products, the winding fastening degree is poor, and the building materials are easy to slip off.
SUMMERY OF THE UTILITY MODEL
The utility model provides a not enough to prior art, the utility model provides a lifting devices for building engineering who prevents the landing has solved current bundled reinforcing bar or steel when hanging on the lifting hook, and winding fastening degree is poor, and easily takes place the problem of building material's landing.
In order to achieve the above purpose, the utility model discloses a following technical scheme realizes: the lifting equipment for the building engineering for preventing the slipping comprises binding ropes and a hanger, wherein the two binding ropes are respectively sleeved at two ends of a bundled building material, the hanger is erected above the bundled building material and is connected with the two binding ropes,
the hanger comprises two supporting rods and two limiting assemblies, the two limiting assemblies are respectively arranged at the tops of the two binding ropes, the supporting rods are erected between the two limiting assemblies, the limiting assemblies penetrate through the end parts of the supporting rods and are fixedly connected with the supporting rods through nuts positioned at the two sides of the limiting assemblies, lifting lugs are arranged at the tops of the supporting rods,
the limiting assembly comprises a seat shell, a support, a screw rod and a rope hook, the support is welded at the top of the seat shell, the screw rod penetrates through the support through threads of a threaded seat, a sliding block movably attached to the inner wall of the support is arranged on the inner side of the support, the sliding block is sleeved at the bottom end of the screw rod in a rotating mode, the rope hook is installed at the bottom of the sliding block through an installation sleeve, and the installation sleeve penetrates through the support and is matched with the supporting rod.
Preferably, the lug is established to a plurality of and is equidistance evenly distributed and weld on the outer wall of bracing piece, a plurality of the lug all with lifting hook looks adaptation.
Preferably, all set up along vertical direction distribution and with the bar hole of installation cover looks adaptation on the both sides wall of support, the both ends of installation cover flush with two outside walls of support respectively.
Preferably, two sides of the bottom of the inner side of the seat shell are respectively and rotatably connected with two rope guide sleeves through two pin shafts, and arc-shaped panels are arranged at the tops of two side walls of the seat shell.
Preferably, the binding rope comprises a steel wire rope wound around a circle of bundled building materials, rope sleeves are arranged at two ends of the steel wire rope, and one of the rope sleeves is buckled with the other rope sleeve through a hanging ring buckle arranged on the rope sleeve.
Advantageous effects
The utility model provides a lifting devices for building engineering who prevents landing. Compared with the prior art, the method has the following beneficial effects:
this lifting device for building engineering who prevents landing through two tying up the rope in bundled reinforcing bar or steel both ends respectively, and the hanger that the cooperation was installed on two tying up the rope can ensure that two tying up the rope and fasten the winding to bundled reinforcing bar or steel to avoid building material to take place the landing, ensured building material's handling safety.
Drawings
Fig. 1 is a schematic structural view of the present invention;
fig. 2 is a schematic structural view of the hanger of the present invention;
fig. 3 is a schematic structural view of the limiting assembly of the present invention;
fig. 4 is a schematic structural view of the seat shell of the present invention;
FIG. 5 is a schematic view of the rope binding of the present invention;
in the figure: 1. tying a rope; 2. a hanger; 3. a support bar; 4. a limiting component; 5. a nut; 6. lifting lugs; 7. a seat shell; 8. a support; 9. a screw; 10. a rope hook; 11. a threaded seat; 12. a slider; 13. installing a sleeve; 14. a strip-shaped hole; 15. a pin shaft; 16. a rope guide sleeve; 17. an arcuate panel; 18. a wire rope; 19. rope sleeves; 20. and a lifting ring fastener.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-5, the present invention provides a technical solution: the utility model provides a prevent lifting equipment for building engineering of landing, including tying up rope 1 and hanger 2, tie up rope 1 establishes to two and suit respectively in the both ends of bundled building material, hanger 2 erects in bundled building material top and is connected with two tying up rope 1, hanger 2 includes bracing piece 3 and spacing subassembly 4, spacing subassembly 4 establishes to two and installs respectively in the top of two tying up rope 1, bracing piece 3 erects between two spacing subassembly 4, spacing subassembly 4 runs through in the tip of bracing piece 3 and through nut 5 and bracing piece 3 fixed connection that is located spacing subassembly 4 both sides, the top of bracing piece 3 is equipped with lug 6, spacing subassembly 4 includes seat shell 7, support 8, screw rod 9 and rope hook 10, support 8 welds in the top of seat shell 7, screw rod 9 runs through in support 8 through screw thread seat 11 screw thread, support 8 inboard is equipped with the slider 12 with support 8 inner wall activity laminating, and slider 12 rotates the bottom of cover screw rod 9, rope hook 10 passes through the installation cover 13 and installs in the bottom of slider 12, installation cover 13 runs through in support 8 and adorns in the adaptation with bracing piece 3 mutually.
Based on the above structure, this lifting device for building engineering for preventing landing, by hanger 2 and two wiring 1 constitution, wherein, two wiring 1 are used for the winding wiring at bundled reinforcing bar and steel both ends respectively, hanger 2 is used for fixing spacing to two wiring 1, so as to ensure that wiring 1 twines the firm and firm to bundled reinforcing bar and steel, specifically, hanger 2 comprises bracing piece 3 and two spacing subassemblies 4, in spacing subassembly 4, hang wire rope 18 on rope hook 10 and through rotating screw 9, make slider 12 move up along support 8, can tighten wire rope 18 with the help of rope hook 10, thereby realize wire rope 18 accomplishes the fastening winding to bundled reinforcing bar and steel under the effect of spacing subassembly 4, bracing piece 3 erects between two spacing subassemblies 4 and cooperates lug 6 on it to hang on, thereby realize the stable handling of building material, this lifting device for building engineering for preventing landing, through tying in wiring 1 or two wiring 1 at bundled reinforcing bar or two steel both ends respectively, install in two wiring 1 on it and can guarantee to hang the lifting hook of wiring 1 to the steel to take place the safety of wiring, thereby the safety of wiring material is guaranteed to hang the building material.
Further, lug 6 establishes to a plurality of and is equidistant evenly distributed and welds on the outer wall of bracing piece 3, and a plurality of lug 6 all with lifting hook looks adaptation. Preferably, the plurality of lifting lugs 6 are arranged at the top of the support rod 3, the lifting lugs 6 at proper positions can be selected according to the gravity center of building materials, stable lifting of bundled steel bars or steel products is guaranteed, in addition, the two lifting lugs 6 can be hung by means of two lifting hooks respectively, the use is flexible, and the installation adaptability is strong.
Further, all set up along vertical direction distribution and with the bar hole 14 of installation cover 13 looks adaptation on the both sides wall of support 8, the both ends of installation cover 13 are flushed with two outside walls of support 8 respectively. Wherein, the bar hole 14 is used for spacing to installation cover 13 to when having ensured to carry out screw rod 9 and rotating, rope hook 10 can stabilize the tensioning to wire rope 18, and the tip of installation cover 13 flushes with the 8 outer walls of support mutually, can realize with the help of two nuts 5 that spacing subassembly 4 is fixed spacingly on bracing piece 3, simultaneously, can realize that installation cover 13 is fixed spacingly on support 8.
Furthermore, two sides of the bottom of the inner side of the seat shell 7 are rotatably connected with two rope guide sleeves 16 through two pin shafts 15, and arc-shaped panels 17 are arranged at the tops of two side walls of the seat shell 7. Preferably, two rope guide sleeves 16 are arranged in the seat shell 7, and an arc-shaped panel 17 is arranged at the top of the side wall of the seat shell 7, so that the steel wire rope 18 can move smoothly and stably in the tensioning process.
Further, the binding rope 1 comprises a steel wire rope 18 wound around a circle of bundled building materials, two ends of the steel wire rope 18 are respectively provided with a rope sleeve 19, and one rope sleeve 19 is buckled with the other rope sleeve 19 through a hanging ring buckle 20 arranged on the rope sleeve 19. Specifically, after the two ends of the binding rope 1 are fastened, the steel wire rope 18 at the non-fastened end penetrates through the seat shell 7 and is hung on the rope hook 10, the self-weight of the bundled steel bars or steel products is matched with the screw 9 to drive the rope hook 10 to move upwards, and the bundled steel bars or steel products can be firmly bound under the limiting action of the seat shell 7.
It is noted that, herein, relational terms such as first and second, and the like may be used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Also, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (5)

1. A lifting device for construction engineering for preventing slipping is characterized in that: the binding rope is characterized by comprising two binding ropes (1) and a hanger (2), wherein the two binding ropes (1) are respectively sleeved at two ends of a bundled building material, and the hanger (2) is erected above the bundled building material and is connected with the two binding ropes (1);
the hanger (2) comprises two supporting rods (3) and two limiting assemblies (4), the two limiting assemblies (4) are respectively installed at the tops of the two binding ropes (1), the supporting rods (3) are erected between the two limiting assemblies (4), the limiting assemblies (4) penetrate through the end parts of the supporting rods (3) and are fixedly connected with the supporting rods (3) through nuts (5) located on the two sides of the limiting assemblies (4), and lifting lugs (6) are arranged at the tops of the supporting rods (3);
spacing subassembly (4) are including seat shell (7), support (8), screw rod (9) and rope hook (10), support (8) weld in the top of seat shell (7), screw rod (9) run through in support (8) through screw thread seat (11) screw thread, support (8) inboard is equipped with slider (12) with support (8) inner wall activity laminating, and slider (12) rotate the suit in the bottom of screw rod (9), rope hook (10) are installed in the bottom of slider (12) through installation cover (13), installation cover (13) run through in support (8) and with bracing piece (3) looks adaptation.
2. The anti-slipping lifting equipment for construction engineering as claimed in claim 1, wherein: lifting lugs (6) are arranged into a plurality of lifting lugs and are welded on the outer wall of the supporting rod (3) in an evenly distributed mode, and the lifting lugs (6) are all matched with lifting hooks.
3. The slip-preventing lifting apparatus for construction engineering according to claim 1, wherein: all set up on the both sides wall of support (8) along vertical direction distribution and with strip hole (14) of installation cover (13) looks adaptation, the both ends of installation cover (13) flush with two outside walls of support (8) respectively.
4. The anti-slipping lifting equipment for construction engineering as claimed in claim 1, wherein: two sides of the bottom of the inner side of the seat shell (7) are respectively connected with two rope guide sleeves (16) through two pin shafts (15) in a rotating mode, and arc-shaped panels (17) are arranged on the tops of two side walls of the seat shell (7).
5. The slip-preventing lifting apparatus for construction engineering according to claim 1, wherein: the binding rope (1) comprises a steel wire rope (18) wound around a circle of bundled building materials, rope sleeves (19) are arranged at two ends of the steel wire rope (18), and one rope sleeve (19) is buckled with the other rope sleeve (19) through a lifting ring buckle (20) arranged on the rope sleeve.
CN202221743895.4U 2022-07-06 2022-07-06 Lifting equipment for constructional engineering for preventing landing Active CN218403309U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221743895.4U CN218403309U (en) 2022-07-06 2022-07-06 Lifting equipment for constructional engineering for preventing landing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221743895.4U CN218403309U (en) 2022-07-06 2022-07-06 Lifting equipment for constructional engineering for preventing landing

Publications (1)

Publication Number Publication Date
CN218403309U true CN218403309U (en) 2023-01-31

Family

ID=85012312

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221743895.4U Active CN218403309U (en) 2022-07-06 2022-07-06 Lifting equipment for constructional engineering for preventing landing

Country Status (1)

Country Link
CN (1) CN218403309U (en)

Similar Documents

Publication Publication Date Title
US5101935A (en) Hoisting and rescue apparatus
CN209844409U (en) Hoisting frame for power transmission line
CN218403309U (en) Lifting equipment for constructional engineering for preventing landing
CN214255445U (en) Cable lifting sling and lifting equipment
CN110668308A (en) Hoisting structure and hoisting method of vertical template
CN209855690U (en) Vertical ladder for wall construction
CN213923658U (en) Conveying device for lifting materials in super high-rise building floor
US6129225A (en) Microcell module lifting and positioning system
CN209127947U (en) A kind of electric pole dismounting auxiliary device
CN217418025U (en) Winch installation device and hoisting system for telegraph pole
CN219908584U (en) Lifting point parent rope device of safety belt for overhead operation of bent cap convenient to install
CN217882790U (en) Cable lifting structure
KR100879042B1 (en) Clamp for the hoist installation of rail
CN205555870U (en) Hoisting equipment for engineering
CN211078280U (en) Building engineering machinery material lift
CN110498008B (en) Apron upper-arranging tool and apron upper-arranging method
CN218088712U (en) Steel hoisting device for iron tower installation
CN218603054U (en) Cable traction device of wind turbine generator
CN217437505U (en) Assembled building hoisting accessory
CN116177429A (en) Transformer mounting device and mounting method thereof
CN216042794U (en) Lifting type external overhanging protective net
CN214899833U (en) Bridge cable laying auxiliary device
CN218280344U (en) Fastening and hanging bracket of safety belt
CN218619918U (en) Steel wire rope supporting device for long-distance hoisting of tower-type small gun carrier
CN218041148U (en) Motor installation auxiliary device

Legal Events

Date Code Title Description
GR01 Patent grant