CN218386589U - Combined cable bridge - Google Patents

Combined cable bridge Download PDF

Info

Publication number
CN218386589U
CN218386589U CN202222637474.XU CN202222637474U CN218386589U CN 218386589 U CN218386589 U CN 218386589U CN 202222637474 U CN202222637474 U CN 202222637474U CN 218386589 U CN218386589 U CN 218386589U
Authority
CN
China
Prior art keywords
backup pad
plate
adjacent
articulated slab
fixedly connected
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222637474.XU
Other languages
Chinese (zh)
Inventor
蔡文
张少丽
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Jianyou Intelligent System Co ltd
Original Assignee
Shenzhen Jianyou Intelligent System Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Jianyou Intelligent System Co ltd filed Critical Shenzhen Jianyou Intelligent System Co ltd
Priority to CN202222637474.XU priority Critical patent/CN218386589U/en
Application granted granted Critical
Publication of CN218386589U publication Critical patent/CN218386589U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses a modular cable testing bridge, including first backup pad and second backup pad, the equal fixedly connected with curb plate in both sides at first backup pad and second backup pad top, the equal fixedly connected with articulated slab of the adjacent one end of first backup pad and second backup pad, two the articulated slab piles up from top to bottom and articulates through the round pin axle, the top of round pin axle and the top of first backup pad and second backup pad all are provided with the lead frame, adjacent two be provided with the wind instrument board between the curb plate, the beneficial effects of the utility model are that: through the articulated slab at the adjacent one end fixed connection of first backup pad and second backup pad, can make buckling between first backup pad and the second backup pad through the articulated slab, and carry out the banding through the wind instrument board to make the cable testing bridge need not to use extra spare part to realize when needs buckle, can effectual saving installation other spare part required time, thereby improve the installation effectiveness of cable testing bridge.

Description

Combined cable bridge
Technical Field
The utility model relates to a cable testing bridge technical field specifically is a modular cable testing bridge.
Background
The cable bridge is divided into structures of a groove type, a tray type, a ladder type, a grid type and the like, and comprises a support, a supporting arm, an installation accessory and the like. The inner bridge frame of the building can be independently erected and can also be attached to various buildings and pipe gallery supports, the characteristics of simple structure, attractive appearance, flexible configuration, convenience in maintenance and the like are reflected, all parts need to be galvanized, and the inner bridge frame is installed outside the building in the open air.
The existing cable bridge is mostly a support made of a single metal plate, and only can be supported by a cable, when the cable bridge meets the positions such as corners and the like, the cable bridge needs to be connected with extra bend-through due to the fact that the cable bridge cannot be bent, the time required by the installation of the cable bridge is prolonged, and therefore the efficiency of the installation of the cable bridge is greatly reduced.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a modular cable testing bridge to solve the problem that proposes in the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a modular cable testing bridge, includes first backup pad and second backup pad, the equal fixedly connected with curb plate in both sides at first backup pad and second backup pad top, the equal fixedly connected with articulated slab of the adjacent one end of first backup pad and second backup pad, two the articulated slab piles up from top to bottom and articulates through the round pin axle, the top of round pin axle and the top of first backup pad and second backup pad all are provided with the lead frame, adjacent two be provided with the wind instrument board between the curb plate, just the both ends of wind instrument board are connected with two adjacent curb plates respectively.
Preferably, through holes are formed in the top of the first supporting plate and the top of the second supporting plate and the side wall of the side plate in a penetrating mode.
Preferably, the hinge plate has a thickness half of that of the first support plate.
Preferably, a plurality of grooves are formed in the side wall of the top of the lead frame in a penetrating mode at equal intervals.
Preferably, the two ends of the piano plate are fixedly connected with fixing plates, and four corners of each fixing plate penetrate through the screw holes.
Compared with the prior art, the beneficial effects of the utility model are that: the utility model relates to a modular cable testing bridge simple structure, convenient to use, through the articulated slab at the adjacent one end fixed connection of first backup pad and second backup pad, can make buckling between first backup pad and the second backup pad through the articulated slab, and carry out the banding through the wind musical instrument board to make the cable testing bridge need not to use extra spare part when needs buckle and can realize, can effectually practice thrift the required time of other spare parts of installation, thereby improve the installation effectiveness of cable testing bridge.
Drawings
Fig. 1 is a schematic structural view of the present invention;
fig. 2 isbase:Sub>A cross-sectional view taken along the directionbase:Sub>A-base:Sub>A in fig. 1 according to the present invention;
FIG. 3 is a schematic structural view of the piano plate of the present invention;
fig. 4 is a schematic structural diagram of a middle lead frame according to the present invention.
In the figure: 1. a first support plate; 2. a second support plate; 3. a hinge plate; 4. a pin shaft; 5. a lead frame; 6. a groove; 7. a piano plate; 8. a fixing plate; 9. side plates.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-4, the present invention provides a technical solution: the utility model provides a modular cable testing bridge, includes first backup pad 1 and second backup pad 2, the equal fixedly connected with curb plate 9 in both sides at first backup pad 1 and second backup pad 2 top, the equal fixedly connected with articulated slab 3 of the one end that first backup pad 1 and second backup pad 2 are adjacent, two 3 articulated slabs pile up from top to bottom and articulate through round pin axle 4, the top of round pin axle 4 and the top of first backup pad 1 and second backup pad 2 all are provided with lead frame 5, adjacent two be provided with wind instrument board 7 between the curb plate 9, just the both ends of wind instrument board 7 are connected with two adjacent curb plates 9 respectively.
All run through on the top of first backup pad 1 and second backup pad 2 and the lateral wall of curb plate 9 and seted up the through-hole, the through-hole is convenient for assemble the cable testing bridge.
The thickness of the hinge plate 3 is half of that of the first support plate 1, and the thickness of the two hinge plates 3 stacked together is just the same as that of the first support plate 1 and the second support plate 2.
A plurality of grooves 6 are formed in the side wall of the top of the lead frame 5 in a penetrating mode at equal intervals, and the plurality of grooves 6 enable the lead frame 5 to support multiple groups of cables simultaneously.
The equal fixedly connected with fixed plate 8 in both ends of wind organ board 7, the screw has all been run through to set up in the four corners department of fixed plate 8, can make the bolt pass fixed plate 8 through the screw and fix it with curb plate 9, is convenient for carry out the dismouting to organ board 7.
Specifically, when the straightway was used, can normally install this cable testing bridge, the same with current crane span structure mounting means, when needs buckle, with the articulated slab 3 on first backup pad 1 and the second backup pad 2 use round pin axle 4 to rotate as the axle center, first backup pad 1 and second backup pad 2 organ board 7 can stretch out and draw back thereupon and produce the change when buckling, organ board 7 can be to first backup pad 1 and second backup pad 2 do not be provided with the banding that carries on of curb plate 9, thereby make the cable testing bridge need not to use extra spare part to realize when needs buckle, can effectually practice thrift the required time of other spare parts of installation, thereby improve the installation effectiveness of cable testing bridge.
In the description of the present invention, it is to be understood that the terms "coaxial", "bottom", "one end", "top", "middle", "other end", "upper", "one side", "top", "inner", "front", "center", "both ends", and the like, indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplicity of description, and do not indicate or imply that the device or element referred to must have a particular orientation, be constructed and operated in a particular orientation, and therefore, should not be construed as limiting the present invention.
Furthermore, the terms "first", "second", "third", "fourth" are used for descriptive purposes only and are not to be construed as indicating or implying a relative importance or implicitly indicating the number of technical features indicated, whereby the features defined as "first", "second", "third", "fourth" may explicitly or implicitly include at least one such feature.
In the present invention, unless otherwise expressly stated or limited, the terms "mounted," "disposed," "connected," "fixed," "screwed" and the like are to be construed broadly, e.g., as meaning fixedly connected, detachably connected, or integrally formed; can be mechanically or electrically connected; they may be directly connected or indirectly connected through an intermediate medium, and may be connected through the inside of two elements or in an interaction relationship between two elements, unless otherwise specifically defined, and the specific meaning of the above terms in the present invention will be understood by those skilled in the art according to specific situations.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (5)

1. The utility model provides a modular cable testing bridge, its characterized in that, includes first backup pad (1) and second backup pad (2), the equal fixedly connected with curb plate (9) in both sides at first backup pad (1) and second backup pad (2) top, the equal fixedly connected with articulated slab (3) of one end that first backup pad (1) and second backup pad (2) are adjacent, two pile up from top to bottom and articulate through round pin axle (4) articulated slab (3), the top of round pin axle (4) and the top of first backup pad (1) and second backup pad (2) all are provided with lead frame (5), adjacent two be provided with between curb plate (9) wind musical instrument board (7), just the both ends of wind musical instrument board (7) are connected with two adjacent curb plate (9) respectively.
2. The modular cable tray of claim 1, wherein: the top of the first supporting plate (1) and the second supporting plate (2) and the side wall of the side plate (9) are provided with through holes in a penetrating mode.
3. The modular cable tray of claim 1, wherein: the thickness of the hinge plate (3) is half of that of the first support plate (1).
4. The modular cable tray of claim 1, wherein: the side wall of the top of the lead frame (5) is provided with a plurality of grooves (6) in a penetrating manner at equal intervals.
5. The modular cable tray of claim 1, wherein: the equal fixedly connected with fixed plate (8) in both ends of wind musical instrument board (7), the screw has all been seted up in the four corners department of fixed plate (8) through.
CN202222637474.XU 2022-10-09 2022-10-09 Combined cable bridge Active CN218386589U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222637474.XU CN218386589U (en) 2022-10-09 2022-10-09 Combined cable bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222637474.XU CN218386589U (en) 2022-10-09 2022-10-09 Combined cable bridge

Publications (1)

Publication Number Publication Date
CN218386589U true CN218386589U (en) 2023-01-24

Family

ID=84956719

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222637474.XU Active CN218386589U (en) 2022-10-09 2022-10-09 Combined cable bridge

Country Status (1)

Country Link
CN (1) CN218386589U (en)

Similar Documents

Publication Publication Date Title
US20220007537A1 (en) Container module, container assembly, and data center
CN218386589U (en) Combined cable bridge
CN214195005U (en) Assembled building hoist and mount girder steel
CN212129575U (en) Light steel keel wall unit
CN212649004U (en) High-strength cable bridge
CN210326810U (en) Carbon fiber crane span structure convenient to installation
CN211018133U (en) Cable bridge convenient to installation is maintained
CN219436573U (en) Cable bridge convenient to installation
CN213547033U (en) Bridge connecting piece
CN216489541U (en) Large arc-shaped cable bridge
CN210806640U (en) Combined bridge frame base
CN219247370U (en) Cable anti-winding frame
CN217215786U (en) High-strength assembled cable bridge
CN212153902U (en) Assembled roof suspended beam structure is built in room
CN214574894U (en) Assembled building outer wall structure
CN212323635U (en) Cable threading subassembly and applied photovoltaic support of this subassembly convenient to nimble equipment
CN221263231U (en) Layered assembled composite cable bridge
CN215378339U (en) Energy-conserving crane span structure of high strength stable form
CN212304546U (en) Large-span cable bridge
CN215252907U (en) Reinforced support piece
CN213341550U (en) Adjustable cable bridge
CN211949927U (en) Fender is enclosed in construction
CN210326803U (en) Reinforced large-span cable bridge
WO2017138251A1 (en) Affixation fitting and photovoltaic power generation device
CN217399993U (en) Energy-saving assembled building structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant