CN218374010U - Fill multi-functional counterfort formula barricade in district - Google Patents

Fill multi-functional counterfort formula barricade in district Download PDF

Info

Publication number
CN218374010U
CN218374010U CN202222197482.7U CN202222197482U CN218374010U CN 218374010 U CN218374010 U CN 218374010U CN 202222197482 U CN202222197482 U CN 202222197482U CN 218374010 U CN218374010 U CN 218374010U
Authority
CN
China
Prior art keywords
campshed
counterfort
side slope
row
piles
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222197482.7U
Other languages
Chinese (zh)
Inventor
邓宇
赵津廷
章�宁
王荧飞
黄泽军
周文灏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CREEC Chengdu Survey Design and Research Co Ltd
Original Assignee
CREEC Chengdu Survey Design and Research Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CREEC Chengdu Survey Design and Research Co Ltd filed Critical CREEC Chengdu Survey Design and Research Co Ltd
Priority to CN202222197482.7U priority Critical patent/CN218374010U/en
Application granted granted Critical
Publication of CN218374010U publication Critical patent/CN218374010U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

The utility model belongs to the technical field of counterfort formula barricade, a fill multi-functional counterfort formula barricade in district is disclosed, for adopting double row pile and chair form double row pile to have the big problem of warping in order to solve current ultralimit side slope. The utility model discloses a set up outer campshed and interior campshed around the side slope, link together through the tie beam between outer campshed and the interior campshed, the lower extreme of outer campshed and interior campshed deepens into the side slope soil body, the original slope surface line of side slope is extended to the upper end of outer campshed and interior campshed, the bottom plate has been pour at the top of outer campshed and interior campshed, counterfort formula barricade has been pour to the top of bottom plate, one side that is close to interior campshed on the counterfort formula barricade is connected with a plurality of reinforced concrete buttresses, counterfort formula barricade and the bottom plate between the outer campshed form first road, fill out the soil compaction between interior campshed and reinforced concrete buttresses and the side slope and form the compaction region and form the second road at the regional top of compaction.

Description

Fill multi-functional counterfort formula barricade in district
Technical Field
The utility model belongs to the technical field of counterfort formula barricade, concretely relates to fill multi-functional counterfort formula barricade in district.
Background
The side slope with soil slope over 15m is usually defined as an overrun side slope, the implementation difficulty of the supporting engineering is high, the construction cost is high, and the deformation of the side slope is difficult to control.
The conventional treatment modes aiming at the ultralimit slope comprise methods of structural overhead, double-row pile supporting structures, chair type double-row piles and the like. Although the construction cost of the structure overhead method is low, the large amount of earthwork transported outside the field is not easy to dispose, the greening cost of the side slope is high, and if unstable mountain bodies exist on the rear side of the side slope, the stability of the mountain body structure is difficult to ensure after the overhead treatment. The double-row pile supporting structure has high cost, and backfill among piles is difficult to compact during construction; the chair type double-row piles are relatively reasonable in stress, but the connecting beams between the front row and the rear row are inconvenient to construct, and the construction period is relatively long; the conventional double-row piles and the chair type double-row piles have the problem that the supporting structure is deformed greatly, and anchor cables and waist beams are often matched for construction.
SUMMERY OF THE UTILITY MODEL
The utility model discloses a solve current transfinite side slope and adopt double row pile and chair form double row pile to have the big problem of warping, and provide a fill multi-functional buttress formula barricade in district.
For solving the technical problem, the utility model discloses the technical scheme who adopts is:
the utility model provides a fill multi-functional counterfort formula barricade in district, its characterized in that, links together through the tie beam between outer campshed and the inner campshed including setting up outer campshed and the inner campshed around the side slope, the lower extreme of outer campshed and inner campshed is deepened in the side slope soil body, the original slope surface line of side slope is extended to the upper end of outer campshed and inner campshed, the bottom plate has been pour at the top of outer campshed and inner campshed, counterfort formula barricade has been pour to the top of bottom plate, one side that is close to the inner campshed on counterfort formula barricade is connected with a plurality of reinforced concrete counterforts, the bottom plate between counterfort formula barricade and the outer campshed forms first road, fill in between inner campshed and reinforced concrete counterfort and the side slope and consolidate the compaction and form the compaction region and form the second road at the top in the compaction region.
In some embodiments, a retaining plate is disposed between the adjacent outer row piles.
In some embodiments, the bottom ends of the outer and inner camplets penetrate into the soil below the groundwater level.
In some embodiments, the outer row of piles and the inner row of piles are backfilled and compacted.
In some embodiments, a geogrid is laid in the backfill soil between the outer row of piles and the inner row of piles.
In some embodiments, the buttress-type retaining wall and the reinforced concrete buttress are embedded with drain pipes, and the drain pipes are gradually inclined downwards along the direction towards the buttress-type retaining wall.
Compared with the prior art, the utility model discloses following beneficial effect has:
the utility model discloses a fill multi-functional counterfort formula barricade in district, the support of specially adapted transfinite side slope can be applicable to about the two-stage be the highway, strut the highly big side slope, also can be applicable to the lower part and be the highway, the support of the side slope or the landslide that upper portion is the slope body or afforestation, promptly the utility model discloses can regard as the passive back pressure district of landslide body leading edge.
The utility model discloses a backfill compaction district and the double row pile of counterfort formula barricade rear side strut the resistance that the system formed and play the effect of presser foot, to the unstable, the less stable massif of side slope rear portion play the effect of presser foot, have the effect that the landslide was administered. Unstable and unstable mountains at the rear part of the side slope are often found on roads in adjacent valleys, river valleys and low-lying areas with digging and filling combination.
In the use process of the utility model, the different embedding depths of the front row piles and the rear row piles and the positions of the outer walls of the buttress retaining walls are considered, so that the moment of the buttress retaining wall tends to be balanced, and the bottom plate is similar to a weighing platform of the weighing retaining wall; the stress of the structure is reduced, so that the reinforcing bars of the structure are reduced; the geogrid is laid in the backfill soil between the outer row piles and the inner row piles, so that equivalent shear strength parameters of the fill soil can be improved, the soil pressure is further reduced, the reinforcing bars and the section size of a supporting system are further reduced, and the purpose of reducing the construction cost is achieved; the utility model discloses the bottom plate of well outer row of piles and interior row of pile top has reduced the road and has subsided deformation and corresponding road bed engineering volume as reinforced concrete structure.
In summary, compared with the double-row pile and chair type double-row pile supporting structure in the prior art, the utility model has the advantages that the pressing foot function can be realized, and the deformation of the supporting structure is reduced because the good treatment effect is realized on the landslide body; and the moment of the counterfort retaining wall tends to be balanced, so that the reinforcing bars and the section size of the supporting system are reduced, and the aim of reducing the construction cost is fulfilled.
Drawings
Fig. 1 is a schematic structural diagram of an embodiment of the present invention;
the labels in the figure are: 01. the method comprises the following steps of an original slope surface line, 02, an underground waterline, 1, double rows of piles, 11, outer rows of piles, 12, inner rows of piles, 2, a counterfort type retaining wall, 3, a connecting beam, 4, a drain pipe, 5, a reinforced concrete counterfort, 6, a retaining plate, 7, a bottom plate, 8, a compaction area, 9, a first road, 10 and a second road.
Detailed Description
The present invention will be further described with reference to the following examples, which are only some, but not all, of the examples of the present invention. Based on the embodiments in the present invention, other embodiments used by those skilled in the art without creative work belong to the protection scope of the present invention.
In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplification of description, but do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and thus, should not be construed as limiting the present invention; the terms "first," "second," and "third" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance; furthermore, unless expressly stated or limited otherwise, the terms "mounted," "connected," and "connected" are to be construed broadly, as they may be fixedly connected, detachably connected, or integrally connected, for example; may be a mechanical connection; may be directly connected or indirectly connected through an intermediate. To those of ordinary skill in the art, the specific meaning of the above terms in the present invention can be understood in combination with the specific situation.
Combine the attached drawing, the utility model discloses a multi-functional counterfort formula barricade in fill district, including setting up outer row of stake 11 and interior row of stake 12 around the side slope, wherein, outer row of stake and interior row of stake constitution double row stake 1, wherein outer row of stake 11 keeps away from the hillside more for interior row of stake 12, and outer row of stake 11 is closer to the toe for interior row of stake 12, links together through tie beam 3 between outer row of stake 11 and the interior row of stake 12, the lower extreme of outer row of stake 11 and interior row of stake 12 is deepened in the side slope soil body, the original facial line 01 of side slope is extended to the upper end of outer row of stake 11 and interior row of stake 12, bottom plate 7 has been pour at the top of outer row of stake 11 and interior row of stake 12, counterfort formula barricade 2 has been pour to the top of bottom plate 7 between bottom plate 7, one side that is close to interior row of buttress formula barricade 12 is connected with a plurality of reinforced concrete counterfort 5, counterfort 2 and bottom plate 7 between outer row of stake 11 form first road 9, interior row of stake 12 and reinforced concrete compaction are carried out the compaction and are carried out the compaction in the region top of compaction and are formed the compaction at second compaction region top 8. Wherein the compaction region 8 refers to: and backfilling and compacting the area above the original slope line 01. When the compaction area 8 is compacted by backfilling soil, the layered compaction thickness and the compaction degree of the backfilled soil meet the requirements of corresponding specifications.
In some embodiments, a retaining plate 6 is disposed between adjacent outer rows of piles 11. In the concrete construction process, firstly, the steel bars are planted on the outer row of piles 11, and then the soil retaining plate 6 and the outer row of piles are connected into a whole through the steel bars.
In some embodiments, the bottom ends of the outer row of piles 11 and the inner row of piles 12 penetrate into the ground below the groundwater level 02.
In some embodiments, the outer row of piles 11 and the inner row of piles 12 are backfilled and compacted. The prior art also has a supporting structure with double rows of piles below and a counterfort retaining wall above, but the distance between the double rows of piles in the prior art is the same as the width of a bottom plate of the counterfort retaining wall, and the structure can cause the distance between the double rows of piles to be smaller, so that the backfill soil between the double rows of piles can not be compacted; on the other hand, the structure is difficult to make the moment balance of the buttress type retaining wall, so that the effect of the presser foot cannot be realized, and the governing effect on the landslide body is limited. And the utility model discloses in, the bottom plate of buttress formula barricade 2 is not only regarded as to the bottom plate of outer campshed and interior campshed top, still extends the partial first road 9 (for example highway, perhaps rescue road etc.) of buttress formula barricade simultaneously, not only can play the effect of presser foot, can also increase the interval between outer campshed 11 and the interior campshed 12 simultaneously to it is inseparable to carry out the compaction to the soil body between outer campshed and the interior campshed, thereby improves the bearing capacity of outer campshed and interior campshed. In the prior art, the distance between the inner row of piles and the outer row of piles is small, and soil between the outer row of piles and the inner row of piles is hardly compacted tightly, so that the bearing capacity of the outer row of piles and the bearing capacity of the inner row of piles are reduced, and the problem of deformation is easily caused.
In some embodiments, a geogrid is laid in the backfill soil between the outer row of piles 11 and the inner row of piles 12, so that the equivalent shear strength parameter of the fill soil is improved, and the soil pressure is reduced.
In some embodiments, the buttress retaining wall 2 and the reinforced concrete buttress 5 are embedded with drain pipes, and the drain pipes 4 are gradually inclined downwards in the direction towards the buttress retaining wall 2. Preferably, the drain 4 extends into the compacted zone 8 to facilitate drainage of the backfill within the compacted zone 8.
The utility model discloses a fill multi-functional counterfort formula barricade in district, the support of specially adapted transfinite side slope can be applicable to about the two-stage be the highway, strut the highly big side slope, also can be applicable to the lower part and be the highway, the support of the side slope or the landslide that upper portion is the slope body or afforestation, promptly the utility model discloses can regard as the passive back pressure district of landslide body leading edge.
The utility model discloses a backfilling compaction district and the double row pile of counterfort formula barricade rear side strut the resistance that the system formed and play the effect of presser foot, to the unstable, the less stable massif of side slope rear portion play the effect of presser foot, have the effect that the landslide was administered. Unstable and unstable mountains at the rear part of the side slope are often found on roads in adjacent valleys, river valleys and low-lying areas with digging and filling combination.
In the use process of the utility model, the different embedding depths of the front row piles and the rear row piles and the positions of the outer walls of the counterfort retaining walls are considered, so that the moment of the counterfort retaining wall tends to be balanced, and the bottom plate is similar to a weighing platform of the weighing retaining wall; the stress of the structure is reduced, so that the reinforcing bars of the structure are reduced; the geogrid is laid in the backfill soil between the outer row piles and the inner row piles, so that equivalent shear strength parameters of the fill soil can be improved, the soil pressure is further reduced, the reinforcing bars and the section size of a supporting system are further reduced, and the purpose of reducing the construction cost is achieved; the utility model discloses the bottom plate of well outer row of piles and interior row of pile top has reduced the road and has subsided deformation and corresponding road bed engineering volume as reinforced concrete structure.
In summary, compared with the double-row pile and chair type double-row pile supporting structure in the prior art, the utility model has the advantages that the pressing foot function can be realized, and the deformation of the supporting structure is reduced because the good treatment effect is realized on the landslide body; and the moment of the counterfort retaining wall tends to be balanced, so that the reinforcing bars and the section size of the supporting system are reduced, and the aim of reducing the construction cost is fulfilled.
The utility model discloses a construction engineering does:
(1) Constructing double-row piles, connecting beams and retaining plates: firstly constructing double-row piles 1 (namely outer row piles and inner row piles), and then constructing connecting beams 3 and soil retaining plates 6;
(2) Pouring a bottom plate 7 above the double-row piles 1;
(3) Pouring a counterfort type retaining wall 2 and a reinforced concrete counterfort 5 on the bottom plate; the drain pipe 4 is also embedded when the counterfort retaining wall and the reinforced concrete counterfort are poured;
(4) The compacted zone 8 is backfilled in layers and compacted and forms a second road 10 at the top.

Claims (6)

1. The utility model provides a fill multi-functional counterfort formula barricade in district, its characterized in that, links together through the tie beam between outer campshed and the inner campshed including setting up outer campshed and the inner campshed around the side slope, the lower extreme of outer campshed and inner campshed is deepened in the side slope soil body, the original slope surface line of side slope is extended to the upper end of outer campshed and inner campshed, the bottom plate has been pour at the top of outer campshed and inner campshed, counterfort formula barricade has been pour to the top of bottom plate, one side that is close to the inner campshed on counterfort formula barricade is connected with a plurality of reinforced concrete counterforts, the bottom plate between counterfort formula barricade and the outer campshed forms first road, fill in between inner campshed and reinforced concrete counterfort and the side slope and consolidate the compaction and form the compaction region and form the second road at the top in the compaction region.
2. The filled section multi-functional buttress wall of claim 1, wherein a retaining plate is disposed between adjacent outer row of piles.
3. The filled section multi-functional buttress retaining wall of claim 1, wherein the bottom ends of the outer and inner pickets penetrate into the soil below the groundwater level.
4. The filled section multifunctional buttress type retaining wall of claim 1, wherein backfilling and compaction are performed between the outer row piles and the inner row piles.
5. The filled section multifunctional buttress type retaining wall according to claim 4, wherein a geogrid is laid in the backfill soil between the outer row piles and the inner row piles.
6. The filled segment multi-functional buttress wall of any one of claims 1-5, wherein the buttress wall and the reinforced concrete buttress are embedded with drain pipes, and the drain pipes are gradually inclined downwards in the direction towards the buttress wall.
CN202222197482.7U 2022-08-22 2022-08-22 Fill multi-functional counterfort formula barricade in district Active CN218374010U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222197482.7U CN218374010U (en) 2022-08-22 2022-08-22 Fill multi-functional counterfort formula barricade in district

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222197482.7U CN218374010U (en) 2022-08-22 2022-08-22 Fill multi-functional counterfort formula barricade in district

Publications (1)

Publication Number Publication Date
CN218374010U true CN218374010U (en) 2023-01-24

Family

ID=84967209

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222197482.7U Active CN218374010U (en) 2022-08-22 2022-08-22 Fill multi-functional counterfort formula barricade in district

Country Status (1)

Country Link
CN (1) CN218374010U (en)

Similar Documents

Publication Publication Date Title
CN103410167B (en) Three-dimensional reinforced rigid-soft composite ecological retaining wall and construction method
CN102966119B (en) Geogrid reinforced wall and construction method thereof
CN107905089A (en) A kind of reinforcement platform back of the body for preventing bumping at bridge-head and its construction method
CN105155558A (en) Combined retaining structure and construction method thereof
CN203429660U (en) Stereo stiffened rigid-flexible combined ecological retaining wall
CN103334450B (en) Construction method of pile precast slab retaining wall with drainage ditch
CN212611713U (en) Bearing platform type pile plate wall structure
CN218374010U (en) Fill multi-functional counterfort formula barricade in district
CN216275591U (en) Anti-settlement structure adopting prestressed concrete pipe pile composite foundation
CN215165533U (en) Anchoring structure for side slope of solid waste landfill
CN214993514U (en) Landscape river levee reinforced retaining wall
CN215483004U (en) Expansive soil stratum ultra-deep shaft supporting structure
CN215165799U (en) Reinforced retaining wall
CN212956576U (en) Confined space high fill roadbed side slope foam concrete's reinforced structure
CN100593604C (en) Flexible explosion-proof dike and construction method thereof
CN211872840U (en) Face combination retaining wall structure forever among urban hydraulic engineering
CN211340742U (en) Anti-settlement foundation
CN210134292U (en) Z-shaped retaining wall supporting structure for overhanging road shoulder of high-speed railway foundation
CN112832191A (en) Dyke heightening and reinforcing structure
CN208088319U (en) Build-in soil body restricted type pile slab supporting structure before stake
CN219137649U (en) Pile plate structure suitable for hillside fill side slope
CN214782982U (en) Roadbed structure suitable for bridge connection
CN211849509U (en) Novel roadbed slope protection structure
CN220538696U (en) Pile foundation cantilever plate type retaining wall
CN213508561U (en) Inclined overhanging type supporting structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant