CN218323816U - Construction protection mechanism - Google Patents

Construction protection mechanism Download PDF

Info

Publication number
CN218323816U
CN218323816U CN202222464148.3U CN202222464148U CN218323816U CN 218323816 U CN218323816 U CN 218323816U CN 202222464148 U CN202222464148 U CN 202222464148U CN 218323816 U CN218323816 U CN 218323816U
Authority
CN
China
Prior art keywords
plate
wire pole
seat
pole
standpipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222464148.3U
Other languages
Chinese (zh)
Inventor
聂合联
孔建伟
张志刚
孙琪
余军超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiyuan Guotai Electrical Equipment Co ltd
Original Assignee
Jiyuan Guotai Electrical Equipment Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiyuan Guotai Electrical Equipment Co ltd filed Critical Jiyuan Guotai Electrical Equipment Co ltd
Priority to CN202222464148.3U priority Critical patent/CN218323816U/en
Application granted granted Critical
Publication of CN218323816U publication Critical patent/CN218323816U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Emergency Lowering Means (AREA)

Abstract

The utility model belongs to the technical field of protection machanism's technique and specifically relates to a construction protection machanism is related to, it is including installing the standpipe on the wire pole, the standpipe is connected with the seat that is located the wire pole lateral part through two sets of support unit that are setting up from top to bottom, standpipe and seat all are located the below of optic fibre case on the wire pole, seat and two sets of support unit, the standpipe encloses into the cavity that supplies people's health to pass jointly, the seat includes backup plate and the bedplate that integrated into one piece set up, the backup plate articulates through a plurality of torsional springs towards one side of wire pole has the returning face plate, when the torsional spring is in natural state, the lower surface of returning face plate is contradicted in the upper surface of bedplate, and the interval of returning face plate and wire pole is greater than the interval of bedplate and wire pole. The application can reduce the potential safety hazard when the workman is under construction to optic fibre case on the wire pole in the high altitude.

Description

Construction protection mechanism
Technical Field
The application relates to the technical field of protection mechanisms, in particular to a construction protection mechanism.
Background
For optical fiber communication, ultra-high speed, ultra-large capacity and ultra-long distance transmission are always pursued targets; along with the rapid development of science and technology, optical fiber communication is inseparable with people's life, and the optical fiber box is the indispensable partly in the optical fiber communication, and the optical fiber box is applicable to the distribution connection of optical cable and optical communication equipment, through the optical signal adapter in the optical fiber box, draws forth light signal with the optical jumper wire, realizes the optical distribution function, is applicable to the protective of optical cable and distribution pigtail and connects, also is applicable to the optic fibre termination point among the optical access network.
Some fiber boxes are installed on the higher utility pole and then transported to each corresponding user through the entrance and exit of optical fibers, and some fiber boxes are installed in remote places such as the open air, and also installed on the higher utility pole for safety and maintenance.
Because the fiber box is installed in the high altitude, no matter carry out maintenance operation or insert new user's operation in the light signal adapter, all need the staff to climb to the eminence and go on. The instrument that the staff climbing was used is simple safety belt and climbers more, and present fiber device all is that an independent optic fibre case directly hangs in the eminence moreover, does not have other appurtenance, and the staff is when high altitude construction, and operating space is limited, and misoperation appears easily, when operating time is longer, still has certain potential safety hazard, consequently needs provide a construction protection mechanism.
Disclosure of Invention
In order to reduce the potential safety hazard when the workman carries out the construction to optic fibre case on the wire pole in the high altitude, this application provides a construction protection machanism.
The application provides a construction protection mechanism adopts following technical scheme: the utility model provides a construction protection machanism, including installing the standpipe on the wire pole, the standpipe is connected with the seat that is located the wire pole lateral part through two sets of support element that are setting from top to bottom, standpipe and seat all are located the below of optic fibre case on the wire pole, seat and two sets of support element, the standpipe encloses into the cavity that supplies people's health to pass jointly, the seat includes backup plate and the bedplate that integrated into one piece set up, the backup plate articulates through a plurality of torsional springs towards one side of wire pole has the returning face plate, when the torsional spring is in natural state, the lower surface of returning face plate is contradicted in the upper surface of bedplate, and the interval of returning face plate and wire pole is greater than the interval of bedplate and wire pole.
Optionally, the standpipe includes that two are half a section of thick bamboo that the symmetry set up, and two half corresponding both ends of a section of thick bamboo are all connected through a plurality of first bolted connection pairs, and two half a section of thick bamboos enclose jointly into the centre gripping chamber that the power supply line pole inlayed and establish.
Optionally, the supporting unit comprises two cross rods which are respectively located on two sides of the telegraph pole and extend along the horizontal direction, the cross rods located above and below are respectively and fixedly connected to the backup plate and the seat plate, two sleeves which are respectively and fixedly connected to two half cylinders are sleeved on the cross rods, the four sleeves on the half cylinders are arranged in a rectangular mode, and two butterfly nuts clamped in the two sleeves jointly are further in threaded fit on the cross rods.
Optionally, two staple bolts are installed to corresponding backup plate and bedplate on the wire pole, and backup plate and bedplate all are connected with two pull rods that incline up with the staple bolt that corresponds jointly.
Optionally, the spout that runs through both sides wall is seted up along self width direction to the one end of wire pole to the returning face plate, and sliding fit is equipped with the carriage that extends along returning face plate length direction in the spout, and the carriage bottom all articulates there is the dwang, and two dwangs are connected with the same board of supporting that is located the returning face plate below jointly, and when the carriage was located the spout and was close to wire pole one end, the board can upwards overturn to vertical state.
Optionally, when the supporting plate is located below the turnover plate, the lower surface of the supporting plate is fixedly connected with a soft cushion against which the body of a worker leans.
Optionally, the equal screw-thread fit of dwang lateral wall has fixing bolt, and two screw holes have been seted up to the corresponding fixing bolt of returning face plate lower surface, and when the board upwards overturned and be vertical state, fixing bolt screw-thread fit in screw hole.
To sum up, the application comprises the following beneficial technical effects:
1. the arrangement of the supporting unit realizes the fixed connection of the seat and the vertical pipe;
2. due to the arrangement of the seat, workers can sit on the seat to construct the optical fiber box, and the potential safety hazard of the workers in high-altitude optical fiber operation is reduced;
3. when the upper abutting plate of the seat is turned to be in a vertical state, workers in the cavity can lean against the upper abutting plate, and the functionality of the seat is improved.
Drawings
FIG. 1 is a schematic view of the overall structure in the embodiment of the present application;
FIG. 2 is a schematic diagram of an embodiment of the present application showing a standpipe and a seat;
FIG. 3 is a schematic structural diagram of an embodiment of the present application for illustrating a use status of a resisting plate;
fig. 4 is a schematic structural diagram for showing an unused state of the resisting plate in the embodiment of the present application.
Reference numerals are as follows: 1. a vertical tube; 11. half a cylinder; 12. a first bolt connection pair; 13. a clamping cavity; 2. a supporting unit; 21. a cross bar; 22. a sleeve; 23. a butterfly nut; 3. hooping; 31. a pull rod; 4. a seat; 41. a backup plate; 42. a seat plate; 43. a turnover plate; 44. a torsion spring; 45. a cavity; 5. a chute; 51. a carriage; 52. rotating the rod; 53. a resisting plate; 54. a soft cushion; 55. a threaded hole; 56. fixing the bolt; 6. a utility pole; 7. an optical fiber box.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments.
The present application is described in further detail below with reference to figures 1-4.
The embodiment of the application discloses construction protection mechanism. As shown in fig. 1 and fig. 2, a construction protection mechanism includes a vertical pipe 1 installed on a telegraph pole 6, the vertical pipe 1 is connected with a seat 4 located at the side of the telegraph pole 6 through two sets of supporting units 2 arranged up and down, the vertical pipe 1 and the seat 4 are both located below an optical fiber box 7 on the telegraph pole 6, and the seat 4, the two sets of supporting units 2 and the vertical pipe 1 jointly enclose a cavity 45 for a human body to pass through.
The staff is before climbing electric wire pole 6, and the climbers can be dressed to both feet, also can dress the safety belt on one's body, and when the staff climbed 7 departments to optic fibre case, the workman health was located inside cavity 45, and support element 2 and seat 4 can protect the workman to the staff can sit and be under construction optic fibre case 7 on seat 4, thereby has reduced the potential safety hazard that the workman carried out the optic fibre operation in the high altitude.
As shown in fig. 2, the vertical tube 1 includes two symmetrically arranged half tubes 11, two corresponding ends of the two half tubes 11 are connected by a plurality of first bolt connection pairs 12, and the two half tubes 11 together enclose a clamping cavity 13 for the telegraph pole 6 to be embedded; when the vertical pipe 1 is installed, the two half cylinders 11 are placed on two sides of the telegraph pole 6, then the nuts of all the first bolt connection pairs 12 are screwed, the first bolt connection pairs 12 fixedly connect the two half cylinders 11 together, the telegraph pole 6 is located in the clamping cavity 13, the two half cylinders 11 are clamped on the telegraph pole 6 together, and then the installation of the vertical pipe 1 on the telegraph pole 6 is completed.
The supporting unit 2 comprises two cross rods 21 which are respectively positioned on two sides of the telegraph pole 6 and extend along the horizontal direction, two sleeves 22 which are respectively and fixedly connected to two half cylinders 11 are sleeved on the cross rods 21, the four sleeves 22 on the half cylinders 11 are arranged in a rectangular mode, and two butterfly nuts 23 which are clamped between the two sleeves 22 together are further in threaded fit on the cross rods 21.
After the vertical pipe 1 is fixedly installed on the telegraph pole 6, two corresponding sleeves 22 on two half cylinders 11 are coaxially arranged and jointly form a pipe unit, so that eight sleeves 22 jointly form four pipe units, a worker holds the seat 4 and ensures that four cross rods 21 on the seat 4 correspond to the four pipe units, then the seat 4 is moved to enable the cross rods 21 to be movably inserted into the two corresponding sleeves 22, finally two butterfly nuts 23 on the cross rods 21 are screwed, the cross rods 21 and the two corresponding sleeves 22 are fixedly connected together through the two butterfly nuts 23, the vertical pipe 1 is locked and fixed on the telegraph pole 6, and therefore installation of the seat 4 on the telegraph pole 6 is completed.
Two anchor ears 3 are arranged on the telegraph pole 6 corresponding to the backup plate 41 and the seat plate 42, and the backup plate 41 and the seat plate 42 and the corresponding anchor ears 3 are connected with two pull rods 31 which incline upwards; staple bolt 3 includes that two are the arc that the symmetry set up, and two opposite both ends of arc all are connected with same second bolted connection pair jointly, and 3 covers of staple bolt are established on wire pole 6 and are fixed on wire pole 6 through two second bolted connection pairs for staple bolt 3 is locked on wire pole 6 by the lock, and staple bolt 3 upwards draws through pull rod 31 and draws in seat 4, has improved the steadiness that seat 4 installed on wire pole 6.
As shown in fig. 2, 3 and 4, the seat 4 comprises a backup plate 41 and a seat plate 42 which are integrally formed, two cross rods 21 located above the upper portion are fixedly connected to the backup plate 41, two fixed connections located below are connected to the seat plate 42, the backup plate 41 is hinged to a turnover plate 43 through a plurality of torsion springs 44 towards one side of the telegraph pole 6, when the torsion springs 44 are in a natural state, the turnover plate 43 is in a horizontal state, the lower surface of the turnover plate 43 is abutted to the upper surface of the seat plate 42, the seat plate 42 is supported on the turnover plate 43, the turnover plate 43 is prevented from rotating downwards, and the distance between the turnover plate 43 and the telegraph pole 6 is larger than the distance between the seat plate 42 and the telegraph pole 6.
Because of the blockking of backup plate 41 and bedplate 42, the returning face plate 43 can use the pin joint to overturn as the rotation axis between backup plate 41 and bedplate 42, when the staff's health got into in cavity 45, the returning face plate 43 can rotate towards backup plate 41 direction, the accent area of cavity 45 also can increase thereupon, and then the staff of being more convenient for gets into inside cavity 45, when the returning face plate 43 did not receive outside application of force, the restoring force of torsional spring 44 impels the returning face plate 43 reverse rotation to reset, and the returning face plate 43 resumes to the horizontality, the staff alright be under construction to fiber box 7 on the returning face plate 43 with the seat.
The spout 5 that runs through both sides wall is seted up along self width direction to the one end of wire pole 6 to returning face plate 43, and sliding fit is equipped with the carriage 51 that extends along returning face plate 43 length direction in the spout 5, and carriage 51 bottom all articulates has dwang 52, and two dwang 52 are connected with same the board 53 that supports that is located returning face plate 43 below jointly, and when carriage 51 was located spout 5 and was close to wire pole 6 one end, support that board 53 can upwards overturn to vertical state.
The resisting plate 53 is positioned below the turning plate 43 when not used, at the moment, the resisting plate 53 is parallel to the turning plate 43, the rotating rod 52 is perpendicular to the turning plate 43 and the resisting plate 53, and the resisting plate 53 is connected with the turning plate 43 through the two rotating rods 52 and the sliding frame 51; when needing to use and support board 53, along spout 5 towards the direction removal carriage 51 that is close to wire pole 6, carriage 51 drives through two dwang 52 and supports board 53 and remove, slide to spout 5 tip after carriage 51, the staff can use the pin joint of dwang 52 and carriage 51 to upwards overturn as the rotation axis and support board 53, support board 53 after the upset supports perpendicular to returning face plate 43 and contradicts in returning face plate 43 lateral wall, returning face plate 43 can support in supporting board 53, at this moment, the staff who is located cavity 45 can lean on and support board 53, support board 53 can support in staff's back or waist, alleviate the fatigue degree of staff's long-time construction in the high altitude.
The side walls of the rotating rod 52 are in threaded fit with fixing bolts 56, the lower surface of the turnover plate 43 is provided with two threaded holes 55 corresponding to the fixing bolts 56, and when the resisting plate 53 is turned upwards to be in a vertical state, the fixing bolts 56 are in threaded fit with the threaded holes 55; when a worker leans against after the resisting plate 53 is turned over, the worker can screw the fixing bolt 56 on the rotating rod 52 into the corresponding threaded hole 55, and the rotating rod 52 and the turning plate 43 are fixedly connected together through the fixing bolt 56, so that the stability of the resisting plate 53 in the leaning process is improved; when the abutting plate 53 is positioned below the turnover plate 43, the lower surface of the abutting plate 53 is fixedly connected with a cushion 54 against which the body of a worker leans, and the cushion 54 is softer than the abutting plate 53, so that the comfort degree of the worker leaning against the abutting plate 53 can be improved.
The implementation principle of the construction protection mechanism in the embodiment of the application is as follows: when the staff climbed the electric wire eminence and constructed optical fiber box 7, staff's health is located cavity 45, support element 2 and seat 4 can protect the workman, and can sit and construct optical fiber box 7 on seat 4, also perhaps the staff can be with support plate 53 adjustment be vertical and conflict in the state of returning face plate 43 side, support plate 53 can supply the staff to lean on, support plate 53 supports staff's back or waist, thereby the potential safety hazard when having reduced the workman and constructed optical fiber box 7 in the high altitude.
The above embodiments are preferred embodiments of the present application, and the protection scope of the present application is not limited by the above embodiments, so: all equivalent changes made according to the structure, shape and principle of the present application shall be covered by the protection scope of the present application.

Claims (7)

1. The utility model provides a construction protection machanism which characterized in that: including installing standpipe (1) on wire pole (6), standpipe (1) is connected with seat (4) that are located wire pole (6) lateral part through two sets of supporting unit (2) that are the upper and lower setting, standpipe (1) and seat (4) all are located the below of optic fibre case (7) on wire pole (6), seat (4) and two sets of supporting unit (2), standpipe (1) enclose into cavity (45) that supply the people's health to pass jointly, backup plate (41) and bedplate (42) that seat (4) set up including integrated into one piece, backup plate (41) articulate through a plurality of torsional springs (44) towards one side of wire pole (6) has returning face plate (43), torsional spring (44) are when natural state, the lower surface of returning face plate (43) is contradicted in the upper surface of bedplate (42), and the interval of returning face plate (43) and wire pole (6) is greater than the interval of bedplate (42) and wire pole (6).
2. A construction guard mechanism as claimed in claim 1, wherein: the vertical pipe (1) comprises two half cylinders (11) which are symmetrically arranged, two corresponding ends of the two half cylinders (11) are connected through a plurality of first bolt connecting pairs (12), and the two half cylinders (11) jointly enclose a clamping cavity (13) for the telegraph pole (6) to be embedded.
3. A construction guard mechanism as claimed in claim 2, wherein: support element (2) include that two lie in horizontal direction extension's of edge horizontal direction (21) of wire pole (6) both sides respectively, lie in the top, horizontal pole (21) of below are fixed connection respectively in backup plate (41) and bedplate (42), all overlap on horizontal pole (21) and be equipped with two respectively fixed connection in two sleeve pipes (22) of half a section of thick bamboo (11), four sleeve pipes (22) on half a section of thick bamboo (11) are the rectangle and arrange, it has two common centre gripping in butterfly nut (23) of two sleeve pipes (22) to go back screw-thread fit on horizontal pole (21).
4. A construction guard mechanism as claimed in claim 3, wherein: two anchor ears (3) are installed corresponding to the backup plate (41) and the seat plate (42) on the telegraph pole (6), and the backup plate (41) and the seat plate (42) are connected with two upward-inclined pull rods (31) together with the corresponding anchor ears (3).
5. The construction guard mechanism of claim 4, wherein: overturning plate (43) set up spout (5) that run through both sides wall along self width direction towards the one end of wire pole (6), sliding fit is equipped with carriage (51) that extend along overturning plate (43) length direction in spout (5), carriage (51) bottom all articulates there is dwang (52), two dwang (52) are connected with same support board (53) that are located overturning plate (43) below jointly, when carriage (51) are located spout (5) and are close to wire pole (6) one end, support board (53) can upwards overturn to vertical state.
6. The construction guard mechanism of claim 5, wherein: when the resisting plate (53) is positioned below the turnover plate (43), the lower surface of the resisting plate (53) is fixedly connected with a cushion (54) against which the body of a worker leans.
7. The construction guard mechanism of claim 5, wherein: the side wall of the rotating rod (52) is in threaded fit with a fixing bolt (56), the lower surface of the turnover plate (43) is provided with two threaded holes (55) corresponding to the fixing bolt (56), and when the support plate (53) is turned upwards to be in a vertical state, the fixing bolt (56) is in threaded fit with the threaded holes (55).
CN202222464148.3U 2022-09-15 2022-09-15 Construction protection mechanism Active CN218323816U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222464148.3U CN218323816U (en) 2022-09-15 2022-09-15 Construction protection mechanism

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222464148.3U CN218323816U (en) 2022-09-15 2022-09-15 Construction protection mechanism

Publications (1)

Publication Number Publication Date
CN218323816U true CN218323816U (en) 2023-01-17

Family

ID=84836837

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222464148.3U Active CN218323816U (en) 2022-09-15 2022-09-15 Construction protection mechanism

Country Status (1)

Country Link
CN (1) CN218323816U (en)

Similar Documents

Publication Publication Date Title
CN218323816U (en) Construction protection mechanism
CN112109059B (en) Safety protection damping device is used in bottom of automobile maintenance
CN206737455U (en) A kind of safety device of exterior wall scaffold
CN206845078U (en) Steady ladder
CN100587534C (en) Optical cable maintenance safe rope ladder
CN209704473U (en) A kind of shaft tower convenient for climbing
CN211851002U (en) Rail guard for high altitude construction
CN103995317B (en) Optical cable high-altitude fusion splicing devices
CN214886128U (en) Dustproof fender that encloses of construction
CN214706982U (en) Flame-retardant fireproof cable bridge
CN109884758B (en) High altitude is with optic fibre operation protection device, optic fibre guiding mechanism and optic fibre case
CN203981917U (en) Optical cable high-altitude fusion splicing devices
CN217612571U (en) Optical fiber operation protection device for high altitude
CN217652309U (en) Anti-falling safety device for construction
CN116791967B (en) Spliced electric power guardrail of outdoor electric power equipment
CN217714518U (en) Safety protection device for high-altitude amusement facility
CN217557933U (en) Protection device for subway operation is maintained
CN213042381U (en) Prevent fence of climbing
CN213952902U (en) Scaffold with safety protection function
CN209709314U (en) A kind of suspension type electrical construction socket
CN220487273U (en) Protective fence for house building construction
CN115110788B (en) Multifunctional combined type pre-buried pipe orifice protection device
CN104064984A (en) Double split wire line maintenance pulley
CN209685271U (en) A kind of bearing-type support lamps structure based on electric power field work construction
CN219654336U (en) Protection plate for constructional engineering

Legal Events

Date Code Title Description
GR01 Patent grant