CN218323723U - Green building engineering wall plastering unit - Google Patents
Green building engineering wall plastering unit Download PDFInfo
- Publication number
- CN218323723U CN218323723U CN202222647603.3U CN202222647603U CN218323723U CN 218323723 U CN218323723 U CN 218323723U CN 202222647603 U CN202222647603 U CN 202222647603U CN 218323723 U CN218323723 U CN 218323723U
- Authority
- CN
- China
- Prior art keywords
- plate
- plastering
- connecting rod
- sleeve
- support frame
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Spray Control Apparatus (AREA)
Abstract
The utility model relates to a wall plastering unit technical field has solved current mechanical float and has had the ash condition that falls, needs the later stage to carry out the problem that the mortar was collected. The utility model provides a green building engineering wall plastering unit, which comprises a bearing substrate, it has two linking connecting rods of installing from top to bottom to run through on the bearing substrate, the guide has been cup jointed on the linking connecting rod, the movable terminal surface before bearing substrate of installing of guide, install the subassembly of plastering on the preceding terminal surface of linking connecting rod, the subassembly of plastering is including installing the support frame on linking the connecting rod, install spraying piece and the piece of floating on the support frame, the piece of floating is including cup jointing the lagging on the support frame, the horizontal plate is installed to the lagging front end, supplementary dull and stereotyped board is all installed to the left and right ends of horizontal plate, run through on the lagging and install thickness regulating part, wherein the thickness regulating part is including the regulation pole that runs through in the lagging, it is connected with the horizontal plate backplate to adjust the pole. The utilization degree of mortar in the material guiding process is enhanced, and later-stage collection is avoided.
Description
Technical Field
The utility model relates to a wall plastering unit technical field specifically is a green building engineering wall plastering unit.
Background
The existing building wall plastering is basically manually performed, is influenced by techniques and experiences of constructors, is difficult to completely meet the requirement of wall surface flatness, and needs subsequent leveling operation, and some plastering machines are also provided in the existing market.
SUMMERY OF THE UTILITY MODEL
Not enough to prior art, the utility model provides a green building engineering wall plastering unit has solved current mechanical float and has had the ash condition that falls, needs the later stage to carry out the problem that the mortar was collected, and the reinforcing avoids the later stage to collect at the availability of guide in-process mortar.
In order to achieve the above object, the utility model provides a following technical scheme: a green building engineering wall plastering device comprises a bearing substrate, wherein two connecting rods distributed up and down are installed on the bearing substrate in a penetrating mode, a guide piece is sleeved on each connecting rod in a sleeved mode, the guide piece is movably installed on the right end face of the bearing substrate, and a plastering component is installed on the front end face of each connecting rod;
the plastering component comprises a supporting frame arranged on the connecting rod, a spraying piece and a plastering piece are arranged on the supporting frame, the plastering piece comprises a sleeve plate sleeved on the supporting frame, a horizontal plate is arranged at the front end of the sleeve plate, auxiliary plastering plates are arranged at the left end and the right end of the horizontal plate, and a thickness adjusting piece is arranged on the sleeve plate in a penetrating way;
the thickness adjusting part comprises an adjusting rod penetrating through the sleeve plate, the adjusting rod is connected with the horizontal plate back plate, a buckle sleeve in threaded connection with the adjusting rod is sleeved on the adjusting rod, a connecting sleeve with external threads is rotatably installed at the front end of the buckle sleeve, and a thread groove is formed in the rear end face of the sleeve plate and in threaded connection with the connecting sleeve.
Preferably, the spraying part comprises a material storage cylinder sleeved on the support frame, the front end of the material storage cylinder is provided with a plurality of material spraying heads, the adjacent material spraying heads are provided with some spray holes in a staggered manner, and the rear end of the material storage cylinder is connected with a material pipe for pumping materials.
Preferably, the thickness values of the sleeve plate and the material storage cylinder are the same, and the distance between the front end surface of the horizontal plate and the front end surface of the sleeve plate is equivalent to the distance between the front end surface of the material spraying head and the front end of the material storage cylinder.
Preferably, the connecting rod is L-shaped, and the length of a short rod connected with the supporting frame is greater than 1/2 of the length of the bearing substrate.
Preferably, a transition groove matched with the diameter of the connecting rod is formed in the bearing substrate, a plurality of transmission grooves are symmetrically formed in the wall of the transition groove in the front-back direction, rollers extending longitudinally are mounted in the transmission grooves, middle shafts are mounted on the rollers, and stepping motors are coaxially connected to the middle shafts.
Preferably, the guide part comprises a guide plate, sleeves are mounted on the front and rear plate surfaces of the guide plate, the sleeves are in threaded connection with screws mounted on the bearing substrate, and driving motors are mounted on the screws.
Compared with the prior art, the utility model provides a green building engineering wall plastering unit possesses following beneficial effect:
1. through being provided with spraying spare and floating piece at the support frame, after spraying spare with mortar spraying to the wall body, floating piece screeds the mortar immediately, and then realizes that the mortar does not fall the ash condition when the guide to combine the thickness regulating part of installing on the horizontal plate, under spraying spare and the certain condition of wall body distance, adjust the horizontal plate through the thickness regulating part, satisfy the demand of plastering of different thickness.
2. Set up to the L type through linking up the connecting rod, and link up the short bar length that connecting rod and support frame are connected and be greater than the 1/2 of carrier substrate length to under the circumstances that removes about the support frame, it is spacing not receive carrier substrate to the spraying area of the wall body and the area of plastering, carries out the paining of adaptation demand to the wall body.
Drawings
The accompanying drawings, which are included to provide a further understanding of the application and are incorporated in and constitute a part of this application, illustrate embodiment(s) of the application and together with the description serve to explain the application and not to limit the application. In the drawings:
FIG. 1 is a rear 45-degree angle view of the overall structure of the present invention;
FIG. 2 is a rear view of the combined structure of the guiding element and the plastering assembly of the present invention;
FIG. 3 is a view of the front end of the spray member of the present invention at an angle of 45 degrees;
fig. 4 is the shaft measuring and indicating view of the whole structure of the present invention.
In the figure: 1. a carrier substrate; 11. a transition groove; 12. a roller; 2. a guide member; 21. a guide plate; 22. a sleeve; 3. connecting the connecting rods; 4. a plastering assembly; 41. a support frame; 42. spraying a piece; 421. a storage cylinder; 422. a material spraying head; 423. a material pipe; 43. a floating piece; 431. sheathing; 432. a horizontal plate; 433. a thickness adjusting member; 434. adjusting a rod; 435. buckling and sleeving; 436. a connecting sleeve.
Detailed Description
The embodiments of the present application will be described in detail with reference to the drawings and examples, so that how to implement the technical means for solving the technical problems and achieving the technical effects of the present application can be fully understood and implemented.
FIG. 1-FIG. 4 show an embodiment of the present invention, a green plastering device for construction wall, comprising a supporting substrate 1, a base is mounted on the lower end of the supporting substrate 1 for maintaining the stability of the supporting substrate 1, a guiding member 2 is mounted on one end of the supporting substrate 1, the guiding member 2 comprises a guiding plate 21, sleeves 22 are mounted on the front and back surfaces of the guiding plate 21, the sleeves 22 are in threaded connection with screws mounted on the supporting substrate 1, a driving motor is coaxially connected to the screws, the driving motor is mounted on the supporting substrate 1 through a fixing sleeve, two linking rods 3 are mounted on the supporting substrate 1 and the guiding member 2 in a penetrating manner, the distance between the mounting position of the linking rod 3 on the supporting substrate 1 and the front end surface of the supporting substrate 1 is less than 1/2 of the length of the supporting substrate 1, a plastering component 4 is mounted on the front end surface of the linking rod 3, under the drive of a drive motor, a screw rod rotates, a sleeve 22 sleeved on the screw rod drives a guide plate 21 to move up and down to drive a connecting rod 3 to move and further indirectly drive a plastering component 4 to move, a transition groove 11 matched with the diameter of the connecting rod 3 is formed in a bearing substrate 1, a plurality of transmission grooves are symmetrically formed in the front and back of the groove wall of the transition groove 11, specifically four transmission grooves are formed in the embodiment, a longitudinally extending roller 12 is installed in each transmission groove, a rubber layer is pasted on each roller 12, the distance between the two rollers 12 is smaller than the diameter of the connecting rod 3 by 2mm, so that the connecting rod 3 is clamped and transmitted when the rollers 12 rotate, the up and down movement of the connecting rod 3 is not influenced, middle shafts are installed on the rollers 12, belt wheels are connected on the two middle shafts, one of the two middle shafts is connected with a stepping motor, the belt wheels are connected through a belt, and one of the two middle shafts is connected with the stepping motor, the horizontal transmission of the plastering assembly 4 is indirectly completed by clamping and transmitting the connecting rod 3 through the rotation of the roller 12.
When specifically using, through the roller 12 of installing on the load-bearing substrate 1 to linking the transmission about connecting rod 3, link up on the basis that connecting rod 3 and plastering unit 4 are connected, indirectly drive plastering unit 4 and move in left and right directions, realize controlling the drive to plastering unit 4, and guide 2 carries out the drive from top to bottom to plastering unit 4, satisfies the activity of plastering unit 4 in full wall face region.
The plastering assembly 4 comprises a support frame 41 arranged on a connecting rod 3, the connecting rod 3 is L-shaped, the length of a short rod connected between the connecting rod 3 and the support frame 41 is more than 1/2 of the length of a bearing substrate 1, under the condition that the support frame 41 moves left and right, the spraying area and the plastering area of a wall body are not limited by the bearing substrate 1, the wall body is plastered according to the requirement, the support frame 41 is a rectangular frame, 2 connecting rods 3 are respectively connected with an upper frame body and a lower frame body at the rear end of the support frame 41, a fixing plate is arranged on the support frame 41, the fixing plate is wrapped on the connecting points of the support frame 41 and the connecting rod 3, the connecting points of the support frame 41 and the connecting rod 3 are arranged in the structure of the fixing plate, the connecting rod 3 and the support frame 41 are stably connected, a spraying piece 42 and a plastering piece 43 with the height equal to that of the support frame 41 are arranged on the support frame 41, the plastering piece 43 is provided with the spraying piece 42 and the plastering piece 43, and the plastering piece 43 is used for plastering mortar after the spraying on the wall body, so that the mortar is not fallen during the material guiding.
The leveling member 43 comprises a sleeve plate 431 sleeved on the support frame 41, a horizontal plate 432 is installed at the front end of the sleeve plate 431, auxiliary leveling plates are installed at the left end and the right end of the horizontal plate 432, the front end face of each auxiliary leveling plate is flush with the front end face of the horizontal plate 432, a thickness adjusting member 433 is installed on the sleeve plate 431 in a penetrating mode, the thickness adjusting member 433 comprises an adjusting rod 434 penetrating through the sleeve plate 431, the adjusting rod 434 is connected with a back plate of the horizontal plate 432, a buckle sleeve 435 in threaded connection with the adjusting rod 434 is sleeved on the adjusting rod 434, an engagement sleeve 436 with an external thread is rotatably installed at the front end of the buckle sleeve 435, a thread groove is formed in the rear end face of the sleeve plate 431 and in threaded connection with the engagement sleeve 436, when the wall leveling device is used specifically, the position of the buckle sleeve 435 on the adjusting rod 434 is adjusted firstly, the engagement sleeve 435 is rotated backwards and connected with the sleeve plate 431, the distance adjustment between the horizontal plate 432 and the auxiliary leveling plates is completed, the thickness adjustment between the sleeve plate 431 and a storage barrel 421, the thickness value of the sleeve plate 431 is the same as that the distance between the front end face of the spraying head 422 of the horizontal plate 432 and the spraying barrel, the spraying head is not adjusted by the thickness of the spraying barrel, the spraying head on the spraying barrel, the thickness of the spraying barrel is not consistent thickness adjusting device on the wall surface 422, and the thickness of the base spraying barrel 431 is increased, and the thickness of the spraying barrel, and the spraying barrel 431 is consistent thickness of the spraying barrel, and the thickness of the base spraying barrel 431 is not consistent thickness adjusting device on the wall surface of the spraying barrel, and the wall surface of the spraying barrel 431 is also is satisfied.
The spraying part 42 comprises a storage barrel 421 sleeved on a support frame 41, a plurality of material spraying heads 422 are installed at the front end of the storage barrel 421, mortar is sprayed by installing the material spraying heads 422 on the storage barrel 421, namely, mortar blocks possibly doped in the mortar are completely stirred uniformly are removed, damage to the mortar surface is prevented in the floating process of a horizontal plate 432, spraying holes formed in adjacent material spraying heads 422 are staggered to avoid missing spraying when the mortar is sprayed on a wall body, a material pipe 423 for pumping is connected to the rear end of the storage barrel 421, when the spraying part is used specifically, a pipeline with a pump extends in an external material barrel, the material pipe 423 is connected with the pipeline, the pump is opened, so that the mortar in the material barrel is pumped into the storage barrel 421, and then the mortar is sprayed onto the wall body through the material spraying heads 422.
Through being provided with spraying piece 42 and floating piece 43 at support frame 41, after spraying piece 42 sprayed mortar to the wall body, floating piece 43 leveled the mortar immediately, and then realized that the mortar does not have the ash falling condition when the guide to combine the thickness regulating part 433 that installs on the horizontal plate 432, under the certain circumstances of spraying piece 42 and wall body distance, adjust horizontal plate 432 through thickness regulating part 433, satisfy the demand of plastering of different thickness.
The utility model discloses a control mode is through controller come automatic control, and the control circuit of controller can realize through the simple programming of technical staff in this field, and the providing of power also belongs to the common general knowledge in this field, and the utility model discloses mainly be used for protecting mechanical device, so the utility model discloses no longer explain control mode and circuit connection in detail.
It should be noted that, in this document, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.
Claims (6)
1. The utility model provides a green building engineering wall plastering unit, includes load-bearing substrate (1), its characterized in that: two linking connecting rods (3) which are vertically distributed are installed on the bearing substrate (1) in a penetrating mode, a guide piece (2) is sleeved on each linking connecting rod (3), the guide piece (2) is movably installed on the right end face of the bearing substrate (1), and a plastering assembly (4) is installed on the front end face of each linking connecting rod (3);
the plastering assembly (4) comprises a support frame (41) arranged on the connecting rod (3), a spraying part (42) and a plastering part (43) are arranged on the support frame (41), the plastering part (43) comprises a sleeve plate (431) sleeved on the support frame (41), a horizontal plate (432) is arranged at the front end of the sleeve plate (431), auxiliary plastering plates are arranged at the left end and the right end of the horizontal plate (432), and a thickness adjusting part (433) is arranged on the sleeve plate (431) in a penetrating manner;
the thickness adjusting piece (433) comprises an adjusting rod (434) penetrating through the sleeve plate (431), the adjusting rod (434) is connected with the back plate of the horizontal plate (432), a buckle sleeve (435) in threaded connection with the adjusting rod (434) is sleeved on the adjusting rod (434), a connecting sleeve (436) with external threads is rotatably installed at the front end of the buckle sleeve (435), and a thread groove is formed in the rear end face of the sleeve plate (431) and in threaded connection with the connecting sleeve (436).
2. The green building engineering wall plastering device of claim 1, wherein: spraying spare (42) are including cup jointing storage cylinder (421) on support frame (41), and a plurality of material nozzles (422) are installed to storage cylinder (421) front end, and the orifice has been seted up in the dislocation on adjacent material nozzle (422), and storage cylinder (421) rear end is connected with material pipe (423) that are used for taking out the material.
3. The green building engineering wall plastering device of claim 1, wherein: the thickness value of the sleeve plate (431) is the same as that of the storage barrel (421), and the distance between the front end surface of the horizontal plate (432) and the front end surface of the sleeve plate (431) is equivalent to the distance between the front end surface of the spray head (422) and the front end of the storage barrel (421).
4. The green building engineering wall plastering device of claim 1, wherein: the connecting rod (3) is L-shaped, and the length of a short rod connected with the supporting frame (41) of the connecting rod (3) is greater than 1/2 of the length of the bearing substrate (1).
5. A green architectural engineering wall plastering apparatus according to claim 4, wherein: the bearing substrate (1) is provided with a transition groove (11) matched with the diameter of the connecting rod (3), the wall of the transition groove (11) is symmetrically provided with a plurality of transmission grooves in front and back, the transmission grooves are internally provided with rollers (12) extending longitudinally, the rollers (12) are respectively provided with a middle shaft, and the middle shafts are coaxially connected with stepping motors.
6. The green building engineering wall plastering device of claim 1, wherein: the guide piece (2) comprises a guide plate (21), sleeves (22) are mounted on the front plate surface and the rear plate surface of the guide plate (21), the sleeves (22) are in threaded connection with screws mounted on the bearing base plate (1), and driving motors are mounted on the screws.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202222647603.3U CN218323723U (en) | 2022-10-08 | 2022-10-08 | Green building engineering wall plastering unit |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202222647603.3U CN218323723U (en) | 2022-10-08 | 2022-10-08 | Green building engineering wall plastering unit |
Publications (1)
Publication Number | Publication Date |
---|---|
CN218323723U true CN218323723U (en) | 2023-01-17 |
Family
ID=84823611
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202222647603.3U Active CN218323723U (en) | 2022-10-08 | 2022-10-08 | Green building engineering wall plastering unit |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN218323723U (en) |
-
2022
- 2022-10-08 CN CN202222647603.3U patent/CN218323723U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN111622517B (en) | Brick plastering device and brick plastering equipment | |
CN107740566B (en) | Building wall mortar strickle robot | |
CN218323723U (en) | Green building engineering wall plastering unit | |
CN113530180A (en) | Floor mortar scraper blade for building engineering | |
CN111608368A (en) | Plastering machine convenient to move for building | |
CN112293120A (en) | Film laminating equipment for agricultural production and use method thereof | |
CN205502529U (en) | Intelligence wall plastering device | |
CN214783101U (en) | Highway is road surface leveling device for construction | |
CN115139386A (en) | Assembly type PC prefabricated part manufacturing equipment | |
CN213797310U (en) | A loading attachment for concrete placement processing | |
CN211440654U (en) | Ceramic tile cutting device for building engineering | |
CN210508277U (en) | Trowelling device | |
CN219672014U (en) | Board putty spraying equipment for house construction | |
CN218952710U (en) | High-efficient device of paining of mortar of plastering | |
CN218441022U (en) | Floor heating pipe distribution auxiliary mechanism for house building construction | |
CN220504346U (en) | Waterproofing membrane laying device | |
CN201952035U (en) | Winding pressure roller device of lithium ion battery roller | |
CN221219540U (en) | Wall plastering device for building construction | |
CN219909837U (en) | Ground leveling machine | |
CN217508657U (en) | Solar photovoltaic support for slope | |
CN221396705U (en) | Novel irrigation pipe coiling machine | |
CN217079694U (en) | Connecting device for building templates | |
CN218291964U (en) | Ditch concrete levels device | |
CN215829945U (en) | Wall plastering machine for building | |
CN221739490U (en) | Cable feeding device for communication cable laying engineering |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |