CN218292700U - Scaffold quick-building device in oil-gas module building process - Google Patents
Scaffold quick-building device in oil-gas module building process Download PDFInfo
- Publication number
- CN218292700U CN218292700U CN202222230956.3U CN202222230956U CN218292700U CN 218292700 U CN218292700 U CN 218292700U CN 202222230956 U CN202222230956 U CN 202222230956U CN 218292700 U CN218292700 U CN 218292700U
- Authority
- CN
- China
- Prior art keywords
- bottom plate
- movable door
- working
- support frame
- fixed
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Abstract
The utility model discloses a device is built fast to process scaffold frame is built to oil gas module, the device utilize the electricity on the whole hydraulic drive elevating platform as device bottom removal part and reform transform on it, the welding has the work guardrail, movable door plant, the locking dog, parts such as basket are placed to support frame and material, mutually support between each part, provide one can provide safe operational environment's portable work platform. The device can bear various scaffolds and build required parts, and meanwhile, the portable movement of the building process of the scaffolds is realized, and the scaffolds are built quickly.
Description
Technical Field
The utility model relates to a device is built fast to large-scale module scaffold frame of ocean engineering, especially builds fast in the face of the scaffold frame of well low height.
Background
In the construction process of offshore platforms and related buildings, the construction of scaffolds is indispensable, and the convenience degree of workers can be greatly increased. However, the traditional scaffold building method is time-consuming and labor-consuming, and even if the traditional scaffold building method is used for building a scaffold on a smaller scale, the time-consuming manpower and material resources are large, and the consumed working hours are long.
Disclosure of Invention
An object of the utility model is to overcome prior art's shortcoming, provide one kind and can realize putting up fast of scaffold frame, guarantee the workman put up fast device at the oil gas module construction process scaffold frame of putting up the safety of in-process, can remove at any time.
In order to achieve the above purpose, the utility model discloses a technical scheme is:
the utility model discloses a device is built fast to oil gas module construction process scaffold frame, including electric hydraulic lifting platform, be fixed with a work bottom plate on the top surface of electric hydraulic lifting platform, be fixed with a locking dog on the left wall of work bottom plate, work guardrail has been welded respectively to both sides around the work bottom plate, a bearing is installed through the bearing support respectively in both sides around the left end of work bottom plate, the front and back both ends of a pivot that sets up along the horizontal direction are fixed with the inner circle of a bearing respectively, the inboard of movable door plant is welded fastening with the pivot, movable door plant can drive the pivot maximum rotation 90 degrees and reach horizontal position and support on locking dog, movable door plant can be fixed with the work guardrail of both sides around with through connection structure;
the right wall of the working bottom plate is welded with a support frame, a material placing basket is fixed on the support frame, pipe racks are respectively fixed on the front side and the rear side of the support frame above the material placing basket, and the front pipe rack and the rear pipe rack are used for supporting the front end and the rear end of a pipe.
The utility model has the advantages that: by means of the cooperation between the two parts, the scaffold is portable to move in the building process and can be built quickly. The safety of workers in the building process is guaranteed, the workers can move at any time, the operation is flexible and changeable, and the operation method is suitable for various working environments.
Drawings
Fig. 1 is the utility model discloses a scaffold puts up device's operating condition structure sketch map fast.
Detailed Description
The following describes the present invention with reference to fig. 1.
As shown in fig. 1, the scaffold rapid-building device 5 in the oil-gas module building process comprises an electro-hydraulic lifting platform 11, wherein the electro-hydraulic lifting platform 11 is a commercially available product.
The top surface of electro-hydraulic elevating platform 11 on be fixed with a work bottom plate 7's left wall on be fixed with a locking dog 4 work bottom plate 7 around both sides weld respectively work guardrail 6, both sides are installed a bearing through bearing support respectively around the left end of work bottom plate 7, both ends are fixed continuous with the inner circle of a bearing respectively around the pivot that sets up along the horizontal direction, the inboard and the pivot welded fastening of movable door plant 3, movable door plant 3 can drive the pivot maximum rotation 90 degrees and reach horizontal position and support on locking dog 4, locking dog 4 restriction movable door plant 3 continue to rotate. Under the non-working state, the movable door plate is folded up, the movable door plate can be fixedly connected with the working guardrails 6 on the front side and the rear side through a connecting structure, and the connecting structure can be fixed on the working guardrails 6 through a bolt type structure.
The right wall of the working bottom plate 7 is welded with a support frame 10, a counterweight balance block is preferably added in the support frame 10, so that the effect of balancing the bending moment of the cantilever in the working process is achieved, a material placing basket 9 is fixed on the support frame 10, the material placing basket 9 can be used for storing materials such as paint and lock catches, and pipe racks 8 are respectively fixed on the front side and the rear side of the support frame 10 above the material placing basket 9. The front and the back pipe racks 8 are used for supporting the front and the back ends of the pipe.
The construction process method adopting the device comprises the following steps:
when 1 outer wall of oil gas module is built to needs to carry out, build device 5 with the scaffold fast and remove to building on the deck, accomplish on building the deck and build after to the bottom of scaffold 2, utilize the drive arrangement global motion of electro-hydraulic elevating platform 11 to appointed operating position, then utilize electro-hydraulic elevating platform 11 to construct the material with workman and scaffold and transport appointed height, be close to scaffold 2, treat that the locking dog contacts behind scaffold 2, stop moving, and four fixed feet of fixed electro-hydraulic elevating platform 11, can guarantee its stability in the course of the work.
After the movable door plate 3 reaches a specified position, a worker can put down the movable door plate 3, the stop dog limits the maximum rotation of the movable door plate 3 to 90 degrees, the width of the movable door plate 3 is smaller than the width between two vertical rods, so that the movable door plate can extend into the interior of a scaffold built by the vertical rods, the movable door plate 3 can be used as a temporary movable platform of the worker, and the worker can stand on the movable door plate to perform the building work of the interior of the scaffold after the position of the worker reaches 90 degrees. (the locking dog has two effects, wherein the side effect is used for the holistic position of positioner, and the device stops when it touches the scaffold edge, is unlikely to that the integrated device too is close to the scaffold, and the effect of top surface is that the movable door plant of restriction rotates and makes its rotation range become 0 ~ 90 to atress in workman working process), the material on right side is placed basket 9 and is put the part of 2 in the tubular product frame 8 for building scaffold, steel pipe and hasp etc. make things convenient for the workman to take. The work floor 7 and the movable door panel 3 on the electro-hydraulic lift table 11 provide a large work platform for a worker to prevent the worker from falling. After completing the work at the work site, the worker may retract the movable door panel 3, release the four fixed legs, and then move the electro-hydraulic lift table 11 directly down to another work site.
Claims (2)
1. The utility model provides a device is built fast to oil gas module construction process scaffold frame which characterized in that: the hydraulic lifting platform comprises an electro-hydraulic lifting platform (11), wherein a working bottom plate (7) is fixed on the top surface of the electro-hydraulic lifting platform (11), a stop dog (4) is fixed on the left wall of the working bottom plate, working guardrails (6) are respectively welded on the front side and the rear side of the working bottom plate, a bearing is respectively installed on the front side and the rear side of the left end of the working bottom plate through a bearing support, the front end and the rear end of a rotating shaft arranged along the horizontal direction are respectively and fixedly connected with the inner ring of the bearing, the inner side of a movable door plate (3) is fixedly welded with the rotating shaft, the movable door plate (3) can drive the rotating shaft to rotate 90 degrees to the maximum degree to reach the horizontal position and is supported on the stop dog (4), and the movable door plate can be fixedly connected with the working guardrails (6) on the front side and the rear side through a connecting structure;
the right wall of the working bottom plate is welded with a support frame (10), a material placing basket (9) is fixed on the support frame, pipe racks (8) are respectively fixed on the front side and the rear side of the support frame above the material placing basket, and the front pipe rack and the rear pipe rack are used for supporting the front end and the rear end of a pipe.
2. The oil and gas module construction process scaffold rapid-building device of claim 1, characterized in that: a counterweight is added in the support frame.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202222230956.3U CN218292700U (en) | 2022-08-24 | 2022-08-24 | Scaffold quick-building device in oil-gas module building process |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202222230956.3U CN218292700U (en) | 2022-08-24 | 2022-08-24 | Scaffold quick-building device in oil-gas module building process |
Publications (1)
Publication Number | Publication Date |
---|---|
CN218292700U true CN218292700U (en) | 2023-01-13 |
Family
ID=84795321
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202222230956.3U Active CN218292700U (en) | 2022-08-24 | 2022-08-24 | Scaffold quick-building device in oil-gas module building process |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN218292700U (en) |
-
2022
- 2022-08-24 CN CN202222230956.3U patent/CN218292700U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN112938774B (en) | Integral hoisting system and hoisting method for assembly type component | |
CN103590763B (en) | A kind of oil drilling platform preventer transport erecting device | |
CN108526848B (en) | Base turnover device of wind generating set, yaw system assembly platform and method | |
CN218292700U (en) | Scaffold quick-building device in oil-gas module building process | |
JP5191573B1 (en) | Ground improvement construction machine and ground improvement method suitable for construction in confined spaces | |
JP2011226255A (en) | Super-low overhead clearance excavator, kelly rod employed therewith, and excavating reaction securing method and its mobile device | |
CN203486787U (en) | Integral lifting device for cabinet top of Wiggins coal gas cabinet | |
CN111502294B (en) | Automatic installation method of movable precast concrete wallboard | |
CN213623191U (en) | Supporting platform for oil pipeline anticorrosion and heat preservation construction operation | |
KR102149417B1 (en) | Moving Lift Scaffold System | |
CN210064983U (en) | High-rise building electromechanical device installation carrying device | |
CN203626649U (en) | Blowout preventer transportation and installation device for oil drilling platform | |
CN210454874U (en) | Pipe fitting placer is used in civil engineering construction | |
CN209482685U (en) | A kind of wind-powered electricity generation concrete tower mounting platform | |
CN112320704A (en) | Lifting device for building engineering | |
CN106836109B (en) | Suspended platform device for protecting, repairing and processing bottom of suspended building | |
CN213143825U (en) | Large hanging basket stabilizing device for nuclear power plant construction | |
CN218971217U (en) | Movable arch frame continuous construction device | |
CN220081500U (en) | Small-section tunnel excavation self-moving type foldable trolley | |
CN219732716U (en) | Complete equipment for safety quality control of installation of full-bolt connection steel structure | |
CN214423199U (en) | Steel trestle pile foundation unit | |
CN220954537U (en) | Steel construction overhead working anti-furred ceiling tool equipment | |
CN220642508U (en) | Petroleum blowout preventer overturning system | |
CN213865143U (en) | Rail portable all-angle rotating hoisting device | |
CN212425163U (en) | Hoisting device for construction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |