CN218234524U - Steel construction factory building convenient to installation is fixed - Google Patents

Steel construction factory building convenient to installation is fixed Download PDF

Info

Publication number
CN218234524U
CN218234524U CN202222358155.5U CN202222358155U CN218234524U CN 218234524 U CN218234524 U CN 218234524U CN 202222358155 U CN202222358155 U CN 202222358155U CN 218234524 U CN218234524 U CN 218234524U
Authority
CN
China
Prior art keywords
relative
steelframe
fixed
factory building
mutually
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222358155.5U
Other languages
Chinese (zh)
Inventor
刘旭炎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangxi Guigang Santong Construction Co ltd
Original Assignee
Guangxi Guigang Santong Construction Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangxi Guigang Santong Construction Co ltd filed Critical Guangxi Guigang Santong Construction Co ltd
Priority to CN202222358155.5U priority Critical patent/CN218234524U/en
Application granted granted Critical
Publication of CN218234524U publication Critical patent/CN218234524U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Finishing Walls (AREA)

Abstract

The utility model relates to a steel construction factory building technical field just discloses a steel construction factory building convenient to installation is fixed, including two first steelframes, two one side fixed mounting that first steelframe is relative has the second steelframe, two equal activity of one side that first steelframe is relative is pegged graft and is had T shape pole, two the equal fixedly connected with press platen of one end that T shape pole was carried on the back mutually, the inside rotation of press platen is connected with the bull stick. This steel construction factory building convenient to installation is fixed, press the clamp plate through pressing two relatively, make two press clamp plate relative one side respectively with two first steelframes one side contact mutually away from the body, rotate two double-screw bolts on the clamp plate again, make two double-screw bolt both ends threaded connection's connecting block relative movement, the inserted block through two relative one sides of connecting block respectively with two jacks fit in of the mutually backing mutually one side of wallboard, make two wallboards and first steelframe both sides installation fixed, replaced the fixed mode of nail, thereby the installation of the wallboard of being convenient for is fixed.

Description

Steel construction factory building convenient to installation is fixed
Technical Field
The utility model relates to a steel construction factory building technical field specifically is a steel construction factory building convenient to installation is fixed.
Background
The main bearing member of the steel structure factory building is made of steel, the steel structure building has light weight, high strength, large span and short construction period, and has excellent shock resistance, wind resistance, durability, heat preservation, sound insulation and the like.
The bounding wall all need be installed to the steel construction factory building inside and outside, and present bounding wall installation generally extends into inboard bounding wall after the mounting hole on steel frame surface is passed with the nail in the outside bounding wall, and this kind of mounting means is more troublesome, and need demolish the nail when bounding wall is dismantled, and it is big to dismantle the degree of difficulty. Therefore, a steel structure factory building convenient to install, fix and disassemble is urgently needed to be designed.
SUMMERY OF THE UTILITY MODEL
Technical problem to be solved
The utility model provides a not enough to prior art, the utility model provides a steel construction factory building convenient to installation is fixed possesses advantages such as easy dismounting and installation are fixed effectual, has solved present bounding wall installation and has generally extended into inboard bounding wall after the mounting hole that passes the steelframe surface at the outside bounding wall with the nail, and this kind of mounting means is more troublesome, and need demolish the nail when the bounding wall is dismantled, dismantles the problem that the degree of difficulty is big.
(II) technical scheme
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a steel construction factory building convenient to installation is fixed, includes two first steelframes, two one side fixed mounting that first steelframe is relative has the second steelframe, two equal activity of one side that first steelframe is relative is pegged graft and is had T shape pole, two the equal fixedly connected with in one end that the T shape pole was carried on the back mutually presses the clamp plate, the inside of pressing the clamp plate is rotated and is connected with the bull stick, the equal fixedly connected with double-screw bolt in both ends about the bull stick, two the equal threaded connection in side surface of double-screw bolt has connecting block, two the equal fixedly connected with inserted block in one side that the connecting block is relative, the equal swing joint in the left and right sides of first steelframe has the wallboard, two one side that the inserted block is relative is pegged graft with the bottom activity of two wallboard one side of the back mutually respectively.
Preferably, two equal fixedly connected with reset spring in one side that T shape pole carried on the back mutually, two reset spring's the other end respectively with two one side fixed connection that first steelframes is relative, two double-screw bolts of reversal make two connecting blocks move away from each other for two inserted blocks shift out in the jack of one side that the back mutually was carried on the back mutually respectively from two wallboards, through two reset spring's elasticity effect, make two press the flitch shift out mutually, make both sides connecting block shift out from the upper and lower end of two wallboards respectively, can dismantle the wallboard of first steelframe side.
Preferably, two threaded holes are all seted up in the inside of connecting block, two the side surface of double-screw bolt respectively with the internal thread connection of two screw holes, the screw thread opposite direction on two double-screw bolt surfaces for when just reversing the double-screw bolt, drive two relative or the back-to-back movement of connecting block, the installation of the first steelframe both sides wallboard of being convenient for is fixed and is dismantled.
Preferably, two equal fixedly connected with fixed block of the one end that the double-screw bolt was carried on the back mutually, two one side that the connecting block was carried on the back mutually is respectively with one side swing joint that two fixed blocks are relative, and two fixed blocks can carry on spacingly to the removal of carrying on the back mutually of two connecting blocks, prevent that two connecting blocks from falling from the one end of carrying on the back mutually of two double-screw bolts respectively.
Preferably, two the jack has all been seted up at four angles of wallboard one side of carrying on the back mutually, the inside looks adaptation of inserted block and jack makes two wallboard fixed mounting in the both sides of first steelframe through the both sides inserted block respectively with the jack fit of two wallboard one side of carrying on the back mutually.
Preferably, two equal fixedly connected with guide bar in the relative one side of connecting block, the guide hole has all been seted up according to the left and right sides of pressing the board, two the relative one end of guide bar is pegged graft with the inside activity of two guide holes respectively, through two relative one ends of guide bar respectively with press the guide hole interpolation of the board left and right sides, can lead to the relative or back-to-back movement of two connecting blocks, prevents that the connecting block from rotating along with the double-screw bolt.
Compared with the prior art, the utility model provides a steel construction factory building convenient to installation is fixed possesses following beneficial effect:
1. this steel construction factory building convenient to installation is fixed, press the clamp through the setting, the bull stick, the double-screw bolt, connecting block and inserted block, press two relatively and press the clamp, make two press one side that the clamp is relative respectively with one side contact that two first steelframes carried on the back mutually, rotate two double-screw bolts on pressing the clamp again, make two double-screw bolt both ends threaded connection's connecting block relative movement, the inserted block through two relative one sides of connecting block respectively with the jack fit of two wallboard one side of carrying on the back mutually, make two wallboards and first steelframe both sides installation fixed, the fixed mode of nail has been replaced, thereby the installation of the wallboard of being convenient for is fixed.
2. This steel construction factory building convenient to installation is fixed, through setting up reset spring, two double-screw bolts of reversal make two connecting blocks mutually backing on the back move for two inserted blocks shift out in the jack of two wallboards one side mutually respectively, through two reset spring's spring action, make two press plates shift out mutually on the back, make the both sides connecting block shift out from the upper and lower end of two wallboards respectively, can dismantle the wallboard of first steelframe side, thereby the dismantlement operation of the wallboard of being convenient for.
Drawings
FIG. 1 is a sectional view of the present invention;
FIG. 2 is an enlarged view of the structure A of FIG. 1 according to the present invention;
fig. 3 is a side view of the wall panel structure of the present invention.
Wherein: 1. a first steel frame; 2. a second steel frame; 3. a T-shaped rod; 4. a pressing plate; 5. a rotating rod; 6. a stud; 7. connecting blocks; 8. inserting a block; 9. a wallboard; 10. a return spring; 11. a threaded hole; 12. a fixed block; 13. a jack; 14. a guide bar; 15. and (4) a guide hole.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative efforts all belong to the protection scope of the present invention.
Referring to fig. 1-3, a steel structure factory building convenient for installation and fixation comprises two first steel frames 1, a second steel frame 2 is fixedly installed on one side opposite to the two first steel frames 1, the second steel frame 2 and two wallboards 9 form a unit module, one side of the factory building is composed of a plurality of unit modules, the opposite side of the two first steel frames 1 is movably inserted with a T-shaped rod 3, the opposite side of the two T-shaped rods 3 is fixedly connected with a reset spring 10, the other end of the two reset springs 10 is respectively fixedly connected with the opposite side of the two first steel frames 1, a reset spring 10 is arranged, two studs 6 are reversed to make the two connecting blocks 7 move back and back, so that the two inserting blocks 8 are respectively moved out from the jacks 13 on the opposite side of the two wallboards 9, and the two pressing boards 4 are moved back and back by the elastic force of the two reset springs 10, so that the connecting blocks 7 on the two sides are respectively moved out from the upper end and the lower end of the two wall boards 9, the wall boards 9 on the side surface of the first steel frame 1 can be disassembled, thereby facilitating the disassembling operation of the wall boards 9, the back-to-back ends of the two T-shaped rods 3 are respectively and fixedly connected with the pressing board 4, the inner part of the pressing board 4 is rotatably connected with the rotating rod 5, the left end and the right end of the rotating rod 5 are respectively and fixedly connected with the studs 6, the side surfaces of the two studs 6 are respectively and threadedly connected with the connecting blocks 7, the inner parts of the two connecting blocks 7 are respectively provided with the threaded holes 11, the side surfaces of the two studs 6 are respectively and threadedly connected with the inner parts of the two threaded holes 11, the back-to-back ends of the two studs 6 are respectively and fixedly connected with the fixed blocks 12, the back-to-back sides of the two connecting blocks 7 are respectively and movably connected with the opposite sides of the two fixed blocks 12, the opposite sides of the two connecting blocks 7 are respectively and fixedly connected with the wall boards 9, two relative one sides of inserted block 8 are pegged graft with the bottom activity of two wallboard 9 one side that backs on the back respectively, jack 13 has all been seted up at four angles of two wallboard 9 one side that backs on the back, inserted block 8 and jack 13's inside looks adaptation, set up and press panel 4, bull stick 5, stud 6, connecting block 7 and inserted block 8, press two press panel 4 relatively, make two press panel 4 relative one side contact with two first steelframe 1 one side that backs on the back respectively, two stud 6 on pressing panel 4 rotate again, make two stud 6 both ends threaded connection's connecting block 7 relative movement, inserted block 8 through two relative one sides of connecting block 7 respectively with two wallboard 9 jack 13 fit on one side that backs on the back, make two wallboard 9 and first steelframe 1 both sides installation fixed, the fixed mode of nail has been replaced, thereby be convenient for the installation of wallboard 9 is fixed, the equal fixedly connected with guide bar 14 in two relative one sides of connecting block 7, press panel 4's the left and right sides all seted up guide hole 15, two guide bar 14 relative one end is pegged graft with the inside activity of two guide holes 15 respectively.
When the steel structure is used, the two pressing plates 4 are pressed relatively, one side, opposite to the two pressing plates 4, is respectively contacted with one side, opposite to the two first steel frames 1, of each of the two first steel frames 1, the studs 6 on the two pressing plates 4 are rotated again, the connecting blocks 7 in threaded connection at two ends of the two studs 6 are moved relatively, the inserting blocks 8 on one side, opposite to the two wall plates 9, are matched with the inserting holes 13 on one side, opposite to the two wall plates 9, of each of the two wall plates 9 and the two steel frames 1 are fixedly installed, the two studs 6 are reversely rotated to enable the two connecting blocks 7 to move oppositely, the two inserting blocks 8 are respectively moved out of the inserting holes 13 on one side, opposite to the two wall plates 9, through the elastic action of the two reset springs 10, the two pressing plates 4 are moved out oppositely, the connecting blocks 7 on two sides are respectively moved out of the upper ends and the lower ends of the two wall plates 9, the wall plates 9 on the side of the first steel frame 1 can be disassembled, the steel structure convenient to install and fix, the wallboard 9 is simple and convenient to install and disassemble, a fixing mode of nails is replaced, and the wallboard 9 is convenient to install and use.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (6)

1. The utility model provides a steel construction factory building convenient to installation is fixed, includes two first steelframe (1), its characterized in that: two one side fixed mounting that first steelframe (1) is relative has second steelframe (2), two equal activity of one side that first steelframe (1) is relative is pegged graft and is had T shape pole (3), two equal fixedly connected with of one end that T shape pole (3) were carried on the back mutually presses clamp plate (4), the inside of pressing clamp plate (4) is rotated and is connected with bull stick (5), the equal fixedly connected with double-screw bolt (6) in both ends about bull stick (5), two equal threaded connection in side surface of double-screw bolt (6) has connecting block (7), two equal fixedly connected with inserted block (8) in one side that connecting block (7) is relative, the equal swing joint in both sides in the left and right sides of first steelframe (1) has wallboard (9), two one side that inserted block (8) is relative is pegged graft with the bottom activity of two wallboard (9) one side mutually opposite mutually back respectively.
2. The steel structure factory building convenient to install and fix of claim 1, characterized in that: two equal fixedly connected with reset spring (10) in one side that T shape pole (3) carried on the back mutually, two the other end of reset spring (10) respectively with two first steelframe (1) relative one side fixed connection.
3. The steel structure factory building convenient to install and fix of claim 1, characterized in that: threaded holes (11) are formed in the connecting blocks (7), and the side surfaces of the studs (6) are respectively in threaded connection with the inner threads of the threaded holes (11).
4. The steel structure factory building convenient to install and fix of claim 1, characterized in that: two equal fixedly connected with fixed block (12) in the one end that double-screw bolt (6) carried on the back mutually, two one side that connecting block (7) carried on the back mutually is respectively with two fixed block (12) relative one side swing joint.
5. The steel structure factory building convenient to install and fix of claim 1, characterized in that: two jack (13) have all been seted up in four angles of wallboard (9) one side of the back of the body mutually, the inside looks adaptation of inserted block (8) and jack (13).
6. The steel structure factory building convenient to install and fix of claim 1, characterized in that: two equal fixedly connected with guide bar (14) in the relative one side of connecting block (7), guide hole (15) have all been seted up to the left and right sides of pressing board (4), two the relative one end of guide bar (14) is pegged graft with the inside activity of two guide holes (15) respectively.
CN202222358155.5U 2022-09-05 2022-09-05 Steel construction factory building convenient to installation is fixed Active CN218234524U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222358155.5U CN218234524U (en) 2022-09-05 2022-09-05 Steel construction factory building convenient to installation is fixed

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222358155.5U CN218234524U (en) 2022-09-05 2022-09-05 Steel construction factory building convenient to installation is fixed

Publications (1)

Publication Number Publication Date
CN218234524U true CN218234524U (en) 2023-01-06

Family

ID=84685418

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222358155.5U Active CN218234524U (en) 2022-09-05 2022-09-05 Steel construction factory building convenient to installation is fixed

Country Status (1)

Country Link
CN (1) CN218234524U (en)

Similar Documents

Publication Publication Date Title
CN218234524U (en) Steel construction factory building convenient to installation is fixed
CN216787419U (en) Steel structure node with fixed knot constructs is dismantled in fast-assembling
CN214329323U (en) Multi-story high-rise assembled steel structure mounting base
CN215055375U (en) Arbitrary curved surface clear water concrete template bearing structure
CN212801962U (en) Connecting component for assembling house steel structures
CN111980221B (en) Steel plate concrete shear wall assembly structure for building construction
CN214941280U (en) Green building wall system
CN112081252B (en) Mounting, connecting and reinforcing device for building steel structure
CN212878306U (en) Light-duty commodity circulation goods shelves convenient to installation
CN210917759U (en) Construction locking device for building steel structure
CN211113665U (en) Large-span steel support multidirectional connecting piece for building
CN212835975U (en) Assembled structure is used in civil engineering teaching
CN218437794U (en) Assembled steel construction dysmorphism structure post
CN218881183U (en) Bolted ball grid structure
CN219653939U (en) Prefabricated shear wall connecting component
CN214204725U (en) Stainless steel bridge convenient to installation
CN219552142U (en) Steel construction engineering fastening performance check out test set
CN221030638U (en) Steel structure beam column connecting member
CN217232895U (en) Make things convenient for portable house of dismouting
CN219451207U (en) Curtain wall construction convenient to installation
CN221193680U (en) Assembled steel structure frame for building
CN216516149U (en) Steel construction connecting elements convenient to installation usefulness is dismantled
CN216159317U (en) Steel construction air conditioner support
CN215488339U (en) Concrete pump pipe fixing structure for high-rise building construction
CN219587252U (en) Curtain wall installation positioning device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant