CN218204330U - Special high-strength short pile for building reinforcement - Google Patents

Special high-strength short pile for building reinforcement Download PDF

Info

Publication number
CN218204330U
CN218204330U CN202222347383.2U CN202222347383U CN218204330U CN 218204330 U CN218204330 U CN 218204330U CN 202222347383 U CN202222347383 U CN 202222347383U CN 218204330 U CN218204330 U CN 218204330U
Authority
CN
China
Prior art keywords
pile
end plate
reinforcement
refuting
pile body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222347383.2U
Other languages
Chinese (zh)
Inventor
张传金
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202222347383.2U priority Critical patent/CN218204330U/en
Application granted granted Critical
Publication of CN218204330U publication Critical patent/CN218204330U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model relates to a special high strength short pile of refuting of building reinforcement relates to building foundation reinforcement technical field, and it includes the pile body, is located the end plate at pile body both ends and buries a plurality of reinforcement muscle in the pile body underground, and the length direction of reinforcement muscle is parallel with the length direction of pile body, reinforcement muscle tip with end plate fixed connection. This application refutes the stake through the short and splices into the tubular pile of the required length of construction, need not to prefabricate the tubular pile mould of different length in advance on the one hand, has saved construction cost and time, and the stake of refuting of the foretell short of on the other hand can be transported to the construction site, then assembles the concatenation on the scene, refutes the stake for a short time and has the advantage of convenient to detach and transport in the transportation.

Description

Special high-strength short pile for building reinforcement
Technical Field
The application relates to the technical field of building foundation reinforcement, in particular to a high-strength short pile for building reinforcement.
Background
The tubular pile is a reinforced concrete member for reinforcing a foundation mainly bearing a vertical load, and is divided into a prestressed concrete tubular pile, a prestressed concrete thin-wall tubular pile and a prestressed high-strength concrete tubular pile according to the concrete strength grade and the wall thickness.
Along with the comprehensive promotion of old district transformation work in cities and towns, in the work progress of carrying out old building transformation, often use the tubular pile to consolidate the basis of old building to strengthen old building's structural stability, at the reinforcement in-process, because old building form is various, the size differs, consequently need prefabricate the tubular pile of different length in advance according to the old building size of difference, so that the construction demand when prefabricated tubular pile can satisfy the basis and consolidate.
To the above-mentioned correlation technique, the inventor thinks that prefabricating the tubular pile of different length in advance needs prefabricating the tubular pile mould of different length, takes a lot of work and material when making the tubular pile mould to the tubular pile of longer length is inconvenient to dismantle and carry when the construction.
SUMMERY OF THE UTILITY MODEL
In order to improve the defect that tubular pile exists among the correlation technique, this application provides a special high strength short stake of refuting of building reinforcement.
The application provides a special high strength short pile of refuting of building reinforcement adopts following technical scheme:
the utility model provides a stake is refuted to special high strength weak point of building reinforcement, includes the pile body, is located the end plate at pile body both ends and buries a plurality of reinforcement muscle in the pile body underground, the length direction of reinforcement muscle is parallel with the length direction of pile body, reinforcement muscle tip with end plate fixed connection.
Through adopting above-mentioned technical scheme, foretell short pile of refuting has stable in structure, intensity height, the convenient advantage of preparation. When strengthening old building foundation, can select the short coaxial concatenation of refuting of different quantity according to concrete construction needs, and then assemble the tubular pile of the length that accords with the construction needs to the construction demand when can satisfying the foundation reinforcement to various old buildings. Refute the tubular pile of the required length of concatenation into construction through the weak point, need not to prefabricate the tubular pile mould of different length in advance on the one hand, saved construction cost and time, the foretell weak point of on the other hand refutes the stake and can transport to the construction site, then assembles the concatenation on the scene, refutes the stake for a short time and has the advantage of convenient to detach and transport in the transportation.
Optionally, the coaxial fixedly connected with of reinforcement muscle tip is spacing dish, spacing dish diameter is greater than the diameter of reinforcement muscle, set up the mounting hole that supplies spacing dish to pass on the end plate, the end plate in the hole of dodging that supplies the reinforcement muscle to pass is seted up to mounting hole one side, dodge the hole with the mounting hole intercommunication, the aperture of dodging the hole is less than the diameter of spacing dish.
Through adopting above-mentioned technical scheme, when the stake is refuted to the preparation weak point, will add the reinforcement muscle earlier and be connected with the end plate, then refute a stake skeleton with the weak point and wholly put into tubular pile mould concreting, then centrifugal molding. When connecting reinforcement muscle and end plate, pass the mounting hole with the spacing dish of reinforcement muscle tip earlier, then remove the reinforcement muscle, until the reinforcement muscle be located with the dodge of mounting hole intercommunication downthehole, then remove the direction of keeping away from two end plate orientation each other for the reinforcement muscle tensioning, owing to keep away the aperture in hole and be less than the diameter of spacing dish, consequently spacing dish can prevent that the reinforcement muscle from dodging downthehole the coming off, refute the preparation of stake skeleton with reinforcement muscle both ends and end plate welding completion weak point promptly after that. Foretell structure is convenient for with reinforcing bar joint on the end plate to the follow-up welding operation of being convenient for can prevent through spacing dish that reinforcing bar from dodging downthehole droing, thereby has strengthened the short stability of refuting a skeleton, and then is favorable to improving the short holistic intensity of refuting a.
Optionally, a counter bore used for accommodating the limiting disc is formed in one side, away from the pile body, of the end plate, and the counter bore and the avoiding hole are coaxially arranged.
Through adopting above-mentioned technical scheme, make spacing dish be located the counter bore through setting to the counter bore to avoid spacing dish to bulge the end plate, can guarantee the aesthetic property of the stake of refuting for a short time on the one hand, on the other hand in follow-up centrifugal forming's in-process, the end plate lateral wall can be inseparable with the laminating of tubular pile mould, thereby be favorable to guaranteeing fashioned short steady quality of refuting the stake.
Optionally, the diameter of the counter bore is equal to the diameter of the limiting disc.
Through adopting above-mentioned technical scheme, spacing dish joint just can be in the counter bore to avoid spacing dish to rock in the counter bore, consequently strengthened the stability of being connected of reinforcement muscle and end plate, thereby be convenient for follow-up welding, and because spacing dish joint is in the counter bore, consequently can make the reinforcement muscle of different diameters remain stable. Foretell structure is favorable to reinforcing the stability of being connected of muscle and end plate, and then is favorable to improving short pile holistic stability and intensity of refuting.
Optionally, still include the stirrup, the stirrup is around locating a plurality ofly reinforcement bar periphery and with reinforcement bar fixed connection, the stirrup distributes along pile length direction spiral.
Through adopting above-mentioned technical scheme, when the stake skeleton is refuted to the preparation weak point, will strengthen muscle and end plate welding back, will add the muscle and weld with strengthening the muscle again, refute the holistic intensity of stake skeleton through setting up the stirrup and further strengthened the weak point, and then be favorable to improving the intensity of the fashioned weak point stake of refuting.
Optionally, a hoop plate is respectively disposed on one side of each of the two end plates, the hoop plate is cylindrical, the diameter of the hoop plate is equal to that of the end plate, and the hoop plate is coaxially and fixedly connected with the end plate.
Through adopting above-mentioned technical scheme, can effectively protect and wrap up the pile body perisporium through setting up the hoop board to improve the easy defect that produces the crack of pile body.
Optionally, the inner wall of the hoop plate is provided with a plurality of protrusions facing the center of the hoop plate along the circumferential direction.
Through adopting above-mentioned technical scheme, set up the interlock that the arch can strengthen pile body concrete and hoop plate to the stability of being connected of reinforcing pile body and hoop plate, and then be favorable to improving the holistic stability of short stake of refuting.
Optionally, the reinforcing rib is a twisted steel.
Through adopting above-mentioned technical scheme, the interlock power of reinforcement muscle and pile body concrete can further be strengthened to the reinforcement muscle of twisted steel to the pile body is refuted with the short connection stability of a skeleton, and then is favorable to improving the short holistic stability of stake of refuting.
In summary, the present application includes at least one of the following beneficial technical effects:
1. the short pile has the advantages of stable structure, high strength and convenience in manufacturing; during construction, the short pile is spliced into the tubular pile with the length required by construction, on one hand, pipe pile moulds with different lengths do not need to be prefabricated in advance, so that the construction cost and time are saved, on the other hand, the short pile can be transported to a construction site and then assembled and spliced on site, and the short pile has the advantage of convenience in disassembly and transportation in the transportation process;
2. the hoop plate can effectively protect and wrap the peripheral wall of the pile body, so that the defect that the pile body is easy to crack is overcome;
3. this application is convenient for will add the reinforcement bar joint on the end plate when the stake is refuted to the preparation weak point through having seted up the mounting hole on the end plate, dodging hole and counter bore to be convenient for follow-up welding operation that carries on, can prevent through spacing dish that the reinforcement bar from dodging downthehole droing, thereby strengthened the stability of the stake skeleton of short refuting, and then be favorable to improving the holistic intensity of the stake of short refuting.
Drawings
FIG. 1 is a schematic view of the overall structure of embodiment 1 of the present application;
FIG. 2 is a schematic structural view of an end plate, a hoop plate, a reinforcing rib and a hoop rib of example 1 of the present application;
FIG. 3 is a cross-sectional view of an end plate and a hoop plate of embodiment 1 of the present application;
fig. 4 is a schematic view of the overall structure of embodiment 2 of the present application.
Reference numerals: 1. a pile body; 2. an end plate; 21. mounting holes; 22. avoiding holes; 23. a counter bore; 3. a hoop plate; 31. a protrusion; 4. reinforcing ribs; 41. a limiting disc; 5. and (5) hooping.
Detailed Description
The present application is described in further detail below with reference to figures 1-4.
Example 1
The embodiment of the application discloses special high strength short pile of refuting of building reinforcement.
Referring to fig. 1 and 2, the high-strength short pile special for building reinforcement comprises a pile body 1, an end plate 2, a hoop plate 3, a reinforcing rib 4 and a hoop rib 5.
Referring to fig. 1 and 2, a pile body 1 is a hollow pipe pile formed by concrete through centrifugal forming. End plate 2 is the steel sheet, and end plate 2 runs through along thickness direction and has seted up the through-hole, and end plate 2 can be circular or polygon, and end plate 2 is circular in this embodiment, and end plate 2's external diameter is unanimous with 1 external diameter of pile body, and end plate 2's internal diameter is unanimous with 1 internal diameter of pile body, and end plate 2 is equipped with two, and two end plates 2 are located pile body 1 respectively along length direction's both ends.
Referring to fig. 2 and 3, the two end plates 2 are respectively provided with a hoop plate 3 made of iron sheet at one side close to each other, the hoop plate 3 is cylindrical, the diameter of the hoop plate 3 is consistent with the outer diameter of the end plate 2, the hoop plate 3 is coaxially welded with the end plate 2, and two protrusions 31 facing the center of the hoop plate 3 are arranged on the inner wall of the hoop plate 3 along the circumferential direction. Hoop plate 3 parcel is in 1 periphery of pile body to reduce the 1 cracked possibility that produces of pile body, set up protruding 31 and can strengthen pile body 1 concrete and hoop plate 3's occlusal force, thereby strengthen pile body 1 and hoop plate 3's stability of being connected, and then be favorable to improving the holistic stability of short stake of refuting.
Referring to fig. 2 and 3, the reinforcing rib 4 is a threaded reinforcing bar, the reinforcing rib 4 is embedded in the pile body 1, two ends of the reinforcing rib 4 are respectively welded to the two hoop plates 3, and the length direction of the reinforcing rib 4 is parallel to the length direction of the pile body 1.
Referring to fig. 2 and 3, in this embodiment, the reinforcing ribs 4 are provided with eight reinforcing ribs 4, the eight reinforcing ribs 4 are uniformly distributed along the circumferential direction of the end plate 2 at intervals, the number of the reinforcing ribs 4 in other embodiments may be freely selected according to the requirement of the short pile strength, and the number of the reinforcing ribs is not taken as a limitation to the present application.
Referring to fig. 2 and 3, the coaxial welding of 4 tip of reinforcing bar has spacing dish 41, and the diameter of spacing dish 41 is greater than the diameter of reinforcing bar 4, and the mounting hole 21 that supplies spacing dish 41 to pass is seted up with the junction of reinforcing bar 4 to end plate 2, and end plate 2 offers in mounting hole 21 one side to supply the hole 22 of dodging that reinforcing bar 4 passed, dodges hole 22 in mounting hole 21 intercommunication, and the aperture of dodging hole 22 is less than the diameter of spacing dish 41, and the counter bore 23 that is used for holding spacing dish 41 is offered to one side that end plate 2 deviates from pile body 1, counter bore 23 with dodge the coaxial setting in hole 22, the aperture of counter bore 23 equals with the diameter of spacing dish 41.
Referring to fig. 2 and 3, when reinforcing rib 4 and end plate 2 are connected, pass mounting hole 21 with the spacing dish 41 of reinforcing rib 4 tip earlier, then remove reinforcing rib 4, until reinforcing rib 4 is located dodging the hole 22 with the mounting hole 21 intercommunication, then remove two end plate 2 orientation directions of keeping away from each other for reinforcing rib 4 tensioning, and make spacing dish 41 joint in counter bore 23, thereby make reinforcing rib 4 and end plate 2 remain stable, it can with end plate 2 welding to reinforce rib 4 both ends afterwards.
Referring to fig. 2 and 3, the stirrups 5 are wound around the peripheries of the eight reinforcing bars 4 and welded with the reinforcing bars 4, and the stirrups 5 are spirally wound and distributed along the length direction of the pile body 1.
The length of a single pile of the short pile can be any length from 0.5 m to 4 m; the wall thickness of the pile body can be any size of 60-150 mm; the outer diameter of the pile body can be any size of 300-600 mm.
The implementation principle of the special high-strength short pile of refuting of this application embodiment for building reinforcement does: when the short pile is manufactured, the reinforcing ribs 4 are firstly connected with the end plates 2. When connecting reinforcing rib 4 and end plate 2, pass mounting hole 21 with the spacing dish 41 of 4 tip of reinforcing rib earlier, then remove reinforcing rib 4, until reinforcing rib 4 be located with the mounting hole 21 intercommunication dodge the hole 22 in, then remove the direction that two end plates 2 orientation kept away from each other mutually for reinforcing rib 4 tensioning, owing to the aperture of dodging hole 22 is less than spacing dish 41's diameter, consequently spacing dish 41 can prevent that reinforcing rib 4 from following and dodging the hole 22 and coming off, will reinforce 4 both ends of rib and end plate 2 welding and accomplish the preparation of short stake skeleton of refuting promptly. And then placing the whole short pile driving framework into a pipe pile mould to pour concrete, and then carrying out centrifugal forming to obtain the short pile. The short pile has the advantages of stable structure, high strength and convenience in manufacturing.
When consolidating old building foundation, can select the short coaxial concatenation of refuting of different quantity according to concrete construction needs, then refute the end plate 2 welding at stake both ends with the short, and then assemble into the tubular pile that accords with the length that the construction needs to the construction demand when can satisfying the foundation stabilization to various old buildings. The tubular pile of the required length of construction is spliced into through the short stake of refuting, need not to prefabricate the tubular pile mould of different length in advance on the one hand, has saved construction cost and time, and the stake of refuting of the foretell short of on the other hand can be transported to the construction site, then assembles the concatenation on the scene, and the short stake of refuting has the advantage of convenient to detach and transport in the transportation.
Example 2
Referring to fig. 4, embodiment 2 differs from embodiment 1 in that: pile body 1 is concrete placement's solid pile, and end plate 2 can be circular, polygon, I-shaped or T shape, and end plate 2 is circular in this embodiment, does not set up the through-hole on the end plate 2.
The above embodiments are preferred embodiments of the present application, and the protection scope of the present application is not limited by the above embodiments, so: all equivalent changes made according to the structure, shape and principle of the present application shall be covered by the protection scope of the present application.

Claims (8)

1. The utility model provides a stake is refuted to special high strength weak point of building reinforcement which characterized in that: including pile body (1), be located end plate (2) at pile body (1) both ends and bury a plurality of reinforcement muscle (4) in pile body (1) underground, the length direction of reinforcement muscle (4) is parallel with the length direction of pile body (1), reinforcement muscle (4) tip with end plate (2) fixed connection, end plate (2) are the steel sheet, the length of pile body (1) is 0.5-4m.
2. The special high-strength short pile of refuting of building reinforcement of claim 1, characterized by: reinforcing muscle (4) tip coaxial fixedly connected with is spacing dish (41), spacing dish (41) diameter is greater than the diameter of reinforcing muscle (4), set up mounting hole (21) that supply spacing dish (41) to pass on end plate (2), end plate (2) in mounting hole (21) one side is seted up and is supplied hole (22) of dodging that reinforcing muscle (4) passed, dodge hole (22) with mounting hole (21) intercommunication, the aperture of dodging hole (22) is less than the diameter of spacing dish (41).
3. The special high-strength short pile of refuting of building reinforcement of claim 2, characterized by: one side of the end plate (2) departing from the pile body (1) is provided with a counter bore (23) used for accommodating the limiting disc (41), and the counter bore (23) and the avoiding hole (22) are coaxially arranged.
4. The special high-strength short pile of refuting of building reinforcement of claim 3, characterized by: the diameter of the counter bore (23) is equal to that of the limiting disc (41).
5. The special high-strength short pile of refuting of building reinforcement of claim 1, characterized by: still include stirrup (5), stirrup (5) are around locating a plurality ofly reinforcement muscle (4) periphery and with reinforcement muscle (4) fixed connection, stirrup (5) are along pile body (1) length direction spiral distribution.
6. The special high-strength short pile of refuting of building reinforcement of claim 1, characterized by: one side that two end plates (2) are close to each other is equipped with hoop board (3) respectively, hoop board (3) are the tube-shape, hoop board (3) diameter with end plate (2) diameter equals, hoop board (3) with the coaxial fixed connection of end plate (2).
7. The special high-strength short pile of refuting of building reinforcement of claim 6, characterized by: the inner wall of the hoop plate (3) is provided with a plurality of bulges (31) facing the circle center of the hoop plate (3) along the circumferential direction.
8. The special high-strength short pile of refuting of building reinforcement of claim 1, characterized by: the reinforcing ribs (4) are twisted steel bars.
CN202222347383.2U 2022-09-02 2022-09-02 Special high-strength short pile for building reinforcement Active CN218204330U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222347383.2U CN218204330U (en) 2022-09-02 2022-09-02 Special high-strength short pile for building reinforcement

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222347383.2U CN218204330U (en) 2022-09-02 2022-09-02 Special high-strength short pile for building reinforcement

Publications (1)

Publication Number Publication Date
CN218204330U true CN218204330U (en) 2023-01-03

Family

ID=84628676

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222347383.2U Active CN218204330U (en) 2022-09-02 2022-09-02 Special high-strength short pile for building reinforcement

Country Status (1)

Country Link
CN (1) CN218204330U (en)

Similar Documents

Publication Publication Date Title
CN110983968B (en) Prefabricated assembled FRP (fiber reinforced plastic) -section steel-concrete combined bridge deck and construction method thereof
US9580908B2 (en) Fiber reinforced composite system for strengthening of wall-like RC columns and methods for preparing such system
KR100731593B1 (en) A pre-fabricating forms for concrete-structure and the construction method thereof
CN210562975U (en) Prefabricated assembled hollow sandwich concrete-filled steel tube component
CN218204330U (en) Special high-strength short pile for building reinforcement
CN215168600U (en) Steel pipe concrete combination formula tower section of thick bamboo
CN109826186B (en) General prefabricated reinforced concrete guide wall for underground diaphragm wall and implementation method
CN212223878U (en) Concrete pile cap
CN211806910U (en) Box girder steel pedestal end reinforcing structure
CN113738102A (en) Template building block for civil engineering and manufacturing method and using method thereof
CN111042441A (en) Mold-free superposed column and construction method thereof
CN201627196U (en) Double-end-surface pipe piling sheet
CN220848346U (en) Heavy component embedded part for dense reinforcement distribution area
CN216921022U (en) Prefabricated wall body lacing wire
CN214561758U (en) Prefabricated case roof beam mandrel come-up pull rod device
CN220414536U (en) Assembled RCS combined node
CN219547778U (en) Large-diameter prefabricated pipe pile
CN109252711A (en) Precast splice type steel bar meter field and its manufacturing method
CN209742141U (en) Site operation shear force wall T type horizontal connection structure
CN221143683U (en) Reinforcing structure of hole beam
CN219622107U (en) Assembled cladding steel concrete composite structure
CN217923600U (en) Construction pile structure
CN211499479U (en) Steel pipe concrete composite column
CN214423121U (en) Reinforced box girder and transverse series structure thereof
CN210238491U (en) High-efficient fibre uplift pile device and structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant