CN218195018U - Steel pipe indent workstation - Google Patents

Steel pipe indent workstation Download PDF

Info

Publication number
CN218195018U
CN218195018U CN202222039401.0U CN202222039401U CN218195018U CN 218195018 U CN218195018 U CN 218195018U CN 202222039401 U CN202222039401 U CN 202222039401U CN 218195018 U CN218195018 U CN 218195018U
Authority
CN
China
Prior art keywords
supporting seat
roller
steel pipe
group
shaped plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222039401.0U
Other languages
Chinese (zh)
Inventor
张嘉舜
陈书翰
王敏
万伟伟
余锦漂
李宝堂
陈靖
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangmen Hangtong Shipbuilding Co ltd Of Cccc Fourth Harbor Engineering Co ltd
Original Assignee
Jiangmen Hangtong Shipbuilding Co ltd Of Cccc Fourth Harbor Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangmen Hangtong Shipbuilding Co ltd Of Cccc Fourth Harbor Engineering Co ltd filed Critical Jiangmen Hangtong Shipbuilding Co ltd Of Cccc Fourth Harbor Engineering Co ltd
Priority to CN202222039401.0U priority Critical patent/CN218195018U/en
Application granted granted Critical
Publication of CN218195018U publication Critical patent/CN218195018U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Handcart (AREA)

Abstract

The utility model discloses a steel pipe indent workstation, including supporting seat and gyro wheel mechanism. The supporting seat comprises a first supporting seat, a second supporting seat and an elastic telescopic assembly, wherein the first supporting seat is arranged at the top of the second supporting seat and is connected with the second supporting seat through the elastic telescopic assembly; the roller mechanism comprises a first roller and a second roller which extend along a first direction, the first roller and the second roller are rotatably installed on the first supporting seat and are arranged at intervals along a second direction, and a steel pipe is placed between the first roller and the second roller. The steel pipe indent workstation of this technical scheme can absorb the run-out energy that the indent process produced, plays the effect of buffering, avoids the steel pipe to produce the condition that beats and cause the broken axle of indent equipment, improves indent efficiency, reduces the production input cost, reduces or has avoided the potential safety hazard problem because of the broken axle of indent equipment brings.

Description

Steel pipe indent workstation
Technical Field
The utility model is used for steel pipe indent technical field especially relates to a steel pipe indent workstation.
Background
At present, in engineering projects such as high speed and house construction, a groove is usually adopted for clamp connection in pipeline construction. The field pipe has multiple manufacturing tasks, large groove pressing quantity, large diameter of the pipe and different specifications of different pipes. The traditional on-site steel pipe indent construction is with the indent support as supporting, and to the great (diameter >200 mm), the heavy tubular product of quality of pipe diameter, it rotates the process at the indent and beats slightly, just causes the broken axle of indent equipment very easily, and not only indent efficiency receives the influence, and production facility drops into greatly, extravagant cost, still causes construction potential safety hazard problem.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to solve one of the technical problem that exists among the prior art at least, provide a steel pipe indent workstation, its beat energy that can absorb the indent process and produce plays the effect of buffering, avoids the steel pipe to produce to beat and causes the condition of the disconnected axle of indent equipment, improves indent efficiency, reduces the production input cost, reduces or has avoided the potential safety hazard problem because of the disconnected axle of indent equipment brings.
The utility model provides a technical scheme that its technical problem adopted is:
a steel pipe indent work station, comprising:
the supporting seat comprises a first supporting seat, a second supporting seat and an elastic telescopic assembly, wherein the first supporting seat is arranged at the top of the second supporting seat and is connected with the second supporting seat through the elastic telescopic assembly;
the roller mechanism comprises a first roller and a second roller which extend along a first direction, the first roller and the second roller are rotatably installed on the first supporting seat and are arranged at intervals along a second direction, and a steel pipe is placed between the first roller and the second roller.
In combination with the foregoing implementation manner, in certain implementation manners of the present invention, the roller mechanism further includes a roller distance adjusting assembly, the roller distance adjusting assembly is used for adjusting a distance between the first roller and the second roller.
In combination with the above implementation manner, in certain implementation manners of the utility model, first supporting seat is equipped with two spouts along the first direction interval, the spout extends along the second direction, gyro wheel interval adjustment subassembly is including setting up the first interval adjustment group at the both ends of first gyro wheel is in with the setting the second interval adjustment group at the both ends of second gyro wheel, first interval adjustment group and second interval adjustment group all include wear to locate corresponding side the first threaded connection spare of spout with install in first threaded connection spare's retaining member, first interval adjustment group first threaded connection spare and retaining member be used for with the both ends of first gyro wheel correspond the locking in first supporting seat, second interval adjustment group first threaded connection spare and retaining member be used for with the both ends of second gyro wheel correspond the locking in first supporting seat.
In combination with the foregoing implementation manner, in certain implementations of the present invention, the roller mechanism further includes a first L-shaped plate group and a second L-shaped plate group that are arranged along the second direction interval in the first supporting seat, the first L-shaped plate group and the second L-shaped plate group all include two L-shaped plates that are arranged along the first direction interval, the L-shaped plate includes a bottom plate and a riser that is arranged on one side of the top of the bottom plate, the first roller is rotatably installed in two of the first L-shaped plate group the riser of the L-shaped plate, two of the first L-shaped plate group the bottom plate of the L-shaped plate passes through a first interval adjusting group the first threaded connection piece and the retaining member is correspondingly locked to the first supporting seat, the second roller is rotatably installed in two of the second L-shaped plate group the riser of the L-shaped plate, two of the second L-shaped plate group the bottom plate passes through a second interval adjusting group the first threaded connection piece and the retaining member is correspondingly locked to the first supporting seat.
With the foregoing in mind, in certain implementations of the present invention, the L-shaped plate includes angle iron.
In combination with the above implementation manner, in certain implementation manners of the present invention, the first supporting seat is located each the two ends of the sliding groove are both provided with the limit stop, and the limit stop is used for supporting the L-shaped plate.
In combination with the above implementation manner, the utility model discloses an in some implementation manners, first supporting seat is in each the both ends of spout all are equipped with the screw rod that extends along the second direction, the outside cover of screw rod is equipped with the nut, the screw rod passes through the nut install in first supporting seat, limit stop locates the screw rod is close to the one end of spout.
In combination with the above implementation manner, the utility model discloses an in some implementation manners, 4 corner positions of first supporting seat all are equipped with along the second threaded connection spare of vertical extension, second threaded connection spare's outside cover is equipped with first screw thread regulating block, buffering installation piece and second screw thread regulating block in proper order, the elastic expansion subassembly include four correspond install in the elastic buffer spare of buffering installation piece, elastic buffer spare's top connect in first supporting seat.
With the adoption of the implementation mode, the utility model discloses an in some implementation modes, first supporting seat is the square frame structure, the bottom of second supporting seat is equipped with the cushion.
With the foregoing in mind, in certain implementations of the present invention, the top ends of the first and second rollers are higher than the first supporting seat.
One of the above technical solutions has at least one of the following advantages or beneficial effects: rotate the indent in-process at the steel pipe, because the flexible subassembly sets up between first supporting seat and second supporting seat, make to become elastic support between first supporting seat and the second supporting seat, when the steel pipe rotates inhomogeneous or centrifugal force too big arouses the part to rock, the flexible part can absorb the beat energy that the indent process produced, play the effect of buffering, avoid the steel pipe to produce the condition that beats and cause the disconnected axle of indent equipment, improve indent efficiency, reduce the damage that brings the indent equipment, reduce the production input cost, reduce or avoided the potential safety hazard problem because of the disconnected axle of indent equipment brings.
Drawings
The present invention will be further explained with reference to the accompanying drawings:
fig. 1 is a schematic structural diagram of an embodiment of the present invention;
fig. 2 is a schematic top view of an embodiment of the present invention;
fig. 3 is a schematic side view of an embodiment of the invention;
fig. 4 is an enlarged view of a portion of the first roller and the first distance adjusting unit according to an embodiment of the present invention.
Detailed Description
This section will describe in detail the embodiments of the present invention, preferred embodiments of the present invention are shown in the attached drawings, which are used to supplement the description of the text part of the specification with figures, so that one can intuitively and vividly understand each technical feature and the whole technical solution of the present invention, but they cannot be understood as the limitation of the protection scope of the present invention.
In the present invention, if there is a description of directions (up, down, left, right, front and back), it is only for convenience of description of the technical solution of the present invention, and it is not intended to indicate or imply that the technical features indicated must have a specific orientation, be constructed and operated in a specific orientation, and thus should not be construed as limiting the present invention.
In the utility model, the meaning of "several" is one or more, the meaning of "a plurality of" is more than two, "greater than", "less than", "exceed" and so on are understood as not including the number; the terms "above", "below", "within" and the like are understood to include the instant numbers. In the description of the present invention, if there is any description of "first" and "second" only for the purpose of distinguishing technical features, it is not to be understood as indicating or implying relative importance or implicitly indicating the number of indicated technical features or implicitly indicating the precedence of the indicated technical features.
In the present invention, unless otherwise explicitly defined, the terms "set", "install", "connect", and the like are to be understood in a broad sense, and for example, may be directly connected or may be indirectly connected through an intermediate medium; can be fixedly connected, can also be detachably connected and can also be integrally formed; may be mechanically connected, may be electrically connected or may be capable of communicating with each other; either internal to the two elements or in an interactive relationship of the two elements. The technical skill in the art can reasonably determine the specific meaning of the above words in the present invention by combining the specific contents of the technical solution.
Referring to fig. 1 and 2, an embodiment of the present invention provides a steel pipe grooving table, including a supporting seat and a roller mechanism. The supporting seat includes first supporting seat 11, second supporting seat 12 and elastic expansion subassembly, and the top of second supporting seat 12 is located to first supporting seat 11 to link to each other with second supporting seat 12 through elastic expansion subassembly.
The roller mechanism includes a first roller 21 and a second roller 22 extending along a first direction, and the first roller 21 and the second roller 22 are rotatably mounted on the first supporting base 11 and spaced along a second direction. The first roller 21 and the second roller 22 are used for placing a steel pipe (not shown in the figure), and the steel pipe can rotate rapidly under the support of the first roller 21 and the second roller 22.
During operation, place the supporting seat subaerial, the staff places the steel pipe on first gyro wheel 21 and second gyro wheel 22, opens the indent equipment (not shown in the figure), and the staff adopts manual or other modes slowly to rotate the steel pipe again, and the steel pipe can be in the same direction as smooth rotation under the effect of first gyro wheel 21 and second gyro wheel 22, until accomplishing the indent work. Rotate the indent in-process at the steel pipe, because the elastic stretching subassembly sets up between first supporting seat 11 and second supporting seat 12, make and become elastic support between first supporting seat 11 and the second supporting seat 12, when the steel pipe rotates inhomogeneous or centrifugal force too big and arouses the part to rock, the jump energy that the indent process produced can be absorbed to the elastic stretching subassembly, play the effect of buffering, avoid the steel pipe to produce the condition that beats and cause the disconnected axle of indent equipment, improve indent efficiency, reduce the damage that brings the indent equipment, reduce the production input cost, reduce or avoided the potential safety hazard problem because of the disconnected axle of indent equipment brings.
Further, referring to fig. 2, the roller mechanism further includes a roller spacing adjusting assembly, and the roller spacing adjusting assembly is used for adjusting a spacing between the first roller 21 and the second roller 22, so as to meet the groove pressing requirements of steel pipes with different diameters and sizes. It can be understood that the roller spacing adjustment assembly can be directly driven by a driving cylinder, and can also be adjusted in spacing by a ball screw pair or manual adjustment locking and the like.
In some embodiments, referring to fig. 1 to 3, the first supporting seat 11 is provided with two sliding slots 111 at intervals along the first direction, and the sliding slots 111 extend along the second direction. The roller spacing adjusting assembly comprises a first spacing adjusting group 3 arranged at two ends of the first roller 21 and a second spacing adjusting group 4 arranged at two ends of the second roller 22, the first spacing adjusting group 3 and the second spacing adjusting group 4 respectively comprise a first threaded connecting piece 41 arranged on the sliding groove 111 of the corresponding side in a penetrating manner and a locking piece 42 arranged on the first threaded connecting piece 41, and the first threaded connecting pieces 41 of the first spacing adjusting group 3 and the second spacing adjusting group 4 are arranged on the two sliding grooves 111 in a penetrating manner.
The first screw thread connecting member 41 and the locking member 42 of the first distance adjusting group 3 are used for correspondingly locking both ends of the first roller 21 to the first supporting seat 11, and the first screw thread connecting member 41 and the locking member 42 of the second distance adjusting group 4 are used for correspondingly locking both ends of the second roller 22 to the first supporting seat 11. When the distance between the first roller 21 and the second roller 22 needs to be adjusted, the locking member 42 is firstly loosened, the first threaded connecting member 41 is taken out, the first roller 21 and the second roller 22 are moved to proper positions, the first threaded connecting member 41 can be adopted to penetrate through the sliding groove 111 and the two ends of the corresponding first roller 21 or second roller 22 again, the first roller 21 or second roller 22 is correspondingly locked on the first supporting seat 11 through the locking member 42, the distance adjusting work of the first roller 21 and the second roller 22 is completed, and the steel pipe pressure groove requirements of different diameters and specifications are met.
Further, referring to fig. 1 to 4, the roller mechanism further includes a first L-shaped plate group and a second L-shaped plate group that are disposed at intervals along the second direction on the first supporting seat 11, and each of the first L-shaped plate group and the second L-shaped plate group includes two L-shaped plates 5 that are disposed at intervals along the first direction. L template 5 includes bottom plate 51 and locates the riser 52 of bottom plate 51's top one side, first gyro wheel 21 rotationally installs in the riser 52 of two L templates 5 of first L template 5 group through first shaft 211, the bottom plate 51 of two L templates 5 of first L template 5 group is through first threaded connection 41 and the retaining member 42 of first interval regulation group 3 and correspond locking in first supporting seat 11, realize the detachable connection between first gyro wheel 21 and the first supporting seat 11, easy to assemble.
The second roller 22 is rotatably mounted on the vertical plates 52 of the two L-shaped plates 5 of the second L-shaped plate 5 group through a second wheel shaft 221, and the bottom plates 51 of the two L-shaped plates 5 of the second L-shaped plate 5 group are correspondingly locked on the first supporting seat 11 through the first threaded connecting piece 41 and the locking piece 42 of the second distance adjusting group 4, so that the detachable connection between the second roller 22 and the second supporting seat 12 is realized, and the installation is convenient.
Furthermore, the L-shaped plate 5 comprises angle steel, materials are convenient to obtain, and the use cost is relatively low.
Referring to fig. 2 and 3, in some embodiments, the first supporting seat 11 is provided with a limit stop 6 at each of two ends of each sliding groove 111, and the limit stop 6 is used for abutting against the L-shaped plate 5, so as to avoid the phenomenon that the first roller 21 and the second roller 22 slide towards the two ends of the sliding groove 111 due to the looseness of the locking member 42 caused by vibration, so as to ensure the stability of adjusting the roller distance and ensure the smooth operation of the steel pipe grooving.
Further, with reference to fig. 2 and fig. 3, the first supporting seat 11 is provided with screws 61 extending along the second direction at both ends of each sliding slot 111, a nut 62 is sleeved outside the screw 61, the screw 61 is mounted on the first supporting seat 11 through the nut 62, and the limit stop 6 is disposed at one end of the screw 61 close to the sliding slot 111. When clockwise or anticlockwise rotating screw rod 61, screw rod 61 can drive limit stop 6 and remove under the effect of nut 62 to the installation spacing of difference between adaptation first gyro wheel 21 and the second gyro wheel 22 ensures the location accuracy, thereby guarantees the steel pipe indent process of different diameters size and specification and goes on steadily.
Referring to fig. 1, in some embodiments, the top ends of the first roller 21 and the second roller 22 are higher than the first support seat 11, so that when steel pipes with different lengths are placed between the first roller 21 and the second roller 22, the portions of the steel pipes exceeding the first roller 21 and the second roller 22 in the first direction do not interfere with the first support seat 11, and the steel pipes with different lengths can smoothly complete the grooving operation.
In some embodiments, referring to fig. 1 and 3, the second threaded connection member 7 extending vertically is disposed at each of 4 corner positions of the first support seat 11, a first threaded adjustment block 71, a buffering installation block 73, and a second threaded adjustment block 72 are sequentially sleeved outside the second threaded connection member 7, the first threaded adjustment block 71 and the second threaded adjustment block 72 function to fix the buffering installation block 73, the elastic expansion assembly includes four elastic buffer members 8 correspondingly installed on the buffering installation block 73, and the top of each elastic buffer member 8 is connected to the first support seat 11.
When placing the steel pipe between first gyro wheel 21 and the second gyro wheel 22, if the steel pipe is in the state of perk on one side, then accessible adjustment buffering installation piece 73 is the high position on second threaded connection spare 7 to make the compression of the different degree of production of springy damper 8, until first supporting seat 11 is in the horizontality, thereby make the steel pipe can the level set up between first gyro wheel 21 and second gyro wheel 22, can be in the same direction as smooth without whipping when guaranteeing to rotate the steel pipe, do benefit to going on smoothly of indent work.
Referring to fig. 2, in some embodiments, the first supporting seat 11 is formed in a square frame structure by using a plurality of channel steel enclosures, so that the weight of the first supporting seat 11 can be reduced as much as possible while the load-bearing requirement is ensured, the transfer is facilitated, and the pressure on the elastic buffer 8 can be reduced. First supporting seat 11 and second supporting seat 12 all adopt the channel-section steel welding to form, convenient equipment, and the structure quality is lighter relatively, conveniently carries, shifts.
Referring to fig. 1 and 2, a cushion block 9 is arranged at the bottom of the second support seat 12 to adapt to unevenness of the ground on a construction site, and the support stability of the ground to the second support seat 12 is improved.
In the description herein, references to the description of the term "example," "an embodiment," or "some embodiments," etc., mean that a particular feature, structure, material, or characteristic described in connection with the embodiment or example is included in at least one embodiment or example of the invention. In this specification, the schematic representations of the terms used above do not necessarily refer to the same embodiment or example. Furthermore, the particular features, structures, materials, or characteristics described may be combined in any suitable manner in any one or more embodiments or examples.
The invention is not limited to the above embodiments, and those skilled in the art can make equivalent modifications or substitutions without departing from the spirit of the invention, and such equivalent modifications or substitutions are included in the scope defined by the claims of the present application.

Claims (10)

1. The utility model provides a steel pipe indent workstation which characterized in that includes:
the supporting seat comprises a first supporting seat, a second supporting seat and an elastic telescopic assembly, wherein the first supporting seat is arranged at the top of the second supporting seat and is connected with the second supporting seat through the elastic telescopic assembly;
the roller mechanism comprises a first roller and a second roller which extend along a first direction, the first roller and the second roller are rotatably installed on the first supporting seat and are arranged at intervals along a second direction, and a steel pipe is placed between the first roller and the second roller.
2. The steel pipe notching table of claim 1, wherein the roller mechanism further comprises a roller spacing adjustment assembly for adjusting a spacing between the first roller and the second roller.
3. The steel pipe indent workstation of claim 2, characterized in that, first supporting seat is equipped with two spouts along first direction interval, the spout extends along the second direction, gyro wheel interval adjustment subassembly is including setting up the first interval regulation group at the both ends of first gyro wheel and setting up and being in the second interval regulation group at the both ends of second gyro wheel, first interval regulation group and second interval regulation group all include wear to locate corresponding side the first threaded connection spare of spout with install in first threaded connection spare's retaining member, first interval regulation group first threaded connection spare and retaining member be used for with the both ends of first gyro wheel correspond to lock in first supporting seat, second interval regulation group first threaded connection spare and retaining member be used for with the both ends of second gyro wheel correspond to lock in first supporting seat.
4. The steel pipe indent working table of claim 3, wherein the roller mechanism further comprises a first L-shaped plate group and a second L-shaped plate group which are arranged at intervals along the second direction on the first supporting seat, the first L-shaped plate group and the second L-shaped plate group both comprise two L-shaped plates which are arranged at intervals along the first direction, each L-shaped plate comprises a bottom plate and a vertical plate arranged on one side of the top of the bottom plate, the first roller is rotatably arranged on the vertical plates of the two L-shaped plates of the first L-shaped plate group, the bottom plates of the two L-shaped plates of the first L-shaped plate group are correspondingly locked on the first supporting seat through the first threaded connecting piece and the locking piece of the first spacing adjusting group, the second roller is rotatably arranged on the vertical plates of the two L-shaped plates of the second L-shaped plate group, and the bottom plates of the two L-shaped plates of the second L-shaped plate group are correspondingly locked on the first supporting seat through the first threaded connecting piece and the locking piece of the second spacing adjusting group.
5. The steel pipe indenting station as recited in claim 4 wherein the L-shaped plate includes angle iron.
6. The steel pipe grooving work table of claim 4, wherein the first support base is provided with limit stops at both ends of each sliding groove, and the limit stops are used for abutting against the L-shaped plate.
7. The steel pipe grooving workbench according to claim 6, wherein the first support base is provided with a screw rod extending in the second direction at each end of each sliding groove, a nut is sleeved outside the screw rod, the screw rod is mounted on the first support base through the nut, and the limit stop is arranged at one end of the screw rod close to the sliding groove.
8. The steel pipe indenting workbench according to claim 1, wherein 4 corner positions of the first supporting seat are provided with second threaded connectors extending vertically, a first threaded adjusting block, a buffering installation block and a second threaded adjusting block are sequentially sleeved outside the second threaded connectors, the elastic telescopic assembly comprises four elastic buffer members correspondingly installed on the buffering installation block, and the top of each elastic buffer member is connected to the first supporting seat.
9. The steel pipe grooving work table of claim 1, wherein the first support base is a square frame structure, and a cushion block is disposed at a bottom of the second support base.
10. The steel pipe grooving work table of claim 1, wherein the top ends of the first and second rollers are higher than the first support base.
CN202222039401.0U 2022-08-03 2022-08-03 Steel pipe indent workstation Active CN218195018U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222039401.0U CN218195018U (en) 2022-08-03 2022-08-03 Steel pipe indent workstation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222039401.0U CN218195018U (en) 2022-08-03 2022-08-03 Steel pipe indent workstation

Publications (1)

Publication Number Publication Date
CN218195018U true CN218195018U (en) 2023-01-03

Family

ID=84653758

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222039401.0U Active CN218195018U (en) 2022-08-03 2022-08-03 Steel pipe indent workstation

Country Status (1)

Country Link
CN (1) CN218195018U (en)

Similar Documents

Publication Publication Date Title
CN206600588U (en) A kind of theodolite base
CN215803326U (en) Assembled wall body installation auxiliary assembly
CN209344644U (en) A kind of cable auxiliary arrangement tooling with elevating function
CN218195018U (en) Steel pipe indent workstation
CN201913562U (en) Simple maintenance frame for maintaining flat-panel television (TV)
CN209792316U (en) Steel pipe straightening machine for straightening process
CN209077863U (en) A kind of clamping device for the punching of five golden plates
CN115319699A (en) Steel pipe indent workstation
CN209831566U (en) Water heating pipeline erection bracing frame for building
CN208331578U (en) A kind of adjustable mechanical equipment shock-absorbing foot pad
CN214006513U (en) Adjustable diagonal draw bar
CN215763630U (en) Novel adjustable flange group is to device
CN213867387U (en) Supporting equipment for bridge construction of bridge engineering
CN210187563U (en) Bottom fixing seat for three-dimensional rotary roller coating furnace
CN211419989U (en) Glass cutting machine
CN207113909U (en) A kind of engineering survey equipment support of multi-steering
CN207848763U (en) A kind of horizontal adjustment parallels of high-adaptability complex milling machine
CN214746137U (en) Position regulator for central air conditioner
CN216830741U (en) Detachable workbench
CN219705697U (en) Grooving device for wall wire pipe
CN215176106U (en) Fixing device of solar steel pipe
CN211821337U (en) End bender base
CN220600662U (en) Pipeline fixing support
CN212509798U (en) Simple and easy adjustable strutting arrangement
CN220360218U (en) Combined drawing board for architectural design

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant