CN218149152U - Assembled floor connection structure - Google Patents

Assembled floor connection structure Download PDF

Info

Publication number
CN218149152U
CN218149152U CN202222638764.6U CN202222638764U CN218149152U CN 218149152 U CN218149152 U CN 218149152U CN 202222638764 U CN202222638764 U CN 202222638764U CN 218149152 U CN218149152 U CN 218149152U
Authority
CN
China
Prior art keywords
post
connection
connecting hole
connecting sleeve
assembled floor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222638764.6U
Other languages
Chinese (zh)
Inventor
马秋利
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shaanxi Zhenshang Construction Engineering Co ltd
Original Assignee
Shaanxi Zhenshang Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shaanxi Zhenshang Construction Engineering Co ltd filed Critical Shaanxi Zhenshang Construction Engineering Co ltd
Priority to CN202222638764.6U priority Critical patent/CN218149152U/en
Application granted granted Critical
Publication of CN218149152U publication Critical patent/CN218149152U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

The utility model relates to an assembled floor joint construction technical field, and an assembled floor joint construction is disclosed, including the assembled floor, the one end of assembled floor is equipped with the connecting hole post, one side of connecting hole post is equipped with fixed hole, fixed hole through connection hole post and form the hole, the one end that the assembled floor was kept away from to the connecting hole post is equipped with the connecting sleeve post, the connecting sleeve post is established in the connecting hole post, the connecting sleeve post is close to the one end side of connecting hole post and is equipped with movable joint and detains, the bottom that activity joint was detained is equipped with fixed connection board, the one end that activity joint was detained is kept away from to fixed connection board is equipped with working spring, activity joint is detained and working spring fixed connection, activity joint detains the joint in fixed hole, carry out grouting when the junction is connected and connect more firmly, and the plane is the same, effect after carrying out the form removal is better, the more firm of junction.

Description

Assembled floor connection structure
Technical Field
The utility model relates to an assembled floor joint construction technical field, more specifically relate to an assembled floor joint construction.
Background
In an assembly type building, components such as beams, floor slabs and wall boards need to be split into modules during design, then modularized production is achieved in a factory, and prefabricated components are connected through cast-in-place concrete or steel bar anchoring parts on a construction site to form an integral structure. The prefabricated floor slabs are formed into a whole by adopting post-cast concrete between two adjacent prefabricated floor slabs, and a post-cast section of 30-200mm is generally reserved between the two prefabricated floor slabs.
In the existing connection mode of the floor slab and the H-shaped steel beam, the H-shaped steel beam is also called an I-shaped beam, and a steel plate strip is welded on the lower flange of the steel beam; the floor needs pre-buried iron. In the installation process of the floor slab and the steel beam, the embedded iron and the steel plate strips are positioned and welded, the web plate is perforated to penetrate the steel bars, and large-area secondary grouting pouring is carried out.
The prefabricated building is formed by assembling prefabricated parts on a construction site, the prefabricated parts are produced and processed in a workshop, the field construction adopts the assembly operation, and the cast-in-place operation is greatly reduced. The assembly type building has the characteristics of design standardization and management informatization, the more standard the components are, the higher the production efficiency is, the corresponding component cost can be reduced, and the cost performance of the whole assembly type building is very high by matching with the digital management of a factory. At present, the country actively pushes the structural reform and the novel urbanization development to vigorously develop steel structures and concrete assembled buildings, and the building has the effects of developing new energy-saving and environment-friendly industries, improving the safety level of the buildings, promoting the surplus capacity of chemical decomposition and the like.
But in the field operation process now, the space between two floors needs on-the-spot formwork, and the operation is comparatively difficult, and the thick liquid is leaked easily in the space between template and the floor moreover, and the construction progress is slow, and the extravagant manpower and materials of thick liquid are leaked in the later stage clearance.
SUMMERY OF THE UTILITY MODEL
In order to overcome the above-mentioned defect of prior art, the utility model provides an assembled floor joint construction to solve the problem that exists among the above-mentioned background art.
The utility model provides a following technical scheme: an assembled floor slab connection structure comprises an assembled floor slab, wherein a connecting hole column is arranged at one end of the assembled floor slab and is fixedly connected with the assembled floor slab, a fixed hole is formed in one side of the connecting hole column, the fixed hole penetrates through the connecting hole column and forms a hole, a connecting sleeve column is arranged at one end, away from the assembled floor slab, of the connecting hole column, the connecting sleeve column is arranged in the connecting hole column, a movable clamping buckle is arranged on the side face, close to the connecting hole column, of one end of the connecting sleeve column, a fixed connecting plate is arranged at the bottom end of the movable clamping buckle, the fixed connecting plate is fixedly connected with the movable clamping buckle, a working spring is arranged at one end, away from the movable clamping buckle, of the fixed connecting plate, the movable clamping buckle is fixedly connected with the working spring, and the movable clamping buckle is clamped in the fixed hole;
furthermore, one end, far away from the connecting hole column, of the connecting sleeve column is provided with a through block, the connecting sleeve column is fixedly connected with the through block, the connecting sleeve column is located on the side face of the upper end and the lower end of the through block and is fixedly connected with the side face of the upper end and the lower end of the through block, and the connecting sleeve column is divided into twelve parts which are uniformly distributed on the side face of the upper end and the lower end of the through block.
Further, the one end top that assembled floor is close to the connecting hole post is equipped with the connection fixed plate, the bottom of connecting the fixed plate is equipped with bottom connection template, connect fixed plate and bottom connection template swing joint, the middle part of connecting the fixed plate is equipped with fixing bolt, fixing bolt through connection fixed plate, link up piece and bottom connection template and fixed connection are in the bottom surface of bottom connection template, fixing bolt's top is equipped with fixation nut, fixing bolt runs through fixation nut and swing joint.
Furthermore, the both ends that link up the piece and be close to the assembled floor all are equipped with the connecting sleeve post, the corresponding position of connecting sleeve post is equipped with the connecting hole post, the connecting sleeve post is same axle center with the connecting hole post.
Furthermore, the connection fixing plate, the bottom connecting template and the two-end assembled floor slab are connected on the same plane.
The utility model discloses a technological effect and advantage:
1. the utility model discloses a be equipped with connection fixed plate, bottom connection template, link up piece, fixing bolt and fixation nut, be favorable to carrying out grout when carrying out the junction and connect more firmly, and the plane is the same, and the effect after carrying out the form removal is better, and the junction is more firm.
2. The utility model discloses a be equipped with connecting hole post and connecting sleeve post, be favorable to connecting more firm in the back, make its more whole after grout, make the connection of floor firm more, the wholeness is better, life is ensured.
Drawings
Fig. 1 is a schematic view of the overall structure of the present invention.
Fig. 2 is an explosion diagram of the overall structure of the present invention.
Fig. 3 is a schematic view of the connection structure of the present invention.
Fig. 4 is a schematic view of the buckle structure of the present invention.
Fig. 5 is a schematic view of the connection section structure of the present invention.
The reference signs are: 1. an assembled floor slab; 2. connecting the fixed plate; 3. fixing the bolt; 4. fixing a nut; 5. the bottom is connected with a template; 6. a through block; 7. connecting the hole columns; 701. fixing the hole; 8. connecting the sleeve columns; 801. a movable clamping buckle; 9. a working spring; 901. and fixing the connecting plate.
Detailed Description
The technical solution of the present invention will be described clearly and completely with reference to the drawings in the present invention, and the forms of the structures described in the following embodiments are merely examples, and the assembled floor slab connection structure according to the present invention is not limited to the structures described in the following embodiments, and all other embodiments obtained by a person having ordinary skill in the art without creative work belong to the scope of the present invention.
Referring to fig. 1-5, the utility model provides an assembly type floor slab connection structure, including assembly type floor slab 1, one end of assembly type floor slab 1 is equipped with connecting hole post 7, connecting hole post 7 and assembly type floor slab 1 are fixed connection, one side of connecting hole post 7 is equipped with fixed hole 701, fixed hole 701 runs through connecting hole post 7 and forms the hole, the one end of connecting hole post 7 that keeps away from assembly type floor slab 1 is equipped with connecting sleeve post 8, connecting sleeve post 8 is established in connecting hole post 7, connecting sleeve post 8 is close to the one end side of connecting hole post 7 and is equipped with movable joint knot 801, the bottom of movable joint knot 801 is equipped with fixed connection board 901, fixed connection board 901 and movable joint knot 801 fixed connection, the one end of fixed connection board 901 that keeps away from movable joint knot 801 is equipped with work spring 9, movable joint knot 801 and work spring 9 fixed connection, movable joint knot 801 joint knot is in fixed hole 701;
referring to fig. 2, the one end that connecting sleeve post 8 kept away from connecting hole post 7 is equipped with and link up piece 6, connecting sleeve post 8 with link up 6 fixed connection, connecting sleeve post 8 is located the side and the fixed connection of the last lower extreme that link up piece 6, connecting sleeve post 8 falls into the side of twelve even distributions on link up piece 6 last lower extremes, makes when the floor is connected, more firm, connect more smoothly, the wholeness is higher when making looks floor connect.
Referring to fig. 2, the one end top that assembled floor 1 is close to connecting hole post 7 is equipped with connection fixed plate 2, connection fixed plate 2's bottom is equipped with bottom connection template 5, connection fixed plate 2 and bottom connection template 5 swing joint, connection fixed plate 2's middle part is equipped with fixing bolt 3, fixing bolt 3 through connection fixed plate 2, link up piece 6 and bottom connection template 5 and fixed connection in bottom connection template 5's bottom surface, fixing bolt 3's top is equipped with fixing nut 4, fixing bolt 3 runs through fixing nut 4 and swing joint, make more smooth and easy when connecting, firm wholeness more is higher.
Referring to fig. 3, the two ends of the through block 6, which are close to the assembled floor slab 1, are provided with the connecting sleeve columns 8, the connecting sleeve columns 8 are provided with the connecting hole columns 7 at corresponding positions, and the connecting sleeve columns 8 and the connecting hole columns 7 are in the same axis, so that the floor slab is more firm and smoother in connection.
Referring to fig. 2, the connection fixing plate 2, the bottom connection template 5 and the two-end fabricated floor slab 1 are connected at the same plane, so that the whole effect is better, and the floor slab is more attractive and smooth.
The utility model discloses a theory of operation: during operation, the joints of two fabricated floors 1 are placed at the bottom ends of the fabricated floors 1 through bottom connecting templates 5, the joints are connected with connecting fixing plates 2 and fixing nuts 4 at the tops through blocks 6 through fixing bolts 3, connecting hole columns 7 on one side are connected through connecting sleeve columns 8 after connection, movable clamping is carried out through movable clamping buckles 801 on the connecting sleeve columns 8, the movable clamping buckles 801 move through the fixing connecting plates 901 during operation, working springs 9 work when the fixing connecting plates 901 work, the fixing connecting plates 901 work through the pressure of the working springs 9 when the movable clamping buckles 801 reach the fixing holes 701, the movable clamping buckles 801 move when the fixing connecting plates 901 work, the movable clamping buckles 801 are clamped in the fixing holes 701 completely, then the fabricated floors 1 are clamped similarly, after completion, the fixing bolts 3 are fixedly connected through the fixing nuts 4, the bottom connecting templates 5 and the connecting fixing plates 2 are clamped on the fabricated floors 1, grouting is carried out, after specified time, the bottom connecting templates 5 are connected through the fixing nuts 4, and the bottom connecting templates are disconnected.
The points to be finally explained are: first, in the description of the present application, it should be noted that, unless otherwise specified and limited, the terms "mounted," "connected," "connecting," and "connecting" should be understood broadly, and may be a mechanical connection or an electrical connection, or a communication between two elements, and may be directly connected, and "upper," "lower," "left," and "right" are only used to indicate relative positional relationships, and when the absolute position of the object to be described is changed, the relative positional relationships may be changed;
secondly, the method comprises the following steps: in the drawings of the disclosed embodiments of the present invention, only the structures related to the disclosed embodiments are referred to, and other structures can refer to the common design, and under the condition of no conflict, the same embodiment and different embodiments of the present invention can be combined with each other;
and finally: the above description is only for the purpose of illustrating the preferred embodiments of the present invention and is not to be construed as limiting the present invention, and any modifications, equivalent replacements, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (5)

1. The utility model provides an assembled floor joint construction, includes assembled floor (1), its characterized in that: one end of assembled floor (1) is equipped with connecting hole post (7), connecting hole post (7) and assembled floor (1) fixed connection, one side of connecting hole post (7) is equipped with fixed hole (701), fixed hole (701) run through connecting hole post (7) and form the hole, the one end that assembled floor (1) was kept away from in connecting hole post (7) is equipped with connecting sleeve post (8), establish in connecting hole post (7) connecting sleeve post (8), connecting sleeve post (8) are close to the one end side of connecting hole post (7) and are equipped with movable joint and detain (801), the bottom that activity joint detained (801) is equipped with fixed connection board (901), fixed connection board (901) detain (801) fixed connection with the activity joint, the one end that activity joint was detained (801) is kept away from in fixed connection board (901) is equipped with work spring (9), hole (801) and work spring (9) fixed connection are detained in the joint is detained (701) the activity.
2. A fabricated floor slab connection construction according to claim 1, wherein: one end of the connecting sleeve column (8) far away from the connecting hole column (7) is provided with a through block (6), the connecting sleeve column (8) is fixedly connected with the through block (6), the connecting sleeve column (8) is positioned on the side face of the upper end and the lower end of the through block (6) and is fixedly connected with the side face of the upper end and the lower end of the through block (6), and the connecting sleeve column (8) is divided into twelve parts which are uniformly distributed on the side face of the upper end and the lower end of the through block (6).
3. A fabricated floor slab connection construction according to claim 1, wherein: the utility model discloses a fixing device for floor, including assembled floor (1), connecting plate (2), fixing bolt (3), piece (6), bottom connection template (5), fixed bolt (3), fixing nut (4), fixing bolt (3) run through fixing plate (2), link up piece (6) and bottom connection template (5) and fixed connection in the bottom of connecting plate (5), the top of fixing bolt (3) is equipped with fixing nut (4), fixing nut (4) and swing joint are run through to fixing bolt (3), the one end top that is close to connecting hole post (7) is equipped with connection fixed plate (2), the bottom of connecting plate (2) is equipped with bottom connection template (5) swing joint, the middle part of connecting plate (2).
4. A fabricated floor slab connection construction according to claim 2, wherein: link up both ends that piece (6) are close to assembled floor (1) and all be equipped with connecting sleeve post (8), connecting sleeve post (8) corresponding position is equipped with connecting hole post (7), connecting sleeve post (8) are same axle center with connecting hole post (7).
5. A fabricated floor slab connection construction according to claim 3, wherein: the connection fixing plate (2), the bottom connection template (5) and the two-end assembled floor slab (1) are connected at the same plane.
CN202222638764.6U 2022-10-09 2022-10-09 Assembled floor connection structure Active CN218149152U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222638764.6U CN218149152U (en) 2022-10-09 2022-10-09 Assembled floor connection structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222638764.6U CN218149152U (en) 2022-10-09 2022-10-09 Assembled floor connection structure

Publications (1)

Publication Number Publication Date
CN218149152U true CN218149152U (en) 2022-12-27

Family

ID=84566519

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222638764.6U Active CN218149152U (en) 2022-10-09 2022-10-09 Assembled floor connection structure

Country Status (1)

Country Link
CN (1) CN218149152U (en)

Similar Documents

Publication Publication Date Title
CN111424849A (en) Prefabricated reinforced concrete shear wall convenient to install and construction method
CN112196107A (en) Prefabricated assembled type steel reinforced concrete primary and secondary beam connecting joint
CN109057009B (en) Prefabricated assembled concrete frame dry type node
CN216130338U (en) Primary and secondary beam connecting joint
CN218149152U (en) Assembled floor connection structure
KR101658929B1 (en) Precast box structure and construction method thereof
CN116837967A (en) Construction method of large-span cable-stayed truss structure
CN217870942U (en) Beam column connecting structure
CN115324196B (en) Low-layer assembled concrete structure system
CN114575451B (en) Construction method of assembled reinforced concrete frame
CN111101645A (en) Self-in-place reinforced precast concrete wallboard, connecting structure and construction method
CN213653761U (en) Prefabricated assembled type steel reinforced concrete primary and secondary beam connecting joint
CN213477286U (en) L-shaped steel formwork concrete combined wall
CN212053436U (en) Strenghthened type precast concrete wallboard and connection structure with from structure of taking one's place
CN110388116B (en) Preparation method of prefabricated assembly type shock insulation support
CN210917711U (en) Prefabricated assembly type foundation's assembled building
CN108049504B (en) Connecting method for assembled type combined wall
CN111395581A (en) Connection construction process for perforated steel plate combined superimposed shear wall foundation
CN216195447U (en) Hinged joint structure of steel secondary beam and precast concrete main beam
CN110886181A (en) Precast concrete bridge and construction method thereof
CN115262751B (en) Construction method of low-layer assembled concrete structure system
CN220888939U (en) Frame body formwork structure is exempted from to super thick floor of linear accelerator computer lab
CN211762332U (en) Concrete box mould
CN218990896U (en) Assembled steel form with construction operation platform
CN115198926B (en) Frame structure assembled wall-beam connection structure and construction method thereof

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant