CN218130789U CN202222779662.6U CN202222779662U CN218130789U CN 218130789 U CN218130789 U CN 218130789U CN 202222779662 U CN202222779662 U CN 202222779662U CN 218130789 U CN218130789 U CN 218130789U
Authority
CN
China
Prior art keywords
cart
cabin body
construction waste
spraying
water pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222779662.6U
Other languages
Chinese (zh)
Inventor
叶幼文
罗运泉
王贵华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Hanjiang Engineering General Contracting Co ltd
Original Assignee
Guangdong Hanjiang Engineering General Contracting Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Hanjiang Engineering General Contracting Co ltd filed Critical Guangdong Hanjiang Engineering General Contracting Co ltd
Priority to CN202222779662.6U priority Critical patent/CN218130789U/en
Application granted granted Critical
Publication of CN218130789U publication Critical patent/CN218130789U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Catching Or Destruction (AREA)

Abstract

The utility model discloses a construction waste transfer device; belongs to the technical field of construction waste transportation; the technical key points of the device comprise a cart bin body, wherein a push rod is arranged at one end of the cart bin body along the advancing direction, and an opening and closing bin door is arranged at the other end of the cart bin body; mounting brackets are arranged on two sides of the upper end of the cart cabin body along the advancing direction, and a first spraying assembly parallel to the advancing direction is arranged on each mounting bracket; a swinging bracket is hinged between the two mounting brackets, and a second spraying assembly for spraying towards two sides is arranged on the swinging bracket; in an initial state, the second spraying assembly is positioned on the outer side of one end of the cart cabin body; when the cart is in work, the second spraying assembly is positioned above the cart cabin body; a water supply assembly connected with the first spraying assembly and the second spraying assembly is arranged on the outer wall of the cart cabin body; the utility model aims at providing a construction waste material transfer device which has simple structure and reduces the raised dust; the method is used for transferring construction waste during construction.

Description

Construction waste transfer device
Technical Field
The utility model relates to a transfer device, more specifically say, especially relate to a construction waste transfer device.
Background
A large amount of construction waste is inevitably generated in the process of building construction, a small trolley is usually arranged in the existing building site, the construction waste is loaded into the small trolley to be intensively transported away, and a large amount of dust is generated in the loading process.
In order to reduce the dust emission, water pipes and nozzles are usually added at two sides of the upper end of the cart to spray and suppress dust in the cart. In use, it is found that the spray ranges provided on both sides of the cart are reduced as the height of the construction waste increases, and in actual use, the construction waste finally loaded by the cart is generally higher than the upper end of the cart, and when the loaded construction waste approaches the upper end of the cart, the spray is difficult to cover the surface of the construction waste, resulting in poor dust suppression effect.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to the not enough of above-mentioned prior art, provide a simple structure, reduce the construction waste transfer device of raise dust.
The technical scheme of the utility model is realized like this: the utility model provides a construction waste transfer device, includes the shallow storehouse body, the shallow storehouse body is equipped with the push rod along the one end of direction of advance, is equipped with the door that opens and shuts at the shallow storehouse body other end.
Mounting brackets are arranged on the upper end of the cart cabin body along the two sides of the advancing direction, and a first spraying assembly parallel to the advancing direction is arranged on each mounting bracket.
A swinging bracket is hinged between the two mounting brackets, and a second spraying assembly for spraying towards two sides is arranged on the swinging bracket; in an initial state, the second spraying assembly is positioned on the outer side of one end of the cart cabin body; when the cart is in work, the second spraying assembly is positioned above the cart cabin body; a water supply component connected with the first spraying component and the second spraying component is arranged on the outer wall of the cart cabin body.
In the above construction waste transfer device, the first spraying assembly includes mounting seats arranged at two ends of the mounting bracket, and a first water pipe is erected between the mounting seats; one end of the first water pipe is connected with the water supply assembly through a hose; a plurality of first atomizing nozzles are uniformly distributed on one side of the first water pipe facing the cabin body of the trolley along the length direction.
In the construction waste transfer device, the second spraying assembly comprises a second water pipe arranged on the swing bracket along the width direction of the cart body, and one end of the second water pipe is connected with the water supply assembly through a hose; in the initial state, the second water pipe is positioned outside one end of the cabin body of the cart.
And nozzle groups are arranged on the two sides of the second water pipe along the length direction and comprise a plurality of second atomizing nozzles uniformly distributed along the length direction of the second water pipe.
In the construction waste transfer device, a folding wind shield matched with the second spraying component is arranged on the mounting bracket close to one end of the push rod; the height of the folding wind shield is not less than that of the second spraying component.
In the aforementioned construction waste transfer device, one end of the cart cabin body in the advancing direction is provided with a first hinged seat, and the push rod is hinged to the first hinged seat.
In the construction waste transfer device, the opening and closing bin door comprises a door plate hinged to the lower end of the side, far away from the push rod, of the cart bin body; the door plate is provided with a first hinge seat at the front end part of the free end of the door plate along the width direction, a buckle is arranged on the first hinge seat, and a clamping seat matched with the buckle is arranged on the side wall of the cart cabin body; the door plate is internally provided with a sealing boss matched with the inner cavity of the cart cabin body.
By adopting the above structure, the utility model, spray through the first spraying subassembly of both sides when loading less construction waste and press down dirt, it is more when construction waste, when first spraying subassembly can't cover the construction waste surface, spray to the top with second spraying subassembly swing through swing bracket, the raise dust that produces when can effectively restrain the construction waste loading.
Simultaneously, after the spraying, the swing support can rotate and place to the level and make the second spraying subassembly be located the carriage storehouse body wherein one end outside, can not influence bulky building waste and place on the shallow.
Drawings
The present invention will be described in further detail with reference to the embodiments shown in the drawings, which should not be construed as limiting the invention in any way.
Fig. 1 is a schematic structural diagram of the present invention.
Fig. 2 is a schematic sectional structure of the present invention.
Fig. 3 is a schematic structural view of the cart cabin body of the present invention.
Fig. 4 is a schematic view of the local structure at a.
In the figure: 1. a cart cabin body; 2. a push rod; 3. opening and closing the bin door; 3a, a door panel; 3b, a second hinge base; 3c, buckling; 3d, a clamping seat; 3e, sealing the boss; 4. mounting a bracket; 5. a first spray assembly; 5a, a mounting seat; 5b, a first water pipe; 5c, a first atomizing nozzle; 6. a swing bracket; 7. a second spray assembly; 7a, a second water pipe; 7b, a nozzle group; 7c, a second atomizing nozzle; 8. a water supply assembly; 9. a folding wind shield; 10. a first hinged seat.
Detailed Description
Referring to fig. 1, the utility model discloses a construction waste transfer device, including the shallow storehouse body 1, the shallow storehouse body 1 is equipped with push rod 2 along the one end of advancing direction, is equipped with the door 3 that opens and shuts at the shallow storehouse body 1 other end.
The two sides of the upper end of the cart cabin body 1 along the advancing direction are respectively provided with a mounting bracket 4, and each mounting bracket 4 is provided with a first spraying assembly 5 parallel to the advancing direction. When the construction waste in the cabin body of the trolley is less, if the spraying assembly is arranged above the trolley, the spraying is easy to float in the air due to the long distance, so that the dust cannot be well pressed down. Therefore, the spraying can be carried out through the first spraying assemblies on the two sides of the upper end of the cart cabin body.
A swing bracket 6 is hinged between the two mounting brackets 4, and a second spraying assembly 7 for spraying towards two sides is arranged on the swing bracket 6; in an initial state, the second spraying component 7 is positioned at the outer side of one end of the cart cabin body 1; when the cart is in work, the second spraying assembly 7 is positioned above the cart cabin body 1; when transporting construction waste, the waste material that the great unable shallow of packing into of volume directly keeps flat in the shallow upper end usually, makes the second spraying subassembly be located the wherein one end outside of shallow storehouse body through the swing support, can not influence bulky construction waste and place on the shallow.
A water supply component 8 connected with the first spraying component 5 and the second spraying component 7 is arranged on the outer wall of the cart cabin body 1. The structure of the water supply assembly is the prior art, and the structure and the connection mode are common knowledge of those skilled in the art, and are not described in detail herein.
In the present embodiment, the first spraying assembly 5 includes mounting seats 5a disposed at both ends of the mounting bracket 4, and a first water pipe 5b is spanned between the mounting seats 5 a; one end of the first water pipe 5b is connected with a water supply assembly 8 through a hose; a plurality of first atomizing nozzles 5c are uniformly distributed on one side of the first water pipe 5b facing the cart cabin body 1 along the length direction. The height of the mounting seat is 4-8cm, and the first atomizing nozzle is higher than the upper end of the cart cabin body through the mounting seat, so that the spraying coverage area of the cart cabin body is increased. First water pipe passes through hose connection water supply assembly, compares in the stereoplasm water pipe, and the hose is easy to assemble.
In the embodiment, the second spraying assembly 7 comprises a second water pipe 7a arranged on the swing bracket 6 along the width direction of the cart cabin body 1, and one end of the second water pipe 7a is connected with the water supply assembly 8 through a hose; in the initial state, the second water pipe 7a is positioned outside one end of the cart cabin body 1. The second water pipe passes through hose connection water supply assembly and can make things convenient for the second water pipe to rotate along with the swing support, also easy to assemble simultaneously.
And nozzle groups 7b are arranged on two sides of the second water pipe 7a along the length direction, and the nozzle groups 7b comprise a plurality of second atomizing nozzles 7c uniformly distributed along the length direction of the second water pipe 7 a. The second atomizing nozzles symmetrically arranged on the second water pipe can enable the two sides to spray uniformly, and the dust suppression effect of the two sides is ensured to be the same.
In this embodiment, it is preferable that a folding type wind shield 9 matched with the second spraying component 7 is arranged on the mounting bracket 4 near one end of the push rod 2; the height of the folding wind shield 9 is not less than that of the second spraying component. The structure of the folding wind shield is the prior art, and the structure and the connection mode are common knowledge of those skilled in the art, and are not described herein again.
The method for loading the construction waste is generally that the construction waste is shoveled by a shovel and thrown into a cart, and the wind shield is arranged to prevent wind generated when the construction waste is thrown into the cart from blowing away the spray sprayed by the second spraying assembly. Meanwhile, when the second spraying assembly is used, the height of materials in the cart is close to the edge of the upper end of the cart, and the wind shielding shield can prevent construction waste from being thrown out of the cart.
Preferably, one end of the cart cabin body 1 along the advancing direction is provided with a first hinged seat 10, and the push rod 2 is hinged on the first hinged seat 10. After the structure is adopted, when the cart stops, the push rod can be vertically placed downwards, the size of the cart is reduced, and the cart can enter a small space with the same volume of the elevator.
Preferably, the opening and closing bin door 3 comprises a door panel 3a hinged to the lower end of the side of the cart bin body 1 far away from the push rod 2; a second hinge seat 3b is arranged at the near end part of the free end of the door plate 3a along the width direction, a buckle 3c is arranged on the second hinge seat 3b, and a clamping seat 3d matched with the buckle 3c is arranged on the side wall of the cart cabin body 1; by adopting the structure, the bin door can be fixed quickly and conveniently.
The door plate 3a is internally provided with a sealing boss 3e matched with the inner cavity of the cart cabin body 1. The sealing bosses are attached to the inner wall of the cart cabin body all around, so that the leakage of the small-size construction waste from the gap between the opening and closing cabin door and the cart cabin body is prevented.
During the use, use the push rod with the shallow push-and-pull back that targets in place, open the buckle and beat down the door plant, with the less construction waste shovel of volume throw into the shallow storehouse body, first atomizing nozzle continuously presses down dirt towards the internal spraying of shallow storehouse simultaneously.
When the construction waste in the cabin body of the trolley is close to the upper end of the trolley, the swing support is swung to a proper position to be fixed, the folding wind shield is opened, and the second atomizing nozzle continuously sprays and suppresses dust towards the cabin body of the trolley.
After the small-volume building waste loading is completed, the first atomizing nozzle and the second atomizing nozzle stop spraying, the swing support and the folding wind shield are retracted to the original position, and the large-volume building waste is placed on the upper surface of the building waste in the cart.
The above embodiment is the preferred embodiment of the present invention, which is only used to facilitate the explanation of the present invention, and not to the present invention, which makes any restriction on any form, and any person who knows commonly among the technical fields has, if in the scope of the technical features that do not depart from the present invention, the present invention is utilized to make the local change or modification equivalent embodiment, and does not depart from the technical features of the present invention, and all still belong to the technical features of the present invention.

Claims (6)

1. A construction waste transfer device comprises a cart bin body (1), and is characterized in that a push rod (2) is arranged at one end of the cart bin body (1) along the advancing direction, and an opening and closing bin door (3) is arranged at the other end of the cart bin body (1);
mounting brackets (4) are arranged on two sides of the upper end of the cart cabin body (1) along the advancing direction, and a first spraying assembly (5) parallel to the advancing direction is arranged on each mounting bracket (4);
a swing bracket (6) is hinged between the two mounting brackets (4), and a second spraying assembly (7) for spraying towards two sides is arranged on the swing bracket (6); in an initial state, the second spraying component (7) is positioned on the outer side of one end of the cart cabin body (1); when the cart is in work, the second spraying component (7) is positioned above the cart cabin body (1);
a water supply component (8) connected with the first spraying component (5) and the second spraying component (7) is arranged on the outer wall of the cart cabin body (1).
2. The construction waste transfer device according to claim 1, wherein the first spray unit (5) comprises mounting seats (5 a) provided at both ends of the mounting bracket (4), and a first water pipe (5 b) is erected between the mounting seats (5 a); one end of the first water pipe (5 b) is connected with a water supply assembly (8) through a hose;
a plurality of first atomizing nozzles (5 c) are uniformly distributed on one side of the first water pipe (5 b) facing the cart cabin body (1) along the length direction.
3. The construction waste transfer device according to claim 1, wherein the second spraying assembly (7) comprises a second water pipe (7 a) arranged on the swing bracket (6) along the width direction of the cart cabin body (1), and one end of the second water pipe (7 a) is connected with the water supply assembly (8) through a hose; in an initial state, the second water pipe (7 a) is positioned outside one end of the cart cabin body (1);
both sides along length direction at second water pipe (7 a) all are equipped with nozzle group (7 b), nozzle group (7 b) include along a plurality of second atomizing nozzle (7 c) of second water pipe (7 a) length direction equipartition.
4. The construction waste transfer device according to claim 1, wherein a folding windshield (9) is provided on the mounting bracket (4) near one end of the push rod (2) to cooperate with the second spraying assembly (7); the height of the folding wind shield (9) is not less than that of the second spraying component (7).
5. The construction waste transfer device according to claim 1, wherein one end of the cart cabin (1) in the forward direction is provided with a first hinged seat (10), and the push rod (2) is hinged on the first hinged seat (10).
6. The construction waste transfer device according to claim 1, wherein the opening and closing door (3) comprises a door plate (3 a) hinged to the lower end of the side of the cart cabin body (1) far from the push rod (2); a second hinge seat (3 b) is arranged at the near end part of the free end of the door panel (3 a) along the width direction, a buckle (3 c) is arranged on the second hinge seat (3 b), and a clamping seat (3 d) matched with the buckle (3 c) is arranged on the side wall of the cart cabin body (1);
the door plate (3 a) is internally provided with a sealing boss (3 e) matched with the inner cavity of the cart cabin body (1).
CN202222779662.6U 2022-10-21 2022-10-21 Construction waste transfer device Active CN218130789U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222779662.6U CN218130789U (en) 2022-10-21 2022-10-21 Construction waste transfer device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222779662.6U CN218130789U (en) 2022-10-21 2022-10-21 Construction waste transfer device

Publications (1)

Publication Number Publication Date
CN218130789U true CN218130789U (en) 2022-12-27

Family

ID=84571565

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222779662.6U Active CN218130789U (en) 2022-10-21 2022-10-21 Construction waste transfer device

Country Status (1)

Country Link
CN (1) CN218130789U (en)

Similar Documents

Publication Publication Date Title
CN218130789U (en) Construction waste transfer device
CN212667242U (en) Transport vechicle with press down dirt function
CN211032335U (en) Dregs conveyer for foundation construction
CN205932563U (en) Combination bucket -wheel stacker reclaimer curtain formula spraying dedusting device
CN218809187U (en) Spiral ship loading and unloading machine
KR100579939B1 (en) System and method for painting of external wall for a multistoried building
CN112551008A (en) Sanitation garbage truck with clean function
CN110681510A (en) Muck truck top cover spraying system and method thereof
KR101772873B1 (en) Carrier vehicle for collection dust prevention device is equipped with a scattering of dust emissions
JP2852635B2 (en) Chemical sprayer for control
CN214929241U (en) Transport vehicle
CN210941475U (en) Mining dump truck of environmental protection dust fall
CN214402591U (en) Vertical garbage transport channel for high-rise buildings
CN208018294U (en) Device is preliminarily sprayed in deduster powder
CN211366316U (en) Blanking hopper
CN206721782U (en) A kind of common type garbage cleaning vehicle
CN221334935U (en) Environment-friendly paint spray booth
CN213109845U (en) Cleaning vehicle
CN208101815U (en) A kind of dust-proof spray system of dump truck
CN220184528U (en) Floor rubbish transportation channel device
CN212999040U (en) Dust device for construction
CN209905628U (en) Solid useless conveyer for processing
CN218090675U (en) Dust fall equipment for environmental protection building engineering
CN218306986U (en) Multifunctional dust suppression vehicle with folding arm structure
CN212370409U (en) Muck truck top cover spraying system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant