CN218063655U
CN218063655U CN202221027869.1U CN202221027869U CN218063655U CN 218063655 U CN218063655 U CN 218063655U CN 202221027869 U CN202221027869 U CN 202221027869U CN 218063655 U CN218063655 U CN 218063655U
Authority
CN
China
Prior art keywords
installation
sides
clamp
seat
chemical plant
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202221027869.1U
Other languages
Chinese (zh)
Inventor
唐正良
贾冬冬
陈舟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuxi Huiruida Technology Co ltd
Original Assignee
Wuxi Huiruida Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuxi Huiruida Technology Co ltd filed Critical Wuxi Huiruida Technology Co ltd
Priority to CN202221027869.1U priority Critical patent/CN218063655U/en
Application granted granted Critical
Publication of CN218063655U publication Critical patent/CN218063655U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses a chemistry factory building equipment is with novel pipeline installation device, press from both sides and base including first installation, second installation, first installation presss from both sides top one side fixed connection with the base, the equal fixedly connected with slide pipe in rear end both sides of first installation clamp, sliding connection has the slider in the middle of the inside of slide pipe, one side outer wall of slider rotates and is connected with the gim peg, two the opposite side outer wall of slider all presss from both sides fixed connection with the second installation, the bottom of first installation clamp is provided with places the seat, the top of first installation clamp is provided with the roof, first installation clamp is the same with the structure of second installation clamp, the seat of placing of first installation clamp and second installation clamp is located same level, the lower extreme and the base fixed connection of slide pipe. The utility model discloses be convenient for increase pipeline installation device's functionality to can improve pipeline installation device's result of use nature, have the practicality.

Description

Novel pipeline installation device for chemical plant equipment
Technical Field
The utility model relates to a technical field of piping erection device, in particular to chemistry factory building equipment is with novel piping erection device.
Background
The chemical plant is a house without partition walls and is suitable for chemical operation and experiments. According to the demand user of experiment content in the chemistry factory building corresponding equipment of can packing into in the chemistry factory building, and during the installation of multiple equipment and the connection between the equipment, can use installation device to install its connecting line, increase the convenience of tube coupling.
But present pipeline installation device has some defects in the in-process of using, and installation device only can align the one end of two pipelines, and need use a plurality of screwed connection during the piping erection for the pipeline installation precision is lower, can cause the inside outer hourglass of conveying gas or liquid of pipeline, influences the use of pipeline, consequently improves pipeline installation device now.
SUMMERY OF THE UTILITY MODEL
The utility model discloses a main aim at provides chemistry factory building equipment is with novel pipe-line installation device, can effectively solve the problem in the background art.
In order to achieve the above purpose, the utility model adopts the following technical scheme:
chemistry factory building equipment is with novel piping erection device, press from both sides and base including first installation, second installation, first installation presss from both sides top one side fixed connection with the base, the equal fixedly connected with slide pipe in rear end both sides that first installation pressed from both sides, sliding connection has the slider in the middle of the inside of slide pipe, one side outer wall of slider rotates and is connected with the gim peg, two the opposite side outer wall of slider all presss from both sides fixed connection with the second installation, the bottom that first installation pressed from both sides is provided with places the seat, the top that first installation pressed from both sides is provided with the roof, first installation presss from both sides the structure with the second installation and presss from both sides the same.
Preferably, the placing seat of the first mounting clamp and the placing seat of the second mounting clamp are located at the same horizontal height, and the lower end of the sliding pipe is fixedly connected with the base.
Preferably, the outer surfaces of the two sides of the sliding pipe are provided with sliding openings, the sliding blocks are in penetrating type sliding connection with the sliding pipe through the sliding openings, and the fixing bolts are located on the outer wall of one side of the sliding pipe.
Preferably, the top of placing the seat covers there is the rubber pad, the rubber pad is the arc structure, all fixedly connected with bracing piece around the top of placing the seat.
Preferably, mounting grooves are formed in the periphery of the top plate, the size of each mounting groove is matched with the size of each supporting rod, each supporting rod is connected with the top plate in a penetrating mode through the corresponding mounting groove, nuts are movably sleeved on the tops of the supporting rods, and the nuts are located on the tops of the top plates.
Preferably, a screw seat is arranged in the middle of the top plate, a screw rod is rotatably connected in the middle of the screw seat, and the screw rod is in through connection with the screw seat.
Preferably, the lower end of the screw rod is fixedly connected with a bearing, the lower end of the bearing is fixedly connected with a pressing plate, and the outer surface of the lower end of the pressing plate is covered with a rubber layer.
Compared with the prior art, the utility model discloses following beneficial effect has:
1. the mounting device comprises a mounting device, a supporting rod, a screw seat, a screw rod and a pressing plate, wherein the mounting device is provided with the supporting rod, the screw seat is used for rotatably connecting the screw rod with the top plate, the screw rod is used for conveniently adjusting the use height of the pressing plate, so that the mounting device extrudes and fixes the outer surface of the pipeline through the pressing plate with an adjusting structure, the movement of the mounting pipeline is avoided, the nut is used for detaching the supporting rod from the top plate, and the convenience in detaching the mounting device is improved, so that the use safety of the pipeline mounting device is improved;
2. through slide pipe, slider, gim peg and the slip mouth that sets up, the second installation is pressed from both sides and is used for through slider and slip mouth with slide pipe sliding connection, increases the adjustability that the second installation pressed from both sides and uses the distance with first installation for installation device can hold the pipeline installation end to different thickness and connect it, increases the precision that pipeline port connects, avoids the outer hourglass of the inside transport gas of pipeline or liquid, thereby increases pipeline installation device's practicality.
Drawings
FIG. 1 is a schematic view of the overall structure of the novel pipeline installation device for chemical plant equipment of the present invention;
FIG. 2 is an exploded view of the first mounting clip of the novel piping installation device for chemical plant equipment of the present invention;
FIG. 3 is a sectional view showing the structure of the top plate and the screw in the novel piping installation device for chemical plant equipment of the present invention;
FIG. 4 is an exploded view of the second mounting clip and the slide pipe of the novel piping installation device for chemical plant equipment of the present invention;
fig. 5 is the structure section view of the sliding pipe and the sliding block in the novel pipeline installation device for the chemical plant equipment.
In the figure: the device comprises a first mounting clamp 1, a second mounting clamp 2, a base 3, a sliding pipe 4, a sliding block 5, a fixing bolt 6, a placing seat 7, a top plate 8, a sliding opening 9, a rubber pad 11, a supporting rod 12, a mounting groove 13, a nut 14, a screw seat 15, a screw rod 16, a bearing 17 and a pressing plate 18.
Detailed Description
In order to make the utility model realize technical means creation characteristics to achieve the purpose and the effect is easy to understand and understand, the utility model is further explained by combining the detailed implementation mode.
In the description of the present invention, it should be noted that the terms "upper", "lower" and "inner"
The directions or positional relationships indicated by "outer", "front", "rear", "both ends", "one end" and the other end "are based on the directions or positional relationships shown in the drawings, and are only for convenience of description and simplification of the description, but do not indicate or imply that the device or element referred to must have a specific direction to be constructed and operated in a specific direction, and thus, should not be construed as limiting the present invention. Furthermore, the terms "first" and "second" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance.
In the description of the present invention, it should be noted that, unless otherwise explicitly specified or limited, the terms "mounted," "provided," "connected," and the like are to be construed broadly, such as "connected," which may be fixedly connected, detachably connected, or integrally connected; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meaning of the above terms in the present invention can be understood according to specific situations by those skilled in the art.
As shown in fig. 1-5, chemistry factory building equipment is with novel pipeline installation device, including first installation clamp 1, second installation clamp 2 and base 3, first installation clamp 1 is with top one side fixed connection of base 3, the equal fixedly connected with slide pipe 4 in rear end both sides of first installation clamp 1, sliding connection has slider 5 in the middle of the inside of slide pipe 4, one side outer wall of slider 5 rotates and is connected with gim peg 6, the opposite side outer wall of two sliders 5 all presss from both sides 2 fixed connection with the second installation, the bottom of first installation clamp 1 is provided with places seat 7, the top of first installation clamp 1 is provided with roof 8, first installation clamp 1 is the same with the structure of second installation clamp 2.
Wherein, the seat 7 of placing of first installation clamp 1 and the seat 7 of placing of second installation clamp 2 are located same level, and the lower extreme and the base 3 fixed connection of slide pipe 4 are used for aligning the installation to the one end of two pipelines through first installation clamp 1 and second installation clamp 2.
Wherein, sliding opening 9 has all been seted up to the both sides surface of slide pipe 4, and slider 5 is run through formula sliding connection through sliding opening 9 and slide pipe 4, and gim peg 6 is located one side outer wall of slide pipe 4, is used for increasing slider 5's portable function through slide pipe 4 for the second installation presss from both sides 2 and can carry out the fixed of different user positions, increases the commonality that steps up the pipeline between first installation clamp 1 and second installation clamp 2.
Wherein, the top of placing seat 7 is covered with rubber pad 11, and rubber pad 11 is the arc structure, and the top of placing seat 7 all around all fixedly connected with bracing piece 12, installation device supports the installation pipeline outside through placing seat 7.
Wherein, mounting groove 13 has all been seted up around roof 8, mounting groove 13's size and bracing piece 12's size phase-match, and bracing piece 12 passes through mounting groove 13 and roof 8 through connection, and the top movable sleeve of bracing piece 12 is equipped with nut 14, and nut 14 is located the top of roof 8, and bracing piece 12 is used and is connected roof 8 with placing seat 7, increases roof 8 and places the detachability between seat 7.
Wherein, the centre of roof 8 is provided with screw seat 15, and the centre of screw seat 15 is rotated and is connected with screw rod 16, screw rod 16 and screw seat 15 through connection, and screw seat 15 is used for 16 and roof 8 swing joint with screw rod for through the rotation of screw rod 16, the distance between its bottom and roof 8 can be adjusted.
The lower end of the screw 16 is fixedly connected with a bearing 17, the lower end of the bearing 17 is fixedly connected with a pressing plate 18, the outer surface of the lower end of the pressing plate 18 is covered with a rubber layer, and the bearing 17 is convenient for increasing the flexibility between the screw 16 and the pressing plate 18, so that when the rotating length of the screw 16 is adjusted, the pressing plate 18 does not rotate along with the screw, and the outer side of the pipeline is extruded and fixed.
It should be noted that, the utility model discloses a chemistry factory building equipment is with novel pipe-line installation device, during the use, use nut 14 to run through bracing piece 12 and roof 8 and screw and be connected, place base 3 in the mounted position department of pipeline afterwards, place first mounting clip 1 and second mounting clip 2 respectively on placing the rubber pad 11 of seat 7, rotatory screw rod 16, make it rotate and prolong downwards through screw seat 15, clamp plate 18 passes through bearing 17's the rotation that sets up surface clamp plate 18, make clamp plate 18 hug closely with the surface of pipeline after prolonging downwards, promote second mounting clip 2 afterwards, make its both sides slider 5 remove to first mounting clip 1 through slip mouth 9, the installation end of two pipelines is hugged closely, again with gim peg 6 and slide tube 4, the back is installed according to the connected method of two pipelines, after the installation through nut 14 with bracing piece 12 and roof 8 unpack apart, part installation device and two pipelines, accomplish the installation of pipeline.
The basic principles and the main features of the invention and the advantages of the invention have been shown and described above. It will be understood by those skilled in the art that the present invention is not limited to the above embodiments, and that the foregoing embodiments and descriptions are provided only to illustrate the principles of the present invention without departing from the spirit and scope of the present invention. The scope of the invention is defined by the appended claims and equivalents thereof.

Claims (7)

1. Chemistry factory building equipment is with novel piping erection device, press from both sides (2) and base (3) including first installation, second installation, its characterized in that: first installation presss from both sides the top one side fixed connection of (1) and base (3), the equal fixedly connected with slide pipe (4) in rear end both sides of first installation clamp (1), sliding connection has slider (5) in the middle of the inside of slide pipe (4), one side outer wall of slider (5) rotates and is connected with gim peg (6), two the opposite side outer wall of slider (5) all presss from both sides (2) fixed connection with the second installation, the bottom that first installation pressed from both sides (1) is provided with places seat (7), the top that first installation pressed from both sides (1) is provided with roof (8), the structure that first installation pressed from both sides (1) and second installation clamp (2) is the same.
2. The novel pipeline installation device for the chemical plant equipment according to claim 1, characterized in that: the placing seat (7) of the first mounting clamp (1) and the placing seat (7) of the second mounting clamp (2) are located at the same horizontal height, and the lower end of the sliding pipe (4) is fixedly connected with the base (3).
3. The novel pipeline installation device for the chemical plant equipment according to claim 1, characterized in that: sliding opening (9) have all been seted up to the both sides surface of slide pipe (4), slider (5) are run-through formula sliding connection through sliding opening (9) and slide pipe (4), gim peg (6) are located one side outer wall of slide pipe (4).
4. The novel pipeline installation device for the chemical plant equipment according to claim 1, characterized in that: the top of the placing seat (7) is covered with a rubber pad (11), the rubber pad (11) is of an arc-shaped structure, and supporting rods (12) are fixedly connected to the periphery of the top of the placing seat (7).
5. The novel pipeline installation device for the chemical plant equipment according to claim 4, characterized in that: mounting groove (13) have all been seted up around roof (8), the size of mounting groove (13) and the size phase-match of bracing piece (12), bracing piece (12) are through mounting groove (13) and roof (8) through connection, the top movable sleeve of bracing piece (12) is equipped with nut (14), nut (14) are located the top of roof (8).
6. The novel pipeline installation device for the chemical plant equipment according to claim 1, characterized in that: the middle of roof (8) is provided with screw seat (15), the centre of screw seat (15) is rotated and is connected with screw rod (16), screw rod (16) and screw seat (15) through connection.
7. The novel pipeline installation device for the chemical plant equipment according to claim 6, characterized in that: the lower end of the screw rod (16) is fixedly connected with a bearing (17), the lower end of the bearing (17) is fixedly connected with a pressing plate (18), and the outer surface of the lower end of the pressing plate (18) is covered with a rubber layer.
CN202221027869.1U 2022-04-28 2022-04-28 Novel pipeline installation device for chemical plant equipment Active CN218063655U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221027869.1U CN218063655U (en) 2022-04-28 2022-04-28 Novel pipeline installation device for chemical plant equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221027869.1U CN218063655U (en) 2022-04-28 2022-04-28 Novel pipeline installation device for chemical plant equipment

Publications (1)

Publication Number Publication Date
CN218063655U true CN218063655U (en) 2022-12-16

Family

ID=84430690

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221027869.1U Active CN218063655U (en) 2022-04-28 2022-04-28 Novel pipeline installation device for chemical plant equipment

Country Status (1)

Country Link
CN (1) CN218063655U (en)

Similar Documents

Publication Publication Date Title
CN218063655U (en) Novel pipeline installation device for chemical plant equipment
CN210941850U (en) Pipe conveying device
CN211388401U (en) Connecting device for pipeline installation
CN216279743U (en) Electromechanical device reforms transform and uses auxiliary fixture
CN213926354U (en) Fixing device is used in installation of underground pipe gallery
CN215334953U (en) Pipeline connector with anti-falling function
CN214368200U (en) Pipeline positioning device for municipal gas engineering
CN215721307U (en) Radius size adjustable fastener for insulating tube connection
CN219975807U (en) Plug connector convenient to installation
CN215908728U (en) Special hot oil cleaning pump station
CN217301875U (en) Intelligent auxiliary device for pipeline installation
CN216669572U (en) Natural gas conveying pipeline pressure testing safety device
CN219756398U (en) Waste gas catalytic combustion temperature conversion device
CN220063281U (en) Waterproof testing device
CN216442367U (en) Fixed mounting construction platform for gas pipeline
CN215034959U (en) Be applied to gas pipeline's fixing device
CN219734544U (en) Connecting and stabilizing device for water supply and drainage pipes
CN217765974U (en) Engineering building material's waterproof detection device of portable
CN220727343U (en) Pipeline fixing device
CN112161138B (en) MPVE double-wall corrugated pipe connecting and sealing device
CN212311323U (en) Portable petrochemical pipeline welding jig
CN216103568U (en) Emergency drainage device for repairing urban pipeline water leakage
CN214980489U (en) Assembly device convenient to carry for pipeline installation
CN217688241U (en) Detection equipment for corrugated pipe
CN214466999U (en) Gas is strutting arrangement for pipeline with protect function

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant