CN218028472U - Installation steel construction that steel construction engineering used - Google Patents

Installation steel construction that steel construction engineering used Download PDF

Info

Publication number
CN218028472U
CN218028472U CN202222028014.7U CN202222028014U CN218028472U CN 218028472 U CN218028472 U CN 218028472U CN 202222028014 U CN202222028014 U CN 202222028014U CN 218028472 U CN218028472 U CN 218028472U
Authority
CN
China
Prior art keywords
limiting seat
bottom plate
steel structure
steel construction
stand
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN202222028014.7U
Other languages
Chinese (zh)
Inventor
姜日云
夏伟国
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangxi Zhongtian Jianguo Construction Engineering Co ltd
Original Assignee
Hainan Zhongrui Jiexin Steel Structure Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hainan Zhongrui Jiexin Steel Structure Co ltd filed Critical Hainan Zhongrui Jiexin Steel Structure Co ltd
Priority to CN202222028014.7U priority Critical patent/CN218028472U/en
Application granted granted Critical
Publication of CN218028472U publication Critical patent/CN218028472U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses an installation steel construction that steel construction engineering used relates to steel construction technical field, including the prefabricated plate, place in the bottom plate at prefabricated plate top and set up in the stand at bottom plate top, the prefabricated plate top is provided with a plurality of screw thread posts, has seted up the through-hole of a plurality of cooperation screw thread posts in the bottom plate, and the prefabricated plate top is provided with the auxiliary assembly who is used for supplementary prefabricated plate to be connected with the bottom plate. The utility model discloses in, through having increased auxiliary assembly, and then made things convenient for being connected between prefabricated plate and the stand, can be accurate support the screw thread post to the through-hole in, avoid needing to remove the stand many times just can support the screw thread post to the through-hole in to improve work efficiency, solved the stand and can produce when the downstream and rock the problem that leads to threaded rod and through-hole not need realignment on same vertical plane.

Description

Installation steel construction that steel construction engineering used
Technical Field
The utility model relates to a steel construction technical field especially relates to an installation steel construction that steel construction engineering used.
Background
The existing steel structure column base is provided with a bottom plate mostly at the bottom of a column in the installation process, a through hole matched with a threaded rod at the top of an embedded part is formed in the bottom plate, the bottom plate is placed at the top of the embedded part during connection, the threaded rod is ensured to penetrate through the through hole, and a nut is screwed at the moment, so that the embedded part is connected with the column.
Because the volume of stand is great, and heavier, when being connected stand and built-in fitting, be through hoist with the stand hoist and lift and remove, the slow removal stand of hoist, the threaded rod on the built-in fitting is aimed at to the through-hole on the bottom plate, the stand moves down again this moment, make stand bottom and built-in fitting top contact, nevertheless the stand can produce when moving down and rock, lead to threaded rod and through-hole not on same vertical plane, need aim at threaded rod and through-hole again this moment, thereby can reduce work efficiency, consequently, need improve the processing to above-mentioned problem.
SUMMERY OF THE UTILITY MODEL
The utility model aims at solving the problem that prior art is not enough, and the installation steel construction that a steel construction engineering used that proposes.
In order to achieve the above purpose, the utility model adopts the following technical scheme:
an installation steel structure for steel structure engineering comprises a precast slab, a bottom plate placed at the top of the precast slab and an upright column arranged at the top of the bottom plate, wherein a plurality of threaded columns are arranged at the top of the precast slab, a plurality of through holes matched with the threaded columns are formed in the bottom plate, and an auxiliary assembly for assisting the connection of the precast slab and the bottom plate is arranged at the top of the precast slab;
the auxiliary assembly comprises a first limiting seat and a second limiting seat, the first limiting seat and the second limiting seat are arranged on the outer side of the prefabricated plate and are specifically of a convex type, a mounting groove matched with the prefabricated plate is formed in the bottom of the first limiting seat and the bottom of the second limiting seat, a clamping groove matched with the bottom plate is formed in the top of the first limiting seat and the top of the second limiting seat, the bottom of the clamping groove is communicated with the top of the mounting groove, an insertion plate is arranged on the front side of the first limiting seat, an insertion groove matched with the insertion plate is formed in the rear side of the second limiting seat, and the insertion plate is connected with the second limiting seat through a plurality of bolts.
Further, first restriction seat and second restriction seat top all are provided with the direction and fight, the direction is fought inboard and joint inslot wall and all is provided with the blotter.
Further, the rear side of the first limiting seat and the front side of the second limiting seat are both provided with handles, and the handles are sleeved with anti-slip pads.
Furthermore, a plurality of guide plates are arranged on the front side of the insertion plate, and the guide plates are arc-shaped plates.
Compared with the prior art, the utility model discloses possess following beneficial effect:
the utility model discloses in, through having increased auxiliary assembly, and then made things convenient for being connected between prefabricated plate and the stand, can be accurate support the screw thread post to the through-hole in, avoid needing to remove the stand many times just can support the screw thread post to the through-hole in to improve work efficiency, solved the stand and can produce when the downstream and rock the problem that leads to threaded rod and through-hole not need realignment on same vertical plane.
Drawings
Fig. 1 is an external view of an installation steel structure for steel structure engineering proposed by the present invention;
fig. 2 is a schematic structural view of an installation steel structure for steel structure engineering according to the present invention;
fig. 3 is a display diagram of an auxiliary assembly in an installation steel structure for steel structure engineering according to the present invention;
fig. 4 is the utility model provides a side view of auxiliary assembly in installation steel construction that steel construction engineering used.
Number in the figure: 1. prefabricating a slab; 2. a column; 3. an auxiliary component; 11. a threaded post; 21. a base plate; 31. a first restriction seat; 32. a second restriction seat; 33. a plugboard; 34. a guide plate; 35. a guide hopper; 36. a handle.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments.
In the description of the present invention, it is to be understood that the terms "upper", "lower", "front", "rear", "left", "right", "top", "bottom", "inner", "outer", and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplicity of description, and do not indicate or imply that the device or element being referred to must have a particular orientation, be constructed and operated in a particular orientation, and therefore, should not be construed as limiting the present invention.
Referring to fig. 1-4, an installation steel structure for steel structure engineering comprises a prefabricated slab 1, a bottom plate 21 placed at the top of the prefabricated slab 1 and a stand column 2 arranged at the top of the bottom plate 21, wherein the top of the prefabricated slab 1 is provided with a plurality of threaded columns 11, a plurality of through holes matched with the threaded columns 11 are formed in the bottom plate 21, and the top of the prefabricated slab 1 is provided with an auxiliary assembly 3 for assisting the prefabricated slab 1 to be connected with the bottom plate 21;
the auxiliary assembly 3 comprises a first limiting seat 31 and a second limiting seat 32 which are arranged on the outer side of the prefabricated slab 1, the first limiting seat 31 and the second limiting seat 32 are in a convex shape, mounting grooves matched with the prefabricated slab 1 are formed in the bottoms of the first limiting seat 31 and the second limiting seat 32, clamping grooves matched with the bottom plate 21 are formed in the tops of the first limiting seat 31 and the second limiting seat 32, the bottoms of the clamping grooves are communicated with the tops of the mounting grooves, when the prefabricated slab 1 is positioned in the mounting grooves, the bottom plate 21 is moved until the bottom plate 21 moves into the clamping grooves, the threaded columns 11 can be quickly abutted into through holes when the prefabricated slab moves downwards, an insertion plate 33 is arranged on the front side of the first limiting seat 31, an insertion groove matched with the insertion plate 33 is formed in the rear side of the second limiting seat 32, the insertion plate 33 is abutted into the insertion groove, pre-fixing of the first limiting seat 31 and the second limiting seat 32 can be realized, the insertion plate 33 is connected with the second limiting seat 32 through a plurality of bolts, a plurality of bolts are unscrewed, the plurality of bolts are taken down, the plurality of bolts are used for limiting seats, the first limiting seat 31 and the second limiting seat 32 can be moved backwards, the guide plates 34 is arranged in the insertion plate, the insertion plate 34, and the guide plate is conveniently separated from the insertion plate, and the guide plate 34 is arranged on the insertion plate; first restriction seat 31 and second restriction seat 32 top all are provided with the direction and fight 35, and the direction is fought 35 inboard and all is provided with the blotter with joint inslot wall, with bottom plate 21 to go into the direction fight 35 in, can support bottom plate 21 into the joint inslot fast.
Further, the rear side of the first limiting seat 31 and the front side of the second limiting seat 32 are both provided with handles 36, the handles 11 are sleeved with anti-slip pads, and the two handles 36 are pulled towards two sides, so that the first limiting seat 31 can be separated from the second limiting seat 32.
The above, only be the concrete implementation of the preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art is in the technical scope of the present invention, according to the technical solution of the present invention and the utility model, the concept of which is equivalent to replace or change, should be covered within the protection scope of the present invention.

Claims (4)

1. The mounting steel structure for the steel structure engineering is characterized by comprising a precast slab (1), a bottom plate (21) placed at the top of the precast slab (1) and an upright post (2) arranged at the top of the bottom plate (21), wherein a plurality of threaded columns (11) are arranged at the top of the precast slab (1), a plurality of through holes matched with the threaded columns (11) are formed in the bottom plate (21), and an auxiliary assembly (3) used for assisting the connection of the precast slab (1) and the bottom plate (21) is arranged at the top of the precast slab (1);
the auxiliary assembly (3) comprises a first limiting seat (31) and a second limiting seat (32) which are arranged on the outer side of the precast slab (1), the first limiting seat (31) and the second limiting seat (32) are convex, mounting grooves matched with the precast slab (1) are formed in the bottoms of the first limiting seat (31) and the second limiting seat (32), clamping grooves matched with the bottom plate (21) are formed in the tops of the first limiting seat (31) and the second limiting seat (32), the bottom of each clamping groove is communicated with the tops of the mounting grooves, a plug board (33) is arranged on the front side of the first limiting seat (31), a plug groove matched with the plug board (33) is formed in the rear side of the second limiting seat (32), and the plug board (33) is connected with the second limiting seat (32) through a plurality of bolts.
2. The mounting steel structure for the steel structure engineering according to claim 1, wherein the top of the first limiting seat (31) and the top of the second limiting seat (32) are both provided with a guide bucket (35), and the inner side of the guide bucket (35) and the inner wall of the clamping groove are both provided with a buffer pad.
3. The mounting steel structure for the steel structure engineering according to claim 1, wherein handles (36) are arranged on the rear side of the first limiting seat (31) and the front side of the second limiting seat (32), and anti-skid pads are sleeved on the handles (36).
4. The installation steel structure for the steel structure engineering according to claim 1, wherein a plurality of guide plates (34) are arranged on the front side of the insertion plate (33), and the guide plates (34) are arc-shaped plates.
CN202222028014.7U 2022-08-03 2022-08-03 Installation steel construction that steel construction engineering used Withdrawn - After Issue CN218028472U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222028014.7U CN218028472U (en) 2022-08-03 2022-08-03 Installation steel construction that steel construction engineering used

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222028014.7U CN218028472U (en) 2022-08-03 2022-08-03 Installation steel construction that steel construction engineering used

Publications (1)

Publication Number Publication Date
CN218028472U true CN218028472U (en) 2022-12-13

Family

ID=84343901

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222028014.7U Withdrawn - After Issue CN218028472U (en) 2022-08-03 2022-08-03 Installation steel construction that steel construction engineering used

Country Status (1)

Country Link
CN (1) CN218028472U (en)

Similar Documents

Publication Publication Date Title
CN203359155U (en) Transportation and storage integrated rack for staircase prefabricated partition board
CN218028472U (en) Installation steel construction that steel construction engineering used
CN209741895U (en) Connection structure of assembled elevator steel construction and base
CN215748390U (en) Polishing tool for bottom film of cover beam workpiece
CN210947340U (en) Steel bar truss floor support plate
CN204660277U (en) A kind of turnover protective device of aluminium casing
CN210947339U (en) Self-supporting steel bar truss building carrier plate
CN211219399U (en) Welding fixing device for machining elevator guide rail
CN210099524U (en) Multifunctional clamp
CN201433342Y (en) T beam bottom web steel bar binding mould
CN218277276U (en) Circuit board convenient to dismantle
CN217680498U (en) Simple template support jackscrew device
CN210092809U (en) High-strength energy-saving pipe master metal tool
CN217082028U (en) High strength formula casting support
CN220247397U (en) Combined cushion block for controlling thickness of reinforcement protection layer and floor slab
CN214978970U (en) Auxiliary welding frame for large pipe truss
CN216316531U (en) Footing device with good strength
CN212351152U (en) Backup plate tool convenient to adjust
CN214418596U (en) Steel construction positioning device
CN210025050U (en) Spacing fixing device of diaphragm
CN209919394U (en) Numerical control boring machine for machining steering knuckle taper hole
CN201306173Y (en) Drivage face forestope hanging device
CN209396730U (en) One kind being based on construction lifting device
CN217375265U (en) Prefabricated rack for side fascia
CN217400048U (en) Prefabricated ribbed floor

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20230721

Address after: B216, Floor 2, Baiwang E-commerce Center, No. 6, Hedong Avenue, Jianchang Town, Nancheng County, Fuzhou City, Jiangxi Province, 344000

Patentee after: Jiangxi Zhongtian Jianguo Construction Engineering Co.,Ltd.

Address before: 571926 In Hainan Zhenbang Logistics Park, the intersection of Yiheng West Road and Zonger Road, Jinma Avenue, Jinma Modern Logistics Center, Dafeng Town, Chengmai County, the county level Administrative division directly under the Central Government of Hainan Province

Patentee before: Hainan Zhongrui Jiexin Steel Structure Co.,Ltd.

TR01 Transfer of patent right
AV01 Patent right actively abandoned

Granted publication date: 20221213

Effective date of abandoning: 20230816

AV01 Patent right actively abandoned

Granted publication date: 20221213

Effective date of abandoning: 20230816

AV01 Patent right actively abandoned