CN217998063U - Pre-buried mounting that concrete pile was used - Google Patents

Pre-buried mounting that concrete pile was used Download PDF

Info

Publication number
CN217998063U
CN217998063U CN202221676749.4U CN202221676749U CN217998063U CN 217998063 U CN217998063 U CN 217998063U CN 202221676749 U CN202221676749 U CN 202221676749U CN 217998063 U CN217998063 U CN 217998063U
Authority
CN
China
Prior art keywords
buried
frame
concrete pile
mounting
nut
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202221676749.4U
Other languages
Chinese (zh)
Inventor
梁欢
华光宇
叶帅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhongnan Construction Nantong Building Industry Co ltd
Original Assignee
Zhongnan Construction Nantong Building Industry Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhongnan Construction Nantong Building Industry Co ltd filed Critical Zhongnan Construction Nantong Building Industry Co ltd
Priority to CN202221676749.4U priority Critical patent/CN217998063U/en
Application granted granted Critical
Publication of CN217998063U publication Critical patent/CN217998063U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses a pre-buried mounting that concrete pile was used, including fixed underframe and baffle, the equal contact in both sides on fixed underframe top is connected with the limiting plate, and the equal fixed mounting in both sides on two limiting plate tops has the fixture block, the utility model relates to a pre-buried mounting that concrete pile was used, through setting up strengthening mechanism, fixed underframe, setting element and pre-buried frame, the staff twists the first nut, promotes the movable frame from one side, adjusts the height of anchor strut on the movable frame, ground stake and ground contact on the anchor strut increase the lifting surface area between pre-buried mounting and the ground, avoid appearing the phenomenon that pre-buried mounting subsides in the ground, fixed frame and setting element are mutually supported, pour pre-buried mounting base through concrete solution, pour pre-buried frame through concrete solution again, install the concrete pile in pre-buried frame, accomplish the overlap joint of concrete pile and ground, improve staff's work efficiency.

Description

Pre-buried mounting that concrete pile was used
Technical Field
The utility model relates to a concrete pile technical field specifically is a pre-buried mounting that concrete pile was used.
Background
When the geological conditions are poor and the bearing capacity of the foundation is small, concrete piles are adopted, one concrete pile is driven into the ground, the weight of a building on the ground is transmitted to a soil layer with high bearing capacity on the lower layer through the concrete pile, if the soil layer with high bearing capacity on the lower layer is deep, the weight of the building on the upper part can be supported by utilizing the friction force of the pile foundation and the surrounding soil, the concrete pile is a stressed rod piece with certain compression resistance and bending resistance, the concrete pile effectively transmits the load of the building to the foundation soil in a semi-extrusion or extrusion mode, because the concrete pile is produced in a large scale mode, the self quality, construction progress and the like of a pipe pile can be effectively controlled, the single concrete pile has high bearing capacity and is widely used, when workers construct the concrete pile, the foundation and the concrete pile need to be connected together by using the embedded fixing pieces, however, the traditional embedded fixing pieces are embedded in a soft foundation, the stress area between the foundations of the embedded fixing pieces is limited, the phenomenon of the embedded fixing pieces in the foundation is easy to occur, the time of the subsequent concrete pile overlap joint adjustment fixing pieces is increased, and the worker needs to readjust the fixing pieces, and the embedded efficiency of the worker needs to reduce the embedded efficiency.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a pre-buried mounting that concrete pile was used to solve the pre-buried in soft ground of traditional pre-buried mounting that proposes in the above-mentioned background art, because the lifting surface area between the ground of pre-buried mounting is limited, the phenomenon that pre-buried mounting subsides in the ground appears easily, increases follow-up concrete pile lapped time, and the staff need readjust pre-buried mounting position, has reduced staff's work efficiency's problem.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a pre-buried mounting that concrete pile was used, includes fixed underframe and baffle, the equal contact connection in both sides on fixed underframe top has a limiting plate, two the equal fixed mounting in both sides on limiting plate top has a fixture block, two top between the limiting plate is equipped with the baffle, the through-hole has all been seted up to four corners on baffle top, the top fixed mounting of fixed underframe has pre-buried frame, the inside of fixed underframe is equipped with four setting elements that run through the baffle, the middle part fixed mounting of pre-buried frame has strengthening mechanism, strengthening mechanism includes locating frame, three first lead screw, movable frame, three first nut, three anchor post and three ground stake, and three first nut promotes the movable frame from one side, and the movable frame slides along fixed underframe, and the in-process that the movable frame slided drives the anchor post and carries out synchronous motion, ground stake and the ground contact on the anchor post increase the lifting surface between pre-buried mounting and the ground.
Preferably, the three first lead screw that runs through the movable frame of top fixedly connected with of posting is three the equal threaded connection in junction of first lead screw and movable frame has first nut, the bottom fixed mounting of movable frame has three reinforcement post, and is three the equal fixed mounting in bottom of reinforcement post has the ground stake, and the staff twists and moves first nut, and the screw thread of first nut inner wall matches each other with the screw thread on first lead screw surface, so first nut takes place the rotational slip along first lead screw.
Preferably, three a plurality of hole for dumping is seted up on the surface of reinforcement post, and the dust granule that flows in the ground freely circulates through the hole for dumping.
Preferably, the inside of the positioning frame is fixedly connected with the embedded frame, and the reinforcing mechanism is installed in the embedded frame through the positioning frame.
Preferably, four the locating pieces all include support base, second lead screw and second nut, the top fixed mounting who supports the base has the second lead screw, the top of second lead screw is passed through-hole threaded connection and is had the second nut, and the staff twists the second nut, and the screw thread on second nut inner wall and the screw thread on second lead screw surface match each other, so the second nut is rotatory along the second lead screw and is gone up and down.
Preferably, four all sliding connection has the gasket that is located the second nut below on the second lead screw, and the installation of gasket can increase the area of contact between second nut and the baffle, reduces pressure, prevents that the second nut is not hard up, protects second nut and second lead screw.
Preferably, the four clamping blocks are respectively connected with clamping grooves formed in two ends of two sides of the baffle in a clamping mode, a worker aligns the clamping grooves in the baffle with the clamping blocks, and the baffle is assembled between the two limiting plates.
Compared with the prior art, the beneficial effects of the utility model are that: through setting up reinforcing mechanism, fixed underframe, setting element and pre-buried frame, the staff twists and moves first nut, promote the movable frame from one side, adjust the height of reinforcement post on the movable frame, ground stake and the ground contact on the reinforcement post, increase the lifting surface between pre-buried mounting and the ground, the phenomenon of pre-buried mounting settlement in the ground avoids appearing, fixed frame and setting element are mutually supported, pour into pre-buried mounting base through concrete solution, pour pre-buried frame through concrete solution again, install the concrete pile in pre-buried frame, accomplish the overlap joint of concrete pile and ground, improve staff's work efficiency.
Drawings
Fig. 1 is a side view of the present invention;
FIG. 2 is a partial schematic view of the present invention;
FIG. 3 is a side view of the reinforcement mechanism of the present invention;
fig. 4 is a side view of the positioning member of the present invention.
In the figure: 1. fixing the bottom frame; 2. a reinforcement mechanism; 21. a positioning frame; 22. a first lead screw; 23. a movable frame; 24. a first nut; 25. reinforcing columns; 26. piling; 27. a soil discharge hole; 3. pre-embedding a frame; 4. a limiting plate; 5. a clamping block; 6. a positioning member; 61. a support base; 62. a second lead screw; 63. a gasket; 64. a second nut; 7. a baffle plate; 8. a through hole; 9. a clamping groove.
Detailed Description
The technical solution in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present invention.
Please refer to fig. 1-4, the utility model provides a pre-buried mounting that concrete pile was used, including fixed underframe 1 and baffle 7, the equal contact connection in both sides on fixed underframe 1 top has limiting plate 4, the equal fixed mounting in both sides on two limiting plate 4 tops has fixture block 5, top between two limiting plate 4 is equipped with baffle 7, through-hole 8 has all been seted up to four corners on baffle 7 top, the top contact connection of fixed underframe 1 has pre-buried frame 3, the inside of fixed underframe 1 is equipped with four setting elements 6 that run through baffle 7, the middle part fixed mounting of pre-buried frame 3 has strengthening mechanism 2, strengthening mechanism 2 includes locating frame 21, three first lead screw 22, movable frame 23, three first nut 24, three anchor strut 25 and three ground stake 26, three first nut 24 promotes movable frame 23 from one side, movable frame 23 slides along fixed underframe 1, the in-process that movable frame 23 slided drives anchor strut 25 and carries out synchronous motion, ground stake 26 on the anchor strut 25 and the ground contact, increase the lifting surface between pre-buried mounting and the ground.
The three first lead screw 22 that runs through activity frame 23 of the top fixedly connected with of locating frame 21, the equal threaded connection in junction of three first lead screw 22 and activity frame 23 has first nut 24, the bottom fixed mounting of activity frame 23 has three reinforcement post 25, the equal fixed mounting in bottom of three reinforcement post 25 has ground stake 26, the staff twists first nut 24, the screw thread on the 24 inner walls of first nut matches each other with the screw thread on first lead screw 22 surface, so first nut 24 takes place the rotational sliding along first lead screw 22.
A plurality of dumping holes 27 are opened on the surface of three reinforcing columns 25, and dust particles flowing in the foundation freely circulate through the dumping holes 27.
The inside and pre-buried frame 3 fixed connection of locating frame 21, reinforcing mechanism 2 passes through locating frame 21 to be installed in pre-buried frame 3.
The four positioning pieces 6 respectively comprise a supporting base 61, a second lead screw 62 and a second nut 64, the second lead screw 62 is fixedly mounted at the top end of the supporting base 61, the top end of the second lead screw 62 penetrates through the through hole 8 and is in threaded connection with the second nut 64, a worker screws the second nut 64, and threads on the inner wall of the second nut 64 are matched with threads on the surface of the second lead screw 62, so that the second nut 64 rotates and ascends along the second lead screw 62.
All sliding connection has the gasket 63 that is located the second nut 64 below on four second lead screws 62, and the installation of gasket 63 can increase the area of contact between second nut 64 and the baffle 7, reduces pressure, prevents that second nut 64 from becoming flexible, protects second nut 64 and second lead screw 62.
The four clamping blocks 5 are respectively clamped and connected with clamping grooves 9 formed in two ends of two sides of the baffle 7, a worker aligns the clamping grooves 9 in the baffle 7 with the clamping blocks 5, and the baffle 7 is assembled between the two limiting plates 4.
When the embodiment of the application is used: the worker places the fixed bottom frame 1 in the foundation, place two limiting plates 4 on the fixed bottom frame 1, the worker aligns the draw-in groove 9 on the baffle 7 with the fixture block 5, assemble the baffle 7 between two limiting plates 4, the support base 61 of four locating parts 6 of the worker is placed on the foundation in the fixed bottom frame 1, and the second lead screw 62 passes through the through hole 8, the worker twists the second nut 64, the screw thread of the inner wall of the second nut 64 matches with the screw thread on the surface of the second lead screw 62, so the second nut 64 rotates along the second lead screw 62 to lift, fix the second lead screw 62, the worker puts the concrete solution for fixing into the fixed bottom frame 1, the limiting plate 4 is spacing from the top of the fixed bottom frame 1, the worker twists the second nut 64, rotate the second nut 64 from the second lead screw 62, the worker places the embedded frame 3 on the fixed bottom frame 1, the worker passes through the second nut 62 at the four holes at the bottom end of the concrete pile, the worker twists the second nut 64, fix the second nut 62 from the second lead screw 62, the second lead screw 23, the embedded frame 24 slides along the ground, the embedded frame 24 of the embedded pile 24, the embedded pile moves along the ground, the embedded pile 24, the embedded pile moves along the embedded concrete pile.
Although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications may be made to the embodiments or portions thereof without departing from the spirit and scope of the invention.

Claims (7)

1. The utility model provides a pre-buried mounting that concrete pile was used, includes fixed underframe (1) and baffle (7), its characterized in that: the utility model discloses a fixing device for ground piles, including fixed underframe (1), limiting plate (4), two the equal contact in both sides on limiting plate (4) top is connected with limiting plate (4), two the equal fixed mounting in both sides on limiting plate (4) top has fixture block (5), two top between limiting plate (4) is equipped with baffle (7), through-hole (8) have all been seted up to four corners on baffle (7) top, the top contact of fixed underframe (1) is connected with pre-buried frame (3), the inside of fixed underframe (1) is equipped with four setting element (6) that run through baffle (7), the middle part fixed mounting of pre-buried frame (3) has strengthening mechanism (2), strengthening mechanism (2) include posting (21), three first lead screw (22), movable frame (23), three first nut (24), three reinforcement column (25) and three ground stake (26).
2. The pre-buried fixed part that concrete pile used of claim 1, its characterized in that: the utility model discloses a fixing device for concrete pile, including locating frame (21), the top fixedly connected with of locating frame (21) is three first lead screw (22) that runs through activity frame (23), and is three the equal threaded connection in junction of first lead screw (22) and activity frame (23) has first nut (24), the bottom fixed mounting of activity frame (23) has three reinforcement post (25), and is three the equal fixed mounting in bottom of reinforcement post (25) has ground stake (26).
3. The pre-buried mounting that a concrete pile used of claim 1, characterized in that: the surfaces of the three reinforcing columns (25) are provided with a plurality of soil discharge holes (27).
4. The pre-buried fixed part that concrete pile used of claim 1, its characterized in that: the inside of the positioning frame (21) is fixedly connected with the embedded frame (3).
5. The pre-buried fixed part that concrete pile used of claim 1, its characterized in that: four the setting element (6) all includes support base (61), second lead screw (62) and second nut (64), the top fixed mounting who supports base (61) has second lead screw (62), the top of second lead screw (62) is passed through-hole (8) threaded connection and is had second nut (64).
6. The pre-buried mounting that a concrete pile used of claim 5, characterized in that: the four second screw rods (62) are connected with gaskets (63) below the second nuts (64) in a sliding mode.
7. The pre-buried fixed part that concrete pile used of claim 1, its characterized in that: the four clamping blocks (5) are respectively connected with clamping grooves (9) formed in two ends of two sides of the baffle (7) in a clamping mode.
CN202221676749.4U 2022-07-01 2022-07-01 Pre-buried mounting that concrete pile was used Active CN217998063U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221676749.4U CN217998063U (en) 2022-07-01 2022-07-01 Pre-buried mounting that concrete pile was used

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221676749.4U CN217998063U (en) 2022-07-01 2022-07-01 Pre-buried mounting that concrete pile was used

Publications (1)

Publication Number Publication Date
CN217998063U true CN217998063U (en) 2022-12-09

Family

ID=84313265

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221676749.4U Active CN217998063U (en) 2022-07-01 2022-07-01 Pre-buried mounting that concrete pile was used

Country Status (1)

Country Link
CN (1) CN217998063U (en)

Similar Documents

Publication Publication Date Title
CN211113707U (en) Embedded positioning device for foundation bolt
CN208456111U (en) Adjustable receipts face mould plate supporting device
CN215906792U (en) Lattice column guiding, positioning and verticality adjusting installation equipment
CN217998063U (en) Pre-buried mounting that concrete pile was used
CN109518942B (en) Tool-based bracket system for controlling precision of two-dimensional component and application method thereof
JP2014051848A (en) Solar panel installation base
CN209568564U (en) A kind of civil engineering anti-seismic structure
CN217076793U (en) Tower crane installation adjusting base
CN110700432A (en) Shock insulation layer structure
CN113174986B (en) Base structure of steel structure building
CN214089894U (en) Pit foundation supporting device for municipal works
CN112282074A (en) Adjusting device for embedded part and construction method thereof
CN209760786U (en) instrumentization support system for controlling precision of two-dimensional component
CN209620047U (en) Building foundation pit diagonal brace structure
CN206607706U (en) A kind of drawing shore for shear wall construction
CN213358716U (en) Fastening and leveling device for anchor bolt cage
CN206000167U (en) Adjustable Alminum Project slab form support meanss
CN219773265U (en) Novel shockproof shear wall
CN209923908U (en) Direct vent difference vacuum pre-compaction foundation treatment structure
CN106638650B (en) Fabricated concrete foundation structure
CN218438009U (en) Fast assembly elevator shaft
CN219887178U (en) Novel foundation leveling structure for bottom building
CN219621717U (en) River-to-river hinge mechanism for steel dam gate
CN218375532U (en) Supporting device convenient to disassemble
CN214834942U (en) Height-adjustable cushion block for steel structure construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant