CN217976240U - Prefabricated assembled lining of mountain tunnel water drainage prevention - Google Patents

Prefabricated assembled lining of mountain tunnel water drainage prevention Download PDF

Info

Publication number
CN217976240U
CN217976240U CN202221294574.0U CN202221294574U CN217976240U CN 217976240 U CN217976240 U CN 217976240U CN 202221294574 U CN202221294574 U CN 202221294574U CN 217976240 U CN217976240 U CN 217976240U
Authority
CN
China
Prior art keywords
drainage
lining
prefabricated
waterproof
lining cutting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202221294574.0U
Other languages
Chinese (zh)
Inventor
李睿骞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Survey And Design Institute Of China Railway 11th Bureau Group Co ltd
China Railway 11th Bureau Group Co Ltd
Original Assignee
Survey And Design Institute Of China Railway 11th Bureau Group Co ltd
China Railway 11th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Survey And Design Institute Of China Railway 11th Bureau Group Co ltd, China Railway 11th Bureau Group Co Ltd filed Critical Survey And Design Institute Of China Railway 11th Bureau Group Co ltd
Priority to CN202221294574.0U priority Critical patent/CN217976240U/en
Application granted granted Critical
Publication of CN217976240U publication Critical patent/CN217976240U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model provides a prefabricated assembled lining cutting of mountain tunnel water drainage prevention, including the lining cutting body, the lining cutting body includes the prefabricated assembled lining cutting of outer preliminary bracing and inlayer, it has geotechnological cloth layer to fill between the two, stagnant water zone layer and backfill slip casting layer behind one's back, the hoop construction joint department of assembling between preliminary bracing and the geotechnological cloth layer is equipped with convex shell type drain bar, seam department is equipped with the sealed pad of elastic rubber between the lining cutting piece, the bottom center of lining cutting body is equipped with central escape canal, the low wall is equipped with the drainage side ditch, it is equipped with vertical drainage blind pipe and outlet to lie in side wall foot department between preliminary bracing and the convex shell type drain bar, wherein the export of vertical drainage blind pipe and the slant drain pipe intercommunication of bending into the drainage side ditch, through central drain pipe intercommunication between drainage side ditch and the central escape canal. The utility model discloses use the tradition to prevent that drainage lining cutting structure is the basis, combine the characteristics in assembled tunnel to improve, can improve mountain tunnel prefabricated assembled lining cutting's waterproof and drainage effect by a wide margin.

Description

Prefabricated assembled lining of mountain tunnel water drainage prevention
Technical Field
The utility model relates to a tunnel design construction technical field especially relates to a prefabricated assembled lining cutting of mountain tunnel waterproof and drainage.
Background
Since the establishment of new China, various careers in China are developed, and especially in the last two decades, traffic infrastructure is unprecedentedly and greatly developed. Mountain tunnels in China have undergone the progress from traditional supporting structures to modern supporting structures and from integral lining to composite lining. The construction method of mountain tunnel is also developed from traditional mine method to new Austrian method and TBM construction method.
At present, the application of prefabricated technology for mountain tunnels built by a new Olympic method in China is relatively few. Traditional waterproof lining cutting structure is difficult to reach the ideal effect, easily leads to the percolating water, and the percolating water problem appears in the tunnel not only can weaken weak country rock on every side slightly, leads to touchdown nature country rock to be in the inflation state, leads to the fact the threat to tunnel structure safety, also can lead to the inside fog of tunnel to increase simultaneously, the bottom surface is too slippery, and visibility is low, has increased the potential safety hazard.
In some special environments, such as regions such as high and cold frozen soil and the like, the fabricated lining can effectively adapt to the environment under the condition that the molded concrete is difficult to implement, thereby not only ensuring the quality of the concrete, but also reducing corresponding auxiliary construction measures and improving the construction environment of the tunnel. Therefore, the waterproof and drainage structure based on the prefabricated assembled lining on the mountain ridge needs to be further researched and perfected.
Disclosure of Invention
In order to solve the not enough of prior art, the utility model provides a prefabricated assembled lining cutting of drainage is prevented in mountain tunnel to the drainage lining cutting structure is prevented to the tradition is based, combines the characteristics in assembled tunnel to improve, can improve mountain tunnel prefabricated assembled lining cutting's drainage effect of preventing by a wide margin.
The utility model discloses a solve the technical scheme that its technical problem adopted and be: the prefabricated lining comprises a lining body, wherein the lining body comprises an outer primary support and an inner prefabricated lining, short side walls are arranged at the bottoms of two sides of an inverted arch of the prefabricated lining, a geotextile layer, a water stop belt layer and a back backfill grouting layer are sequentially filled between the primary support and the prefabricated lining from outside to inside, a convex shell type drainage plate is arranged between the primary support and the geotextile layer at an assembly circumferential construction joint of the prefabricated lining, an elastic rubber sealing gasket is arranged at a joint between lining sheets of the prefabricated lining, a central drainage ditch extending along the longitudinal depth direction of a tunnel is arranged in the center of the bottom of the lining body, a drainage side ditch extending along the longitudinal depth direction of the tunnel is arranged on the short side walls, a longitudinal drainage blind pipe and a drainage hole are arranged between the primary support and the convex shell type waterproof plate at a side wall foot, an outlet of the longitudinal drainage blind pipe is communicated with an oblique drainage pipe bent into the drainage side ditch, and the drainage side ditch is communicated through the central drainage pipe.
A middle embedded rubber water stop is arranged between the low side wall and the assembling annular construction joint of the prefabricated assembly type lining, and an outer surface edge of the middle embedded rubber water stop is provided with an outer attached rubber water stop.
An elastic rubber sealing gasket is arranged between the short side wall and the longitudinal joint of the prefabricated lining.
The distance between the opening of the water drainage hole and the bottom of the drainage side ditch is not less than 25cm, the gradient is not less than 10 percent, and the longitudinal distance is 1.5 to 2.5m.
The width of the convex-shell type drainage plate is 0.8-1.2 m, and the longitudinal distance is 3.5-4.5 m.
The diameter of the longitudinal drainage blind pipe is 80-120 mm.
The distance between each drainage side ditch, each drainage blind pipe, each inclined drainage pipe and each central drainage pipe and the assembly annular construction joint of the prefabricated assembly type lining is not less than 1m.
The utility model discloses based on the beneficial effect that its technical scheme had lies in:
(1) The prefabricated assembled lining structure for mountain tunnel water drainage prevention provided by the utility model has compact and reasonable structure, and on the basis of the existing lining water drainage prevention structure, the structure of the prefabricated assembled lining is considered to be improved, so that the water drainage prevention effect of the prefabricated assembled lining of mountain tunnel can be greatly improved;
(2) The utility model provides a pair of prefabricated assembled lining cutting of mountain tunnel water drainage has been removed hoop blind pipe among the traditional drainage structures from, adopts the drainage side ditch of two sides in the hole to add central escape canal, sets up protruding shell type drain bar in prefabricated lining cutting circumferential weld department, utilizes the vertical drainage blind pipe of limit plinth to incorporate into the drainage side ditch, reaches the drainage purpose, easily installs, and drainage effect is good.
Drawings
Fig. 1 is the utility model provides a prefabricated assembled lining cutting section structure sketch of mountain tunnel waterproof and drainage.
Fig. 2 is a schematic sectional view taken along line I-I of fig. 1.
In the figure: 1-primary support, 2-convex shell type drainage plates, 3-geotextile layers, 4-water stop belt layers, 5-back backfill grouting layers, 6-prefabricated assembly type lining, 7-elastic rubber sealing gaskets, 8-central drainage pipes, 9-longitudinal drainage blind pipes, 10-oblique drainage pipes, 11-central drainage ditches, 12-drainage side ditches, 13-short side walls and 14-assembly annular construction joints.
Detailed Description
The present invention will be further explained with reference to the drawings and examples.
The utility model provides a prefabricated assembled lining cutting of mountain ridge tunnel waterproof and drainage, refer to figure 1 and figure 2, including the lining cutting body, the lining cutting body includes the prefabricated assembled lining cutting 6 of outer preliminary bracing 1 and inlayer, the invert both sides bottom of prefabricated assembled lining cutting is equipped with short side wall 13, outside-in has filled geotechnological cloth layer 3 in proper order between preliminary bracing and the prefabricated assembled lining cutting, waterstop layer 4 and backfill slip casting layer 5 behind one's back, the hoop 14 departments of assembling that lie in prefabricated assembled lining between preliminary bracing and the geotechnological cloth layer are equipped with convex shell type drain bar 2 to construction joint, seam department is equipped with the sealed pad 7 of elastic rubber between the lining cutting piece of prefabricated assembled lining cutting.
The bottom center of lining cutting body is equipped with along the central escape canal 11 of tunnel depth direction extension, and low boundary wall is equipped with along the drainage lateral ditch 12 of tunnel depth direction extension, lies in boundary wall foot department between preliminary bracing and the convex shell type waterproof board and is equipped with vertical drainage blind pipe 9 and outlet, and wherein the export of vertical drainage blind pipe and the slant drain pipe 10 intercommunication of bending into the drainage lateral ditch, communicate through central drain pipe 8 between drainage lateral ditch and the central escape canal.
A middle embedded rubber water stop is arranged between the low side wall and the assembling annular construction joint of the prefabricated assembly type lining, and an outer surface edge of the middle embedded rubber water stop is provided with an outer attached rubber water stop.
An elastic rubber sealing gasket is arranged between the short side wall and the longitudinal joint of the prefabricated lining.
The distance between the opening of the drain hole and the drain side ditch bottom is not less than 25cm, the gradient is not less than 10 percent, and the longitudinal distance is 1.5 to 2.5m. In this embodiment, a longitudinal interval of 2m is adopted.
The width of the convex shell type drainage plate is 0.8-1.2 m, the longitudinal distance is 3.5-4.5 m, in the embodiment, the convex shell type drainage plate with the width of 1m is adopted, and the longitudinal distance is 4m.
The diameter of the longitudinal drainage blind pipe is 80-120 mm, in the embodiment, a maintainable plastic fiber drainage filter pipe with the diameter of 100mm is adopted as the longitudinal drainage blind pipe, and the distance between the pipes can be set to be 10m.
The distance between each drainage side ditch, each drainage blind pipe, each inclined drainage pipe and each central drainage pipe and the assembly annular construction joint of the prefabricated assembly type lining is not less than 1m.
The utility model provides a pair of prefabricated assembled lining cutting of mountain tunnel water drainage is compact reasonable, on current lining cutting water drainage structures's basis, considers the structure of prefabricated assembled lining cutting to improve, can improve mountain tunnel prefabricated assembled lining cutting's water drainage effect of preventing by a wide margin.

Claims (7)

1. The utility model provides a prefabricated assembled lining of mountain tunnel waterproof and drainage, includes the lining cutting body, its characterized in that: the lining body comprises an outer primary support (1) and an inner prefabricated assembly type lining (6), wherein short side walls (13) are arranged at the bottoms of two sides of an inverted arch of the prefabricated assembly type lining, a geotextile layer (3), a water stop belt layer (4) and a back backfill grouting layer (5) are sequentially filled between the primary support and the prefabricated assembly type lining from outside to inside, a convex shell type drainage plate (2) is arranged at an assembly annular construction joint (14) between the primary support and the geotextile layer, an elastic rubber sealing gasket (7) is arranged at a joint between lining pieces of the prefabricated assembly type lining, a central drainage ditch (11) extending along the longitudinal depth direction of the tunnel is arranged at the center of the bottom of the lining body, a drainage side ditch (12) extending along the longitudinal depth direction of the tunnel is arranged on the short side wall, a longitudinal drainage pipe (9) and a drainage hole are arranged at a side wall foot between the primary support and the convex shell type waterproof plate, an outlet of the longitudinal drainage blind pipe is communicated with an inclined drainage pipe (10) bent into the drainage side ditch, and the central drainage pipe is communicated with the central drainage ditch through the central drainage pipe (8).
2. The prefabricated waterproof and waterproof fabricated lining for mountain tunnels of claim 1, wherein: a middle embedded rubber water stop is arranged between the low side wall and the assembling annular construction joint of the prefabricated assembly type lining, and an outer surface edge of the middle embedded rubber water stop is provided with an outer attached rubber water stop.
3. The mountain tunnel waterproof and drainage prefabricated lining as claimed in claim 1, wherein: an elastic rubber sealing gasket is arranged between the short side wall and the longitudinal joint of the prefabricated lining.
4. The mountain tunnel waterproof and drainage prefabricated lining as claimed in claim 1, wherein: the distance between the opening of the drain hole and the drain side ditch bottom is not less than 25cm, the gradient is not less than 10 percent, and the longitudinal distance is 1.5 to 2.5m.
5. The mountain tunnel waterproof and drainage prefabricated lining as claimed in claim 1, wherein: the width of the convex-shell type drainage plate is 0.8-1.2 m, and the longitudinal distance is 3.5-4.5 m.
6. The prefabricated waterproof and waterproof fabricated lining for mountain tunnels of claim 1, wherein: the diameter of the longitudinal drainage blind pipe is 80-120 mm.
7. The prefabricated waterproof and waterproof fabricated lining for mountain tunnels of claim 1, wherein: the distance between each drainage lateral ditch, each drainage blind pipe, each inclined drainage pipe and each central drainage pipe and the spliced annular construction joint of the prefabricated lining is not less than 1m.
CN202221294574.0U 2022-05-27 2022-05-27 Prefabricated assembled lining of mountain tunnel water drainage prevention Active CN217976240U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221294574.0U CN217976240U (en) 2022-05-27 2022-05-27 Prefabricated assembled lining of mountain tunnel water drainage prevention

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221294574.0U CN217976240U (en) 2022-05-27 2022-05-27 Prefabricated assembled lining of mountain tunnel water drainage prevention

Publications (1)

Publication Number Publication Date
CN217976240U true CN217976240U (en) 2022-12-06

Family

ID=84267923

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221294574.0U Active CN217976240U (en) 2022-05-27 2022-05-27 Prefabricated assembled lining of mountain tunnel water drainage prevention

Country Status (1)

Country Link
CN (1) CN217976240U (en)

Similar Documents

Publication Publication Date Title
CN205895312U (en) Be used for rich irrigated land section tunnel water handling system
CN101748755B (en) Flexible connecting and sealing bitumastic impervious structure of tunnel deformation joint and constructing method
CN202124865U (en) Quick plugging device for dewatering wellhead of sand-free cement pipe deep well
CN105986836B (en) A kind of single-track railway tunnel substrate guarded drainage strengthen the system
CN104088295B (en) The embedded connecting structure of enclosure wall and middle plate and construction method thereof in covered back-digging
CN111608727A (en) Cold region mountain tunnel composite drainage system and construction method thereof
CN108361065B (en) Tunnel inverted arch filling drainage structure
CN106894830A (en) A kind of double curvature arch supporting construction and construction method for underground engineering
CN207795260U (en) The tunneling main body of electric power tunnel is worn under a kind of
CN217976240U (en) Prefabricated assembled lining of mountain tunnel water drainage prevention
CN207700221U (en) A kind of prefabricated pipe gallery steel plate cast-in-place concrete sealing connection structure
CN213538991U (en) Wall-penetrating connecting structure for front-supporting type grouting steel pipe
CN111594184A (en) Main hole excavating method for hole bias tunnel
CN104404919A (en) Dam foundation corridor and bank slope bedrock connecting structure
CN204783063U (en) Doubly -linked encircles tunnel mid -board prevents drainage structures
CN204266170U (en) A kind of dam foundation gallery syndeton
CN218757308U (en) Annular structure seam structure between riverbed dam foundation gallery and bank slope gallery concrete
CN213450403U (en) Weak surrounding rock tunnel large deformation section bearing structure
CN212296413U (en) Back-pasting type pi-shaped rubber water stop for tunnel engineering
CN213508576U (en) Anti building structure that floats
CN114263219A (en) Advanced water stop structure of bottom plate post-cast strip for underground engineering and construction method
CN111779503A (en) Triple baffling type partition waterproof structure of underground excavation tunnel
CN217897961U (en) Double-arch tunnel mid-partition wall water-drainage-preventing structure
CN213926355U (en) Prefabricated utility tunnel waterproof construction of assembling
CN216198173U (en) Prevent drain bar with drainage function

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant