CN217949750U - House building residence water electric heating reserved hole construction device - Google Patents

House building residence water electric heating reserved hole construction device Download PDF

Info

Publication number
CN217949750U
CN217949750U CN202222278656.2U CN202222278656U CN217949750U CN 217949750 U CN217949750 U CN 217949750U CN 202222278656 U CN202222278656 U CN 202222278656U CN 217949750 U CN217949750 U CN 217949750U
Authority
CN
China
Prior art keywords
column
fixed
reserved
reserved hole
sliding plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222278656.2U
Other languages
Chinese (zh)
Inventor
杨利
徐泰鹏
孙天兴
王家继
李昌庭
马驰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Second Engineering Bureau Co Ltd
Original Assignee
China Construction Second Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Second Engineering Bureau Co Ltd filed Critical China Construction Second Engineering Bureau Co Ltd
Priority to CN202222278656.2U priority Critical patent/CN217949750U/en
Application granted granted Critical
Publication of CN217949750U publication Critical patent/CN217949750U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Housings, Intake/Discharge, And Installation Of Fluid Heaters (AREA)

Abstract

The utility model discloses a house is built house water electricity and is warmed up and reserve hole construction equipment relates to construction technical field, comprising a main body, the upper end of main part is provided with the concrete, the reservation sleeve pipe is installed to the upper end of main part, the one end of reserving the intraduct is provided with fixing device, it is provided with strutting arrangement to reserve the sheathed tube upper end, strutting arrangement's one end is provided with withdrawing device. The utility model discloses a fixed shell, the screw thread post, first slide, under the combined action of fixed column and screw cap, the function of fixed reservation hole position has been increased, under the combined action through backup pad, the spout, the second slide, the fixed block, bracer and bolt, the function that can not warp when having increased the reservation sleeve pipe and receiving the extrusion, under the combined action through fixed plate, runner, column spinner and flexible post, increased and reserved the function that can be taken out by the whole after the sleeve pipe uses, can make reservation sleeve pipe repetitious usage.

Description

House building residence water electric heating reserved hole construction device
Technical Field
The utility model relates to a construction technical field, concretely relates to house is built residential water and electricity and is warm to reserve hole construction equipment.
Background
The construction of building residential water electric heating reserved hole is a common construction in the civil construction work progress, and the reservation of current cast in concrete floor pipeline hole commonly adopts reservation sleeve pipes such as PVC pipe, iron sheet pipe, finished product pre-buried pipe fitting. During construction, the reserved sleeve is placed on the template, concrete is poured on the template, after the concrete is poured, the reserved sleeve is taken out of the concrete, and therefore a reserved hole is formed, the residential building water and electric heating reserved hole construction device is a device for constructing the residential building water and electric heating reserved hole for a house, and the construction of the water and electric heating reserved hole is more practical.
The following problems exist in the prior art:
1. in the existing construction device for the water and electricity heating reserved hole of the house building, after the reserved hole is selected in the using process, when concrete is extruded, the position of the reserved hole can be deviated, so that the reserved hole cannot be used;
2. in the existing construction device for the water and electricity heating reserved hole of the house building, in the using process, the reserved sleeve is extruded by concrete, so that the reserved hole is irregular in shape and can be used only by secondary processing, and time is wasted;
3. the existing construction device for the water and electric heating reserved hole of the house building is not easy to completely take out after the reserved sleeve is used in the using process, can not be used for multiple times, and wastes materials.
SUMMERY OF THE UTILITY MODEL
In order to solve the technical problem, the utility model discloses the technical scheme who adopts is:
a construction device for a water and electricity heating reserved hole of a house building comprises a main body, wherein concrete is arranged at the upper end of the main body, a reserved sleeve is installed at the upper end of the main body, a fixing device is arranged at one end inside the reserved sleeve, a supporting device is arranged at the upper end of the reserved sleeve, and a drawing-out device is arranged at one end of the supporting device; the fixing device comprises a fixing shell, one end of the fixing shell is fixedly connected with one end of the inside of the reserved sleeve, a threaded column is arranged at one end of the fixing shell, a first sliding plate is arranged at the lower end of the threaded column, a fixing column is arranged at the lower end of the first sliding plate, and a threaded cap is arranged at the upper end of the threaded column; the supporting device comprises a supporting plate, the lower end of the supporting plate is fixedly connected with the upper end of the reserved sleeve, a sliding groove is installed at the upper end of the supporting plate, a second sliding plate is arranged at one end of the inside of the sliding groove, a fixing block is installed at the lower end of the second sliding plate, a supporting block is installed at the lower end of the fixing block, and a bolt is arranged at one end of the second sliding plate.
The utility model discloses technical scheme's further improvement lies in: one end of the fixed shell is in threaded connection with one end of the threaded column, and the lower end of the threaded column is movably connected with the upper end of the first sliding plate.
The utility model discloses technical scheme's further improvement lies in: the lower end of the first sliding plate is fixedly connected with the upper end of the fixing column, and the upper end of the threaded column is fixedly connected with the lower end of the threaded cap.
The utility model discloses technical scheme's further improvement lies in: the upper end of the supporting plate is fixedly connected with the lower end of the sliding groove, one end of the inside of the sliding groove is slidably connected with one end of the second sliding plate, and the lower end of the second sliding plate is fixedly connected with the upper end of the fixing block.
The utility model discloses technical scheme's further improvement lies in: the lower extreme of fixed block and the upper end fixed connection of bracer, the other end of second slide and the one end threaded connection of bolt.
The utility model discloses technical scheme's further improvement lies in: the withdrawing device comprises a fixed plate, one end of the fixed plate is fixedly connected with one end of the supporting device, the rotating wheel is installed at one end of the fixed plate, the rotating column is installed at the lower end of the rotating wheel, and the telescopic column is installed at one end of the inner portion of the rotating column.
The utility model discloses technical scheme's further improvement lies in: one end of the fixed plate is rotatably connected with one end of the rotating wheel, the lower end of the rotating wheel is fixedly connected with the upper end of the rotating column, and one end of the inside of the rotating column is movably connected with one end of the telescopic column.
Owing to adopted above-mentioned technical scheme, the utility model discloses relative prior art, the technological progress who gains is:
1. the utility model provides a house is built residential water electric heating and is reserved hole construction equipment, through fixed shell, the screw thread post, first slide, under the combined action of fixed column and screw cap, the function of fixed reserved hole position has been increased, this change is put after reserving the hole position through reserving the sleeve pipe, screw thread post is screwed up, this moment under the rotation of screw thread post, first slide can move down in fixed shell, the fixed column also removes along with first slide this moment, the fixed column stops when inserting the main part inside, make and reserve sleeve pipe and reserved hole rigidity.
2. The utility model provides a house is built in house water and electricity and is heated reservation hole construction equipment under the combined action through backup pad, spout, second slide, fixed block, bracer and bolt, increased and reserved the function that can not warp when the sleeve pipe receives the extrusion, this change through the second slide that slides in the spout, make second slide take fixed block and bracer to remove, stop when the bracer pastes the reservation sleeve pipe, screw up the bolt again, make the second slide fixed.
3. The utility model provides a house is built residential water electric heating and is reserved hole construction equipment, through the combined action of fixed plate, runner, column spinner and flexible post under, increased and reserved the function that can be taken out by the whole after the sleeve pipe uses, can make and reserve sleeve pipe repetitious usage, this change is through rotating the runner, then the runner can drive the column spinner and rotate, at this moment flexible post can extend downwards under the rotation of column spinner, then contact the concrete, it is ejecting to reserve the sleeve pipe.
Drawings
FIG. 1 is a schematic structural view of the construction device for a water and electricity heating reserved hole of a house building of the present invention;
fig. 2 is a schematic structural view of the fixing device of the present invention;
fig. 3 is a schematic structural view of the supporting device of the present invention;
fig. 4 is a schematic structural view of the drawing-out device of the present invention.
In the figure: 1. a main body; 2. concrete; 3. reserving a sleeve; 4. a fixing device; 5. a support device; 6. a drawing-out device; 41. fixing the housing; 42. a threaded post; 43. a slide plate; 44. fixing a column; 45. a screw cap; 51. a support plate; 52. a chute; 53. a slide plate; 54. a fixed block; 55. a support block; 56. a bolt; 61. a fixing plate; 62. a rotating wheel; 63. a spin column; 64. a telescopic column.
Detailed Description
The present invention will be described in further detail with reference to the following examples:
example 1
As shown in fig. 1-4, the utility model provides a house is built residential water electric heating and is reserved hole construction equipment, including main part 1, the upper end of main part 1 is provided with concrete 2, and reserve sleeve pipe 3 is installed to the upper end of main part 1, and the inside one end of reserve sleeve pipe 3 is provided with fixing device 4, and the upper end of reserve sleeve pipe 3 is provided with strutting arrangement 5, and strutting arrangement 5's one end is provided with withdrawing device 6.
Example 2
As shown in fig. 1-4, on the basis of embodiment 1, the utility model provides a technical solution: preferably, the fixing device 4 includes a fixing housing 41, one end of the fixing housing 41 is fixedly connected with one end inside the reserved casing 3, one end of the fixing housing 41 is provided with a threaded column 42, the lower end of the threaded column 42 is provided with a first sliding plate 43, the lower end of the first sliding plate 43 is provided with a fixing column 44, and the upper end of the threaded column 42 is provided with a threaded cap 45; one end of the fixed shell 41 is in threaded connection with one end of the threaded column 42, the lower end of the threaded column 42 is movably connected with the upper end of the first sliding plate 43, the lower end of the first sliding plate 43 is fixedly connected with the upper end of the fixed column 44, and the upper end of the threaded column 42 is fixedly connected with the lower end of the threaded cap 45.
In this embodiment, the function of fixing the reserved hole position is added, the modification is that after the reserved sleeve 3 is placed at the reserved hole position, the threaded column 42 is screwed, at this time, under the rotation of the threaded column 42, the first sliding plate 43 moves downwards in the fixed housing 41, at this time, the fixed column 44 also moves along with the first sliding plate 43, and the fixed column 44 stops when being inserted into the main body 1, so that the reserved sleeve 3 is fixed with the reserved hole position.
Example 3
As shown in fig. 1, on the basis of embodiment 1, the utility model provides a technical solution: preferably, the supporting device 5 includes a supporting plate 51, the lower end of the supporting plate 51 is fixedly connected with the upper end of the reserved sleeve 3, a sliding groove 52 is installed at the upper end of the supporting plate 51, a second sliding plate 53 is arranged at one end inside the sliding groove 52, a fixing block 54 is installed at the lower end of the second sliding plate 53, a supporting block 55 is installed at the lower end of the fixing block 54, a bolt 56 is arranged at one end of the second sliding plate 53, the upper end of the supporting plate 51 is fixedly connected with the lower end of the sliding groove 52, one end inside the sliding groove 52 is slidably connected with one end of the second sliding plate 53, the lower end of the second sliding plate 53 is fixedly connected with the upper end of the fixing block 54, the lower end of the fixing block 54 is fixedly connected with the upper end of the supporting block 55, and the other end of the second sliding plate 53 is in threaded connection with one end of the bolt 56.
In this embodiment, the function of preventing the reserved pipe from deforming when being squeezed is added, and the modification is that the second sliding plate 53 is moved by sliding the second sliding plate 53 in the sliding groove, the second sliding plate 53 carries the fixed block 54 and the supporting block 55, the supporting block 55 stops when being attached to the reserved pipe 3, and the bolt 56 is tightened to fix the second sliding plate 53.
Example 4
As shown in fig. 1, on the basis of embodiment 1, the utility model provides a technical solution: preferably, the drawing-out device 6 comprises a fixing plate 61, one end of the fixing plate 61 is fixedly connected with one end of the supporting device 5, a rotating wheel 62 is mounted at one end of the fixing plate 61, a rotating column 63 is mounted at the lower end of the rotating wheel 62, a telescopic column 64 is mounted at one end inside the rotating column 63, one end of the fixing plate 61 is rotatably connected with one end of the rotating wheel 62, the lower end of the rotating wheel 62 is fixedly connected with the upper end of the rotating column 63, and one end inside the rotating column 63 is movably connected with one end of the telescopic column 64.
In this embodiment, increased and reserved the function that can be taken out completely after the sleeve pipe uses, can make reserved sleeve pipe repetitious usage, this change is through rotating runner 62, and then runner 62 can drive column spinner 63 and rotate, and flexible post 64 can extend downwards under column spinner 63's rotation at this moment, then contacts the concrete, will reserve sleeve pipe 3 and ejecting.
The working principle of the construction device for the water and electricity heating reserved hole of the house building is described in detail below.
As shown in fig. 1-4, when the construction device for water and electric heating reserved holes of houses is used, the function of fixing the reserved hole position is added through the fixing device 4, the modification is that after the reserved sleeve 3 is placed at the reserved hole position, the threaded column 42 is screwed, at this time, under the rotation of the threaded column 42, the first sliding plate 43 moves downwards in the fixed shell 41, at this time, the fixed column 44 also moves along with the first sliding plate 43, the fixed column 44 stops when being inserted into the main body 1, so that the reserved sleeve 3 is fixed with the reserved hole position, the function that the reserved sleeve cannot be deformed when being extruded is added through the supporting device 5, the modification is that by sliding the second sliding plate 53 in the sliding chute, the second sliding plate 53 carries the fixed block 54 and the supporting block 55 to move, the supporting block 55 stops when being attached to the reserved sleeve 3, then screwing the bolt 56 to fix the second sliding plate 53, then, after the reserved sleeve is used, the function that the reserved sleeve can be completely taken out after being used is added through the reserved sleeve, the reserved sleeve can be used for multiple times, then, the rotating wheel 62 is modified to drive the rotating column 63 to contact with the rotating telescopic column 63, and then the rotating column 64 can be extended downwards and can be ejected out.
The present invention has been described in detail with reference to the above general description, but it will be apparent to one of ordinary skill in the art that modifications and improvements can be made to the invention. Therefore, modifications or improvements without departing from the spirit of the invention are within the scope of the invention.

Claims (7)

1. The utility model provides a house is built residential water electric heating and is reserved hole construction equipment, includes main part (1), its characterized in that: the concrete (2) is arranged at the upper end of the main body (1), the reserved sleeve (3) is arranged at the upper end of the main body (1), a fixing device (4) is arranged at one end inside the reserved sleeve (3), a supporting device (5) is arranged at the upper end of the reserved sleeve (3), and a drawing-out device (6) is arranged at one end of the supporting device (5);
the fixing device (4) comprises a fixing shell (41), one end of the fixing shell (41) is fixedly connected with one end of the inside of the reserved sleeve (3), a threaded column (42) is arranged at one end of the fixing shell (41), a first sliding plate (43) is installed at the lower end of the threaded column (42), a fixing column (44) is installed at the lower end of the first sliding plate (43), and a threaded cap (45) is arranged at the upper end of the threaded column (42);
strutting arrangement (5) are including backup pad (51), the lower extreme of backup pad (51) and the upper end fixed connection who reserves sleeve pipe (3), spout (52) are installed to the upper end of backup pad (51), the inside one end of spout (52) is provided with second slide (53), fixed block (54) are installed to the lower extreme of second slide (53), bracer (55) are installed to the lower extreme of fixed block (54), the one end of second slide (53) is provided with bolt (56).
2. The construction equipment for the water and electric heating reserved hole of the house building according to the claim 1, characterized in that: one end of the fixed shell (41) is in threaded connection with one end of the threaded column (42), and the lower end of the threaded column (42) is movably connected with the upper end of the first sliding plate (43).
3. The construction equipment for the water and electric heating reserved hole of the house building according to the claim 2, characterized in that: the lower end of the first sliding plate (43) is fixedly connected with the upper end of the fixed column (44), and the upper end of the threaded column (42) is fixedly connected with the lower end of the threaded cap (45).
4. The construction equipment for the water and electric heating reserved hole of the house building according to the claim 1, characterized in that: the upper end of the supporting plate (51) is fixedly connected with the lower end of the sliding groove (52), one end of the inner portion of the sliding groove (52) is in sliding connection with one end of the second sliding plate (53), and the lower end of the second sliding plate (53) is fixedly connected with the upper end of the fixing block (54).
5. The construction equipment for building the residential water and electric heating reserved hole according to claim 4, which is characterized in that: the lower end of the fixing block (54) is fixedly connected with the upper end of the supporting block (55), and the other end of the second sliding plate (53) is in threaded connection with one end of the bolt (56).
6. The construction equipment for the water and electric heating reserved hole of the house building according to the claim 1, characterized in that: draw-out device (6) including fixed plate (61), the one end of fixed plate (61) and the one end fixed connection of strutting arrangement (5), runner (62) are installed to the one end of fixed plate (61), column spinner (63) are installed to the lower extreme of runner (62), flexible post (64) are installed to the inside one end of column spinner (63).
7. The construction equipment for the water and electricity heating reserved hole of the house building according to the claim 6, characterized in that: the one end of fixed plate (61) is rotated with the one end of runner (62) and is connected, the lower extreme of runner (62) and the upper end fixed connection of column spinner (63), the inside one end of column spinner (63) and the one end swing joint of flexible post (64).
CN202222278656.2U 2022-08-29 2022-08-29 House building residence water electric heating reserved hole construction device Active CN217949750U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222278656.2U CN217949750U (en) 2022-08-29 2022-08-29 House building residence water electric heating reserved hole construction device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222278656.2U CN217949750U (en) 2022-08-29 2022-08-29 House building residence water electric heating reserved hole construction device

Publications (1)

Publication Number Publication Date
CN217949750U true CN217949750U (en) 2022-12-02

Family

ID=84212014

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222278656.2U Active CN217949750U (en) 2022-08-29 2022-08-29 House building residence water electric heating reserved hole construction device

Country Status (1)

Country Link
CN (1) CN217949750U (en)

Similar Documents

Publication Publication Date Title
CN110344411B (en) Underground supporting and anchoring equipment for building construction
CN217949750U (en) House building residence water electric heating reserved hole construction device
CN210713833U (en) Combined type clip-shaped water stop split screw for reinforcing cement formwork
CN216520308U (en) Warm logical sleeve pipe device of reserving of plumbing of building plumbing
CN214885530U (en) Building water and electricity warm up hole construction equipment that reserves
CN212926619U (en) Hollow floor formed by core-mold anti-floating structure
CN211959114U (en) Support frame for solar photovoltaic
CN209860527U (en) Winding displacement box for electric power construction
CN210658381U (en) Detachable temporary support for constructional engineering construction
CN210260835U (en) Precast concrete wallboard lifting device
CN220868814U (en) Reusable floor reserved hole directional pipe
CN219080998U (en) Construction device for building water heating reserved hole
CN217975384U (en) Entrance to a cave shutoff template device is reserved to integral type convenient to equipment
CN215443123U (en) Warm logical sleeve pipe device of reserving of plumbing of building plumbing
CN215564456U (en) House building residence water electric heating reserved hole construction device
CN214350677U (en) A vertical radiator installation auxiliary device for construction
CN109750480B (en) Ironing integrated machine with water saving function
CN216693698U (en) Electric heating device
CN217927542U (en) Building plumbing outer wall pipeline fixing device
CN220888613U (en) Civil engineering composite pile
CN218843760U (en) Water stop screw
CN217451391U (en) Quick barreling equipment of non-curing rubber asphalt waterproof coating
CN215702067U (en) Pulling type auxiliary equipment for cutting plastic hose
CN215371718U (en) Building engineering detects fixing device
CN115613807A (en) House building residential water electric heating reserved hole construction device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant