CN217842981U - Pipeline supporting device for concrete structure - Google Patents

Pipeline supporting device for concrete structure Download PDF

Info

Publication number
CN217842981U
CN217842981U CN202221822358.9U CN202221822358U CN217842981U CN 217842981 U CN217842981 U CN 217842981U CN 202221822358 U CN202221822358 U CN 202221822358U CN 217842981 U CN217842981 U CN 217842981U
Authority
CN
China
Prior art keywords
embedded
concrete structure
positioning
support
pipeline
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202221822358.9U
Other languages
Chinese (zh)
Inventor
蔡广友
陈宗飞
陈宇丹
程成
王超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhongtian Northwest Construction Investment Group Co ltd
Zhongtian Construction Group Co Ltd
Original Assignee
Zhongtian Northwest Construction Investment Group Co ltd
Zhongtian Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhongtian Northwest Construction Investment Group Co ltd, Zhongtian Construction Group Co Ltd filed Critical Zhongtian Northwest Construction Investment Group Co ltd
Priority to CN202221822358.9U priority Critical patent/CN217842981U/en
Application granted granted Critical
Publication of CN217842981U publication Critical patent/CN217842981U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

A pipeline supporting device for a concrete structure comprises a support and an embedded part, wherein the inner end of the embedded part is prefabricated in concrete, the support is fixedly installed at the outer end part of the embedded part, and a connecting piece for fixing a pipeline is installed on the support; the embedded part comprises an embedded plate and a positioning part, and the positioning part is fixedly installed on the inner end face of the embedded plate. In the pipeline supporting device for the concrete structure, the bracket is fixed on the embedded plate, does not need to be in contact with the concrete wall body, and cannot damage the concrete wall body structure. The utility model discloses can with the scaffold weldment on the built-in panel, when guaranteeing that wall structure is complete, realized the firm fixed of pipeline, the installation is simple swift, through installation positioning element on the wall body reinforcing bar, the cooperation is pour the accurate location that the template can realize the built-in panel fast, long service life, and mounting structure is not fragile, has avoided the damage wall body, can not influence building quality, has thoroughly stopped the potential safety hazard.

Description

Pipeline supporting device for concrete structure
Technical Field
The utility model belongs to the technical field of the construction, the pipeline that relates to wall and structure face supports fixedly, especially a pipeline strutting arrangement for concrete structure.
Background
Various pipelines are often required to be installed on a wall body in building construction, a drainage pipeline used in a building can be divided into a metal drainage pipe, a pottery clay drainage pipe, an asbestos cement drainage pipe, a plastic drainage pipe and a glass fiber reinforced plastic sand drainage pipe according to the material of the pipeline, and the common metal drainage pipe in the market is mainly made of iron and steel. In the prior art, expansion bolts are usually used to fix the pipes directly to the wall.
The installation method has the following technical problems: 1. the pipeline is fixed with the wall body through the expansion bolts, so that the structure of the wall body is damaged, and the quality of the wall body is influenced; 2. the expansion bolts have limited service life, and can age along with the increase of service time, so that the firmness of the pipeline installation is seriously influenced, and potential safety hazards exist.
SUMMERY OF THE UTILITY MODEL
The utility model provides a pipeline strutting arrangement for concrete structure to solve the above-mentioned problem that exists among the prior art.
The utility model provides a pipeline supporting device for concrete structure, including support and built-in fitting, the inner end of built-in fitting is prefabricated in the concrete, the outer tip of built-in fitting is adorned firmly the support, install the connecting piece of fixed pipeline on the support;
the embedded part comprises an embedded plate and a positioning part, and the positioning part is fixedly installed on the inner end face of the embedded plate.
Furthermore, the positioning part comprises a plurality of positioning ribs and a plurality of sleeves, the rear end face of the embedded plate is fixedly provided with the plurality of positioning ribs, the plurality of sleeves are sleeved on the positioning ribs in a sliding manner, and the sleeves are fixedly arranged on the reinforcing steel bars in the concrete.
Furthermore, the support is of a U-shaped structure, two end portions of the support are respectively welded to the embedded plates, and a plurality of connecting pieces are installed on the inner end face or the outer end face of the support at intervals.
Furthermore, the cross section of the bracket is of an L-shaped structure, and the connecting piece is installed on the side end face of the bracket.
Further, the connecting piece is a U-shaped hoop.
Furthermore, the number of the positioning ribs is two, and the two positioning ribs are respectively and fixedly arranged on the upper part and the lower part of the inner side of the embedded plate in parallel.
Further, the bracket is made of angle steel.
Furthermore, the positioning rib is a steel bar, a steel pipe or a round steel or other metal product.
The utility model discloses an advantage is with positive effect:
1. in the pipeline supporting device for the concrete structure, the bracket is fixed on the embedded plate, does not need to be in contact with the concrete wall body, and cannot damage the concrete wall body structure.
2. This a pipeline strutting arrangement for concrete structure, support beading is on the built-in board, ensures that the pipeline firmly installs all the time on the wall body, need not to fix with the help of expansion bolts, and no life restriction avoids mounting structure ageing, has thoroughly stopped the potential safety hazard.
3. According to the pipeline supporting device for the concrete structure, the embedded plate is positioned through the positioning part, the embedded plate is effectively prevented from deviating in the pouring process, the flatness and the formwork attaching rate of the embedded plate are ensured, and after pouring is completed, the positioning part is poured in a wall body, so that the embedded plate can be firmly fixed.
4. In the pipeline supporting device for the concrete structure, the positioning part is arranged on the wall body reinforcing steel bars through the sleeve, the positioning ribs move relative to the sleeve, the position in the front-back direction of the positioning ribs is clamped and positioned through the pouring template, the accurate positioning of the embedded plate is ensured, and the positioning error of the embedded plate in the front-back direction is effectively avoided.
5. The utility model discloses can with the scaffold weldment on the built-in panel, when guaranteeing that wall structure is complete, realized the firm fixed of pipeline, the installation is simple swift, through installation positioning element on the wall body reinforcing bar, the cooperation is pour the accurate location that the template can realize the built-in panel fast, long service life, and mounting structure is not fragile, has avoided the damage wall body, can not influence building quality, has thoroughly stopped the potential safety hazard.
Drawings
Fig. 1 is a schematic structural diagram of a first embodiment of the present invention;
fig. 2 is a schematic structural diagram of a second embodiment of the present invention;
fig. 3 is a schematic structural diagram of a third embodiment of the present invention;
fig. 4 is a schematic view of the installation of the pipeline according to the first embodiment of the present invention;
FIG. 5 is a schematic view illustrating the installation of the pipeline according to the second embodiment of the present invention;
fig. 6 is a schematic view of the installation of the pipeline in the third embodiment of the present invention;
fig. 7 is a schematic view of the installation of the present invention on the wall reinforcing bars (the bracket is not shown).
In the figure, 1 is an embedded plate, 2 is a positioning part, 3 is a connecting piece, 4 is a support, 5 is a pipeline, 6 is a wall reinforcing steel bar, 21 is a sleeve, and 22 is a positioning rib.
Detailed Description
The present invention will be described in detail with reference to the accompanying drawings.
The utility model provides a pipeline supporting device for concrete structure, including support 4 and built-in fitting, the inside end of built-in fitting is prefabricated in the concrete wall, the outer tip of built-in fitting is adorned fixedly support 4, install connecting piece 3 of fixed pipeline 5 on support 4; the embedded part comprises an embedded plate 1 and a positioning part 2, and the positioning part 2 is fixedly arranged on the inner end face of the embedded plate 1. Preferably, the bracket 4 is welded on the embedded plate 1. The embedded plate 1 is poured in the wall surface, and when the pipeline 5 is installed, the support 4 is directly welded on the embedded plate 1, so that the wall structure cannot be damaged. In the pouring process, the embedded plate 1 is positioned by matching the positioning part 2 with the wall body reinforcing steel bars 6 and the pouring template, and the positioning part 2 is poured in the wall body and can fix the embedded plate 1. The support 4 is directly welded on the embedded plate 1, so that the pipeline 5 is ensured to be always firmly installed on a wall body without being fixed by means of expansion bolts, the service life limitation is avoided, the aging of the installation structure is avoided, and the potential safety hazard is thoroughly avoided.
The positioning part 2 comprises a plurality of positioning ribs 22 and a plurality of sleeves 21, the rear end face of the embedded plate 1 is fixedly provided with the plurality of positioning ribs 22, the positioning ribs 22 are slidably sleeved with the plurality of sleeves 21, and the sleeves 21 are fixedly arranged on the wall body reinforcing steel bars 6. Furthermore, two positioning ribs 22 are fixedly arranged on the upper part and the lower part of the inner side of the embedded plate 1 in parallel respectively. Two limiting sleeves 21 are sleeved on each limiting rod in a sliding mode. Preferably, the positioning rib 22 is a steel bar, a steel pipe, or a metal product such as round steel. Preferably, the positioning rib 22 is welded to the embedded plate 1, and the positioning rib 22 is a steel bar, a steel pipe or a round steel or other metal product. Before pouring, the sleeve 21 of the positioning part 2 is welded on the wall body steel bar 6 and used for limiting the position of the embedded plate 1 in the vertical and horizontal directions; the length of the positioning rib 22 corresponds to the thickness of the wall body, and the embedded plate 1 is abutted between the two pouring formworks through the positioning rib 22 so as to limit the position of the embedded plate 1 in the front-back direction. The positioning part 2 is arranged on the wall body reinforcing steel bars 6 through the sleeve 21, the positioning ribs 22 slide relative to the sleeve 21, the position in the front-back direction of the positioning part is clamped and positioned through the pouring template, the accurate positioning of the embedded plate 1 is ensured, and the positioning error of the embedded plate 1 in the front-back direction is effectively avoided.
Example one
The multiple pipelines are fixed on the wall body, as shown in fig. 1, the support 4 is of a U-shaped structure, two end portions of the support 4 are respectively welded on the embedded plate 1, and the connecting pieces 3 are installed on the end face of the support 4 at intervals. Preferably, support 4 is shaped steel or channel-section steel, connecting piece 3 is U type clamp, U type clamp is installed on support 4.
Example two
The single pipeline is fixed on the wall, as shown in fig. 2, the section of the bracket 4 is an L-shaped structure, and the connecting piece 3 is installed on the side end face of the bracket 4. Preferably, the bracket 4 is an angle steel. Preferably, the connecting piece 3 is a U-shaped clamp, and the U-shaped clamp is welded on the bracket 4 or fixed on the bracket 4 through a bolt.
EXAMPLE III
Many pipelines are fixed on the roof, as shown in fig. 3, the cross-section of support 4 is the U type, both ends weld respectively about support 4 top on pre-buried plate 1, 4 inboard top intervals of support are installed a plurality of connecting piece 3, preferably, support 4 is shaped steel or channel-section steel, preferably, connecting piece 3 is U type clamp, U type clamp is installed on support 4.
The utility model discloses an installation method does:
weld the sleeve 21 of locating component 2 on wall body reinforcing bar 6, from top to bottom, fixed embedded plate 1 in the left and right sides direction, install the pouring template afterwards, make embedded plate 1 firmly press from both sides tightly between two pouring templates through location muscle 22, thereby fix embedded plate 1 in the front and back direction, begin to pour the wall body after accomplishing embedded plate 1 location, embedded plate 1 realizes omnidirectional firm location under locating component 2's fixed, guarantee to pour in-process embedded plate 1 and can not take place the skew, bring very big guarantee for construction quality, pour after accomplishing, weld support 4 and embedded plate 1 on the wall together, and clamp pipeline 5 in the U type clamp on support 4.
The utility model discloses can with the scaffold weldment on the built-in panel, when guaranteeing that wall structure is complete, realized the firm fixed of pipeline, the installation is simple swift, through installation positioning element on the wall body reinforcing bar, the cooperation is pour the accurate location that the template can realize the built-in panel fast, long service life, and mounting structure is not fragile, has avoided the damage wall body, can not influence building quality, has thoroughly stopped the potential safety hazard.
It should be understood that the above examples are only for clarity of illustration and are not intended to limit the embodiments. Other variations and modifications will be apparent to persons skilled in the art in light of the above description. And are neither required nor exhaustive of all embodiments. And obvious changes and modifications can be made without departing from the scope of the invention.

Claims (9)

1. The pipeline supporting device for the concrete structure is characterized by comprising a support (4) and an embedded part, wherein the inner end of the embedded part is prefabricated in concrete, the support (4) is fixedly installed at the outer end of the embedded part, and a connecting piece (3) for fixing a pipeline (5) is installed on the support (4);
the embedded part comprises an embedded plate (1) and a positioning part (2), and the positioning part (2) is fixedly installed on the inner end face of the embedded plate (1).
2. The pipe supporting device for the concrete structure is characterized in that the positioning part (2) comprises a plurality of positioning ribs (22) and a plurality of sleeves (21), the positioning ribs (22) are fixedly installed on the inner end surface of the embedded plate (1), the sleeves (21) are slidably sleeved on the positioning ribs (22), and the sleeves (21) are fixedly installed on the steel bars (6) in the concrete.
3. The pipe supporting device for the concrete structure according to claim 1, wherein the bracket (4) is a U-shaped structure, two ends of the bracket (4) are respectively welded on the embedded plates (1), and a plurality of the connecting pieces are installed on the outer end surface or the inner end surface of the bracket (4) at intervals.
4. The pipe supporting device for a concrete structure according to claim 1, wherein said bracket (4) has an L-shaped cross section, and said connecting member (3) is installed on the side end surface of said bracket (4).
5. The pipe supporting apparatus for a concrete structure according to claim 1, wherein said connecting member (3) is a U-shaped yoke.
6. The pipe supporting apparatus for a concrete structure according to claim 2, wherein the number of the positioning ribs (22) is two, and the two positioning ribs are respectively and fixedly arranged at the upper part and the lower part of the inner side of the embedment plate (1) in parallel.
7. The pipe supporting apparatus for a concrete structure according to claim 4, wherein said bracket (4) is an angle iron.
8. A pipe support apparatus for a concrete structure according to claim 3, wherein said bracket (4) is a steel section or a channel steel.
9. The pipe supporting apparatus for a concrete structure according to claim 2, wherein the positioning rib (22) is a steel bar, a steel pipe or a round steel.
CN202221822358.9U 2022-07-14 2022-07-14 Pipeline supporting device for concrete structure Active CN217842981U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221822358.9U CN217842981U (en) 2022-07-14 2022-07-14 Pipeline supporting device for concrete structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221822358.9U CN217842981U (en) 2022-07-14 2022-07-14 Pipeline supporting device for concrete structure

Publications (1)

Publication Number Publication Date
CN217842981U true CN217842981U (en) 2022-11-18

Family

ID=84036537

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221822358.9U Active CN217842981U (en) 2022-07-14 2022-07-14 Pipeline supporting device for concrete structure

Country Status (1)

Country Link
CN (1) CN217842981U (en)

Similar Documents

Publication Publication Date Title
KR20180045140A (en) The structure of non-binding dismantling formwork beams and deck plates without the need to secure jobs
CN108678193B (en) Post-cast strip and construction method thereof
CN107313787B (en) Tunnel lining trolley end die and construction method
CN217842981U (en) Pipeline supporting device for concrete structure
CN113090015B (en) Beam plate post-cast strip formwork supporting method
KR101105836B1 (en) Junction paper form and junction construction method for src structure of paper form
CN106985273B (en) Cement mortar plastering tool for concrete plain end pipeline interface
CN211898553U (en) Fixing template of underground pipe gallery band steel edge rubber waterstop
CN210049586U (en) Shear wall template reinforcing structure for expansion joint position
CN109208900B (en) Formwork system for assembled building and construction method thereof
CN210317351U (en) Tunnel waterstop mounting fixture
CN209760295U (en) Pre-buried T type bolt fixed knot of underground pipe gallery electric power support constructs
CN209040549U (en) A kind of formwork erecting structure that oblique arch face structural concrete pours
CN111379277A (en) Fixing device for box culvert connected bin pouring rubber waterstop and foam board and using method of fixing device
CN111271096A (en) Tunnel induced seam steel edge rubber water stop mounting structure and method
CN211948579U (en) Novel underground concrete structure construction joint waterstop installation fixed knot constructs
CN212176097U (en) Temporary fixing system for embedded steel plates on surface of wall
CN211257821U (en) Frame column die reinforcing apparatus
CN220813980U (en) Combined end mould frame for construction of pipe gallery deformation joint
CN215441943U (en) Wall guide support frame
CN219509158U (en) Supporting template for deformation joint of double-shear wall and double-shear wall structure
CN210659251U (en) Non-dismantling formed beam template containing reinforcement cage and template structure
CN218758706U (en) A template system of consolidating for superimposed sheet post-cast strip construction
CN216380574U (en) Assembled steel-wood mixed stair template
CN220814887U (en) Contain waterstop side wall end wall structure template

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant