CN217815358U - Utility tunnel pipeline safety fixed bolster - Google Patents

Utility tunnel pipeline safety fixed bolster Download PDF

Info

Publication number
CN217815358U
CN217815358U CN202221004337.6U CN202221004337U CN217815358U CN 217815358 U CN217815358 U CN 217815358U CN 202221004337 U CN202221004337 U CN 202221004337U CN 217815358 U CN217815358 U CN 217815358U
Authority
CN
China
Prior art keywords
fixture block
fixed
pipeline
connecting plate
connecting rod
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202221004337.6U
Other languages
Chinese (zh)
Inventor
胥明星
高健
高飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hubei Jiangweizhizuo Construction Co ltd
Original Assignee
Hubei Jiangweizhizuo Construction Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hubei Jiangweizhizuo Construction Co ltd filed Critical Hubei Jiangweizhizuo Construction Co ltd
Priority to CN202221004337.6U priority Critical patent/CN217815358U/en
Application granted granted Critical
Publication of CN217815358U publication Critical patent/CN217815358U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Supports For Pipes And Cables (AREA)

Abstract

The utility model discloses a comprehensive pipe gallery pipeline safety fixing support, which belongs to the technical field of pipeline installation and aims at the problems of time and labor waste, lower assembly and disassembly efficiency and poorer installation shock resistance of the existing pipeline fixing support; the utility model discloses a locking mechanical system carries on spacingly to last fixture block, goes up the fixture block and carries out the clamping of circumference with lower fixture block to the pipeline to effectively improve the steadiness that the pipeline is fixed, avoid the pipeline problem of droing, on the one end of fixture block is fixed to the wall under keeping away from the connecting rod through dismouting mechanism, accomplish the fixed of pipeline, save the operation of dismouting screw when maintaining the dismantlement lower fixture block, thereby the quick assembly disassembly of fixture block under the convenience, the convenient maintenance.

Description

Utility tunnel pipeline safety fixed bolster
Technical Field
The utility model belongs to the technical field of the pipeline installation, concretely relates to utility tunnel pipeline safety fixed bolster.
Background
With the rapid development of the economic society and the acceleration of the urbanization process, the utilization of land resources is more and more tense, and the importance of the construction of the urban comprehensive pipe gallery is further highlighted. The three-dimensional planning construction is the direction of future urban infrastructure construction, and the country encourages and supports vigorously, and in recent years, due to the continuous development of underground pipelines, repeated excavation and lateral displacement of a road network are caused, a plurality of supports are usually arranged in the construction process, and long-distance facilities such as pipelines and cables are laid and installed on pipeline supports.
On the piping lane pipeline adopted U-shaped pipe clamp to fix to the wall usually among the prior art, through installing a plurality of pipe clamps, accomplish the erectting of pipeline fixed, have following problem:
(1) the existing pipeline fixing support is generally fixedly connected with a wall surface through screws, the pipeline is supported and limited, a plurality of screws need to be installed, the installation is time-consuming and labor-consuming, and the installation efficiency is low.
(2) Present pipeline fixed bolster and pipeline are the integral type after fixed, and pipeline rigid connection is relatively poor on the U-shaped clamping, and pipeline shock absorption performance is influenced by the vibrations for a long time and is damaged easily.
Therefore, a comprehensive pipe gallery pipeline safety fixing support is needed, and the problems that an existing pipeline fixing support is time-consuming and labor-consuming in installation, low in assembly and disassembly efficiency and poor in installation shock resistance are solved.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a utility tunnel pipeline safety fixed bolster to solve the problem that proposes in the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a utility tunnel pipeline safety fixed bolster, includes fixture block down, the top of fixture block is provided with the fixture block down, go up the fixture block and all seted up the cambered surface on the side that the fixture block is close to down mutually, it is located cambered surface both sides connecting plate an to be fixed with on the side of going up the fixture block, be fixed with on the side of fixture block down and correspond complex connecting plate b with connecting plate a, be provided with locking mechanical system jointly on connecting plate a and the connecting plate b, the lateral wall of fixture block is fixed with the connecting rod down, the one end that the fixture block was kept away from down to the connecting rod is provided with dismouting mechanism.
What need explain in the scheme is that locking mechanical system includes the locking post fixed with connecting plate b side, set up on connecting plate a's the side with locking post sliding fit's through-hole, the card hole has been seted up on the locking post side, the card hole is provided with a plurality ofly and is the equidistance and distributes, threaded connection has the locking bolt of arranging with the locking post is perpendicular on connecting plate a's the side, locking bolt medial extremity and card hole adaptation.
It is further worth explaining that dismouting mechanism includes the fixed plate, the one end that lower fixture block was kept away from to the connecting rod is fixed with the picture peg, set up the slot with the picture peg adaptation in the fixed plate, be fixed with two mounting panels that are the symmetric distribution on the fixed plate lateral wall, the screw hole has been seted up on the mounting panel.
It should be further noted that two connecting rods are provided, and the two connecting rods are symmetrically distributed.
As a preferred embodiment, a reinforcing rib b is fixed between the inserting plate and the connecting rod, and a reinforcing rib a is fixed on the side surface of the connecting rod and the outer side wall of the lower fixture block.
In a preferred embodiment, a rubber pad is attached and fixed on the side surface of the cambered surface, and the length of the rubber pad is equal to that of the cambered surface.
As a preferred embodiment, the outer surface of the cambered surface is fixed with a plurality of rubber bumps, and the plurality of rubber bumps are distributed at equal intervals.
Compared with the prior art, the utility model provides a pair of utility tunnel pipeline safety fixed bolster includes following beneficial effect at least:
(1) Through the locking bolt of screwing, insert the card downthehole with the medial extremity of locking bolt, thereby fix down on the fixture block to last fixture block, carry out the clamping with the pipeline through the cooperation of last fixture block and lower fixture block, carry out spacing support to the pipeline, the installation is convenient, it carries out circumference's clamping with lower fixture block to go up the fixture block, thereby effectively improve the fixed steadiness of pipeline, avoid the pipeline problem of droing, when carrying out the centre gripping to the surface of pipeline, go up the fixture block and press the movable rubber pad with lower fixture block and produce elastic deformation, make the fixed of pipeline have certain shock-absorbing nature, long service life.
(2) Through on the mounting expansion bolts fixes the fixed plate to the wall in the screw hole, insert the picture peg in the slot, the fixed plate carries on spacingly to the picture peg, realize the fixed of connecting rod, thereby on the fixture block is fixed to the wall down, it is convenient to install, when needing to be torn open out, only need pull out the picture peg from the slot, can pull down the fixture block, save when maintaining the fixture block of dismantling down, the operation of dismouting screw, thereby the quick assembly disassembly of fixture block under the convenience, convenient maintenance.
Drawings
Fig. 1 is a schematic view of the overall structure of the present invention;
FIG. 2 is an enlarged schematic view of the structure at A in FIG. 1;
FIG. 3 is an enlarged view of the structure at B in FIG. 1;
FIG. 4 is a schematic overall side view of the present invention;
FIG. 5 is a schematic view of a partial structure of a rubber pad of the present invention;
FIG. 6 is an enlarged view of the structure at C in FIG. 5;
fig. 7 is a schematic view of a partial structure of the slot of the present invention.
In the figure: 1. a locking mechanism; 101. a locking post; 102. a clamping hole; 103. a through hole; 104. a locking bolt; 2. a disassembly and assembly mechanism; 201. inserting plates; 202. a fixing plate; 203. inserting slots; 204. mounting a plate; 205. screw holes; 3. an upper clamping block; 4. a lower clamping block; 5. a connecting rod; 6. a reinforcing rib a; 7. a rubber pad; 8. a cambered surface; 9. a connecting plate a; 10. rubber bumps; 11. reinforcing ribs b; 12. and (b) a connecting plate.
Detailed Description
The present invention will be further described with reference to the following examples.
In order to make the purpose, technical scheme and advantage of the embodiment of the present invention clearer, the following will combine the drawings of the embodiments of the present invention to clearly and completely describe the technical scheme of the embodiments of the present invention, and obviously, the described embodiments are a part of the embodiments of the present invention, rather than all embodiments, and based on the described embodiments of the present invention, all other embodiments obtained by the ordinary skilled person in the art on the premise of not needing creative work all belong to the scope of protection of the present invention.
The following examples are intended to illustrate the invention, but are not intended to limit the scope of the invention. The condition in the embodiment can be further adjusted according to concrete condition the utility model discloses a it is right under the design prerequisite the utility model discloses a simple improvement of method all belongs to the utility model discloses the scope of claiming.
Please refer to fig. 1-7, the utility model provides a utility tunnel pipeline safety fixed bolster, including fixture block 4 down, the top of fixture block 4 is provided with fixture block 3 down, go up fixture block 3 and all seted up cambered surface 8 on the side that fixture block 4 is close to down mutually, it is located 8 both sides connecting plate an 9 of cambered surface to be fixed with on the side of going up fixture block 3, be fixed with on the side of fixture block 4 down and correspond complex connecting plate b12 with connecting plate a9, be provided with locking mechanical system 1 jointly on connecting plate a9 and the connecting plate b12, the lateral wall of fixture block 4 is fixed with connecting rod 5 down, the one end that fixture block 4 was kept away from down to connecting rod 5 is provided with dismouting mechanism 2.
The locking mechanism 1 comprises a locking column 101 fixed with the side surface of a connecting plate b12, the side surface of a connecting plate a9 is provided with through holes 103 in sliding fit with the locking column 101, the side surface of the locking column 101 is provided with clamping holes 102, the clamping holes 102 are arranged in a plurality and are distributed at equal intervals, the side surface of the connecting plate a9 is in threaded connection with locking bolts 104 which are perpendicular to the locking column 101, and the inner side ends of the locking bolts 104 are matched with the clamping holes 102; when the pipeline is placed and installed, the pipeline is placed in the cambered surface 8 of the lower clamping block 4, the upper clamping block 3 covers the top end of the lower clamping block 4, the top end of the locking column 101 penetrates out of the through hole 103, the inner side end of the locking bolt 104 is inserted into the clamping hole 102 by screwing the locking bolt 104, the upper clamping block 3 is fixed onto the lower clamping block 4, the pipeline is clamped through the cooperation of the upper clamping block 3 and the lower clamping block 4, the pipeline is limited and supported, the pipeline is convenient to install, the upper clamping block 3 and the lower clamping block 4 clamp the pipeline in the circumferential direction, the pipeline fixing stability is effectively improved, and the pipeline falling problem is avoided.
The disassembling and assembling mechanism 2 comprises a fixing plate 202, an inserting plate 201 is fixed at one end, far away from the lower clamping block 4, of the connecting rod 5, a slot 203 matched with the inserting plate 201 is formed in the fixing plate 202, two symmetrically-distributed mounting plates 204 are fixed on the outer side wall of the fixing plate 202, and screw holes 205 are formed in the mounting plates 204; fixing plate 202 is fixed to the wall through installing expansion bolts in screw hole 205 earlier, insert picture peg 201 in the slot 203, fixing plate 202 carries on spacingly to picture peg 201, realize connecting rod 5's fixed, thereby will descend fixture block 4 to be fixed to the wall, it is convenient to install, when needing to be torn open, only need pull out picture peg 201 from slot 203, can pull down fixture block 4, save when maintaining the dismouting fixture block 4, the operation of dismouting screw, thereby conveniently lower fixture block 4's quick assembly disassembly, convenient maintenance.
The scheme has the following working processes: fixing plate 202 to the wall by installing expansion bolts in screw holes 205, inserting insertion plate 201 into insertion groove 203, fixing plate 202 limits insertion plate 201, fixing of connecting rod 5 is achieved, fixing lower fixture block 4 to the wall, when the pipeline is placed and installed, the pipeline is placed in arc surface 8 of lower fixture block 4, then upper fixture block 3 is covered on the top end of lower fixture block 4, the top end of locking column 101 penetrates out of through hole 103, the inner side end of locking bolt 104 is inserted into clamp hole 102 by screwing locking bolt 104, so that upper fixture block 3 is fixed to lower fixture block 4, the pipeline is clamped by matching upper fixture block 3 and lower fixture block 4, the pipeline is limited and supported, when fixture block 4 needs to be detached, only insertion plate 201 needs to be pulled out from insertion groove 203, and lower fixture block 4 can be detached and maintained.
According to the working process, the following steps are known: carry out the clamping through the cooperation of last fixture block 3 and lower fixture block 4 with the pipeline, carry out spacing support to the pipeline, the installation is convenient, go up fixture block 3 and lower fixture block 4 and carry out circumference's clamping to the pipeline, thereby effectively improve the steadiness that the pipeline is fixed, avoid the pipeline problem of droing, pull out picture peg 201 from slot 203, can pull down fixture block 4 and pull down, save when maintaining the removal fixture block 4, the operation of dismouting screw, thereby the convenient quick assembly disassembly of fixture block 4 down, convenient maintenance.
The connecting rods 5 are arranged in two numbers, and the two connecting rods 5 are symmetrically distributed.
A reinforcing rib b11 is fixed between the inserting plate 201 and the connecting rod 5, and a reinforcing rib a6 is fixed on the side surface of the connecting rod 5 and the outer side wall of the lower clamping block 4; during specific work, the reinforcing rib b11 effectively increases the fixed connection strength of the inserting plate 201 and the connecting rod 5, and the reinforcing rib a6 enhances the fixed connection strength of the connecting rod 5 and the lower fixture block 4.
A rubber pad 7 is fixedly attached to the side surface of the cambered surface 8, and the length of the rubber pad 7 is equal to that of the cambered surface 8; when the pipeline clamp is used for clamping the surface of a pipeline in specific work, the rubber pad 7 generates elastic deformation, so that the pipeline is fixed to have certain elasticity, and the surface of the pipeline is protected.
The outer surface of the cambered surface 8 is fixed with a plurality of rubber bumps 10, and the plurality of rubber bumps 10 are distributed at equal intervals; during specific work, the arranged rubber bumps 10 further increase the friction force for clamping the pipeline, and the stability for clamping and fixing the pipeline is improved.
To sum up: strengthening rib b11 has effectively increased picture peg 201 and 5 fixed connection intensity of connecting rod, and strengthening rib a6 reinforcing connecting rod 5 and 4 fixed connection intensity of lower fixture block when carrying out the centre gripping to the surface of pipeline, and rubber pad 7 produces elastic deformation for the fixed of pipeline has certain elasticity, protects the surface of pipeline, and the rubber bump 10 that sets up has further increased the frictional force of holding to the pipeline, improves the fixed steadiness of pipeline centre gripping.
Unless otherwise defined, technical or scientific terms used herein shall have the ordinary meaning as understood by those of ordinary skill in the art, and the use of the term "including" or "comprising" in the present application shall mean that the element or item preceding the term covers the element or item listed after the term and its equivalents, but does not exclude other elements or items, and the term "connected" or "connected" is not limited to physical or mechanical connections, and may include electrical connections, whether direct or indirect, "upper", "lower", "left", "right", etc. merely indicate relative positional relationships, and when the absolute position of the object being described is changed, the relative positional relationships may be changed accordingly.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (7)

1. The utility model provides a utility tunnel pipeline safety fixed bolster, includes fixture block (4) down, its characterized in that, the top of fixture block (4) is provided with fixture block (3) down, last fixture block (3) and lower fixture block (4) have all been seted up cambered surface (8) on being close to the side mutually, it is fixed with on the side of fixture block (3) and is located cambered surface (8) both sides connecting plate a (9), be fixed with on the side of fixture block (4) down and correspond complex connecting plate b (12) with connecting plate a (9), be provided with locking mechanical system (1) on connecting plate a (9) and connecting plate b (12) jointly, the lateral wall of fixture block (4) is fixed with connecting rod (5) down, the one end that fixture block (4) was kept away from down in connecting rod (5) is provided with dismouting mechanism (2).
2. The utility tunnel pipeline safety fixing support according to claim 1, characterized in that the locking mechanism (1) comprises a locking column (101) fixed with the side of a connecting plate b (12), a through hole (103) sliding-fitted with the locking column (101) is opened on the side of the connecting plate a (9), a plurality of clamping holes (102) are opened on the side of the locking column (101), the clamping holes (102) are arranged in an equidistant distribution, a locking bolt (104) arranged perpendicular to the locking column (101) is connected with the side of the connecting plate a (9) through a screw thread, and the inner side end of the locking bolt (104) is adapted to the clamping hole (102).
3. The utility model provides a utility tunnel pipeline safety fixed bolster of claim 2, characterized in that, dismouting mechanism (2) includes fixed plate (202), the one end that lower fixture block (4) was kept away from in connecting rod (5) is fixed with picture peg (201), slot (203) with picture peg (201) adaptation is seted up in fixed plate (202), be fixed with two mounting panels (204) that are the symmetric distribution on fixed plate (202) lateral wall, screw hole (205) have been seted up on mounting panel (204).
4. The utility tunnel pipeline safety fixing support of claim 1, characterized in that, the connecting rod (5) is provided with two, two connecting rods (5) and be the symmetric distribution.
5. The utility tunnel pipeline safety fixing bracket according to claim 3, characterized in that a reinforcing rib b (11) is fixed between the inserting plate (201) and the connecting rod (5), and a reinforcing rib a (6) is fixed on the side surface of the connecting rod (5) and the outer side wall of the lower clamping block (4).
6. The utility tunnel pipeline safety fixing support according to claim 1, characterized in that a rubber pad (7) is fixedly attached to the side of the cambered surface (8), and the length of the rubber pad (7) is equal to that of the cambered surface (8).
7. The utility tunnel pipeline safety fixed bolster of claim 6, characterized in that, the surface mounting of rubber pad (7) has rubber bump (10), rubber bump (10) are provided with a plurality ofly, a plurality ofly rubber bump (10) are the equidistance and distribute.
CN202221004337.6U 2022-04-27 2022-04-27 Utility tunnel pipeline safety fixed bolster Active CN217815358U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221004337.6U CN217815358U (en) 2022-04-27 2022-04-27 Utility tunnel pipeline safety fixed bolster

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221004337.6U CN217815358U (en) 2022-04-27 2022-04-27 Utility tunnel pipeline safety fixed bolster

Publications (1)

Publication Number Publication Date
CN217815358U true CN217815358U (en) 2022-11-15

Family

ID=83981057

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221004337.6U Active CN217815358U (en) 2022-04-27 2022-04-27 Utility tunnel pipeline safety fixed bolster

Country Status (1)

Country Link
CN (1) CN217815358U (en)

Similar Documents

Publication Publication Date Title
CN217815358U (en) Utility tunnel pipeline safety fixed bolster
CN209833418U (en) Bending-resistant adjustable conversion base for embedded channel
CN217767787U (en) Mounting system for advertising cloth
CN207959267U (en) A kind of pipe gallery C-type steel holder
CN214089458U (en) Concrete structure for expansion joint
CN218508297U (en) Simple auxiliary device for installing tunnel speed-limiting signboard
CN210003937U (en) comprehensive pipeline type lateral anti-seismic support
CN217027459U (en) Reinforced steel structure at energy-saving steel structure joint
CN217439319U (en) Hinged type suspension and suspended ceiling module with adjustable arm length
CN215717350U (en) Cement fibre building carrier plate hangs piece with hanging knot convenient to installation
CN217490293U (en) Energy-concerving and environment-protective type mine is opened and is adopted exhaust gas purification device
CN215367311U (en) Pipeline foundation pit supporting structure
CN217972234U (en) Hanging bracket for mounting drain pipe
CN217439624U (en) Building structure supports steelframe
CN218206721U (en) Variable-diameter arch frame for mine reserved filling return air duct support
CN221921006U (en) Support frame for mine roadway
CN220688250U (en) Subway water supply and drainage pipeline hanger
CN210888076U (en) Prefabricated assembled aluminum alloy template installation device
CN217380651U (en) Adjustable support of tunnel construction geomantic omen pipeline
CN213712291U (en) Multi-column spring support hanger
CN218587098U (en) Reinforced structure is used in installation of solar energy component cover
CN219659350U (en) Reinforced bridge connecting assembly
CN215673919U (en) A reassembling type module for in subway computer lab
CN219754499U (en) Lubricator butt joint device for oil extraction wellhead
CN221877729U (en) Bridge supporting seat

Legal Events