CN217810765U - Construction platform for reservoir danger removal and reinforcement - Google Patents

Construction platform for reservoir danger removal and reinforcement Download PDF

Info

Publication number
CN217810765U
CN217810765U CN202221965309.0U CN202221965309U CN217810765U CN 217810765 U CN217810765 U CN 217810765U CN 202221965309 U CN202221965309 U CN 202221965309U CN 217810765 U CN217810765 U CN 217810765U
Authority
CN
China
Prior art keywords
fixedly connected
construction platform
reservoir
round mouth
brace table
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202221965309.0U
Other languages
Chinese (zh)
Inventor
陈振
苏冠仁
席勇
裴扬群
梁健德
李红杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Shunshui Project Construction Management Co ltd
Original Assignee
Guangdong Shunshui Project Construction Management Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Shunshui Project Construction Management Co ltd filed Critical Guangdong Shunshui Project Construction Management Co ltd
Priority to CN202221965309.0U priority Critical patent/CN217810765U/en
Application granted granted Critical
Publication of CN217810765U publication Critical patent/CN217810765U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Emergency Lowering Means (AREA)

Abstract

The application discloses a reservoir removes dangerous construction platform of consolidating and uses, belong to construction platform technical field, including dykes and dams and brace table, the brace table can be dismantled and connect on the inclined plane of dykes and dams, the round mouth has been seted up on the brace table, two extension boards of both sides fixedly connected with that lie in the round mouth on the brace table, it is connected with same pivot to rotate between two extension boards, the fixed wind-up roll that is provided with in the pivot, be provided with the rope on the wind-up roll, round mouth and fixedly connected with movable seat are passed to the bottom of rope, the bottom fixedly connected with a plurality of cables of movable seat, the same carriage of bottom fixedly connected with of a plurality of cables, the round mouth is run through in the carriage activity, extension board and fixedly connected with carousel are extended to the one end of pivot, staff's carrying tool and construction material get into in the carriage, make the rope drive carriage descend, and then make staff closely contact with dykes, remove danger and consolidate, staff's accessible opening stretches out the health and carries out work, simultaneously, can the cable hold, guarantee personal safety.

Description

Construction platform for reservoir danger removal and reinforcement
Technical Field
The application belongs to the technical field of construction platforms, and particularly relates to a construction platform for reservoir danger removal and reinforcement.
Background
Reservoirs, generally interpreted as "hydraulic engineering buildings that hold water for flood diversion and regulate water flow, can be utilized for irrigation, power generation, flood control and fish farming. "it refers to an artificial lake formed by constructing a barrage at the throat of a mountain trench or river. After the reservoir is built, the functions of flood control, water storage irrigation, water supply, power generation, fish culture and the like can be realized. Sometimes natural lakes are also called reservoirs (natural reservoirs). The size of the reservoir is generally divided into small, medium and large sizes according to the size of the reservoir capacity.
In order to guarantee the actual action of the reservoir, danger removal and reinforcement are required to be carried out on the reservoir dam regularly or according to the actual condition, and a Chinese patent with the authorization number of CN215165181U discloses a working platform for reservoir danger removal and reinforcement engineering.
SUMMERY OF THE UTILITY MODEL
In order to conveniently lift the working personnel to enable the working personnel to be in close contact with the reservoir dam, the application provides a construction platform for reservoir danger removal and reinforcement.
In order to achieve the purpose, the following technical scheme is adopted in the application: the utility model provides a reservoir removes dangerous reinforcement and uses construction platform, includes dykes and dams and a supporting bench, the supporting bench can dismantle the connection on the inclined plane of dykes and dams, the round mouth has been seted up on the supporting bench, two both sides fixedly connected with extension boards that lie in the round mouth on the supporting bench, two rotate between the extension board and be connected with same pivot, the fixed wind-up roll that is provided with in the pivot, be provided with the rope on the wind-up roll, round mouth and fixedly connected with movable seat are passed to the bottom of rope, a plurality of cables of bottom fixedly connected with of movable seat, a plurality of the same lifting frame of bottom fixedly connected with of cable, the round mouth is run through in the lifting frame activity, extension board and fixedly connected with carousel are extended to the one end of pivot.
Through adopting above-mentioned technical scheme, the staff carries instrument and construction material and gets into the lifting frame in, makes the rope drive the lifting frame and descends, and then makes the staff closely contact dykes and dams, removes danger and consolidates.
Preferably, the bottom of the supporting table is fixedly connected with four supporting legs, four the bottom of each supporting leg is fixedly connected with a fixing seat matched with the inclined plane of the dam, a screw penetrates through the fixing seat, and the bottom of the screw extends into the dam.
Through adopting above-mentioned technical scheme, through the screw with fixing base fixed mounting on the inclined plane of dykes and dams, and then carry out fixed mounting to the brace table.
Preferably, the side wall all around of lifting frame has seted up the opening.
Through adopting above-mentioned technical scheme, set up the opening, the staff of being convenient for finds out the health and carries out work.
Preferably, an insertion rod penetrates through the rotary table, a plurality of insertion holes matched with the insertion rod are formed in the side wall of the support plate, and the insertion holes are distributed on the ring side of the rotary shaft in an annular array mode.
Through adopting above-mentioned technical scheme, run through the carousel with the inserted bar and insert in an jack, fix the carousel, and then make the pivot can not take place to rotate.
Preferably, a plurality of handles distributed annularly are fixedly connected to the annular side of the rotating disc.
Through adopting above-mentioned technical scheme, be convenient for rotate the carousel through the handle.
Preferably, the side wall of the support platform is hinged with a support inclined plate, and one side of the support inclined plate, which is far away from the support platform, is abutted against the horizontal plane of the dam.
Through adopting above-mentioned technical scheme, be convenient for transport the material to the brace table on through supporting the swash plate.
Preferably, a plurality of anti-slip columns are fixedly arranged on the surface of the supporting sloping plate.
Through adopting above-mentioned technical scheme, improve the security through the antislip column.
Preferably, the supporting table is fixedly connected with fixing columns at four corners, and the four fixing columns are fixedly provided with three guardrails.
Through adopting above-mentioned technical scheme, protect through the guardrail.
Compared with the prior art, the beneficial effect of this application is:
1. workers carry tools and construction materials into the lifting frame, so that the lifting frame is driven by the rope to descend, the workers can contact the dam closely to remove danger and reinforce, the workers can lean out of the body through the opening to work, and meanwhile, the workers can hold the stay rope to guarantee personal safety;
2. rotate the carousel through the handle, drive the pivot and rotate, the pivot drives the wind-up roll and rotates, receive and releases the rope through the wind-up roll, is convenient for drive the lift frame through the rope and reciprocates, runs through the inserted bar carousel and inserts in an inserting hole, fixes the carousel, and then makes the pivot can not take place to rotate.
Drawings
Fig. 1 is a schematic structural diagram of an entire construction platform for reservoir danger removal and reinforcement, which is provided by the application;
fig. 2 is a schematic structural diagram of a construction platform support platform for reservoir danger removal and reinforcement according to the application;
FIG. 3 is a schematic structural view of a construction platform lifting frame for reservoir danger removal reinforcement according to the present application;
fig. 4 is a schematic structural diagram of another view of the whole construction platform for reservoir danger removal and reinforcement according to the application.
In the figure: 1. a dam; 2. a support table; 3. a round mouth; 4. a support plate; 5. a rotating shaft; 6. a wind-up roll; 7. a rope; 8. a movable seat; 9. a cable; 10. a lifting frame; 11. a turntable; 12. a rod is inserted; 13. a jack; 14. a handle; 15. supporting legs; 16. a fixed seat; 17. a screw; 18. an opening; 19. supporting the inclined plate; 20. an anti-slip column; 21. fixing a column; 22. and (4) a guardrail.
Detailed Description
The technical solutions in the embodiments of the present application will be clearly and completely described below with reference to the drawings in the embodiments of the present application, and it is obvious that the described embodiments are only a part of the embodiments of the present application, and not all of the embodiments.
Referring to fig. 1-3, a construction platform for reservoir danger removal and reinforcement, including dykes and dams 1 and a supporting bench 2, supporting bench 2 can be dismantled and connect on the inclined plane of dykes and dams 1, round mouth 3 has been seted up on supporting bench 2, two extension boards 4 of both sides fixedly connected with that lie in round mouth 3 on supporting bench 2, it is connected with same pivot 5 to rotate between two extension boards 4, fixedly on the pivot 5 be provided with wind-up roll 6, fixedly on the wind-up roll 6 be provided with rope 7, rotate pivot 5, drive wind-up roll 6 and rotate, receive and release rope 7 through wind-up roll 6. Round mouth 3 and fixedly connected with sliding seat 8 are passed to the bottom of rope 7, a plurality of cables 9 of bottom fixedly connected with of sliding seat 8, the same lifting frame 10 of bottom fixedly connected with of a plurality of cables 9, lifting frame 10 activity runs through round mouth 3, in staff's carrying tool and construction material got into lifting frame 10, make rope 7 drive lifting frame 10 descend, and then make the staff closely contact dykes and dams 1, remove the danger and consolidate, opening 18 has all been seted up to the lateral wall all around of lifting frame 10, set up opening 18, the staff of being convenient for finds out the health and carries out work. One end of the rotating shaft 5 extends out of the support plate 4 and is fixedly connected with a rotating disc 11, so that the rotating shaft 5 is driven to rotate through the rotating disc 11.
Referring to fig. 4, four supporting legs 15 are fixedly connected to the bottom of the supporting table 2, the fixing bases 16 matched with the inclined planes of the dam 1 are fixedly connected to the bottom ends of the four supporting legs 15, screws 17 are arranged on the fixing bases 16 in a penetrating mode, the bottom ends of the screws 17 extend into the dam 1, the fixing bases 16 are fixedly mounted on the inclined planes of the dam 1 through the screws 17, and then the supporting table 2 is fixedly mounted.
Referring to fig. 2, an insertion rod 12 is provided on the rotary table 11 in a penetrating manner, a plurality of insertion holes 13 adapted to the insertion rod 12 are provided on the side wall of the support plate 4, the plurality of insertion holes 13 are distributed on the ring side of the rotary shaft 5 in an annular array manner, the insertion rod 12 penetrates through the rotary table 11 and is inserted into one insertion hole 13, the rotary table 11 is fixed, and the rotary shaft 5 is prevented from rotating. A plurality of handles 14 distributed annularly are fixedly connected to the ring side of the rotary plate 11, so that the rotary plate 11 can be rotated by the handles 14.
Referring to fig. 1, the lateral wall of the supporting platform 2 is hinged with a supporting sloping plate 19, and one side of the supporting sloping plate 19 away from the supporting platform 2 is abutted against the horizontal plane of the dam 1, so that the supporting sloping plate 19 can convey materials to the supporting platform 2 conveniently. The supporting sloping plate 19 is provided with a plurality of anti-skid columns 20 on the surface, and the anti-skid columns 20 improve the safety.
Refer to fig. 2, the equal fixedly connected with fixed column 21 in four corners department on the supporting bench 2, four fixed columns 21 are gone up the fixed three guardrail 22 that is provided with, protect through guardrail 22.
The operating principle of the present application is now described as follows: rotating carousel 11, driving pivot 5 and rotating, pivot 5 drives wind-up roll 6 and rotates, receive and releases rope 7 through wind-up roll 6, and rope 7 drives lifting frame 10 and reciprocates, runs through carousel 11 with inserted bar 12 and inserts in a jack 13, fixes carousel 11, and then makes pivot 5 can not take place to rotate. The staff carries instrument and construction material to get into in the lift frame 10, makes rope 7 drive lift frame 10 descend, and then makes the staff closely contact dykes and dams 1, removes danger and consolidates, and the staff accessible opening 18 stretches out the health and carries out work, can hold cable 9 simultaneously, guarantees personal safety.
The above description is only for the preferred embodiments of the present application, but the scope of the present application is not limited thereto, and any person skilled in the art should be considered to be within the technical scope of the present application, and equivalent alternatives or modifications according to the technical solutions and the application concepts of the present application, which are within the technical scope of the present application.

Claims (8)

1. The utility model provides a reservoir removes dangerous reinforcement and uses construction platform, includes dykes and dams (1) and brace table (2), its characterized in that, brace table (2) can be dismantled and connect on the inclined plane of dykes and dams (1), round mouth (3) have been seted up on brace table (2), lie in two extension boards (4) of both sides fixedly connected with of round mouth (3) on brace table (2), two rotate between extension board (4) and be connected with same pivot (5), fixed wind-up roll (6) that are provided with on pivot (5), be provided with rope (7) on wind-up roll (6), round mouth (3) and fixedly connected with sliding seat (8) are passed to the bottom of rope (7), a plurality of cable (9) of bottom fixedly connected with of sliding seat (8), it is a plurality of same lift frame (10) of bottom fixedly connected with of cable (9), lift frame (10) activity runs through round mouth (3), extension board (4) and fixedly connected with carousel (11) are extended to the one end of pivot (5).
2. The construction platform for reservoir danger-removing reinforcement according to claim 1, wherein four supporting legs (15) are fixedly connected to the bottom of the supporting platform (2), the bottom ends of the four supporting legs (15) are fixedly connected to fixing seats (16) matched with the inclined surface of the dam (1), screws (17) are arranged on the fixing seats (16) in a penetrating manner, and the bottom ends of the screws (17) extend into the dam (1).
3. The construction platform for reservoir danger elimination and reinforcement according to claim 1, wherein the peripheral side wall of the lifting frame (10) is provided with openings (18).
4. The construction platform for reservoir danger removal and reinforcement according to claim 1, wherein an insert rod (12) penetrates through the rotary plate (11), a plurality of insertion holes (13) matched with the insert rod (12) are formed in the side wall of the support plate (4), and the plurality of insertion holes (13) are distributed on the annular side of the rotating shaft (5) in an annular array mode.
5. The construction platform for reservoir danger elimination and reinforcement according to claim 4, wherein a plurality of handles (14) are fixedly connected to the ring side of the rotary plate (11).
6. The construction platform for reservoir danger eliminating and strengthening according to claim 1, wherein the side wall of the support platform (2) is hinged with a support sloping plate (19), and one side of the support sloping plate (19) far away from the support platform (2) is abutted with the horizontal surface of the dam (1).
7. The construction platform for reservoir danger elimination and reinforcement according to claim 6, wherein a plurality of anti-slip columns (20) are fixedly arranged on the surface of the inclined supporting plate (19).
8. The construction platform for reservoir danger eliminating and reinforcing as claimed in claim 1, wherein fixed columns (21) are fixedly connected to four corners of the support platform (2), and three guardrails (22) are fixedly arranged on the four fixed columns (21).
CN202221965309.0U 2022-07-28 2022-07-28 Construction platform for reservoir danger removal and reinforcement Active CN217810765U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221965309.0U CN217810765U (en) 2022-07-28 2022-07-28 Construction platform for reservoir danger removal and reinforcement

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221965309.0U CN217810765U (en) 2022-07-28 2022-07-28 Construction platform for reservoir danger removal and reinforcement

Publications (1)

Publication Number Publication Date
CN217810765U true CN217810765U (en) 2022-11-15

Family

ID=83970154

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221965309.0U Active CN217810765U (en) 2022-07-28 2022-07-28 Construction platform for reservoir danger removal and reinforcement

Country Status (1)

Country Link
CN (1) CN217810765U (en)

Similar Documents

Publication Publication Date Title
CN214939976U (en) Multifunctional self-elevating offshore wind power construction platform
CN217810765U (en) Construction platform for reservoir danger removal and reinforcement
CN110409368B (en) Angle-adjustable permeable T-dam
CN216194719U (en) Dam gap plugging equipment with piles
CN205961759U (en) Easily operate hand -held earth boring machine
CN107178307A (en) A kind of Assembled punch for water conservancy construction
CN211210441U (en) Equipment for digging pit for afforestation
CN213923830U (en) Pipe burying device for hydraulic and hydroelectric engineering
CN213476806U (en) Gate suitable for lining channel
CN210917205U (en) Angle-adjustable permeable spur dike
CN214573681U (en) Hydraulic engineering construction safety device
CN107902762B (en) River sewage treatment device
CN206865995U (en) A kind of Chinese garden planting digging apparatus
CN218098479U (en) Lake sampling device
CN221185210U (en) Reinforced concrete welding device
CN216367936U (en) Reaction kettle for repairing polluted underground water
CN211850719U (en) Civil construction crane
CN215985256U (en) Water conservancy bank protection detects sampling device
CN217298985U (en) Cofferdam device for hydraulic design construction
CN111021942A (en) Small-size hole equipment that draws suitable for finite space
CN217947717U (en) Physical defoaming device for treating oilfield operation chemical flooding sewage
CN216892340U (en) Hydraulic engineering foundation detection device
CN218202325U (en) Chemical oxygen demand removal device in oil and gas field water
CN213510460U (en) Formula rig that spatters outward is prevented to flying stone of hydraulic engineering construction usefulness
CN213330924U (en) Be applied to down-the-hole drill of water conservancy construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant