CN217708804U - Hanging basket for elevator installation - Google Patents

Hanging basket for elevator installation Download PDF

Info

Publication number
CN217708804U
CN217708804U CN202221793073.7U CN202221793073U CN217708804U CN 217708804 U CN217708804 U CN 217708804U CN 202221793073 U CN202221793073 U CN 202221793073U CN 217708804 U CN217708804 U CN 217708804U
Authority
CN
China
Prior art keywords
hanging
steel wire
basket
bearing block
jib
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202221793073.7U
Other languages
Chinese (zh)
Inventor
黄璜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhangzhou Jiecheng Electromechanical Equipment Co ltd
Original Assignee
Zhangzhou Jiecheng Electromechanical Equipment Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhangzhou Jiecheng Electromechanical Equipment Co ltd filed Critical Zhangzhou Jiecheng Electromechanical Equipment Co ltd
Priority to CN202221793073.7U priority Critical patent/CN217708804U/en
Application granted granted Critical
Publication of CN217708804U publication Critical patent/CN217708804U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Load-Engaging Elements For Cranes (AREA)

Abstract

The utility model relates to the technical field of construction hanging baskets, in particular to a hanging basket for elevator installation, which comprises a hanging basket and hanging rods fixed at the middle parts of the top ends of the two sides of the hanging basket, wherein a bearing block is fixed at the position where the hanging basket is connected with the hanging rods, a tensioning steel wire fixedly connected with the bearing block is arranged inside the two sides of the bearing block, and the other end of the tensioning steel wire is sleeved on the outer wall of the top end of the hanging rod; the utility model discloses the rigidity that is connected at hanging flower basket and jib has the carrier block to be equipped with taut steel wire in the inboard of carrier block, make the hanging flower basket when being connected through the jib and lifting by crane equipment, can be through fixing the top at the jib with taut steel wire, make the both sides of hanging flower basket have the atress performance, avoided the hanging flower basket to take place to incline in the use, improved the stability of workman in the course of the work on the hanging flower basket, improved the security of workman to the elevator work progress.

Description

Hanging basket for elevator installation
Technical Field
The utility model relates to a construction hanging flower basket technical field especially relates to a hanging flower basket is used in elevator installation.
Background
Elevator installation hanging flower basket is used for bearing the artifical supporting body that installs the elevator when the elevator installation, make the manual work can support the installation to the elevator in the high altitude, at present, the hanging flower basket is when the installation is used, all lift by crane equipment with the jib and the upside at both ends and be connected, thereby make the hanging flower basket can bear artifical the standing, but current hanging flower basket is at the in-process that uses, because jib and the connected mode who lifts by crane equipment, can cause the hanging flower basket can take place to rock or slope when receiving the tiltmotion, cause the slope that the workman takes place the hanging flower basket at the in-process that uses very easily, lead to constructor's injures and deaths.
Therefore, it is necessary to provide a basket for installing an elevator to solve the above-mentioned technical problems.
SUMMERY OF THE UTILITY MODEL
In order to solve the technical problem, the utility model provides a hanging flower basket is used in elevator installation.
The utility model provides a pair of hanging flower basket for elevator installation includes:
the hanging flower basket is fixed in the jib at hanging flower basket both sides top middle part, and the position that hanging flower basket and jib are connected is fixed with the carrier block, and the inside taut steel wire rather than fixed connection that wears to be equipped with in carrier block both sides, taut steel wire other end suit in jib top outer wall.
Preferably, the position where the bearing block is connected with the tensioning steel wire is rotatably connected with a steel wire roller, and one end of the tensioning steel wire connected with the steel wire roller is wound outside the steel wire roller.
Preferably, the one end that the carrier block was kept away from to the steel wire roller is located the carrier block outside, and the one end that the steel wire roller is located the carrier block outside articulates there is the driving plate, and a side end face middle part of driving plate is fixed with changes the handle, changes to wear to locate the carrier block outer wall inboard.
Preferably, the outer wall of the bearing block is connected with the rotating handle, positioning holes distributed in an annular shape at equal intervals are formed in the position of the rotating handle, and the rotating handle penetrates through the inner sides of the positioning holes.
Preferably, a magnetic block is fixed at one end of the rotating handle far away from the transmission plate and is adsorbed on the inner wall of the positioning hole.
Preferably, one side that the transmission plate was kept away from to the carrier block outer wall has seted up the draw-in groove, and the line mouth has been seted up at the draw-in groove top, and the one end middle part that the jib was connected to taut steel wire fits in the jib top outside, and the one end top that the jib was connected to taut steel wire is fixed with the fixture block, and the fixture block is blocked in the draw-in groove inboardly.
Compared with the prior art, the utility model provides a pair of hanging flower basket is used in elevator installation has following beneficial effect:
1. the utility model discloses the rigidity that is connected at hanging flower basket and jib has the carrier block to be equipped with taut steel wire in the inboard of carrier block, make the hanging flower basket when being connected through the jib and lifting by crane equipment, can be through fixing the top at the jib with taut steel wire, make the both sides of hanging flower basket have the atress performance, avoided the hanging flower basket to take place to incline in the use, improved the stability of workman in the course of the work on the hanging flower basket, improved the security of workman to the elevator work progress.
Drawings
Fig. 1 is a schematic structural view of a preferred embodiment of a hanging basket for elevator installation according to the present invention;
FIG. 2 is a schematic structural diagram of the position of the bearing block shown in FIG. 1;
FIG. 3 is a schematic cross-sectional view of a structure on one side of the bearing block shown in FIG. 2;
fig. 4 is an exploded view of the cross-sectional position of the carrier block shown in fig. 3.
Reference numbers in the figures: 1. a hanging basket; 2. a boom; 3. a bearing block; 4. a steel wire roller; 5. tensioning the steel wire; 6. a clamping block; 7. a drive plate; 8. turning a handle; 9. a magnetic block; 10. positioning holes; 11. a card slot; 12. and (4) line ports.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more clearly understood, the present invention is further described in detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the invention and are not intended to limit the invention.
The following detailed description is provided for the specific embodiments of the present invention.
Referring to the drawings, an embodiment of the present invention provides a hanging basket for elevator installation, including:
hanging flower basket 1 is fixed in the jib 2 at 1 both sides top middle part of hanging flower basket, and the position that hanging flower basket 1 is connected with jib 2 is fixed with carrier block 3, and carrier block 3 both sides are inside to wear to be equipped with rather than fixed connection's taut steel wire 5, and 5 other ends of taut steel wire fit in 2 top outer walls of jib.
It should be noted that: bearing block 3 rotates with the position that taut steel wire 5 is connected and is connected with steel wire roller 4, the one end that taut steel wire 5 connects steel wire roller 4 is convoluteed in the steel wire roller 4 outside, the one end that bearing block 3 was kept away from to steel wire roller 4 is located the bearing block 3 outside, the one end that steel wire roller 4 is located the bearing block 3 outside articulates there is driving plate 7, 7 side end face middle part of driving plate is fixed with changes 8, it wears to locate the 3 outer wall inboards of bearing block to change 8, 3 outer wall connection of bearing block changes 8 the position of setting up the locating hole 10 that ring shape equidistance distributes, it wears to locate locating hole 10 inboardly to change 8, it is fixed with magnetic path 9 to change 8 one end of keeping away from driving plate 7, magnetic path 9 adsorbs in locating hole 10 inner wall, draw-in groove 11 has been seted up to the one side that driving plate 7 was kept away from to the 3 outer walls of bearing block, line mouth 12 has been seted up at draw-in 11 top, the one end middle part that taut steel wire 5 connects jib 2 registrates in the jib 2 outside, the one end top that taut steel wire 5 connects jib 2 is fixed with fixture block 6, fixture block 6 blocks is inboard in draw-in 11.
In the present embodiment: the utility model discloses the rigidity that is connected at hanging flower basket 1 and jib 2 has carrier block 3, and be equipped with taut steel wire 5 in carrier block 3's inboard, make hanging flower basket 1 when being connected through jib 2 and lifting by crane equipment, can be through fixing taut steel wire 5 at the top of jib 2, make hanging flower basket 1's both sides have the atress performance, avoided hanging flower basket 1 to take place to incline in the use, the stability of workman in the course of the work on hanging flower basket 1 has been improved, the security of workman to the elevator work progress has been improved.
The use process comprises the following steps:
when the steel wire tensioning device is used, a steel wire used for hoisting a hanging basket 1 by a hoisting device is connected to the upper sides of the hanging rods 2 at two sides of the hanging basket 1, then the clamping block 6 is pulled, so that the tensioning steel wire 5 connected with the clamping block 6 is pulled out from the outer side of the steel wire roller 4, when the tensioning steel wire 5 is pulled, the rotating handle 8 and the magnetic block 9 arranged at one side of the steel wire roller 4 need to be pulled out from the inner side of the positioning hole 10, when the tensioning steel wire 5 is pulled, the rotating plate is driven to rotate, so that the steel wire wound at the outer side can be wound and unwound by the steel wire roller 4, after the tensioning steel wire 5 is released from the outer side of the steel wire roller 4, the clamping block 6 is penetrated through from the top of the hanging rod 2, the tensioning steel wire 5 is sleeved at the top of the hanging rod 2, then the clamping block 6 is pulled, the clamping block 6 is placed on the inner side of the clamping groove 11 arranged at one side of the bearing block 3 far away from the rotating handle 8, and after the clamping block 6 is placed in the clamping groove 11, the tensioning steel wire 5 connected with the clamping block is penetrated through the inner side of the wire opening 12, after the clamping block 6 is placed, the transmission plate 7 is rotated, the rotating handle 8 is buckled at the inner side of a positioning hole 10 formed in the outer wall of the bearing block 3, so that the two sides of the hanging basket 1 can be stressed and fixed, after the tensioning steel wires 5 at the four ends are all sleeved at the outer side of the hanging rod 2, the hanging equipment can be started to hang the hanging basket 1, after the hanging basket 1 is hung, the lifting steel wire firstly pulls the hanging rod 2 to hang the hanging basket 1, at the moment, the tensioning steel wires 5 arranged at the four ends of the bearing block 3 are all sleeved at the top of the hanging rod 2, so when a worker moves on the hanging basket 1, the hanging basket 1 is subjected to an inclination force, the inclination force produced by the worker is transmitted to the hanging rod 2 due to the stress pulling of the tensioning steel wires 5, and the inclination force produced by the worker can be counteracted through the tensioning steel wires 5 under the self gravity of the hanging basket 1 due to the connection of the tensioning steel wires 5, thereby improving the stability of the hanging basket 1 after the lifting is finished;
it should be noted that: after rotating 8 and penetrating locating hole 10 inboard, rotate the magnetic path 9 that 8 one end set up and can will change 8 and adsorb the inboard at locating hole 10, guarantee to change 8 fastness after fixing, avoid taut steel wire 5 to relax, improve the stability of taut steel wire 5 when the atress.
The utility model discloses circuit and control that relate to are prior art, do not carry out too much repetition here.
The above only is the embodiment of the present invention, not limiting the scope of the present invention, all the equivalent structures or equivalent processes of the present invention are used in the specification and the attached drawings, or directly or indirectly applied to other related technical fields, and the same principle is included in the protection scope of the present invention.

Claims (6)

1. The utility model provides a hanging flower basket is used in elevator installation, includes hanging flower basket (1), is fixed in jib (2) at hanging flower basket (1) both sides top middle part, its characterized in that, the position that hanging flower basket (1) and jib (2) are connected is fixed with carrier block (3), inside taut steel wire (5) rather than fixed connection of wearing to be equipped with in carrier block (3) both sides, taut steel wire (5) other end fits jib (2) top outer wall in the cover.
2. The hanging basket for installing the elevator according to claim 1, wherein the position where the bearing block (3) is connected with the tension steel wire (5) is rotatably connected with the steel wire roller (4), and one end of the tension steel wire (5) connected with the steel wire roller (4) is wound outside the steel wire roller (4).
3. The hanging basket for installing the elevator according to claim 2, wherein one end, far away from the bearing block (3), of the steel wire roller (4) is located on the outer side of the bearing block (3), one end, located on the outer side of the bearing block (3), of the steel wire roller (4) is hinged to a transmission plate (7), a rotating handle (8) is fixed to the middle of the end face of one side of the transmission plate (7), and the rotating handle (8) penetrates through the inner side of the outer wall of the bearing block (3).
4. The hanging basket for installing the elevator as claimed in claim 3, wherein the position of the outer wall of the bearing block (3) connected with the rotating handle (8) is provided with positioning holes (10) which are distributed in a circular ring shape at equal intervals, and the rotating handle (8) penetrates through the inner sides of the positioning holes (10).
5. The hanging basket for mounting the elevator as claimed in claim 3, wherein a magnet (9) is fixed at one end of the rotating handle (8) far away from the transmission plate (7), and the magnet (9) is attached to the inner wall of the positioning hole (10).
6. The hanging basket for installing the elevator according to claim 3, wherein a clamping groove (11) is formed in one side, away from the transmission plate (7), of the outer wall of the bearing block (3), a wire opening (12) is formed in the top of the clamping groove (11), the middle of one end, connected with the hanging rod (2), of the tensioning steel wire (5) is sleeved outside the top of the hanging rod (2), a clamping block (6) is fixed at the top of one end, connected with the hanging rod (2), of the tensioning steel wire (5), and the clamping block (6) is clamped inside the clamping groove (11).
CN202221793073.7U 2022-07-12 2022-07-12 Hanging basket for elevator installation Expired - Fee Related CN217708804U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221793073.7U CN217708804U (en) 2022-07-12 2022-07-12 Hanging basket for elevator installation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221793073.7U CN217708804U (en) 2022-07-12 2022-07-12 Hanging basket for elevator installation

Publications (1)

Publication Number Publication Date
CN217708804U true CN217708804U (en) 2022-11-01

Family

ID=83779721

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221793073.7U Expired - Fee Related CN217708804U (en) 2022-07-12 2022-07-12 Hanging basket for elevator installation

Country Status (1)

Country Link
CN (1) CN217708804U (en)

Similar Documents

Publication Publication Date Title
CN211545757U (en) Auxiliary assembly is used in switch board installation
CN217708804U (en) Hanging basket for elevator installation
CN210682955U (en) Hoisting clamp for crane
CN210885011U (en) Multifunctional crane assembled on forklift
CN219636707U (en) Stone curtain wall lifting device
CN212897506U (en) Aerial construction platform device based on steel construction special-shaped curtain that encorbelments
CN207406013U (en) A kind of FRAME ON THE ROOF OF HIGH-RISE BUILDING curtain wall lifting device
CN214653150U (en) Equipment for hoisting prefabricated arched tunnel roof structure
CN109721000B (en) Lifting equipment for gum dipping cord fabric convenient to operate
CN115159366A (en) Large steel structure support suspension construction equipment and hoisting method
CN109052205B (en) Stable high altitude hangs thing device when heavy object promotes
CN209955592U (en) Drawing hanger for industrial design
JPH07144850A (en) Shackle equipped with roller and car suspending device
CN112374407A (en) Auxiliary hoisting tool for electric power construction
CN109795949A (en) Lifting appliance used in engineering construction process
CN111792525A (en) Anti-shaking device for crane
CN213011652U (en) Hoist device is used in engineering machine tool maintenance
CN214399581U (en) Lifting device for electromechanical engineering
CN218145415U (en) Hoisting equipment for engineering
CN213171164U (en) Tree hoisting device for garden engineering
CN212953995U (en) Hoisting structure for mechanical equipment installation
CN221028757U (en) Hanging tool for electroplating
CN116620999B (en) Electric permanent magnet sucker convenient to fix and use method
JP2001302184A (en) Swing preventing tag line device of construction machinery
CN218665146U (en) Single-layer self-rope-arranging suspender machine

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20221101