Pipe support is used in fresh air pipeline installation Download PDFInfo
- Publication number
- CN217685631U CN217685631U CN202221537071.1U CN202221537071U CN217685631U CN 217685631 U CN217685631 U CN 217685631U CN 202221537071 U CN202221537071 U CN 202221537071U CN 217685631 U CN217685631 U CN 217685631U
- Authority
- CN
- China
- Prior art keywords
- mounting plate
- threaded hole
- plate
- bolt
- fresh air
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Supports For Pipes And Cables (AREA)
Abstract
The utility model provides a pipe support is used in new trend pipeline installation, include: the first fixing plate is fixedly arranged on a wall; the first mounting plate is arranged on the first fixing plate; the second fixing plate is fixedly arranged on the top wall; the second mounting plate is arranged on the second fixing plate, and one end of the second mounting plate is detachably connected with the first mounting plate; one end of the third mounting plate is detachably connected with the first mounting plate; one end of the fourth mounting plate is detachably connected with the other end of the second mounting plate, and the other end of the fourth mounting plate is detachably connected with the other end of the third mounting plate; the first arc-shaped clamping block is arranged on the first mounting plate; the second arc-shaped clamping block is arranged on the second mounting plate; the third arc-shaped clamping block is arranged on the third mounting plate; the fourth arc-shaped clamping block is arranged on the fourth mounting plate. When the pipe support is used in fresh air pipeline installation, the fresh air pipeline can not be obstructed by drooping fresh air pipeline, and the fresh air pipeline also does not need to be dismounted and then installed, so that the installation efficiency is relatively high.
Description
Technical Field
The utility model belongs to the technical field of the installation pipe support technique of new trend pipeline and specifically relates to a pipe support is used in new trend pipeline installation.
Background
Along with the improvement of living standard of people, a room using an air conditioner needs to be capable of adjusting temperature, outdoor fresh air supplement is needed, and air of a closed air-conditioned room is improved. Most of the existing decorated air-conditioned rooms are provided with a fresh air pipeline, and outdoor fresh air can be conveniently introduced into the room.
However, after the fresh air pipeline is used for a long time, the mounting frame of the fresh air pipeline can slowly become loose, the fresh air pipeline can gradually droop, the mounting frame can not support and fix the fresh air pipeline any more, the fresh air pipeline has a risk of falling at any time, the mounting frame needs to be installed again to support and fix the fresh air pipeline again, however, the drooped fresh air pipeline is generally installed by being attached to the wall and the top wall in the air-conditioned room, the drooped fresh air pipeline can block the re-installation of the mounting frame, the mounting frame is installed after the fresh air pipeline is taken down, the workload of the re-installation can be large, and the installation efficiency is low; therefore, it is necessary to provide a new air duct installation pipe support.
SUMMERY OF THE UTILITY MODEL
The utility model provides a fresh air pipeline is pipe support for installation to in support again and fix fresh air pipeline, the installation effectiveness is higher relatively moreover.
In order to achieve the above purpose, the utility model adopts the following technical proposal:
a pipe support for installing a fresh air pipeline comprises: the first fixing plate is fixedly arranged on a wall; the first mounting plate is vertically arranged on the first fixing plate in a vertical manner in a vertically sliding manner; the second fixing plate is fixedly arranged on the top wall; the second mounting plate can be horizontally arranged on the second fixing plate in a left-right sliding manner, and one end of the second mounting plate is detachably connected with the first mounting plate; one end of the third mounting plate is detachably connected with the first mounting plate and is arranged in parallel with the second mounting plate; one end of the fourth mounting plate is detachably connected with the other end of the second mounting plate, the other end of the fourth mounting plate is detachably connected with the other end of the third mounting plate, and the fourth mounting plate is parallel to the first mounting plate; a first arcuate clamp block horizontally adjustably mounted on the first mounting plate; a second arcuate clamp block mounted on the second mounting plate in a height position adjustable manner; a third arcuate clamp block height position adjustably mounted on the third mounting plate; a fourth arcuate clamp block horizontally adjustably mounted on the fourth mounting plate; the first mounting plate, the second mounting plate, the third mounting plate and the fourth mounting plate are connected with each other to form a pipe frame main body for surrounding a fresh air pipeline; first arc clamp splice second arc clamp splice third arc clamp splice with fourth arc clamp splice all is located in the pipe support main part for clip the new trend pipeline jointly.
The utility model discloses an embodiment, first spout has been seted up along its length direction to first mounting panel, first spout is equipped with can be in it the free first slide bar that slides from top to bottom, first slide bar one end with first fixed plate fixed connection, the other end passes first spout is connected with first plectane, the diameter of first plectane is greater than the width of first spout, first screw hole has been seted up to first mounting panel, first screw hole has a plurality ofly and follows the length direction of first spout distributes, second screw hole has been seted up to first plectane, the second screw hole with first screw hole is equipped with first bolt jointly, fixes when needs during the first mounting panel, first bolt with second screw hole threaded connection just passes behind the second screw hole with first screw hole threaded connection.
The utility model discloses an embodiment, the second mounting panel is equipped with first fixed block, a third screw hole has been seted up to a fixed block, third screw hole with first screw hole is equipped with the second bolt jointly, and is fixed as needs during the second mounting panel, the second bolt with third screw hole threaded connection just passes behind the third screw hole with first screw hole threaded connection.
The utility model discloses an embodiment, the third mounting panel is equipped with the second fixed block, fourth screw hole has been seted up to two fixed blocks, fourth screw hole with first screw hole is equipped with the third bolt jointly, and is fixed as needs during the third mounting panel, the third bolt with fourth screw hole threaded connection just passes behind the fourth screw hole with first screw hole threaded connection.
The utility model discloses an in one embodiment, the second spout has been seted up along its length direction to the second mounting panel, the second spout is equipped with can be in it the free second slide bar that slides from top to bottom, second slide bar one end with second fixed plate fixed connection, the other end passes the second spout is connected with the second plectane, the diameter of second plectane is greater than the width of second spout, the second slide bar is equipped with external screw thread and has cup jointed two first nuts, two the first nut is located respectively the upper and lower both sides of second mounting panel, with the locking the second slide bar.
The utility model discloses an in one embodiment, the fourth mounting panel is equipped with fifth screw hole and sixth screw hole, the second mounting panel is equipped with seventh screw hole, the third mounting panel is equipped with eighth screw hole, fifth screw hole with seventh screw hole is equipped with the fourth bolt jointly, sixth screw hole with eighth screw hole is equipped with the fifth bolt jointly, fixes when needs during the fourth mounting panel, the fourth bolt with fifth screw hole threaded connection just passes behind the fifth screw hole with seventh screw hole threaded connection, the fifth bolt with sixth screw hole threaded connection just passes behind the sixth screw hole with eighth screw hole threaded connection.
The utility model discloses an in one embodiment, first spout is equipped with the third slide bar that can freely slide from top to bottom in it, third slide bar one end with first arc clamp splice rotates to be connected, and the other end is connected with the third plectane, the diameter of third plectane is greater than the width of first spout, the third slide bar is equipped with external screw thread and has cup jointed two second nuts, two the second nut is located respectively the symmetry both sides of first mounting panel, with locking the third slide bar.
The utility model discloses an in the embodiment, the second spout is equipped with the fourth slide bar that can freely slide from top to bottom in it, fourth slide bar one end with second arc clamp splice rotates to be connected, and the other end is connected with the fourth plectane, the diameter of fourth plectane is greater than the width of second spout, the fourth slide bar is equipped with external screw thread and has cup jointed two third nuts, two the third nut is located respectively the symmetry both sides of second mounting panel, with locking the fourth slide bar.
The utility model discloses an in one embodiment, two through-holes have been seted up to the third mounting panel, the third arc clamp splice articulates there is the push rod of two symmetric distributions, the push rod is kept away from the one end of third arc clamp splice is run through be connected with the fifth plectane behind the through-hole, the diameter of fifth plectane is greater than the diameter of through-hole, the fifth plectane is equipped with a plurality of ninth screw holes that are circumference array distribution, the third mounting panel correspond with the tenth screw hole has been seted up to the position of ninth screw hole, the ninth screw hole with the tenth screw hole is equipped with sixth bolt jointly, fixes as needs during the third arc clamp splice, sixth bolt with ninth screw hole threaded connection just passes behind the ninth screw hole with tenth screw hole threaded connection.
The utility model discloses an in one embodiment, eleventh screw hole has been seted up to the fourth mounting panel, the eleventh screw hole is equipped with the seventh bolt, seventh bolt one end is connected with the sixth plectane, and the other end runs through the eleventh screw hole with the second arc clamp splice rotates to be connected, the diameter of sixth plectane is greater than the diameter of eleventh screw hole, two fourth nuts, two have been cup jointed to seventh bolt screw thread the fourth nut is located respectively the symmetry both sides of fourth mounting panel, in order to lock the seventh bolt.
To sum up, the utility model discloses following beneficial effect has at least:
when the pipe support is installed, the first fixing plate can be installed on the wall at a position lower than the height of the drooping fresh air pipeline, after the first fixing plate is fixed, the first mounting plate is pushed to slide upwards, the second fixing plate is installed on the top wall and located on one side, far away from the wall, of the drooping fresh air pipeline, after the second fixing plate is fixed, the second mounting plate is pushed to slide towards the wall, and then the first mounting plate, the second mounting plate, the third mounting plate and the fourth mounting plate can be connected with one another to form a pipe support main body; this kind of setting up of pipe support main part makes when the installation, can not be hindered by flagging fresh air pipeline, also need not to pull down fresh air pipeline and install again, make the installation effectiveness relatively higher, can realize single installation, can reduce the cost of reinstallation, and horizontal position can be adjusted to first arc clamp splice and fourth arc clamp splice, third arc clamp splice and third arc clamp splice can height-adjusting position, can adapt to the fresh air pipeline of multiple size, also can be convenient for install, need not the accurate mounted position who measures the pipe support main part when installing, only need the pipe support main part can surround fresh air pipeline, after pipe support main part installation, the rethread adjusts first arc clamp splice, third arc clamp splice, the relative position of third arc clamp splice and fourth arc clamp splice, thereby support again and fix fresh air pipeline can, can further improve the installation effectiveness.
Drawings
In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings used in the description of the embodiments will be briefly introduced below, and it is obvious that the drawings in the following description are only some embodiments of the present invention, and it is obvious for those skilled in the art that other drawings can be obtained according to these drawings without creative efforts.
Fig. 1 is a schematic structural diagram of a pipe rack for installing a fresh air pipeline according to some embodiments of the present invention.
Fig. 2 is a schematic structural diagram of a first mounting plate according to some embodiments of the present invention.
Fig. 3 is a schematic structural diagram of a second mounting plate according to some embodiments of the present invention.
Fig. 4 is a schematic structural diagram of a third mounting plate according to some embodiments of the present invention.
Fig. 5 is a schematic structural diagram of a fourth mounting plate according to some embodiments of the present invention.
Reference numerals:
1. a first mounting plate; 11. a first fixing plate; 111. a first slide bar; 112. a first circular plate; 113. a second threaded hole; 12. a first arc-shaped clamping block; 13. a first chute; 14. a first threaded hole; 15. a first bolt; 16. a third slide bar; 17. a third circular plate; 18. a second nut;
2. a second mounting plate; 21. a second fixing plate; 22. a second arc-shaped clamping block; 221. a fourth slide bar; 222. a fourth circular plate; 223. a third nut; 23. a first fixed block; 231. a third threaded hole; 24. a second bolt; 25. a second chute; 26. a second slide bar; 27. a second circular plate; 28. a first nut; 29. a seventh threaded hole;
3. a third mounting plate; 31. a third arc-shaped clamping block; 311. a push rod; 312. a fifth circular plate; 313. a ninth threaded hole; 32. a second fixed block; 33. a fourth threaded hole; 34. a third bolt; 35. an eighth threaded hole; 36. a through hole; 37. a tenth threaded hole; 38. a sixth bolt;
4. a fourth mounting plate; 41. a fourth arc-shaped clamping block; 42. a fifth threaded hole; 43. a sixth threaded hole; 44. a fourth bolt; 45. a fifth bolt; 46. an eleventh threaded hole; 47. a seventh bolt; 48. a sixth circular plate; 49. a fourth nut;
5. a fresh air pipeline.
Detailed Description
In the following, only certain exemplary embodiments are briefly described. As those skilled in the art will recognize, the described embodiments may be modified in various different ways, all without departing from the spirit or scope of the embodiments of the present invention. Accordingly, the drawings and description are to be regarded as illustrative in nature, and not as restrictive.
In the description of the embodiments of the present invention, it should be understood that the terms "length," "vertical," "horizontal," "top," "bottom," and the like are used in the orientation and positional relationship shown in the drawings for convenience in describing the embodiments of the present invention and for simplicity in description, and do not indicate or imply that the device or element being referred to must have a particular orientation, be constructed and operated in a particular orientation, and therefore should not be considered as limiting the embodiments of the present invention.
Furthermore, the terms "first", "second" and "first" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of that feature. In the description of the embodiments of the present invention, "a plurality" means two or more unless specifically limited otherwise.
In the embodiments of the present invention, unless otherwise explicitly specified or limited, the terms "mounted," "connected," "fixed," and the like are to be construed broadly, and may be, for example, fixedly connected, detachably connected, or integrated; the connection can be mechanical connection, electrical connection or communication; they may be directly connected or indirectly connected through intervening media, or may be connected through the use of two elements or the interaction of two elements. The specific meaning of the above terms in the embodiments of the present invention can be understood by those of ordinary skill in the art according to specific situations.
In embodiments of the invention, unless expressly stated or limited otherwise, the first feature "on" or "under" the second feature may comprise direct contact between the first and second features, or may comprise contact between the first and second features through another feature not in direct contact. Also, the first feature "on," "above" and "over" the second feature may include the first feature being directly above and obliquely above the second feature, or simply indicating that the first feature is at a higher level than the second feature. A first feature being "under," "below," and "beneath" a second feature includes the first feature being directly under and obliquely below the second feature, or simply meaning that the first feature is at a lesser elevation than the second feature.
The following disclosure provides many different embodiments or examples for implementing different configurations of embodiments of the invention. In order to simplify the disclosure of embodiments of the present invention, the components and arrangements of specific examples are described below. Of course, they are merely examples and are not intended to limit embodiments of the present invention. Furthermore, embodiments of the present invention may repeat reference numerals and/or reference letters in the various examples for purposes of simplicity and clarity and do not in themselves dictate a relationship between the various embodiments and/or arrangements discussed.
Embodiments of the present invention will be described in detail below with reference to the accompanying drawings.
As shown in fig. 1, 2, 3, 4, and 5, the present embodiment provides a pipe rack for installing a fresh air duct 5, including: a first fixing plate 11 for fixing to a wall; the first mounting plate 1 is vertically arranged on the first fixing plate 11 in a vertical manner in a vertically sliding manner; a second fixing plate 21 for fixedly mounting on the top wall; the second mounting plate 2 is horizontally arranged on the second fixing plate 21 in a left-right sliding manner, and one end of the second mounting plate is detachably connected with the first mounting plate 1; one end of the third mounting plate 3 is detachably connected with the first mounting plate 1 and is arranged in parallel with the second mounting plate 2; one end of the fourth mounting plate 4 is detachably connected with the other end of the second mounting plate 2, the other end of the fourth mounting plate 4 is detachably connected with the other end of the third mounting plate 3, and the fourth mounting plate is arranged in parallel with the first mounting plate 1; a first arc-shaped clamping block 12 which is horizontally and adjustably arranged on the first mounting plate 1; a second arc-shaped clamping block 22 which is height position-adjustably mounted on the second mounting plate 2; a third arc-shaped clamping block 31 which is adjustably mounted on the third mounting plate 3 in height position; a fourth arc-shaped clamping block 41 which is horizontally adjustably mounted on the fourth mounting plate 4; the first mounting plate 1, the second mounting plate 2, the third mounting plate 3 and the fourth mounting plate 4 are connected with one another to form a pipe frame main body for surrounding a fresh air pipeline 5; the first arc-shaped clamping block 12, the second arc-shaped clamping block 22, the third arc-shaped clamping block 31 and the fourth arc-shaped clamping block 41 are all located in the pipe frame main body and used for clamping the fresh air pipeline 5 together.
In some embodiments, as shown in fig. 1 and fig. 2, the first mounting plate 1 is provided with a first sliding groove 13 along a length direction thereof, the first sliding groove 13 is provided with a first sliding rod 111 capable of sliding up and down freely therein, one end of the first sliding rod 111 is fixedly connected with the first fixing plate 11, the other end passes through the first sliding groove 13 and is connected with a first circular plate 112, a diameter of the first circular plate 112 is larger than a width of the first sliding groove 13, the first mounting plate 1 is provided with a first threaded hole 14, the first threaded holes 14 are provided in plurality and distributed along the length direction of the first sliding groove 13, the first circular plate 112 is provided with a second threaded hole 113, the second threaded hole 113 and the first threaded hole 14 are jointly provided with a first bolt 15, and when the first mounting plate 1 needs to be fixed, the first bolt 15 is in threaded connection with the second threaded hole 113 and is in threaded connection with the first threaded hole 14 after passing through the second threaded hole 113.
In some embodiments, as shown in fig. 1 and 3, the second mounting plate 2 is provided with a first fixing block 23, a third threaded hole 231 is formed in one fixing block, the third threaded hole 231 and the first threaded hole 14 are jointly provided with a second bolt 24, and when the second mounting plate 2 needs to be fixed, the second bolt 24 is in threaded connection with the third threaded hole 231 and is in threaded connection with the first threaded hole 14 after passing through the third threaded hole 231.
In some embodiments, as shown in fig. 1 and 4, the third mounting plate 3 is provided with a second fixing block 32, the second fixing block is provided with a fourth threaded hole 33, the fourth threaded hole 33 and the first threaded hole 14 are jointly provided with a third bolt 34, and when the third mounting plate 3 needs to be fixed, the third bolt 34 is in threaded connection with the fourth threaded hole 33 and is in threaded connection with the first threaded hole 14 after penetrating through the fourth threaded hole 33.
In some embodiments, the second mounting plate 2 is provided with a second sliding groove 25 along the length direction thereof, the second sliding groove 25 is provided with a second sliding rod 26 capable of sliding up and down freely therein, one end of the second sliding rod 26 is fixedly connected with the second fixing plate 21, the other end of the second sliding rod passes through the second sliding groove 25 and is connected with a second circular plate 27, the diameter of the second circular plate 27 is larger than the width of the second sliding groove 25, the second sliding rod 26 is provided with external threads and is sleeved with two first nuts 28, and the two first nuts 28 are respectively located at the upper side and the lower side of the second mounting plate 2 to lock the second sliding rod 26.
In some embodiments, as shown in fig. 1 and 5, the fourth mounting plate 4 is provided with a fifth threaded hole 42 and a sixth threaded hole 43, the second mounting plate 2 is provided with a seventh threaded hole 29, the third mounting plate 3 is provided with an eighth threaded hole 35, the fifth threaded hole 42 and the seventh threaded hole 29 are commonly provided with a fourth bolt 44, the sixth threaded hole 43 and the eighth threaded hole 35 are commonly provided with a fifth bolt 45, when the fourth mounting plate 4 needs to be fixed, the fourth bolt 44 is in threaded connection with the fifth threaded hole 42 and is in threaded connection with the seventh threaded hole 29 after penetrating through the fifth threaded hole 42, and the fifth bolt 45 is in threaded connection with the sixth threaded hole 43 and is in threaded connection with the eighth threaded hole 35 after penetrating through the sixth threaded hole 43.
In some embodiments, the first sliding groove 13 is provided with a third sliding rod 16 capable of sliding up and down freely therein, one end of the third sliding rod 16 is rotatably connected with the first arc-shaped clamping block 12, the other end of the third sliding rod is connected with a third circular plate 17, the diameter of the third circular plate 17 is larger than the width of the first sliding groove 13, the third sliding rod 16 is provided with external threads and is sleeved with two second nuts 18, and the two second nuts 18 are respectively located at two symmetrical sides of the first mounting plate 1 to lock the third sliding rod 16.
In some embodiments, the second sliding slot 25 is provided with a fourth sliding rod 221 capable of freely sliding up and down therein, one end of the fourth sliding rod 221 is rotatably connected with the second arc-shaped clamping block 22, the other end of the fourth sliding rod is connected with a fourth circular plate 222, the diameter of the fourth circular plate 222 is greater than the width of the second sliding slot 25, the fourth sliding rod 221 is provided with external threads and is threadedly sleeved with two third nuts 223, and the two third nuts 223 are respectively located at two symmetrical sides of the second mounting plate 2 to lock the fourth sliding rod 221.
In some embodiments, the third mounting plate 3 is provided with two through holes 36, the third arc-shaped clamping block 31 is hinged with two push rods 311 which are symmetrically distributed, one end of each push rod 311, which is far away from the third arc-shaped clamping block 31, penetrates through the through hole 36 and is connected with a fifth circular plate 312, the diameter of the fifth circular plate 312 is larger than that of the through hole 36, the fifth circular plate 312 is provided with a plurality of ninth threaded holes 313 which are distributed in a circumferential array, the third mounting plate 3 is provided with tenth threaded holes 37 at positions corresponding to the ninth threaded holes 313, the ninth threaded holes 313 and the tenth threaded holes 37 are jointly provided with sixth bolts 38, and when the third arc-shaped clamping block 31 needs to be fixed, the sixth bolts 38 are in threaded connection with the ninth threaded holes 313 and are in threaded connection with the tenth threaded holes 37 after penetrating through the ninth threaded holes 313.
In some embodiments, the fourth mounting plate 4 is provided with an eleventh threaded hole 46, the eleventh threaded hole 46 is provided with a seventh bolt 47, one end of the seventh bolt 47 is connected with a sixth circular plate 48, the other end of the seventh bolt 47 penetrates through the eleventh threaded hole 46 to be rotatably connected with the second arc-shaped clamping block 22, the diameter of the sixth circular plate 48 is larger than that of the eleventh threaded hole 46, the seventh bolt 47 is threadedly sleeved with two fourth nuts 49, and the two fourth nuts 49 are respectively located at two symmetrical sides of the fourth mounting plate 4 to lock the seventh bolt 47.
In conclusion, when the installation is carried out, the first fixing plate 11 can be fixed on the wall and the second fixing plate 21 can be fixed on the top wall without any difference, the first fixing plate 11 can be installed at a position lower than the height of the drooping fresh air pipeline 5, so that the situation that the drooping fresh air pipeline 5 obstructs and influences the installation of the first fixing plate 11 can be avoided, the installation efficiency can be improved, and meanwhile, the single installation can be realized;
firstly, after the connecting position of the first mounting plate 1 and the second mounting plate 2 is determined, the first mounting plate 1 is pushed to slide upwards and is fixed through the first bolt 15, the first threaded hole 14 and the second threaded hole 113, wherein the distance between the first circular plate 112 and the first mounting plate 1 can be adjusted by rotating the first bolt 15, namely, the distance between the first arc-shaped clamping block 12 and the fresh air pipeline 5 can be adjusted; in practical application, the position of the first arc-shaped clamping block 12 can be adjusted in advance through the third sliding rod 16, the third circular plate 17 and the second nut 18 before the first mounting plate 1 is fixed according to the position of the fresh air pipeline 5 without sagging, so as to clamp the sagging fresh air pipeline 5 subsequently;
then, the second mounting plate 2 is pushed to slide towards the first mounting plate 1, the second mounting plate 2 is connected with the first mounting plate 1 through the first fixing block 23 and the second bolt 24, and the second mounting plate 2 is fixed through the second sliding rod 26, the second circular plate 27 and the first nut 28; in practical application, the position of the second arc-shaped clamping block 22 can be adjusted in advance through the fourth sliding rod 221, the fourth circular plate 222 and the third nut 223 before the second mounting plate 2 is fixed according to the position of the fresh air pipeline 5 which does not hang down, so as to clamp the hanging fresh air pipeline 5 subsequently;
then, through the third mounting plate 3, the third arc-shaped clamping block 31 is used for supporting the drooping fresh air pipeline 5, and the drooping fresh air pipeline 5 is pushed to the positions of the first arc-shaped clamping block 12 and the second clamping block, so that the drooping fresh air pipeline 5 is restored to the original position, at the moment, the position of the third mounting plate 3 is determined, and the third mounting plate 3 is connected with the first mounting plate 1 through the second fixing block 32 and the third bolt 34;
subsequently, the fourth mounting plate 4 is fixed between the second mounting plate 2 and the third mounting plate 3 by the fourth bolt 44 and the fifth bolt 45, wherein the third mounting plate 3 and the fourth mounting plate 4 can be mounted partially in sequence; the fourth arc-shaped clamping block 41 can be directly pushed through the seventh bolt 47 and the sixth circular plate 48, the drooping fresh air pipeline 5 is indirectly moved to the positions of the first arc-shaped clamping block 12 and the second clamping block, so that the drooping fresh air pipeline 5 is restored to the original position, and the seventh bolt 47 is locked through the fourth nut 49;
finally, the distance between the push rod 311 and the third mounting plate 3 can be adjusted through the push rod 311, the fifth circular plate 312 and the sixth bolt 38, and the supporting height of the third arc-shaped clamping block 31 to the fresh air pipeline 5 can be adjusted; the height of the two push rods 311 is adjusted, so that the third arc-shaped clamping block 31 inclines to one side, the corrected fresh air pipeline 5 can deviate from the horizontal position of the first arc-shaped clamping block 12 or the fourth arc-shaped clamping block 41, and the final adjustment after installation can be performed by matching the seventh bolt 47, the fourth nut 49 and the sixth circular plate 48, so that the drooping fresh air pipeline 5 is completely restored to the original position, and the adjustment can be performed when the fresh air pipeline 5 deviates in the later period.
The above embodiments describe a plurality of specific embodiments of the present invention, but it should be understood by those skilled in the art that various changes or modifications may be made to these embodiments without departing from the principles and spirit of the present invention, and these changes and modifications all fall into the protection scope of the present invention.
Claims (10)
1. The utility model provides a pipe support is used in fresh air pipeline installation which characterized in that includes:
the first fixing plate is fixedly arranged on a wall;
the first mounting plate is vertically arranged on the first fixing plate in a vertical manner and can slide up and down;
the second fixing plate is fixedly arranged on the top wall;
the second mounting plate can be horizontally arranged on the second fixing plate in a left-right sliding manner, and one end of the second mounting plate is detachably connected with the first mounting plate;
one end of the third mounting plate is detachably connected with the first mounting plate and is arranged in parallel with the second mounting plate;
one end of the fourth mounting plate is detachably connected with the other end of the second mounting plate, the other end of the fourth mounting plate is detachably connected with the other end of the third mounting plate, and the fourth mounting plate is parallel to the first mounting plate;
a first arcuate clamp block horizontally adjustably mounted on the first mounting plate;
a second arcuate clamp block mounted on the second mounting plate in a height position adjustable manner;
a third arcuate clamp block height position adjustably mounted on the third mounting plate;
a fourth arcuate clamp block horizontally adjustably mounted on the fourth mounting plate;
the first mounting plate, the second mounting plate, the third mounting plate and the fourth mounting plate are connected with one another to form a pipe frame main body for surrounding a fresh air pipeline; first arc clamp splice second arc clamp splice third arc clamp splice with fourth arc clamp splice all is located in the pipe support main part for clip the new trend pipeline jointly.
2. The pipe support for installing a fresh air pipeline according to claim 1, wherein the first mounting plate is provided with a first sliding groove along a length direction thereof, the first sliding groove is provided with a first sliding rod capable of sliding vertically freely therein, one end of the first sliding rod is fixedly connected with the first fixing plate, the other end of the first sliding rod penetrates through the first sliding groove to be connected with a first circular plate, a diameter of the first circular plate is larger than a width of the first sliding groove, the first mounting plate is provided with a first threaded hole, the first threaded hole is provided with a plurality of first threaded holes and distributed along the length direction of the first sliding groove, the first circular plate is provided with a second threaded hole, the second threaded hole and the first threaded hole are provided with a first bolt together, and when the first mounting plate needs to be fixed, the first bolt is in threaded connection with the second threaded hole and is in threaded connection with the first threaded hole after penetrating through the second threaded hole.
3. The fresh air pipeline installation pipe support according to claim 2, wherein the second installation plate is provided with a first fixing block, the first fixing block is provided with a third threaded hole, the third threaded hole and the first threaded hole are jointly provided with a second bolt, and when the second installation plate needs to be fixed, the second bolt is in threaded connection with the third threaded hole, penetrates through the third threaded hole and then is in threaded connection with the first threaded hole.
4. The fresh air pipeline installation pipe support according to claim 2, wherein the third installation plate is provided with a second fixed block, the second fixed block is provided with a fourth threaded hole, the fourth threaded hole and the first threaded hole are jointly provided with a third bolt, and when the third installation plate needs to be fixed, the third bolt is in threaded connection with the fourth threaded hole, penetrates through the fourth threaded hole and then is in threaded connection with the first threaded hole.
5. The pipe support for installing the fresh air pipeline according to claim 1, wherein a second sliding groove is formed in the second installation plate along the length direction of the second installation plate, a second sliding rod capable of sliding vertically freely is arranged in the second sliding groove, one end of the second sliding rod is fixedly connected with the second fixing plate, the other end of the second sliding rod penetrates through the second sliding groove and is connected with a second circular plate, the diameter of the second circular plate is larger than the width of the second sliding groove, the second sliding rod is provided with an external thread and two first nuts are sleeved with the external thread and the threads, and the two first nuts are respectively located on the upper side and the lower side of the second installation plate so as to lock the second sliding rod.
6. The fresh air duct installation pipe support according to claim 1, wherein the fourth mounting plate is provided with a fifth screw hole and a sixth screw hole, the second mounting plate is provided with a seventh screw hole, the third mounting plate is provided with an eighth screw hole, the fifth screw hole and the seventh screw hole are jointly provided with a fourth bolt, the sixth screw hole and the eighth screw hole are jointly provided with a fifth bolt, when the fourth mounting plate needs to be fixed, the fourth bolt is in threaded connection with the fifth screw hole, penetrates through the fifth screw hole and then is in threaded connection with the seventh screw hole, and the fifth bolt is in threaded connection with the sixth screw hole, penetrates through the sixth screw hole and then is in threaded connection with the eighth screw hole.
7. The pipe support for installing the fresh air pipeline according to claim 2, wherein the first sliding groove is provided with a third sliding rod which can freely slide up and down in the first sliding groove, one end of the third sliding rod is rotatably connected with the first arc-shaped clamping block, the other end of the third sliding rod is connected with a third circular plate, the diameter of the third circular plate is larger than the width of the first sliding groove, the third sliding rod is provided with an external thread, two second nuts are sleeved on the third sliding rod through the external thread, and the two second nuts are respectively positioned on two symmetrical sides of the first mounting plate to lock the third sliding rod.
8. The pipe support for installing the fresh air pipeline according to claim 5, wherein the second sliding groove is provided with a fourth sliding rod which can slide up and down freely in the second sliding groove, one end of the fourth sliding rod is rotatably connected with the second arc-shaped clamping block, the other end of the fourth sliding rod is connected with a fourth circular plate, the diameter of the fourth circular plate is larger than the width of the second sliding groove, the fourth sliding rod is provided with an external thread, two third nuts are sleeved on the external thread, and the two third nuts are respectively positioned on two symmetrical sides of the second mounting plate so as to lock the fourth sliding rod.
9. The pipe support for installing the fresh air pipeline according to claim 1, wherein the third mounting plate is provided with two through holes, the third arc-shaped clamping block is hinged with two push rods which are symmetrically distributed, one end of each push rod, which is far away from the third arc-shaped clamping block, penetrates through the through hole and then is connected with a fifth circular plate, the diameter of each fifth circular plate is larger than that of the through hole, the fifth circular plate is provided with a plurality of ninth threaded holes which are distributed in a circumferential array manner, the third mounting plate is provided with a tenth threaded hole corresponding to the ninth threaded hole, the ninth threaded hole and the tenth threaded hole are jointly provided with a sixth bolt, and when the third arc-shaped clamping block needs to be fixed, the sixth bolt is in threaded connection with the ninth threaded hole and penetrates through the ninth threaded hole and then is in threaded connection with the tenth threaded hole.
10. The pipe support for installing the fresh air pipeline according to claim 1, wherein an eleventh threaded hole is formed in the fourth mounting plate, the eleventh threaded hole is provided with a seventh bolt, one end of the seventh bolt is connected with a sixth circular plate, the other end of the seventh bolt penetrates through the eleventh threaded hole to be rotatably connected with the second arc-shaped clamping block, the diameter of the sixth circular plate is larger than that of the eleventh threaded hole, two fourth nuts are sleeved on the seventh bolt in a threaded manner, and the two fourth nuts are respectively located on two symmetrical sides of the fourth mounting plate to lock the seventh bolt.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202221537071.1U CN217685631U (en) | 2022-06-20 | 2022-06-20 | Pipe support is used in fresh air pipeline installation |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202221537071.1U CN217685631U (en) | 2022-06-20 | 2022-06-20 | Pipe support is used in fresh air pipeline installation |
Publications (1)
Publication Number | Publication Date |
---|---|
CN217685631U true CN217685631U (en) | 2022-10-28 |
Family
ID=83711300
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202221537071.1U Active CN217685631U (en) | 2022-06-20 | 2022-06-20 | Pipe support is used in fresh air pipeline installation |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN217685631U (en) |
-
2022
- 2022-06-20 CN CN202221537071.1U patent/CN217685631U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN207935711U (en) | Adjustable mounting rack and range hood | |
CN217685631U (en) | Pipe support is used in fresh air pipeline installation | |
CN217522525U (en) | Municipal works interlude cable special stand | |
CN220817188U (en) | Display screen installing support | |
CN220191623U (en) | A air release machine for cold region greenhouse | |
CN210431308U (en) | Novel solar cell panel support | |
CN205778441U (en) | A kind of scalable body of wall mounting bracket of tubular screen rolling machine | |
CN220523829U (en) | Projector fixing device | |
CN220830215U (en) | Adjustable support for mounting contactor in power cabinet | |
CN213178603U (en) | Cabinet air conditioner base with adjustable | |
CN221177156U (en) | Light cable support and hanger | |
CN221380389U (en) | Cable hanger | |
CN218472686U (en) | Pipeline auxiliary positioning device for electromechanical engineering | |
CN220152046U (en) | Support assembly | |
CN110578834A (en) | Multidirectional regulation support | |
CN221929280U (en) | Support frame structure of building wiring | |
CN220551556U (en) | Flow valve with stable installation | |
CN221075540U (en) | Heating and ventilation pipeline mounting bracket | |
CN219796394U (en) | Sliding pipe support for multidirectional horizontal pipeline | |
CN220749582U (en) | Mounting structure and cloud computing terminal | |
CN218534236U (en) | Anchor clamps are used in electromechanical engineering construction | |
CN220980502U (en) | Pipe clamp | |
CN217178068U (en) | Mounting bracket with adjusting structure | |
CN221839271U (en) | Projector bracket | |
CN220045473U (en) | Stage is placed to sightseeing plant area lamp |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |