CN217679075U - Recyclable hanging rib for drilled pile reinforcement cage - Google Patents

Recyclable hanging rib for drilled pile reinforcement cage Download PDF

Info

Publication number
CN217679075U
CN217679075U CN202221253168.XU CN202221253168U CN217679075U CN 217679075 U CN217679075 U CN 217679075U CN 202221253168 U CN202221253168 U CN 202221253168U CN 217679075 U CN217679075 U CN 217679075U
Authority
CN
China
Prior art keywords
reinforcement
big rings
connecting reinforcement
bar
recyclable
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202221253168.XU
Other languages
Chinese (zh)
Inventor
代永海
郑宇浩
章超平
杨国富
陈浩
田新国
齐世超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Third Construction Engineering Co Ltd of China Construction Second Engineering Bureau Co Ltd
Original Assignee
Third Construction Engineering Co Ltd of China Construction Second Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Third Construction Engineering Co Ltd of China Construction Second Engineering Bureau Co Ltd filed Critical Third Construction Engineering Co Ltd of China Construction Second Engineering Bureau Co Ltd
Priority to CN202221253168.XU priority Critical patent/CN217679075U/en
Application granted granted Critical
Publication of CN217679075U publication Critical patent/CN217679075U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02WCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO WASTEWATER TREATMENT OR WASTE MANAGEMENT
    • Y02W30/00Technologies for solid waste management
    • Y02W30/50Reuse, recycling or recovery technologies
    • Y02W30/80Packaging reuse or recycling, e.g. of multilayer packaging

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses a drilling pile steel reinforcement cage hanging bar of circulated use, including big rings, the cross-section semicircular in shape of big rings, the quantity of big rings sets up to two, two big rings are located the bilateral symmetry setting, the one end fixedly connected with that big rings were kept away from mutually is the first connecting reinforcement of vertical state, the little lifting hook of one end fixedly connected with of big rings is kept away from to first connecting reinforcement, the one end fixedly connected with that big rings are close to mutually is the second connecting reinforcement of vertical state, the length of second connecting reinforcement is less than the length of first connecting reinforcement, fixed mounting has a plurality of connecting blocks between the outer anchor ring of upper portion front side of first connecting reinforcement and the outer anchor ring of front side of second connecting reinforcement, the middle part fixed mounting of connecting block front side has the stub bar. The utility model discloses at the in-process that uses, reducible former material is extravagant, reduces engineering cost, and can more conveniently use, helps improving the efficiency of construction.

Description

Recyclable hanging rib for drilled pile reinforcement cage
Technical Field
The utility model relates to a steel reinforcement cage hangs the muscle field, specifically is a drilling pile steel reinforcement cage who recycles hangs muscle.
Background
The bored pile is divided into a bored pile and an excavated pile, and is mainly used for engineering construction, the pile can be divided into the bored pile and the excavated pile according to a hole forming mode, the excavated pile adopts manual excavation, and the bored pile adopts mechanical hole forming.
In the process of putting down a pile foundation bored pile steel reinforcement cage, a hanging rib needs to be arranged on a cage top main rib, the hanging rib is fixed on the top surface of a pile casing through square timber and a supporting steel pipe (penetrating rod), the traditional hanging rib using mode is all that the hanging rib is manufactured on site and welded on the main rib, the hanging rib is used at one time, material waste is easily caused, the on-site welding time is increased, the construction cost and the construction quality of a bored pile are influenced, and then the construction quality and the cost of the bored pile are effectively controlled by improving the hanging rib construction technology, so that the hanging rib construction technology is very necessary.
We have therefore proposed a recyclable drilled pile cage bar.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a drilling pile steel reinforcement cage hanging bar of circulated use to solve the problem that provides among the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme:
the cross-section semicircular in shape of big rings, the quantity of big rings sets up to two, two big rings are located the bilateral symmetry and set up, the one end fixedly connected with that big rings were kept away from mutually is the first connecting reinforcement of vertical state, the little lifting hook of one end fixedly connected with that big rings were kept away from to first connecting reinforcement, the one end fixedly connected with that big rings are close to mutually is the second connecting reinforcement of vertical state, the length of second connecting reinforcement is less than the length of first connecting reinforcement, fixed mounting has a plurality of connecting blocks between the upper portion front side outer anchor ring of first connecting reinforcement and the front side outer anchor ring of second connecting reinforcement, the middle part fixed mounting of connecting block front side has the stub bar.
As a further aspect of the present invention: the connecting blocks are in a horizontal state, are positioned on the outer ring surfaces of the front sides of the first connecting reinforcing steel bars and the second connecting reinforcing steel bars and are arranged along the vertical direction, and the short reinforcing steel bars are in a horizontal state.
By adopting the technical scheme: the setting of connecting block for can be better install and fix the short reinforcement, and then make and guarantee this use of hanging that the muscle is better.
As a further aspect of the present invention: and a reinforcing hoop is arranged between the inner ring surfaces of the small lifting hooks on the two sides, and the reinforcing hoop is in a circular ring shape.
By adopting the technical scheme: the arrangement of the reinforcing hoop enables the hanging rib to be better recycled.
As a further aspect of the present invention: and a reinforcement cage is fixedly arranged on the outer ring surface of the reinforcement hoop and is in a vertical state.
By adopting the technical scheme: the arrangement of the steel reinforcement cage enables the operation to be better guaranteed.
As a further aspect of the present invention: the two sides of the big hanging ring are provided with skids which are arranged in a horizontal state.
By adopting the technical scheme: the arrangement of the skid can further contribute to the use of the hanging bar.
As a further aspect of the present invention: the upper surface of the skid is provided with a through bar, and the through bar and the skid are vertical to each other.
By adopting the technical scheme: the arrangement of the penetrating bar is beneficial to the use of the hanging bar under the support of the skid.
As a further aspect of the present invention: the penetrating bars are positioned on two sides and are correspondingly arranged, and the penetrating bars penetrate through the corresponding connecting blocks.
By adopting the technical scheme: the through bar is arranged between the connecting blocks, so that the through bar can better assist the hanging rib to use.
Compared with the prior art, the beneficial effects of the utility model are that:
1. the utility model discloses in, this hangs muscle convenient for material collection in the in-process of preparation, simple manufacture can use repeatedly, and then makes the reducible former material of in-process of preparation extravagant, reduces engineering cost, and former ground elevation is higher, hangs the muscle longer more, and material cost is higher, and the bored pile quantity is more, and the device's economic effect is just more obvious, and should hang muscle preparation, installation, demolish all simpler, can reduce steel reinforcement cage installation time with the tradition hangs the muscle welding phase, improves the efficiency of construction.
2. The utility model discloses in, to the damage of pile body when can reducing the pile head and abolish, the tradition hangs the muscle and stays the pile body into pile back part and hangs the muscle, and mechanical equipment digs when the foundation ditch excavation hangs the muscle and exposes the pile body part and draw hard to destroy the pile head and influence the pile body quality, use steel reinforcement cage to hang the muscle device and can effectively avoid this kind of phenomenon.
Drawings
Fig. 1 is a schematic view of the construction of a recyclable bored pile cage suspension bar of the present invention;
fig. 2 is a left side view of a recyclable bored pile cage suspension bar of the present invention;
FIG. 3 is a schematic view of the front view of the present invention in use;
fig. 4 is a schematic diagram of the left side view in the use of the present invention.
Description of the reference numerals:
1. a large hoisting ring; 2. a small hook; 3. short reinforcing steel bars; 4. a first connecting bar; 5. a second connecting reinforcement; 6. connecting blocks; 7. wood padding; 8. penetrating a bar; 9. a reinforcing hoop; 10. and (4) a reinforcement cage.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Please refer to fig. 1-4, the utility model provides a drilling pile steel reinforcement cage who can recycle hangs muscle, including big rings 1, the cross-section semicircular in shape of big rings, the quantity of big rings sets up to two, and two big rings are located the bilateral symmetry and set up, and the one end fixedly connected with that two big rings 1 kept away from mutually is the first connecting reinforcement 4 of vertical state, and the little lifting hook 2 of one end fixedly connected with that big rings 1 was kept away from to first connecting reinforcement 4, and the one end fixedly connected with that big rings 1 is close to mutually is the second connecting reinforcement 5 of vertical state. The length of second connecting reinforcement 5 is less than the length of first connecting reinforcement 4, and fixed mounting has a plurality of connecting blocks 6 between the outer anchor ring of upper portion front side of first connecting reinforcement 4 and the outer anchor ring of front side of second connecting reinforcement 5, and the middle part fixed mounting of the 6 front sides of connecting block has short reinforcing bar 3. This hangs muscle convenient for material selection at the in-process of preparation, simple manufacture can use repeatedly, and then makes the reducible raw materials of in-process at the preparation extravagant, reduces engineering cost, and former ground elevation is higher, hangs the muscle longer, and material cost is higher, and the drilling stake quantity is more, and the device's economic effect is just more obvious, and should hang muscle preparation, installation, demolish all simpler, can reduce steel reinforcement cage 10's installation time with traditional hanging muscle welding compares, improves the efficiency of construction.
Wherein, connecting block 6 is the horizontality to the outside anchor ring in front side that is located first connecting reinforcement 4 and second connecting reinforcement 5 is arranged along vertical direction, and stub bar 3 is the horizontality, and connecting block 6 makes can be better install and fix stub bar 3, and then makes and to guarantee this use of hanging that the muscle is better. The reinforcing hoops 9 are arranged between the inner ring surfaces of the small lifting hooks 2 on the two sides, the reinforcing hoops 9 are annular, and the reinforcing hoops 9 can better recycle the lifting rib; strengthen hoop 9 outer circumferencial fixed mounting have steel reinforcement cage 10, and steel reinforcement cage 10 is vertical state, and steel reinforcement cage 10 makes going on of assurance work that can be better.
Furthermore, two sides of the large hanging ring 1 are provided with the skids 7, the skids 7 are arranged in a horizontal state, and the skids 7 can further contribute to the use of the hanging bar. The upper surface of the skid 7 is provided with a through bar 8, the through bar 8 and the skid 7 are in a mutually vertical state, and the through bar 8 is used for supporting the skid 7, so that the use of the hanging bar is facilitated. The penetrating bar 8 is located both sides and is corresponding setting, and the penetrating bar 8 runs through between corresponding connecting block 6, and the penetrating bar 8 is located between the connecting block 6 so that the penetrating bar 8 can be better help this to hang the muscle and use.
The utility model discloses a theory of operation does: the utility model discloses a drilling pile steel reinforcement cage hoisting bar that can recycle is provided with big rings 1, when the installation hoisting bar was transferred, the crane was broken out and is connected with big rings 1, hoisting bar afterbody small lifting hook 2 hooks steel reinforcement cage 10 first way and strengthens the hoop, hoist and put steel reinforcement cage 10, form the sash between the adjacent connecting block 6 of arranging on first connecting reinforcement 4 on the hoisting bar and the second connecting reinforcement 5, hang to suitable position after, will wear in the thick stick 8 penetrates the sash, and then fixed steel reinforcement cage 10, when concrete placement to afterbody lifting hook below, demolish the hoisting bar, the circulation is used to next drilling pile.
When the reinforcement cage 10 is installed, the length of the hanging rib is calculated in advance, the hanging rib device with the most appropriate length is selected according to the calculation result, the length of the hanging rib is adjusted through the hanging frame, and the height of the hanging rib is accurately adjusted by utilizing a wedge block which is additionally arranged between the skid 7 and the penetrating rod 8, so that the length requirement of the hanging rib is met. With steel reinforcement cage 10 and first reinforcement hoop 9 welding firm, when hanging the muscle installation, will hang muscle afterbody small lifting hook 2 from steel reinforcement cage 10 inboard hang reinforcement hoop 9 can, treat steel reinforcement cage 10 complete hand-hole after, will wear thick stick 8 to penetrate and hang in the muscle hangs the frame, wear thick stick 8 and protect a square timber of laying in the outside at the steel, suspend fixed steel reinforcement cage 10 in midair, it is firm whether to need to inspect reinforcement hoop and main muscle welding in advance in the muscle installation, hang the muscle installation under the circumstances of guaranteeing safety.
When concrete is poured below the first reinforcing hoop 9, namely below the small lifting hook 2, the skid 7 and the penetrating rod 8 are loosened, the hanging rib is lifted out of the pile hole and placed well, so that the next drilled pile can be used, and after the hanging rib is lifted out, residual concrete is continuously poured to the designed elevation.
The above, only be the concrete implementation of the preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art is in the technical scope of the present invention, according to the technical solution of the present invention and the utility model, the concept of which is equivalent to replace or change, should be covered within the protection scope of the present invention.

Claims (7)

1. The utility model provides a drilling pile steel reinforcement cage of circulated use hangs muscle, includes big rings (1), its characterized in that: the cross-section semicircular in shape of big rings (1), the quantity of big rings (1) sets up to two, two big rings (1) are located bilateral symmetry and set up, the one end fixedly connected with that big rings (1) kept away from mutually is first connecting reinforcement (4) of vertical state, the little lifting hook (2) of one end fixedly connected with that big rings (1) were kept away from in first connecting reinforcement (4), the one end fixedly connected with that big rings (1) are close to mutually is second connecting reinforcement (5) of vertical state, the length of second connecting reinforcement (5) is less than the length of first connecting reinforcement (4), fixed mounting has a plurality of connecting blocks (6) between the outer anchor ring of the upper portion front side of first connecting reinforcement (4) and the outer anchor ring of the front side of second connecting reinforcement (5), the middle part fixed mounting of connecting block (6) front side has reinforcing bar short (3).
2. A recyclable drilled pile cage suspension bar as claimed in claim 1 wherein: the connecting block (6) is in a horizontal state and is positioned on the front outer ring surface of the first connecting reinforcing steel bars (4) and the front outer ring surface of the second connecting reinforcing steel bars (5) are arranged in the vertical direction, and the short reinforcing steel bars (3) are in a horizontal state.
3. A recyclable drilled pile cage suspension bar as claimed in claim 1 wherein: and a reinforcing hoop (9) is arranged between the inner annular surfaces of the small lifting hooks (2) positioned at two sides, and the reinforcing hoop (9) is in a circular ring shape.
4. A recyclable drilled pile cage suspension bar as claimed in claim 3 wherein: and a reinforcement cage (10) is fixedly mounted on the outer annular surface of the reinforcing hoop (9), and the reinforcement cage (10) is in a vertical state.
5. A recyclable drilled pile cage bar as claimed in claim 1 wherein: both sides of the large lifting ring (1) are provided with skids (7), and the skids (7) are arranged in a horizontal state.
6. A recyclable drilled pile cage suspension bar as claimed in claim 5 wherein: and a penetrating rod (8) is arranged on the upper surface of the skid (7), and the penetrating rod (8) and the skid (7) are in a mutually vertical state.
7. A recyclable drilled pile cage suspension bar as claimed in claim 6 wherein: the penetrating bars (8) are correspondingly arranged on two sides, and the penetrating bars (8) penetrate through the corresponding connecting blocks (6).
CN202221253168.XU 2022-05-24 2022-05-24 Recyclable hanging rib for drilled pile reinforcement cage Active CN217679075U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221253168.XU CN217679075U (en) 2022-05-24 2022-05-24 Recyclable hanging rib for drilled pile reinforcement cage

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221253168.XU CN217679075U (en) 2022-05-24 2022-05-24 Recyclable hanging rib for drilled pile reinforcement cage

Publications (1)

Publication Number Publication Date
CN217679075U true CN217679075U (en) 2022-10-28

Family

ID=83741490

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221253168.XU Active CN217679075U (en) 2022-05-24 2022-05-24 Recyclable hanging rib for drilled pile reinforcement cage

Country Status (1)

Country Link
CN (1) CN217679075U (en)

Similar Documents

Publication Publication Date Title
CN107299643B (en) Steel lattice column combined type tower crane foundation structure in foundation pit and construction method
CN106120839B (en) A kind of construction technology of off-lying sea blower foundation embedded rock pile
CN104947654B (en) Complicated water area inclined rock face large-diameter cast-in-place pile construction method
CN102191777B (en) Steel sheet pile coefferdam structure and topdown construction method thereof
CN205712137U (en) Foundation pit supporting construction
CN108978644A (en) Energy saving and environment friendly bored pile construction method
CN111560962A (en) Backfill area foundation pit supporting structure and construction method thereof
CN102644290A (en) Steel cofferdam construction method suitable for construction of deep silt layer bridge in shallow sea area
CN105133575A (en) Suspended formwork supporting device for casting lining on surface of underground continuous wall and construction method
KR101311803B1 (en) Slurry wall underpinning construction method using underpinning concrete tube with uneven surface
CN101962946A (en) Method for arranging hoisting points and floating-supported conduit frame with skirt pile sleeves
CN213804905U (en) Bailey beam suspension structure
CN203160254U (en) Pit support structure
CN208309581U (en) Anti-collapse aperture apparatus
CN217679075U (en) Recyclable hanging rib for drilled pile reinforcement cage
CN204780870U (en) Complicated waters slope scar major diameter drilling bored concrete pile
CN209923935U (en) Co-location combined pile wall supporting structure in upper-soft and lower-hard stratum
CN108221954B (en) Easy-to-detach prefabricated underground diaphragm wall, lifting appliance and construction method
CN217325391U (en) Construction tool for high-speed rail line deep foundation pit secant pile
CN202131602U (en) Steel sheet pile cofferdam structure
CN215562600U (en) Lattice column bored concrete pile steel column positioner
CN211690397U (en) Anti-floating single-wall steel hanging box
CN213508424U (en) Water-rich stratum gravel filtering pile tip drilling cast-in-place pile
CN210530848U (en) Large-span small-clear-distance asymmetric section tunnel supporting structure in loess region
CN106988361A (en) Pick machine is repaiied in a kind of square hole stake

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant