CN217671176U - Production equipment for sealing and filling conjoined extraction tube - Google Patents

Production equipment for sealing and filling conjoined extraction tube Download PDF

Info

Publication number
CN217671176U
CN217671176U CN202221831322.7U CN202221831322U CN217671176U CN 217671176 U CN217671176 U CN 217671176U CN 202221831322 U CN202221831322 U CN 202221831322U CN 217671176 U CN217671176 U CN 217671176U
Authority
CN
China
Prior art keywords
base
positioning
extraction tube
installation
push rod
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202221831322.7U
Other languages
Chinese (zh)
Inventor
王伟
阮佳浩
何旭杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shaoxing Shangyu Dongshan Precision Plastic Co ltd
Original Assignee
Shaoxing Shangyu Dongshan Precision Plastic Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shaoxing Shangyu Dongshan Precision Plastic Co ltd filed Critical Shaoxing Shangyu Dongshan Precision Plastic Co ltd
Priority to CN202221831322.7U priority Critical patent/CN217671176U/en
Application granted granted Critical
Publication of CN217671176U publication Critical patent/CN217671176U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Automatic Assembly (AREA)

Abstract

The utility model discloses a seal production facility of filling disjunctor extraction tube relates to extraction tube production technical field. Including the equipment base, equipment base intermediate position movable mounting has the drive shaft, and drive shaft upper end fixed mounting has the drive revolving stage, and installation opening has been seted up at drive revolving stage edge, and movable mounting has a locating component in the installation opening, and locating component includes first constant head tank, second constant head tank, location base, loose axle and drive sailboard, and drive revolving stage top is equipped with hold-down mechanism, and hold-down mechanism includes locating support, installation screw, installation base, hydraulic push rod and compresses tightly the briquetting. The motor that can drive the drive shaft through in the equipment base after the extraction tube subassembly is arranged in on the location base is rotatory, can remove the extraction tube subassembly to the hold-down mechanism below after the drive shaft is rotatory, can start hydraulic push rod after the extraction tube subassembly removes the hold-down mechanism below, compress tightly the briquetting and will move down after starting hydraulic push rod to assemble the extraction tube subassembly.

Description

Production equipment for sealing and filling conjoined extraction tube
Technical Field
The utility model relates to an extraction tube production technical field, in particular to seal production facility of filling disjunctor extraction tube.
Background
The traditional pre-sealed filling extraction tube is made of common PE (polyethylene), the effective period is only one year, the solution volatilizes quickly, the sensitivity and the product detection performance of the detection kit are seriously influenced, the volatilization of the solution can be effectively reduced by adopting the pre-filled extraction tube made of a high-barrier material, the effective period of the detection reagent is increased to two or even three years, good hand feeling and user experience are kept, the comfort of a customer during use is not influenced, and the performance of the detection kit is better ensured. The extraction tube consists of a tube body, a connecting band and a tube cap, and the tube body and the tube cap are required to be assembled on the connecting band body during production and processing, so that a composition device is required to rapidly assemble the tube body, the connecting band and the tube cap together.
SUMMERY OF THE UTILITY MODEL
The utility model discloses a main aim at provides a seal production facility of filling disjunctor extraction tube can effectively solve the problem of mentioning in the background art.
In order to achieve the above purpose, the utility model adopts the following technical scheme:
the utility model provides a seal production facility of filling disjunctor extraction tube, includes the equipment base, equipment base intermediate position movable mounting has the drive shaft, drive shaft upper end fixed mounting has the drive revolving stage, drive revolving stage edge has seted up the installation opening, movable mounting has locating component in the installation opening, locating component includes first constant head tank, second constant head tank, location base, loose axle and drive sailboard, loose axle movable mounting has seted up in the installation opening, fixed mounting has the location base on the loose axle, first constant head tank has been seted up on the location base, the second constant head tank has been seted up to lie in first constant head tank one side on the location base, location base bottom fixed mounting has the drive sailboard, be equipped with the extraction tube subassembly in first constant head tank and the second constant head tank, drive revolving stage top is equipped with hold-down mechanism, hold-down mechanism includes locating support, installation screw, installation base, hydraulic push rod and compresses tightly the briquetting, locating support fixed mounting is on the equipment base, locating support upper end department fixed mounting has the installation base, installation base intermediate position fixed mounting has the hydraulic push rod, drive revolving stage one side is equipped with the blowing mouth.
Furthermore, a movable hole is formed in the mounting opening, and the movable shaft is movably mounted in the mounting opening through the movable hole.
Furthermore, the positioning base is movably mounted in the mounting notch through a movable shaft, and the extracting tube assembly is positioned on the positioning base through a first positioning groove and a second positioning groove.
Furthermore, an installation screw hole is formed in the edge of the installation base, and a screw is arranged in the installation screw hole.
Furthermore, the mounting base is fixed on the positioning support through a screw, the hydraulic push rod is fixed on the positioning support through the mounting base, and the pressing block is fixed at the output tail end of the hydraulic push rod through threads.
Furthermore, the positioning assembly is arranged on the driving rotary table through an installation opening, and the driving rotary table is movably arranged above the equipment base through a driving shaft.
Compared with the prior art, the utility model discloses following beneficial effect has:
can arrange the extraction tube subassembly in during the use on the location base, the extraction tube subassembly can drive the drive shaft rotation through the motor in the equipment base after arranging in on the location base, can remove the extraction tube subassembly to the hold-down mechanism below after the drive shaft is rotatory, can start hydraulic push rod after the extraction tube subassembly removes the hold-down mechanism below, compress tightly the briquetting and will move down after starting hydraulic push rod to the extraction tube subassembly is assembled.
Drawings
FIG. 1 is a schematic view of the overall structure of the present invention;
fig. 2 is a schematic view of the pressing mechanism of the present invention;
FIG. 3 is a schematic view of the positioning assembly of the present invention;
fig. 4 is a schematic view of the extraction tube assembly of the present invention.
In the figure: 1. driving the turntable; 2. installing a gap; 3. a drive shaft; 4. an equipment base; 5. an extraction tube assembly; 6. a blowing nozzle; 7. a positioning assembly; 701. a first positioning groove; 702. a second positioning groove; 703. Positioning a base; 704. a movable shaft; 705. driving the sailboard; 8. a hold-down mechanism; 801. positioning the bracket; 802. mounting a screw hole; 803. installing a base; 804. a hydraulic push rod; 805. and (5) pressing the pressing block.
Detailed Description
In order to make the technical means, creation features, achievement purposes and functions of the present invention easy to understand, the present invention is further described below with reference to the following embodiments.
As shown in fig. 1-4, a production facility of filling disjunctor extraction tube seals, including equipment base 4, 4 intermediate position movable mounting of equipment base have drive shaft 3, 3 upper ends fixed mounting of drive shaft have drive revolving stage 1, 1 edge of drive revolving stage has seted up installation opening 2, movable mounting has locating component 7 in the installation opening 2, 1 top of drive revolving stage is equipped with hold-down mechanism 8, locating component 7 passes through installation opening 2 and installs on love drive revolving stage 1, drive revolving stage 1 passes through 3 movable mounting of drive shaft in 4 tops of equipment base.
Movable mounting has locating component 7 in installation opening 2, locating component 7 includes first constant head tank 701, second constant head tank 702, location base 703, loose axle 704 and drive sailboard 705, loose axle 704 movable mounting has in installation opening 2, fixed mounting has location base 703 on the loose axle 704, first constant head tank 701 has been seted up on the location base 703, lie in first constant head tank 701 one side on the location base 703 and seted up second constant head tank 702, location base 703 bottom fixed mounting has drive sailboard 705, be equipped with in first constant head tank 701 and the second constant head tank 702 and draw the tubular component 5, can arrange on location base 703 with drawing the tubular component 5 during the use, it is rotatory to drive shaft 3 through the motor in the equipment base 4 after arranging on location base 703 in to draw the tubular component 5, can remove after the drive shaft 3 is rotatory to draw the tubular component 5 to hold-down mechanism 8 below.
Drive revolving stage 1 top is equipped with hold-down mechanism 8, hold-down mechanism 8 includes locating support 801, installation screw 802, installation base 803, hydraulic rod 804 and compress tightly briquetting 805, locating support 801 fixed mounting is on equipment base 4, locating support 801 upper end department fixed mounting has installation base 803, installation base 803 intermediate position fixed mounting has hydraulic rod 804, hydraulic rod 804's department fixed mounting has compresses tightly briquetting 805, drive revolving stage 1 one side is equipped with blowing mouth 6, can start hydraulic rod 804 after extraction tube subassembly 5 moves to hold-down mechanism 8 below, it will downstream to compress tightly briquetting 805 after starting hydraulic rod 804, thereby will extract tube subassembly 5 and assemble.
It should be noted that, the utility model relates to a seal production facility of filling disjunctor extraction tube, when in actual use, at first arrange extraction tube subassembly 5 in on location base 703, extraction tube subassembly 5 can drive shaft 3 through the motor in the equipment base 4 rotatory after arranging in on location base 703, can remove extraction tube subassembly 5 to hold-down mechanism 8 below after drive shaft 3 is rotatory, can start hydraulic push rod 804 after extraction tube subassembly 5 moves to hold-down mechanism 8 below, because installation screw 802 has been seted up to installation base 803 edge, and be equipped with the screw in the installation screw 802, installation base 803 passes through the screw fixation on locating support 801, hydraulic push rod 804 is fixed on locating support 801 through installation base 803, it compresses tightly briquetting 805 through the output end of hydraulic push rod 804, so compress tightly the briquetting 805 will the downstream behind the start hydraulic push rod 804, thereby with body and cap in-press connection in-band, thereby will extract extraction tube subassembly 5 and assemble, can make location subassembly 7 move to blowing nozzle 6 after extracting 5 is assembled, be connected with the air pump on blowing nozzle 6, can make blowing nozzle 6 after extracting assembly, thereby make blowing nozzle 6 the rotatory base 703 of blowing nozzle drive and can drop, thereby the unloading can make the blowing nozzle drive during the unloading and can make the blowing nozzle.
Finally, it should be noted that: although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications may be made to the embodiments described in the foregoing embodiments, or equivalents may be substituted for elements thereof. Any modification, equivalent replacement, or improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (6)

1. The utility model provides a production facility of filling disjunctor extraction tube seals which characterized in that: the device comprises a device base (4), a driving shaft (3) is movably installed in the middle of the device base (4), a driving rotary table (1) is fixedly installed at the upper end of the driving shaft (3), an installation opening (2) is formed in the edge of the driving rotary table (1), a positioning assembly (7) is movably installed in the installation opening (2), the positioning assembly (7) comprises a first positioning groove (701), a second positioning groove (702), a positioning base (703), a movable shaft (704) and a driving sailboard (705), the movable shaft (704) is movably installed in the installation opening (2), the positioning base (703) is fixedly installed on the movable shaft (704), the first positioning groove (701) is formed in the positioning base (703), the second positioning groove (702) is formed in one side of the first positioning groove (701) on the positioning base (703), the driving sailboard (705) is fixedly installed at the bottom of the positioning base (703), an extraction pipe assembly (5) is arranged in the first positioning groove (701) and the second positioning groove (702), a pressing mechanism (8) is arranged above the driving rotary table (1), the pressing mechanism (802) comprises a pressing block (802), a pressing mechanism (802), a pressing block installing base (804) and a pressing mechanism (804), the positioning support (801) is fixedly installed on the equipment base (4), the upper end of the positioning support (801) is fixedly installed with an installation base (803), the middle of the installation base (803) is fixedly installed with a hydraulic push rod (804), the hydraulic push rod (804) is fixedly installed with a pressing block (805), and one side of the driving rotary table (1) is provided with an air blowing nozzle (6).
2. The production equipment of the sealed and filled conjoined extraction tube according to claim 1, wherein: a movable hole is formed in the mounting opening (2), and the movable shaft (704) is movably mounted in the mounting opening (2) through the movable hole.
3. The production equipment of the sealed and filled conjoined extraction tube according to claim 2, wherein: the positioning base (703) is movably arranged in the installation notch (2) through a movable shaft (704), and the extraction pipe assembly (5) is positioned on the positioning base (703) through a first positioning groove (701) and a second positioning groove (702).
4. The production equipment of the sealed and filled conjoined extraction tube according to claim 3, wherein: the edge of the mounting base (803) is provided with a mounting screw hole (802), and a screw is arranged in the mounting screw hole (802).
5. The production equipment of the sealed and filled conjoined extraction tube according to claim 4, wherein: the mounting base (803) is fixed on the positioning support (801) through screws, the hydraulic push rod (804) is fixed on the positioning support (801) through the mounting base (803), and the pressing block (805) is fixed at the output tail end of the hydraulic push rod (804) through threads.
6. The production equipment of the sealed and filled conjoined extraction tube according to claim 5, wherein: the positioning assembly (7) is arranged on the driving rotary table (1) through the installation gap (2), and the driving rotary table (1) is movably arranged above the equipment base (4) through the driving shaft (3).
CN202221831322.7U 2022-07-15 2022-07-15 Production equipment for sealing and filling conjoined extraction tube Active CN217671176U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221831322.7U CN217671176U (en) 2022-07-15 2022-07-15 Production equipment for sealing and filling conjoined extraction tube

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221831322.7U CN217671176U (en) 2022-07-15 2022-07-15 Production equipment for sealing and filling conjoined extraction tube

Publications (1)

Publication Number Publication Date
CN217671176U true CN217671176U (en) 2022-10-28

Family

ID=83717138

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221831322.7U Active CN217671176U (en) 2022-07-15 2022-07-15 Production equipment for sealing and filling conjoined extraction tube

Country Status (1)

Country Link
CN (1) CN217671176U (en)

Similar Documents

Publication Publication Date Title
CN217671176U (en) Production equipment for sealing and filling conjoined extraction tube
CN210969624U (en) Mould is used in processing of rubber gasket
CN213924494U (en) Glass cutter
CN1833955A (en) Sucking, cutting and sealing means of rubber membrane sealer
CN201070298Y (en) Meat grinder with function of producing tomato paste
CN116175135B (en) Glass door body compression fittings
CN2777008Y (en) Device for sucking cloth scraps and thread end of sewing machine
CN2928685Y (en) Sucking and cutting seal device for glue seal machine
CN206591356U (en) A kind of cloth automatic sampler
CN212954915U (en) Can retrieve ecological fertilizer fermenting installation who purifies to gas
CN201364933Y (en) Tooling equipment for sticking adhesive tape of flexible-packaging lithium ion battery
CN203599794U (en) Edge rolling and opening cutting device
CN210451420U (en) Laser cutting equipment with dust suction device
CN220322887U (en) Purification device capable of preparing sample
CN213079711U (en) Structure of punching stub bar in hardware punching die
CN203151295U (en) Motor
CN218046573U (en) Centrifugal extraction machine for plant nutrients
CN212352249U (en) Cutting device with cutter convenient to replace
CN211334402U (en) Automatic cutting device of notebook computer injection molding
CN213591343U (en) Belt cleaning device for traditional chinese medicine is separated to water extraction alcohol precipitation method
CN216441575U (en) Rim roll forming device
CN215356541U (en) Cutting machine for producing bicycle bell
CN221131336U (en) Vacuum unit oil filtering production equipment for producing rare earth metal and alloy
CN219886028U (en) Extrusion separation device for green plum wine production and fermentation
CN217324018U (en) Fermenting installation is used in white spirit production

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant