CN217621207U - Concrete slab's preparation mould - Google Patents
Concrete slab's preparation mould Download PDFInfo
- Publication number
- CN217621207U CN217621207U CN202220970676.3U CN202220970676U CN217621207U CN 217621207 U CN217621207 U CN 217621207U CN 202220970676 U CN202220970676 U CN 202220970676U CN 217621207 U CN217621207 U CN 217621207U
- Authority
- CN
- China
- Prior art keywords
- apron
- die carrier
- subplate
- concrete slab
- silo
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 239000000463 material Substances 0.000 claims 2
- 230000003014 reinforcing effect Effects 0.000 abstract description 7
- 230000002787 reinforcement Effects 0.000 description 5
- 239000004568 cement Substances 0.000 description 4
- 238000009415 formwork Methods 0.000 description 3
- 238000004519 manufacturing process Methods 0.000 description 3
- 229910001294 Reinforcing steel Inorganic materials 0.000 description 2
- 238000007599 discharging Methods 0.000 description 2
- 229910000831 Steel Inorganic materials 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 239000002994 raw material Substances 0.000 description 1
- 238000007790 scraping Methods 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
Images
Landscapes
- Manufacturing Of Tubular Articles Or Embedded Moulded Articles (AREA)
Abstract
The utility model relates to a concrete slab's preparation mould, including die carrier and apron, die carrier threaded connection has the apron, be equipped with connecting groove on the apron, the die carrier includes master module and subplate, the master module is connected with the subplate, and the master module is equipped with the die cavity, is equipped with first spacing hole in the die cavity, be equipped with the spacing hole of second on the subplate, the die carrier from left to right is equipped with the constant head tank in proper order, scrapes silo and row's silo, the apron passes through constant head tank, row's silo and die carrier joint. An object of the utility model is to use the utility model provides a preparation of concrete preparation mould has concrete slab of reinforcing bar net, through the spacing hole of first spacing hole and second on the die carrier for the relative position of fixed reinforcing bar net in concrete slab makes the concrete slab stable in shape who produces, and the bulk strength is high and application environment is extensive.
Description
Technical Field
The utility model relates to a technical field of building production, in particular to concrete slab's preparation mould.
Background
Most of the existing concrete is formed by pouring concrete into a mould and then standing, the concrete has the characteristics of abundant raw materials, low price and simple production process, and in order to improve the strength of the concrete, the concrete and steel bars are combined and matched, so that the application range of the concrete is wider; however, when a concrete slab with reinforcing steel bars is manufactured, the reinforcing steel bars are difficult to fix by the existing mold, so that the manufactured concrete slab is poor in strength and low in application environment.
Disclosure of Invention
In order to overcome the deficiency of the background art, the utility model discloses the technical scheme who adopts is: the utility model provides a concrete slab's preparation mould, includes die carrier and apron, die carrier threaded connection has the apron, be equipped with connecting slot on the apron, the die carrier includes master module and subplate, the master module is connected with the subplate, and the master module is equipped with the die cavity, is equipped with first spacing hole in the die cavity, be equipped with the spacing hole of second on the subplate, the die carrier from left to right is equipped with the constant head tank in proper order, scrapes silo and row's silo, the apron passes through constant head tank, row's silo and die carrier joint.
Furthermore, the auxiliary plate both ends are equipped with the locating piece, and the locating piece is equipped with the screw hole, the master module is equipped with the draw-in groove with the locating piece joint, and the auxiliary plate has the master module through screw hole threaded connection.
Further, the both sides of master module are equipped with the mounting panel, and the mounting panel is equipped with first mounting hole and second mounting hole, the subplate is through first mounting hole threaded connection in master module, and forms row's silo between subplate and the mounting panel, the apron passes through second mounting hole threaded connection on the mounting panel.
Furthermore, the cover plate is provided with positioning blocks at two ends, and when the cover plate is connected with the die carrier, the positioning blocks are respectively clamped in the positioning groove and the discharge groove.
Compared with the prior art, the beneficial effects of the utility model are that:
use the utility model provides a concrete preparation mould preparation has concrete slab of reinforcing bar net, through first spacing hole and the spacing hole of second on the die carrier for the relative position of fixed reinforcing bar net in concrete slab makes the concrete slab shape stability who produces, and the bulk strength is high and the application environment is extensive.
The embodiments of the present invention will be further explained with reference to the drawings.
Drawings
FIG. 1 is an exploded view of the structure of the present invention;
fig. 2 is a cross-sectional view of the present invention;
FIG. 3 is a front view of the subplate of the present invention;
fig. 4 is a schematic structural view of the formwork of the present invention for installing the reinforcing mesh;
FIG. 5 is a rear view of the cement in the middle screed leveling formwork of the present invention;
wherein: 1-mould frame, 2-cover plate, 3-reinforcing mesh, 4-scraper, 11-main template, 12-auxiliary plate, 13-mould cavity, 14-first limiting hole, 15-second limiting hole, 16-positioning groove, 17-scraper groove, 18-discharge groove, 19-mounting plate, 21-connecting clamping groove, 22-clamping block, 111-clamping groove, 121-positioning block, 122-threaded hole, 191-first mounting hole and 192-second mounting hole;
Detailed Description
As shown in fig. 1-3, a mold for manufacturing a concrete slab includes a mold frame 1 and a cover plate 2, the mold frame 1 is in threaded connection with the cover plate 2, the cover plate 2 is provided with a connecting clamping groove 21, the mold frame 1 includes a main mold plate 11 and an auxiliary mold plate 12, the main mold plate 11 is connected with the auxiliary mold plate 12, the main mold plate 11 is provided with a mold cavity 13, the mold cavity 13 is internally provided with a first limiting hole 14, the auxiliary mold plate 12 is provided with a second limiting hole 15, the mold frame 1 is sequentially provided with a positioning groove 16, a scraping groove 17 and a discharging groove 18 from left to right, and the cover plate 2 is clamped with the mold frame 1 through the positioning groove 16 and the discharging groove 18.
The two ends of the auxiliary board 12 are provided with positioning blocks 121, the positioning blocks 121 are provided with threaded holes 122, the main board 11 is provided with a clamping groove 111 clamped with the positioning blocks 121, and the auxiliary board 12 is in threaded connection with the main board 11 through the threaded holes 122. Mounting plates 19 are arranged on two sides of the main template 11, the mounting plates 19 are provided with first mounting holes 191 and second mounting holes 192, the auxiliary plate 12 is connected to the main template 11 through the first mounting holes 191 in a threaded mode, a discharge groove 18 is formed between the auxiliary plate 12 and the mounting plates 19, and the cover plate 2 is connected to the mounting plates 19 through the second mounting holes 192 in a threaded mode. Both ends are equipped with fixture block 22 on the apron 2, and when apron 2 was connected with die carrier 1, fixture block 22 joint was in constant head tank 16, row's silo 18 respectively.
As shown in fig. 4 and 5, before the concrete slab is manufactured, the mesh reinforcement 3 is installed in the cavity 13 through the first limiting hole 14, and is pre-installed on the secondary plate 12 through the second limiting hole 15, after the secondary plate 12 is connected with the main template 11, the mesh reinforcement 3 is suspended and fixed in the cavity 13, the stirred cement is added into the cavity 13 and passes through the mesh reinforcement 3, the scraper plate 4 is moved from the positioning groove 16 through the scraper groove 17 to the direction of the discharge groove 18, so that the scraper plate 4 levels the cement along the scraper groove 17, and the excess cement is discharged along the discharge groove 18, so that the cover plate 2 is attached and fixed with the formwork 1, the movable cover plate 2 is connected with the main template 11 through the connecting clamping groove 21, after the mould is set, the cover plate 2 and the secondary plate 12 are sequentially removed, so as to obtain the concrete slab containing the mesh reinforcement 3, and the exposed mesh reinforcement can be cut off as required, and the concrete slab is made into a regular cuboid; use the utility model provides a concrete preparation mould preparation has concrete slab of reinforcing bar net, through the spacing hole of first spacing hole 14 and the spacing hole of second 15 on the die carrier 1 for the relative position of fixed reinforcing bar net 3 in concrete slab makes the concrete slab stable in shape who produces, and bulk strength is high.
The skilled person should know that: although the present invention has been described in terms of the above embodiments, the inventive concepts are not limited thereto, and any modification that utilizes the inventive concepts will be within the scope of the patent claims.
Claims (4)
1. The utility model provides a concrete slab's preparation mould, includes die carrier (1) and apron (2), die carrier (1) threaded connection has apron (2), be equipped with connecting slot (21) on apron (2), its characterized in that, die carrier (1) includes master template (11) and subplate (12), master template (11) are connected with subplate (12), and master template (11) are equipped with die cavity (13), are equipped with first spacing hole (14) in die cavity (13), be equipped with spacing hole of second (15) on subplate (12), die carrier (1) from left to right is equipped with constant head tank (16) in proper order, scrapes silo (17) and arranges silo (18), apron (2) are through constant head tank (16), silo (18) and die carrier (1) joint.
2. A concrete panel making mould according to claim 1, characterized in that: locating blocks (121) are arranged at two ends of the auxiliary plate (12), threaded holes (122) are formed in the locating blocks (121), clamping grooves (111) clamped with the locating blocks (121) are formed in the main plate (11), and the auxiliary plate (12) is connected with the main plate (11) through the threaded holes (122) in a threaded mode.
3. A concrete panel making mould according to claim 2 wherein: the both sides of master module (11) are equipped with mounting panel (19), and mounting panel (19) are equipped with first mounting hole (191) and second mounting hole (192), subplate (12) are through first mounting hole (191) threaded connection in master module (11), and form between subplate (12) and mounting panel (19) arrange material groove (18), apron (2) are through second mounting hole (192) threaded connection on mounting panel (19).
4. A concrete panel making mould according to claim 3 wherein: both ends are equipped with locating piece (121) on apron (2), when apron (2) with when die carrier (1) is connected, locating piece (121) joint respectively in constant head tank (16), row material groove (18).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202220970676.3U CN217621207U (en) | 2022-04-22 | 2022-04-22 | Concrete slab's preparation mould |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202220970676.3U CN217621207U (en) | 2022-04-22 | 2022-04-22 | Concrete slab's preparation mould |
Publications (1)
Publication Number | Publication Date |
---|---|
CN217621207U true CN217621207U (en) | 2022-10-21 |
Family
ID=83648860
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202220970676.3U Expired - Fee Related CN217621207U (en) | 2022-04-22 | 2022-04-22 | Concrete slab's preparation mould |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN217621207U (en) |
-
2022
- 2022-04-22 CN CN202220970676.3U patent/CN217621207U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN210791422U (en) | Building block combined mould | |
CN216372666U (en) | Autoclaved aerated concrete production mold | |
CN217621207U (en) | Concrete slab's preparation mould | |
CN110027110A (en) | A kind of ring fastening type floats wall prefabricated mould and method for prefabricating outside window | |
CN216329003U (en) | External wall panel forming die | |
CN210375928U (en) | Self-vibration concrete test mould | |
CN209851193U (en) | Precast concrete wallboard mould with standard mould quantity mode of splicing panel | |
CN201002303Y (en) | Model for producing gypsum auxiliary building block | |
CN210551997U (en) | Adjustable concrete precast block mould | |
CN221291745U (en) | Adjustable L-shaped prefabricated part die | |
CN220322880U (en) | Adjustable cement sample preparation die | |
CN211622197U (en) | Steel bar truss floor support plate | |
CN219547678U (en) | Pointing-free integrated template | |
CN217597373U (en) | Mould for manufacturing masonry secondary structure prefabricated part | |
CN215702590U (en) | Novel wallboard mould | |
CN221186969U (en) | Prefabricated concrete block aluminum mould | |
CN219726665U (en) | Die device for construction of assembled wallboard | |
CN212888150U (en) | Be used for concrete truss coincide floor combined type mould fixing device | |
CN115233902B (en) | Assembled precast beam, forming die and processing technology of precast beam | |
CN214687114U (en) | Evaporate and press mould for aerated concrete test | |
CN211590611U (en) | Splicing type recyclable mold | |
CN220162756U (en) | Cement product mould | |
CN220725458U (en) | Superimposed shear wallboard | |
CN217579799U (en) | Large-scale bridge pier is with concatenation formula mould of pouring | |
CN214819443U (en) | Prefabricated mould for water retaining platform of pipe well |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20221021 |