CN217601744U - Construction joint waterproof construction - Google Patents
Construction joint waterproof construction Download PDFInfo
- Publication number
- CN217601744U CN217601744U CN202221089175.0U CN202221089175U CN217601744U CN 217601744 U CN217601744 U CN 217601744U CN 202221089175 U CN202221089175 U CN 202221089175U CN 217601744 U CN217601744 U CN 217601744U
- Authority
- CN
- China
- Prior art keywords
- baffle
- wall body
- block
- construction joint
- connecting block
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Building Environments (AREA)
Abstract
The application relates to the field of construction waterproof structures, in particular to a construction joint waterproof structure which comprises a first wall body, a second wall body, a first baffle plate, a second baffle plate, a water stop plate and a fixing assembly, wherein a construction joint is formed between the first wall body and the second wall body; the water stop plate is abutted against the surface of the first wall body and fixedly connected with the first wall body, and the water stop plate is abutted against the surface of the second wall body and fixedly connected with the second wall body; one end of the first baffle is fixedly connected with the first wall, one end of the second baffle is fixedly connected with the second wall, and the fixing assembly is used for fixing the first baffle and the second baffle together; the first baffle is abutted against the surface of the water stop plate, and the second baffle is abutted against the surface of the water stop plate. This application can restrict construction seam size grow.
Description
Technical Field
The application relates to construction waterproof construction field especially relates to a construction joint waterproof construction.
Background
The construction joint refers to a joint formed between the concrete which is poured in advance and then due to the design requirement or the requirement of segmental pouring in the concrete pouring process. The construction joint is not a real existing 'joint', and only because the initial setting time of the first poured concrete is longer than the initial setting time, a joint surface exists between the first poured concrete and the later poured concrete, and the joint surface is called as the construction joint.
With respect to the related art among the above, the inventors consider that the following drawbacks exist: when the wall body of construction joint both sides moves towards the direction of keeping away from each other, lead to construction seam mouth size grow easily to the phenomenon of leaking appears easily.
SUMMERY OF THE UTILITY MODEL
In order to restrict construction seam mouth size grow, this application provides a construction seam waterproof construction.
The application provides a construction joint waterproof construction adopts following technical scheme:
a construction joint waterproof structure comprises a first wall body, a second wall body, a first baffle, a second baffle, a water stop plate and a fixing assembly, wherein a construction joint is formed between the first wall body and the second wall body; the water stop plate is abutted against the surface of the first wall body and fixedly connected with the first wall body, and the water stop plate is abutted against the surface of the second wall body and fixedly connected with the second wall body; one end of the first baffle is fixedly connected with the first wall, one end of the second baffle is fixedly connected with the second wall, and the fixing assembly is used for fixing the first baffle and the second baffle together; the first baffle abuts against the surface of the water stop plate, and the second baffle abuts against the surface of the water stop plate.
By adopting the technical scheme, the water stop plate has a plugging effect on the construction joint, and can limit the water leakage of the construction joint; the first baffle and the second baffle are fixed together through the fixing assembly, so that the first wall body and the second wall body are fixed together, the first wall body and the second wall body can be limited to move towards the direction away from each other, and the construction joint can be limited from increasing; simultaneously first baffle and first wall body have the clamping action to the sealing plate, and second baffle and second wall body have the clamping action to the sealing plate simultaneously, have increased the fastness of sealing plate installation.
Optionally, the fixing assembly includes an insertion block and a first screw rod, the insertion block is fixed on the first baffle, an insertion groove is formed in the second baffle, the insertion block is inserted into the insertion groove, and the insertion block is in sliding fit with the insertion groove; the first screw rod is in threaded fit with the second baffle, and the end part of the first screw rod is abutted against the insertion block.
By adopting the technical scheme, the end part of the first screw rod and the second baffle have a clamping effect on the insertion block, so that the insertion block is fixed in the insertion groove, and the first baffle and the second baffle are connected together; after the staff relieved the fixed action of first screw rod to the grafting piece, the inserting groove has the guide effect to the grafting piece to make the stable slip of the length direction of grafting piece along the inserting groove, thereby make first baffle orientation be close to or keep away from the direction slip of second baffle.
Optionally, a first knob is fixedly arranged on the first screw rod.
Through adopting above-mentioned technical scheme, the staff rotates first screw rod through rotating first knob, has laborsaving effect.
Optionally, a first connecting block is fixedly arranged at one end of the first baffle, a side wall of the first connecting block abuts against a side wall of the first wall, and a first anti-falling groove is formed in the first connecting block; a first anti-falling block is fixedly arranged on the first wall body, the first anti-falling block penetrates through the first anti-falling groove, and the first connecting block is in sliding fit with the first anti-falling block; the first connecting block and the first anti-falling block are fixed through a fastener.
By adopting the technical scheme, a worker can detach the first connecting block from the first anti-falling block by releasing the fixing effect of the fastener on the first connecting block and then sliding the first connecting block along the length direction of the first anti-falling block, so that the first baffle is detached from the first wall body, and the convenience of the worker for installing and detaching the first baffle is improved; first connecting block is at gliding in-process, and first anticreep piece has the guide effect to first connecting block, has increased the gliding stability of first connecting block.
Optionally, the fastener is an angle steel, the angle steel includes a first angle side and a second angle side which are fixedly connected, the first angle side is perpendicular to the second angle side, the first angle side is fixedly connected with the first connecting block, and the second angle side is fixedly connected with the first anti-falling block.
Through adopting above-mentioned technical scheme, first angle limit and second angle limit have the fixed action to first connecting block to be fixed in first connecting block on the anticreep piece.
Optionally, a bolt is arranged on the first corner edge in a penetrating mode, and the bolt is in threaded fit with the first connecting block.
Through adopting above-mentioned technical scheme, increased the convenience that the staff installed and dismantled first angle limit.
Optionally, a second screw is in threaded fit with the second corner edge, and an end of the second screw abuts against a surface of the first anti-falling block.
By adopting the technical scheme, the friction force between the end part of the second screw and the first anti-falling block has a fixing effect on the second corner edge, so that the second corner edge is fixed on the first anti-falling block; the staff can be through rotatory second screw rod to make the second screw rod orientation keep away from the direction slip of first anticreep piece, thereby remove the fixed action of second screw rod to second angle limit, the staff of being convenient for adjusts the position of first connecting block along the length direction of first anticreep piece, thereby the staff of being convenient for adjusts the position of first baffle along the length direction of first anticreep piece.
Optionally, a gap exists between the first baffle and the second baffle, and a gap exists between the first connecting block and the water stop plate.
Through adopting above-mentioned technical scheme, the staff of being convenient for removes first baffle and second baffle orientation direction that is close to each other to drive first wall body and second wall body orientation direction that is close to each other and remove, thereby be convenient for reduce the width of construction joint.
In summary, the present application includes at least one of the following beneficial technical effects:
1. the water stop plate has a plugging effect on the construction joint, and can limit the water leakage of the construction joint; the first baffle and the second baffle are fixed together through the fixing assembly, so that the first wall body and the second wall body are fixed together, the first wall body and the second wall body can be limited to move towards the direction away from each other, and the construction joint can be limited from increasing; meanwhile, the first baffle and the first wall have a clamping effect on the water stop plate, and the second baffle and the second wall have a clamping effect on the water stop plate, so that the mounting firmness of the water stop plate is improved; 2. the end part of the first screw rod and the second baffle have a clamping effect on the inserting block, so that the inserting block is fixed in the inserting groove, and the first baffle and the second baffle are connected together; after the worker releases the fixing effect of the first screw rod on the inserting block, the inserting groove has a guiding effect on the inserting block so that the inserting block can stably slide along the length direction of the inserting groove, and the first baffle plate can slide towards the direction close to or far away from the second baffle plate;
3. the staff rotates first screw rod through rotating first knob, has laborsaving effect.
Drawings
Fig. 1 is a schematic structural diagram of a waterproof structure of a construction joint in an embodiment of the present application.
Fig. 2 is a partially enlarged view of a portion a in fig. 1.
Description of reference numerals:
1. a first wall; 11. a first anti-drop block; 2. a second wall; 21. a second anti-drop block; 3. constructing a joint; 4. a water stop plate; 5. A first baffle; 51. a first connection block; 52. a first drop-preventing groove; 6. a second baffle; 61. a second connecting block 7 and a fixing component; 71. an insertion block; 72. a first screw; 73. a first knob; 8. angle steel; 81. a first corner edge; 82. a second corner edge; 83. a second screw; 84. a second knob.
Detailed Description
The present application is described in further detail below with reference to figures 1-2.
A construction joint waterproof structure, refers to fig. 1, and comprises a first wall body 1, a second wall body 2 and a water stop plate 4. A construction joint 3 is formed between the first wall body 1 and the second wall body 2, the water stop plate 4 is abutted to the surface of the first wall body 1 and fixedly connected with the first wall body 1, and the water stop plate 4 is abutted to the surface of the second wall body 2 and fixedly connected with the second wall body 2. The water stop plate 4 has a plugging effect on the construction joint 3, so that the water leakage of the construction joint 3 can be prevented.
Referring to fig. 1 and 2, the construction joint waterproofing structure further includes a first barrier 5, a second barrier 6, and a fixing member 7. One end of the first baffle 5 is fixedly connected with the first wall body 1, one end of the second baffle 6 is fixedly connected with the second wall body 2, a gap exists between the first baffle 5 and the second baffle 6, and the fixing component 7 is used for fixing the first baffle 5 and the second baffle 6 together. The first baffle 5 abuts against the surface of the water stop plate 4, and the second baffle 6 abuts against the surface of the water stop plate 4. First baffle 5 and first wall body 1 have the clamping action to stagnant water board 4, and second baffle 6 and second wall body 2 have the clamping action to stagnant water board 4 simultaneously, have increased the fastness of stagnant water board 4 installation.
Referring to fig. 2, the fixing assembly 7 includes an insertion block 71 and a first screw 72, the insertion block 71 is integrally formed on a side wall of the first baffle 5 close to the second baffle 6, an insertion groove is formed on the second baffle 6, the insertion block 71 is inserted into the insertion groove, and the insertion block 71 is in sliding fit with the insertion groove. The first screw 72 is screwed to the second shutter 6, and the end of the first screw 72 abuts against the insertion block 71. The end of the first screw 72 and the second baffle 6 have a clamping effect on the insertion block 71, so that the insertion block 71 is fixed in the insertion groove, and the first baffle 5 and the second baffle 6 are connected together. The first screw 72 is fixedly provided with a first knob 73, and the worker rotates the first screw 72 by rotating the first knob 73, so that the labor-saving effect is achieved.
With reference to fig. 2, a first connecting block 51 is integrally formed at one end of the first baffle 5 away from the second baffle 6, a sidewall of the first connecting block 51 abuts against a sidewall of the first wall 1, and a gap exists between the first connecting block 51 and the water stop plate 4. The first connecting block 51 is provided with a first anti-drop groove 52 on the side wall close to the first wall 1, and both ends of the first anti-drop groove 52 are open. First wall body 1 is last to be fixed with first anticreep piece 11, and first anticreep piece 11 passes first anticreep groove 52, and first connecting block 51 and first anticreep piece 11 sliding fit. The first anti-slip block 11 is a dovetail block, and the first anti-slip groove 52 is a dovetail groove, so that the first connection block 51 can be prevented from moving away from the first wall 1.
With continued reference to fig. 2, the first connecting block 51 and the first anti-slip block 11 are fixed by a fastener. In the embodiment, the fastener is angle iron 8, and the angle iron 8 comprises a first angle edge 81 and a second angle edge 82 which are integrally formed, and the first angle edge 81 and the second angle edge 82 are perpendicular to each other. The sidewall of the first corner edge 81 abuts against the sidewall of the first connecting block 51, and the sidewall of the second corner edge 82 abuts against the sidewall of the first wall 1. The first corner edge 81 is provided with a bolt, and the bolt is in threaded fit with the first connecting block 51, so that the first corner edge 81 is fixed on the first connecting block 51. A second screw 83 is screwed to the second corner 82, and an end of the second screw 83 abuts against a surface of the first stopper 11. Frictional force between the end of the second screw 83 and the first anti-falling block 11 fixes the second corner 82 on the first anti-falling block 11, so that the worker can adjust the position of the first connecting block 51 along the direction of the first anti-falling block 11, and further the worker can adjust the position of the first baffle 5 along the length direction of the first anti-falling block 11.
With reference to fig. 2, the second screw 83 is fixedly provided with a second knob 84, and the worker rotates the second screw 83 by rotating the second knob 84, so that the labor-saving effect is achieved.
With reference to fig. 2, a second connecting block 61 is integrally formed at one end of the second baffle 6, which is far away from the first baffle 5, a side wall of the second connecting block 61 abuts against a side wall of the second wall 2, and a gap exists between the second connecting block 61 and the water stop plate 4. The second connecting block 61 has been offered the second anticreep groove near the lateral wall of second wall body 2, and the both ends in second anticreep groove all are the opening setting. The fixed second anticreep piece 21 that is provided with on the second wall body 2, second anticreep piece 21 passes second anticreep groove, and second connecting block 61 and the cooperation of sliding of second anticreep piece 21, second anticreep piece 21 are the dovetail piece, and the second anticreep groove is the dovetail to can prevent that the orientation of second connecting block 61 from keeping away from the direction removal of second wall body 2. The second connecting block 61 and the second anti-falling block 21 are fixed by the angle steel 8, and the specific fixing mode is not described herein.
The application principle of the construction joint waterproof structure of this application does: the water stop plate 4 has a plugging effect on the construction joint 3 and can limit the water leakage of the construction joint 3; the first baffle 5 and the second baffle 6 are fixed together through the fixing assembly 7, so that the first wall body 1 and the second wall body 2 are fixed together, the first wall body 1 and the second wall body 2 can be limited to move towards the direction away from each other, and the construction joint 3 can be limited to increase; simultaneously first baffle 5 and first wall body 1 have the clamping action to stagnant water board 4, and second baffle 6 and second wall body 2 have the clamping action to stagnant water board 4 simultaneously, have increased the fastness of stagnant water board 4 installation.
The above are preferred embodiments of the present application, and the scope of protection of the present application is not limited thereto, so: all equivalent changes made according to the structure, shape and principle of the present application shall be covered by the protection scope of the present application.
Claims (8)
1. The utility model provides a construction joint waterproof construction, includes first wall body (1) and second wall body (2), first wall body (1) with form construction joint (3) between second wall body (2), its characterized in that: the water-stopping device also comprises a first baffle (5), a second baffle (6), a water-stopping plate (4) and a fixing component (7); the water stop plate (4) is abutted against the surface of the first wall body (1) and fixedly connected with the first wall body (1), and the water stop plate (4) is abutted against the surface of the second wall body (2) and fixedly connected with the second wall body (2); one end of the first baffle plate (5) is fixedly connected with the first wall body (1), one end of the second baffle plate (6) is fixedly connected with the second wall body (2), and the fixing component (7) is used for fixing the first baffle plate (5) and the second baffle plate (6) together; the first baffle (5) is connected with the surface of the water stop plate (4) in an abutting mode, and the second baffle (6) is connected with the surface of the water stop plate (4) in an abutting mode.
2. A construction joint waterproofing structure according to claim 1, wherein: the fixing assembly (7) comprises an inserting block (71) and a first screw rod (72), the inserting block (71) is fixed on the first baffle plate (5), an inserting groove is formed in the second baffle plate (6), the inserting block (71) is inserted into the inserting groove, and the inserting block (71) is matched with the inserting groove in a sliding mode; the first screw (72) is in threaded fit with the second baffle (6), and the end of the first screw (72) abuts against the insertion block (71).
3. A construction joint waterproofing structure according to claim 2, wherein: a first knob (73) is fixedly arranged on the first screw rod (72).
4. A construction joint waterproofing structure as claimed in claim 1, wherein: a first connecting block (51) is fixedly arranged at one end of the first baffle (5), the side wall of the first connecting block (51) abuts against the side wall of the first wall body (1), and a first anti-falling groove (52) is formed in the first connecting block (51); a first anti-falling block (11) is fixedly arranged on the first wall body (1), the first anti-falling block (11) penetrates through the first anti-falling groove (52), and the first connecting block (51) is in sliding fit with the first anti-falling block (11); the first connecting block (51) and the first anti-falling block (11) are fixed through a fastener.
5. A construction joint waterproofing structure according to claim 4, wherein: the fastener is angle steel (8), angle steel (8) include fixed connection's first angle limit (81) and second angle limit (82), first angle limit (81) with second angle limit (82) mutually perpendicular, first angle limit (81) with first connecting block (51) fixed connection, second angle limit (82) with first anticreep piece (11) fixed connection.
6. A construction joint waterproofing structure according to claim 5, wherein: and a bolt penetrates through the first corner edge (81), and the bolt is in threaded fit with the first connecting block (51).
7. A construction joint waterproofing structure according to claim 6, wherein: and a second screw (83) is in threaded fit with the second corner edge (82), and the end part of the second screw (83) is abutted against the surface of the first anti-falling block (11).
8. A construction joint waterproofing structure according to claim 4, wherein: a gap exists between the first baffle (5) and the second baffle (6), and a gap exists between the first connecting block (51) and the water stop plate (4).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202221089175.0U CN217601744U (en) | 2022-05-07 | 2022-05-07 | Construction joint waterproof construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202221089175.0U CN217601744U (en) | 2022-05-07 | 2022-05-07 | Construction joint waterproof construction |
Publications (1)
Publication Number | Publication Date |
---|---|
CN217601744U true CN217601744U (en) | 2022-10-18 |
Family
ID=83566905
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202221089175.0U Active CN217601744U (en) | 2022-05-07 | 2022-05-07 | Construction joint waterproof construction |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN217601744U (en) |
-
2022
- 2022-05-07 CN CN202221089175.0U patent/CN217601744U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN207620299U (en) | A kind of cladding connector of back bolt type | |
JP6997795B2 (en) | Ceramic tile leveling brackets, push clamp pliers, and ceramic tile leveling and laying systems | |
KR101469709B1 (en) | Construction Masonry Brick Walls Coupling Apparatus | |
CN217601744U (en) | Construction joint waterproof construction | |
CN214785227U (en) | Basement roof reservation equipment hoist and mount mouth shutoff structure | |
CN214402771U (en) | Prevent leaking aluminium mould wall post root block structure of thick liquid | |
CN213571352U (en) | Edge-sealing angle steel device for pouring CA mortar into track slab | |
CN216360660U (en) | Flashboard connecting structure for river surface trestle approach hole | |
CN214657207U (en) | Abrupt slope road retaining wall | |
CN204397316U (en) | Sea tube connector clamping connection winding device | |
CN211923047U (en) | Water stopping device for concrete construction joint | |
CN212176906U (en) | Heat insulation window with stable installation structure | |
CN209457389U (en) | The temporary fastening device of casing for through-flooring pipeline | |
CN218398678U (en) | Drip forming die for lower surface of platform canopy | |
CN218204578U (en) | Anti-seepage device for raft foundation post-cast strip | |
CN216840341U (en) | Prevent to construct accessory device of caulking strip dislocation | |
CN210597804U (en) | Installation type roof installation structure | |
CN218207842U (en) | Pneumatic butterfly valve | |
CN215977784U (en) | Waterproof connecting piece of curtain | |
CN218779787U (en) | Grouting sleeve | |
CN219325935U (en) | Cleaning unmanned aerial vehicle capable of being clamped reliably | |
CN207714713U (en) | A kind of wall tiling positioning device | |
CN211777465U (en) | Subway embedded channel | |
CN209150653U (en) | A kind of dust-proof cable testing bridge of plug-in type | |
CN218127630U (en) | Cabinet door with embedded handle |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |