Prior art keywords
building
cladding
main body
groove
inserted block
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202220754368.7U
Other languages
Chinese (zh)
Inventor
刘俊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202220754368.7U priority Critical patent/CN217557219U/en
Application granted granted Critical
Publication of CN217557219U publication Critical patent/CN217557219U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses a building joins externally and building subject's connecting device relates to the building field, including building subject, one side of building subject is provided with the cladding, be provided with alignment mechanism between building subject and the cladding, alignment mechanism is including seting up the draw-in groove in building subject one side, the cladding is close to one side fixedly connected with inserted block of building subject, and the inside at the draw-in groove is pegged graft in the inserted block activity, the hollow groove has been seted up to one side of inserted block, the inserted block is located the inside fixedly connected with spring of hollow groove, the mode of the screw rod connection that the cladding material adopted among the prior art has been improved, very easily because of staff's hand cunning, and lead to taking place the problem of slope between cladding material and the building subject, alignment mechanism's setting in this device, make the staff install the cladding to building subject, can be more accurate alignment cladding, be difficult for the staff's hand cunning leads to the cladding to take place the circumstances such as sliding because of the cladding.

Description

Connecting device for building external hanging and building main body
Technical Field
The utility model relates to a building technical field, more specifically say, relate to a building joins externally with building subject's connecting device.
Background
The method refers to assets formed by artificial construction, belongs to the category of fixed assets, and comprises two categories of houses and structures. A house is an engineered building for people to live, work, study, produce, manage, entertain, store goods, and perform other social activities.
In the prior art, in order to make construction convenient enough, part of the building external hanging material is processed firstly and is connected with the building body through the screw, but the inclination between the external hanging material and the building body is easily caused by the smooth hand of workers in the screw installation mode, so that the originally processed external hanging material cannot be normally and smoothly used.
SUMMERY OF THE UTILITY MODEL
To the problem that exists among the prior art, the utility model aims to provide a building is external with building subject's connecting device, the mode that the screw rod that the outer material that hangs adopted in it can effectual solution prior art is connected, because of staff's hand is smooth very easily, and leads to taking place the problem of slope between external material and the building body.
In order to solve the above problem, the utility model adopts the following technical scheme:
a connecting device for a building external hanging and a building main body comprises the building main body, wherein an external hanging plate is arranged on one side of the building main body, and an alignment mechanism is arranged between the building main body and the external hanging plate;
the aligning mechanism comprises a clamping groove formed in one side of the building body, an inserting block is fixedly connected to one side, close to the building body, of the exterior cladding, the inserting block is movably inserted into the clamping groove, a hollow groove is formed in one side of the inserting block, the inserting block is located in the hollow groove and fixedly connected with a spring, a clamping block is fixedly connected to one end of the spring, and the clamping block is movably clamped in the clamping groove.
As an optimized scheme of the utility model, the thread groove has been seted up to one side that building subject is close to the cladding, one side of cladding is provided with the bolt, just the bolt sets up the inside at the thread groove.
As a preferred scheme of the utility model, the spout has been seted up to the inside of inserted block, just spout and hollow groove communicate each other, the inside sliding connection of spout has the slider, fixed connection between slider and the fixture block.
As a preferred scheme of the utility model, the inside that the inserted block is located hollow groove is provided with the syllogic telescopic link, fixed connection between the one end of syllogic telescopic link and the inserted block, fixed connection between the other end of syllogic telescopic link and the fixture block, just the syllogic telescopic link sets up the inboard at the spring.
As a preferred scheme of the utility model, the syllogic telescopic link comprises first telescopic link, second telescopic link and third telescopic link, the activity of first telescopic link is pegged graft in the inside of second telescopic link, the activity of second telescopic link is pegged graft in the inside of third telescopic link.
As a preferred scheme of the utility model, building element has seted up the spacing groove near one side of cladding, the cladding is close to one side fixedly connected with stopper of building element, the stopper activity is pegged graft in the inside of spacing groove.
As an optimized scheme of the utility model, the cladding is close to one side fixedly connected with rubber layer of building subject, the rubber layer sets up the outside at the bolt, the rubber layer is used for protecting building subject and cladding.
Compared with the prior art, the utility model has the advantages of:
1. the setting of alignment mechanism in this device for the staff is installing the cladding panel to the building subject on, alignment cladding panel that can be more accurate, and the difficult condition such as slide takes place for the cladding panel because of staff's smooth hand.
2. Because of the fixed connection between the sliding block and the clamping block in the device, the inserting block can also play a limiting role on the clamping block through the sliding block, and the clamping block is more stable and firm when moving.
Drawings
Fig. 1 is a schematic structural view of the present invention;
FIG. 2 is a first schematic view of the present invention;
FIG. 3 is an enlarged schematic view of the structure of the present invention at A in FIG. 2;
FIG. 4 is a schematic structural view of a thread groove and a limiting groove in an embodiment of the present invention;
fig. 5 is a second schematic view of the structure of the present invention.
The numbering in the figures illustrates:
1. a building body; 2. an outer hanging plate; 31. a bolt; 32. a thread groove; 41. a card slot; 42. inserting a block; 43. a hollow groove; 44. a spring; 45. a clamping block; 5. a three-section telescopic rod; 61. a chute; 62. a slider; 7. a rubber layer; 81. a limiting block; 82. a limiting groove.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention. Obviously, the described embodiments are only a part of the embodiments of the present invention, and not all embodiments, and all other embodiments obtained by those skilled in the art without making creative efforts based on the embodiments of the present invention belong to the protection scope of the present invention.
In the description of the present invention, it should be noted that the terms "upper", "lower", "inner", "outer", "top/bottom", and the like indicate orientations or positional relationships based on orientations or positional relationships shown in the drawings, and are only for convenience of description and simplification of description, but do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and thus should not be construed as limiting the present invention. Furthermore, the terms "first" and "second" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance.
In the description of the present invention, it is to be noted that, unless otherwise explicitly specified or limited, the terms "mounted", "provided", "sleeved/connected", "connected", and the like are to be understood in a broad sense, such as "connected", which may be fixedly connected, detachably connected, or integrally connected; the connection can be mechanical connection or electrical connection; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meaning of the above terms in the present invention can be understood as a specific case by those skilled in the art.
Example (b):
referring to fig. 1-5, a connecting device for a building external hanging plate and a building main body comprises a building main body 1, an external hanging plate 2 is arranged on one side of the building main body 1, an alignment mechanism is arranged between the building main body 1 and the external hanging plate 2, and the arrangement of the alignment mechanism enables a worker to more accurately align the external hanging plate 2 when installing the external hanging plate 2 on the building main body 1, so that the situation that the external hanging plate 2 slides due to the slippage of the hand of the worker is not easy to occur.
Alignment mechanism is including seting up the draw-in groove 41 in building subject 1 one side, cladding 2 is close to one side fixedly connected with inserted block 42 of building subject 1, and inserted block 42 activity is pegged graft in the inside of draw-in groove 41, cladding 2 can play installation and fixed effect to inserted block 42, make inserted block 42 can be stable, firm the use, simultaneously after inserted block 42 pegs graft the inside of draw-in groove 41, building subject 1 accessible draw-in groove 41 plays certain restriction effect to inserted block 42, and be fixed connection between inserted block 42 and cladding 2, this makes building subject 1 accessible inserted block 42 play certain connection and limiting displacement to cladding 2, and make cladding 2 can be stable be installed in one side of building subject 1, hollow groove 43 has been seted up to one side of inserted block 42, inserted block 42 is located the inside fixedly connected with spring 44 of hollow groove 43, inserted block 42 accessible hollow groove 43 plays the effect of connection and fixing to spring 44, make spring 44 can be stable, smooth the use.
In addition, spring 44's one end fixedly connected with fixture block 45, spring 44 then can play the effect of connecting and installing to fixture block 45, make fixture block 45 more stable when using, spring 44 is taking place the shrink back simultaneously, the elasticity of accessible self plays the effect of restoring to the throne to fixture block 45, and fixture block 45 activity joint is in the inside of draw-in groove 41, after fixture block 45 joint to the inside of draw-in groove 41, building subject 1 accessible draw-in groove 41 plays the limiting displacement to fixture block 45, thereby improve the stability between cladding 2 and the building subject 1, make cladding 2 be difficult for taking place the slope because of staff's hand is smooth.
Specifically, the thread groove 32 has been seted up to building subject 1 one side that is close to cladding 2, one side of cladding 2 is provided with bolt 31, and bolt 31 sets up the inside at thread groove 32, the staff can install bolt 31 to the inside of thread groove 32, and at this moment cladding 2 will be linked together by bolt 31 with building subject 1, thereby realize being connected and the installation between building subject 1 and the cladding 2, simultaneously because of the setting of alignment mechanism, make building subject 1 and cladding 2 more steady after being connected, difficult production slides.
It is specific, spout 61 has been seted up to the inside of inserted block 42, and spout 61 communicates with hollow groove 43 each other, the inside sliding connection of spout 61 has slider 62, fixed connection between slider 62 and the fixture block 45, inserted block 42 accessible spout 61 plays limiting displacement to slider 62, make the inside at spout 61 that slider 62 can be stable slide, simultaneously because of being fixed connection between slider 62 and the fixture block 45, this makes inserted block 42 still can play limiting displacement to fixture block 45 through slider 62, and make fixture block 45 more stable when taking place to remove, and is firm, the difficult condition such as skew that takes place.
Specifically, the inside that the inserted block 42 is located hollow groove 43 is provided with syllogic telescopic link 5, fixed connection between the one end of syllogic telescopic link 5 and the inserted block 42, fixed connection between the other end of syllogic telescopic link 5 and fixture block 45, and syllogic telescopic link 5 sets up the inboard at spring 44, syllogic telescopic link 5 can play certain auxiliary action to the flexible of spring 44, make spring 44 more smooth when stretching out and drawing back, it is stable, syllogic telescopic link 5 still can play certain limiting displacement to spring 44 simultaneously, make spring 44 difficult emergence skew when flexible, and syllogic telescopic link 5 still can play certain limiting displacement to fixture block 45, make fixture block 45 when the elasticity through spring 44 resets, be difficult for bumping with the inside of building main part 1 because of elasticity is too big, syllogic 5 is by first telescopic link, second telescopic link and third telescopic link are constituteed, the inside at the second telescopic link activity of pegging graft at the third telescopic link, this makes syllogic 5 can, stable use, and difficult condition such as unable emergence when using smoothly.
Specifically, building subject 1 has been close to one side of cladding 2 and has been seted up spacing groove 82, cladding 2 is close to one side fixedly connected with stopper 81 of building subject 1, stopper 81 activity is pegged graft in the inside of spacing groove 82, when stopper 81 and spacing groove 82's setting, after the staff passes through bolt 31 with cladding 2 and building subject 1 again and is connected, stopper 81 and the relation of being connected between the spacing groove 82, can provide certain support to being connected between building subject 1 and the cladding 2, limiting displacement, while stopper 81 and spacing groove 82's setting still makes the staff when using alignment mechanism, insert block 42 and draw-in groove 41 are more easily to.
Specifically, cladding board 2 is close to one side fixedly connected with rubber layer 7 of building subject 1, and rubber layer 7 sets up in the outside of bolt 31, and rubber layer 7 is used for protecting building subject 1 and cladding board 2, and the setting of rubber layer 7 makes when building subject 1 and cladding board 2 are being connected through bolt 31 the back, is difficult for taking place comparatively serious wearing and tearing each other to make building subject 1 and cladding board 2 can use longer time, improved building subject 1 and cladding board 2's life.
The utility model discloses a theory of operation and use flow: when the device is used, a worker can firstly align the limiting block 81 with the limiting groove 82 and push the external hanging plate 2, after the external hanging plate 2 moves a distance, the inserting block 42 is inserted into the clamping groove 41 due to the alignment of the limiting block 81 and the limiting groove 82, the clamping block 45 can firstly touch the building main body 1 when the inserting block 42 is inserted, the external hanging plate 2 is extruded due to the fact that the inserting block is pushed, the clamping block 45 can move towards the inside of the hollow groove 43 under the action of pressure and extrude the spring 44 and the three-section type telescopic rod 5 when moving, after the inserting block 42 completely enters the inside of the clamping groove 41, the clamping block 45 can reset under the elasticity of the spring 44 and is clamped into the inside of the clamping groove 41, at the moment, the connection between the building main body 1 and the external hanging plate 2 can be completed due to the fact that the inserting block 42 is inserted into the inside of the clamping groove 41 and the clamping block 45 is clamped into the inside of the clamping groove 41, the alignment work between the building main body 1 and the external hanging plate 2 can be completed, the worker can easily connect the external hanging plate 2 with the external hanging plate by adopting the screw rod, and the problem of the sliding of the building main body caused by the sliding of the external hanging material in the sliding screw rod.
The above description is only a preferred embodiment of the present invention, but the scope of the present invention is not limited thereto, and any person skilled in the art can substitute or change the technical solution and the modified concept of the present invention within the technical scope disclosed in the present invention.

Claims (7)

1. The utility model provides a connecting device of external and building subject of building, includes building subject (1), its characterized in that: an outer hanging plate (2) is arranged on one side of the building main body (1), and an alignment mechanism is arranged between the building main body (1) and the outer hanging plate (2);
the aligning gear is including seting up draw-in groove (41) in building subject (1) one side, cladding board (2) are close to one side fixedly connected with inserted block (42) of building subject (1), just inserted block (42) activity is pegged graft in the inside of draw-in groove (41), hollow groove (43) have been seted up to one side of inserted block (42), inserted block (42) are located inside fixedly connected with spring (44) of hollow groove (43), one end fixedly connected with fixture block (45) of spring (44), just fixture block (45) activity joint is in the inside of draw-in groove (41).
2. The connecting device for the building external hanging and the building main body according to claim 1, characterized in that: threaded grooves (32) are formed in one side, close to the exterior cladding (2), of the building main body (1), bolts (31) are arranged on one side of the exterior cladding (2), and the bolts (31) are arranged inside the threaded grooves (32).
3. The connecting device for the building external hanging and the building main body according to claim 1, characterized in that: the inside of inserted block (42) has seted up spout (61), just spout (61) and hollow groove (43) communicate each other, the inside sliding connection of spout (61) has slider (62), fixed connection between slider (62) and fixture block (45).
4. The connecting device for the building external hanging and the building main body according to claim 1, characterized in that: the inside that inserted block (42) are located hollow groove (43) is provided with syllogic telescopic link (5), fixed connection between the one end of syllogic telescopic link (5) and inserted block (42), fixed connection between the other end of syllogic telescopic link (5) and fixture block (45), just syllogic telescopic link (5) set up the inboard at spring (44).
5. The device for connecting a building plug with a building body according to claim 4, characterized in that: the three-section type telescopic rod (5) is composed of a first telescopic rod, a second telescopic rod and a third telescopic rod, the first telescopic rod is movably inserted in the second telescopic rod, and the second telescopic rod is movably inserted in the third telescopic rod.
6. The connecting device for the building external hanging and the building main body according to claim 1, characterized in that: limiting grooves (82) are formed in one side, close to the exterior cladding (2), of the building body (1), limiting blocks (81) are fixedly connected to one side, close to the building body (1), of the exterior cladding (2), and the limiting blocks (81) are movably inserted into the limiting grooves (82).
7. The connecting device for the building external hanging and the building main body according to claim 1, characterized in that: one side fixedly connected with rubber layer (7) that exterior cladding board (2) are close to building subject (1), rubber layer (7) set up in the outside of bolt (31), rubber layer (7) are used for protecting building subject (1) and exterior cladding board (2).
CN202220754368.7U 2022-04-02 2022-04-02 Connecting device for building external hanging and building main body Expired - Fee Related CN217557219U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202220754368.7U CN217557219U (en) 2022-04-02 2022-04-02 Connecting device for building external hanging and building main body

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202220754368.7U CN217557219U (en) 2022-04-02 2022-04-02 Connecting device for building external hanging and building main body

Publications (1)

Publication Number Publication Date
CN217557219U true CN217557219U (en) 2022-10-11

Family

ID=83469928

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202220754368.7U Expired - Fee Related CN217557219U (en) 2022-04-02 2022-04-02 Connecting device for building external hanging and building main body

Country Status (1)

Country Link
CN (1) CN217557219U (en)

Similar Documents

Publication Publication Date Title
CN205400001U (en) Improvement structure be used for clamping device that ceramic tile laid
CN217557219U (en) Connecting device for building external hanging and building main body
CN210976114U (en) Waterproof construction at building structure expansion joint
CN209881263U (en) Novel combined wire harness clip
CN212645619U (en) Real-time monitoring system for building assembly
CN211447450U (en) Novel ceiling aluminum plate
CN214034265U (en) Novel curtain wall module installation technology curtain wall device
CN209975973U (en) Scaffold connecting structure for external wall construction
CN204531136U (en) A kind of novel modularized building block structure
CN211037504U (en) Concatenation formula building backup pad for building
CN209228028U (en) A kind of cement slurry is fixed to use building template mechanism
CN112814379B (en) Connecting and locking device suitable for building template
CN217150790U (en) Environment-friendly wall structure
CN217984327U (en) Electric wire installation fixing device for electrical engineering construction
CN221031450U (en) Building template strutting arrangement for building is built in room
CN213744371U (en) High anti-skid nail
CN215443061U (en) Scaffold frame horizontal pole structure with adjustable length
CN220133451U (en) Novel socket type disc buckle template support
CN201620549U (en) Wall panel unit and fastening mechanism
CN217003770U (en) Automatic leveling instrument
CN204311671U (en) A kind of horizontal pedal
CN218597456U (en) Building curtain wall convenient to assemble
CN211764530U (en) Set square convenient to take and use
CN212057905U (en) Refrigerator plastic top cover easy to disassemble and clean
CN217998909U (en) Scaffold connecting piece for building construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20221011

CF01 Termination of patent right due to non-payment of annual fee