CN217500526U - Wood-concrete frame structure fabricated building - Google Patents

Wood-concrete frame structure fabricated building Download PDF

Info

Publication number
CN217500526U
CN217500526U CN202221024195.XU CN202221024195U CN217500526U CN 217500526 U CN217500526 U CN 217500526U CN 202221024195 U CN202221024195 U CN 202221024195U CN 217500526 U CN217500526 U CN 217500526U
Authority
CN
China
Prior art keywords
building
building platform
wood
baffle
fixedly arranged
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202221024195.XU
Other languages
Chinese (zh)
Inventor
胡国辉
张颢
王海洋
赵宝兰
张瀚文
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Gufeng Jinyun (Shanxi) Technology Group Co.,Ltd.
Original Assignee
Gufeng Jinyun Construction Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Gufeng Jinyun Construction Group Co ltd filed Critical Gufeng Jinyun Construction Group Co ltd
Priority to CN202221024195.XU priority Critical patent/CN217500526U/en
Application granted granted Critical
Publication of CN217500526U publication Critical patent/CN217500526U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Buildings Adapted To Withstand Abnormal External Influences (AREA)

Abstract

The utility model relates to the technical field of concrete frames, in particular to a wood-concrete frame structure fabricated building, which comprises a building platform, wherein the upper end part of the building platform is symmetrically provided with a containing groove, a reinforcing steel bar frame is fixedly arranged at the center inside the building platform, a first baffle and a second baffle are symmetrically and movably arranged at the upper end part of the building platform, the two first baffles and the second baffle are combined to form a cladding structure of the reinforcing steel bar frame, fixed blocks are fixedly arranged on the side walls of the two first baffles, L-shaped blocks are fixedly arranged on the side walls of the two fixed blocks, first fastening nails are arranged on the inner threads of the L-shaped blocks, second fastening nails are arranged on the contact parts of the L-shaped blocks and the fixed blocks in a threaded manner, a supporting mechanism comprises fixed seats, the two fixed seats are fixedly arranged in the building platform, central columns are fixedly arranged on the inner walls of the two fixed seats, and column sleeves are movably sleeved on the surfaces of the two central columns, this equipment is firm when using better effect, and is detachable construction for it is convenient laborsaving to dismantle after accomplishing to pour to this equipment.

Description

Wood-concrete frame structure fabricated building
Technical Field
The utility model relates to a concrete frame technical field especially relates to wood-concrete frame structure assembly type building.
Background
The prefabricated concrete building is a concrete structure type building which is designed and built in a field assembly mode mainly by using reinforced concrete prefabricated parts produced in a factory, and is generally divided into a full-assembly building and a partial-assembly building: the fully assembled building is generally a multi-storey building with low requirements for seismic fortification; the main components of a partially assembled building are generally prefabricated components which are connected through cast-in-place concrete on site to form the building with an assembled integral structure. The building has the characteristics of high construction speed, high production efficiency, good product quality and material loss reduction, and is beneficial to winter construction.
As disclosed in the chinese patent: an ultra-high performance wood-concrete frame structure fabricated building, publication no: CN207331954U, the super high performance wood-concrete frame structure fabricated building is made by pouring concrete material, and the whole main frame is regular rectangle structure, can be matched with general building, can be fixed with conventional wall conveniently, and a support column is arranged at the center of the main frame, a convex block is arranged at the upper part of the support column, can be matched with a crane on the building site, and is provided with a fixed slot and a fixed buckle to fix the main frame on the crane, the main frame can be hung on the building for fixed installation, thus the main frame can be moved conveniently, the position of the pouring gate of the main frame is reasonable, the concrete pouring of the main frame can be performed conveniently, and no air bubble can be generated, the whole device has high use value, the whole structure is simple, the fabrication process is simple, and the rapid production can be realized, the hoisting movement is convenient, but larger pressure can be generated when pouring, the equipment is poor in connection tightness, and the frame is easy to crack under the action of the pressure, so that danger is generated.
Disclosure of Invention
In order to overcome the defects of the prior art, the utility model provides a wood-concrete frame structure assembly type building.
In order to solve the technical problem, the utility model provides a following technical scheme: the wood-concrete frame structure assembly type building comprises a building platform, wherein the upper end part of the building platform is symmetrically provided with a containing groove, a reinforcing steel bar frame is fixedly arranged at the center of the inside of the building platform, a first baffle and a second baffle are symmetrically and movably arranged at the upper end part of the building platform, the two first baffles and the second baffle are combined to form a coating structure of the reinforcing steel bar frame, fixed blocks are fixedly arranged on the side walls of the two first baffles, L-shaped blocks are fixedly arranged on the side walls of the two fixed blocks, first fastening nails are arranged in the L-shaped blocks through threads, and second fastening nails are arranged at the contact parts of the L-shaped blocks and the fixed blocks through threads;
the side wall of the second baffle is detachably provided with a reinforcing mechanism;
and supporting mechanisms are symmetrically arranged inside the building platform.
The reinforcing mechanism comprises fastening strips, two the fastening strips can be detached from the side wall of the second baffle plate, two intermediate columns and two nuts are movably mounted in the fastening strips in a symmetrical mode at the two ends of the intermediate columns.
The supporting mechanism comprises fixed seats, the two fixed seats are fixedly arranged in the building platform, and central columns are fixedly arranged in the inner walls of the two fixed seats.
As a preferred technical scheme of the utility model, building platform upper end fixed mounting has the hydro-cylinder, fixed mounting has the curb plate on the hydro-cylinder lateral wall, the inside equal threaded mounting of curb plate has connecting bolt, establish in the building platform in the connecting bolt screw thread.
As a preferred technical scheme of the utility model, hydro-cylinder upper end fixed mounting has the telescopic link, telescopic link upper end fixed mounting has the connecting strip, tip fixed mounting has the vibrting spear under the connecting strip.
As an optimal technical scheme of the utility model, two the equal movable sleeve in center post surface is equipped with the post cover, two equal fixed mounting has the vaulting pole on the post cover lateral wall.
As a preferred technical scheme of the utility model, two the equal fixed mounting of vaulting pole upper end has the fagging, two the fagging is in the same place with two holding-down strip pastes respectively.
Compared with the prior art, the utility model discloses the beneficial effect that can reach is:
firstly, the equipment has better stabilizing effect when in use, and is of a detachable structure, so that the equipment is convenient and labor-saving to detach after pouring is finished;
secondly, inside this equipment can place into the reinforcing bar frame vibrations stick according to the height of pouring, it sent vibrations this moment and can tamp the cement of pouring for it is better to pour the effect.
Drawings
Fig. 1 is a schematic perspective view of the present invention;
fig. 2 is a schematic view of the connection structure of the reinforcing steel bar frame of the present invention;
FIG. 3 is a schematic view of the stay bar connection structure of the present invention;
fig. 4 is a schematic view of the connection structure of the telescopic rod of the present invention.
Wherein: 11. a building platform; 12. a receiving groove; 13. a reinforcing steel bar frame; 14. a first baffle plate; 15. a second baffle; 16. a fixed block; 17. an L-shaped block; 18. a first fastening nail; 19. a second fastening pin; 21. fastening strips; 22. a middle column; 23. a nut; 24. an oil cylinder; 25. a side plate; 26. a connecting bolt; 27. a telescopic rod; 28. a connecting strip; 29. a vibration rod; 31. a fixed seat; 32. a central column; 33. a column sleeve; 34. a stay bar; 35. and a supporting plate.
Detailed Description
In order to make the technical means, the creation features, the achievement purposes and the functions of the invention easy to understand, the invention is further explained below with reference to the specific embodiments, but the following embodiments are only the preferred embodiments of the invention, not all. Based on the embodiments in the implementation, other embodiments obtained by those skilled in the art without any creative work belong to the protection scope of the present invention. The experimental methods in the following examples are conventional methods unless otherwise specified, and materials, reagents and the like used in the following examples are commercially available unless otherwise specified.
Example (b):
as shown in fig. 1, 2, 3 and 4, the fabricated building with a wood-concrete frame structure comprises a building platform 11, wherein the upper end of the building platform 11 is symmetrically provided with accommodating grooves 12, a reinforcing steel frame 13 is fixedly arranged at the center inside the building platform 11, the upper end of the building platform 11 is symmetrically movably provided with a first baffle plate 14 and a second baffle plate 15, the two first baffle plates 14 and the second baffle plate 15 are combined to form a coating structure of the reinforcing steel frame 13, the side walls of the two first baffle plates 14 are respectively and fixedly provided with a fixing block 16, the side walls of the two fixing blocks 16 are respectively and fixedly provided with an L-shaped block 17, the inside of the L-shaped block 17 is provided with a first fastening nail 18 through threads, and the contact part of the L-shaped block 17 and the fixing block 16 is provided with a second fastening nail 19 through threads;
the side wall of the second baffle 15 is detachably provided with a reinforcing mechanism;
the building platform 11 is internally and symmetrically provided with a supporting mechanism.
The reinforcing mechanism comprises fastening strips 21, wherein the two fastening strips 21 can be detached from the side wall of the second baffle 15, intermediate columns 22 are symmetrically and movably arranged inside the two fastening strips 21, nuts 23 are respectively sleeved at both ends of the two intermediate columns 22 in a threaded manner, an oil cylinder 24 is fixedly arranged at the upper end of the building platform 11, a side plate 25 is fixedly arranged on the side wall of the oil cylinder 24, a connecting bolt 26 is respectively and fixedly arranged inside the side plate 25 in a threaded manner, the connecting bolt 26 is arranged in the building platform 11 in a threaded manner, an expansion rod 27 is fixedly arranged at the upper end of the oil cylinder 24, a connecting strip 28 is fixedly arranged at the upper end of the expansion rod 27, a vibration rod 29 is fixedly arranged at the lower end of the connecting strip 28, after the second baffle 15 and the fixed block 16 are fixed, the oil cylinder 24 can be started, the expansion rod 27 is driven to expand and contract under the action of the oil cylinder 24, the expansion rod 27 drives the connecting strip 28 fixed therewith to ascend and descend, the device can place the vibration rod 29 into the reinforcing steel frame 13 according to the casting height under the lifting of the vibration rod 29, and the vibration rod 29 can be used for compacting the cast cement at the moment, so that the casting effect is better.
The supporting mechanism comprises fixed seats 31, two fixed seats 31 are fixedly arranged in a building platform 11, central columns 32 are fixedly arranged in the inner walls of the two fixed seats 31, column sleeves 33 are movably sleeved on the surfaces of the two central columns 32, supporting rods 34 are fixedly arranged on the side walls of the two column sleeves 33, supporting plates 35 are fixedly arranged at the upper ends of the two supporting rods 34, the two supporting plates 35 are respectively attached to the two fastening strips 21, when the supporting mechanism is used, a reinforcing steel frame 13 is firstly installed on the building platform 11, at the moment, a second baffle plate 15 and a fixed block 16 are sequentially arranged on the periphery of the reinforcing steel frame 13, the fixing between the reinforcing steel frame 13 and the first fastening nail 18 and the second fastening nail 19 is completed, at the moment, screw caps 23 can be rotated at the two ends of a middle column 22, the fastening strips 21 are extruded under the rotation of the screw caps 23 to exert pressure on the reinforcing steel frame, so that the connection between the second baffle plate 15 and the fixed block 16 is tighter, at the moment, the column sleeves 33 can be overturned around the central columns 32, will drive the vaulting pole 34 fixed with it and take place the upset under the rotation of column jacket 33, vaulting pole 34 has driven fixed fagging 35 with it this moment and has taken place to rotate, plays the supporting role to it when fagging 35 and fastening strip 21 contact this for this equipment firm effect is better when using, and is detachable construction, makes this equipment pour and dismantles convenient laborsaving after accomplishing.
The working principle is as follows:
the first step is as follows: when the device is used, the steel bar frame 13 is firstly installed on the building platform 11, the second baffle 15 and the fixed block 16 are sequentially placed on the periphery of the steel bar frame 13 and are fixed through the first fastening nail 18 and the second fastening nail 19, the nuts 23 can be rotated at two ends of the middle column 22 at the moment, the fastening strips 21 are extruded to apply pressure on the second baffle 15 and the fixed block 16 under the rotation of the nuts 23, so that the connection between the second baffle 15 and the fixed block 16 is tighter, the column sleeve 33 can be turned over around the central column 32 at the moment, the stay bar 34 fixed with the column sleeve 33 is driven to turn over under the rotation of the column sleeve 33, the stay bar 34 drives the supporting plate 35 fixed with the stay bar to rotate, the supporting effect is achieved when the supporting plate 35 is in contact with the fastening strips 21, the device is better in stabilizing effect when in use, and is of a detachable structure, so that the device is labor-saving and convenient to dismount after being poured;
the second step is that: after the second baffle 15 and the fixed block 16 are fixed, the oil cylinder 24 can be started at this time, the telescopic rod 27 is driven to stretch under the action of the oil cylinder 24, the telescopic rod 27 drives the connecting strip 28 fixed with the telescopic rod to lift at this time, the vibrating rod 29 fixed with the connecting strip 28 is driven to lift under the lifting of the vibrating rod 29, the vibrating rod 29 can be placed into the reinforcing steel bar frame 13 according to the pouring height under the lifting of the vibrating rod 29, the vibrating rod can vibrate to tamp poured cement at this time, and the pouring effect is better.
The embodiments of the present invention have been described in detail with reference to the accompanying drawings, but the present invention is not limited thereto, and various changes can be made without departing from the gist of the present invention within the scope of knowledge possessed by those skilled in the art.

Claims (7)

1. The wood-concrete frame structure fabricated building comprises a building platform (11), wherein the upper end part of the building platform (11) is symmetrically provided with accommodating grooves (12), a reinforcing steel bar frame (13) is fixedly arranged at the center inside the building platform (11), it is characterized in that a first baffle (14) and a second baffle (15) are symmetrically and movably mounted at the upper end part of the building platform (11), the two first baffles (14) and the second baffle (15) are combined to form a coating structure of a reinforcing steel frame (13), fixed blocks (16) are fixedly mounted on the side walls of the two first baffles (14), L-shaped blocks (17) are fixedly mounted on the side walls of the two fixed blocks (16), a first fastening nail (18) is installed in the L-shaped block (17) through threads, and a second fastening nail (19) is installed at the contact part of the L-shaped block (17) and the fixing block (16) through threads;
the side wall of the second baffle (15) is detachably provided with a reinforcing mechanism;
and supporting mechanisms are symmetrically arranged inside the building platform (11).
2. The fabricated building with a wood-concrete frame structure according to claim 1, wherein the reinforcing mechanism comprises fastening strips (21), two fastening strips (21) are detachable from the side wall of the second baffle plate (15), intermediate columns (22) are symmetrically and movably mounted in the two fastening strips (21), and nuts (23) are respectively sleeved at two ends of each intermediate column (22) in a threaded manner.
3. The wood-concrete frame structure fabricated building of claim 1, wherein the supporting mechanism comprises fixed seats (31), two of the fixed seats (31) are fixedly arranged in the building platform (11), and a central column (32) is fixedly arranged in the inner wall of the two fixed seats (31).
4. The fabricated building of a wood-concrete frame structure according to claim 1, wherein an oil cylinder (24) is fixedly installed at the upper end of the building platform (11), a side plate (25) is fixedly installed on the side wall of the oil cylinder (24), a connecting bolt (26) is installed inside the side plate (25) in a threaded manner, and the connecting bolt (26) is arranged in the building platform (11) in a threaded manner.
5. The wood-concrete frame structure fabricated building of claim 4, wherein the oil cylinder (24) is fixedly provided with an expansion link (27) at an upper end thereof, the expansion link (27) is fixedly provided with a connection bar (28) at an upper end thereof, and a vibration rod (29) is fixedly provided at a lower end of the connection bar (28).
6. The fabricated building with a wood-concrete frame structure according to claim 3, wherein the surface of each of the two central columns (32) is movably sleeved with a column sleeve (33), and a support rod (34) is fixedly arranged on the side wall of each of the two column sleeves (33).
7. The fabricated building of a wood-concrete frame structure according to claim 6, wherein a bracing plate (35) is fixedly installed at the upper end of each of the two struts (34), and the two bracing plates (35) are respectively attached to the two fastening strips (21).
CN202221024195.XU 2022-04-30 2022-04-30 Wood-concrete frame structure fabricated building Active CN217500526U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221024195.XU CN217500526U (en) 2022-04-30 2022-04-30 Wood-concrete frame structure fabricated building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221024195.XU CN217500526U (en) 2022-04-30 2022-04-30 Wood-concrete frame structure fabricated building

Publications (1)

Publication Number Publication Date
CN217500526U true CN217500526U (en) 2022-09-27

Family

ID=83350918

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221024195.XU Active CN217500526U (en) 2022-04-30 2022-04-30 Wood-concrete frame structure fabricated building

Country Status (1)

Country Link
CN (1) CN217500526U (en)

Similar Documents

Publication Publication Date Title
CN111391082B (en) Box girder template for road and bridge construction
CN216427858U (en) Linear adjusting template device for post-cast section of curved track beam
CN113502756A (en) Thin-wall pier hydraulic creeping formwork system and construction method thereof
CN217500526U (en) Wood-concrete frame structure fabricated building
CN212802515U (en) Integral hoisting type hoisting platform
CN114953122B (en) Cast-in-situ multifunctional splicing die for small-radius curved beam bridge
CN206512744U (en) Gallery formwork-support device in a kind of concrete dam body
CN215749782U (en) Evaporate and press aerated concrete slab pouring equipment
CN112176885B (en) Quick construction method for turning over mould of bridge group of viaduct Gao Kongxin
CN115928794A (en) Roof post-cast strip supporting structure and construction method thereof
CN104453217A (en) Elevator shaft whole formwork lifting construction method
CN214272109U (en) Ground beam formwork device
CN114414354B (en) Temporary support test device for large-span box girder erection
CN217711722U (en) Secondary structure is with design reinforcement member
CN221095826U (en) Mounting structure of shaping post-pouring belt mould hanging tool
CN2205444Y (en) Well shaft working device
CN218813165U (en) Box girder wet joint template supporting structure
CN214925586U (en) Auxiliary device for laminated plate forming die
CN215887968U (en) Non-pressure box culvert concrete slip aluminum alloy template device that shears
CN216740686U (en) Cast-in-place slab band of superimposed sheet hangs mould device
CN220927533U (en) Cast-in-situ beam template system without inner pull rod
CN218467104U (en) High-rise outer frame-free unilateral masonry formwork
CN209384642U (en) A kind of building inner room shaping mould
CN220030668U (en) Die for avoiding cracking of bottom end of T-shaped beam
CN220953004U (en) Bridge template separating mechanism

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address

Address after: No. 01, 26th Floor, Building B, Jindong International, Xutan East Street, Xiaodian District, Taiyuan City, Shanxi Province, 030006

Patentee after: Gufeng Jinyun (Shanxi) Technology Group Co.,Ltd.

Address before: No. 01, 26th Floor, Building B, Jindong International, Xutan East Street, Xiaodian District, Taiyuan City, Shanxi Province 030000

Patentee before: Gufeng Jinyun Construction Group Co.,Ltd.

CP03 Change of name, title or address