CN217491869U - Water supply pipeline of water washing module of gas turbine - Google Patents

Water supply pipeline of water washing module of gas turbine Download PDF

Info

Publication number
CN217491869U
CN217491869U CN202220681532.6U CN202220681532U CN217491869U CN 217491869 U CN217491869 U CN 217491869U CN 202220681532 U CN202220681532 U CN 202220681532U CN 217491869 U CN217491869 U CN 217491869U
Authority
CN
China
Prior art keywords
hole enlargement
water
inlet tube
pipe
enlargement portion
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202220681532.6U
Other languages
Chinese (zh)
Inventor
谢为良
李润丰
廖志楠
刘衍双
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Dongguan Shenzhen Energy Zhangyang Power Co ltd
Original Assignee
Dongguan Shenzhen Energy Zhangyang Power Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Dongguan Shenzhen Energy Zhangyang Power Co ltd filed Critical Dongguan Shenzhen Energy Zhangyang Power Co ltd
Priority to CN202220681532.6U priority Critical patent/CN217491869U/en
Application granted granted Critical
Publication of CN217491869U publication Critical patent/CN217491869U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Cleaning By Liquid Or Steam (AREA)

Abstract

The utility model discloses a combustion engine washing module supply channel, including storage water tank, inlet tube, water pump, heating device, temperature probe, venturi, high-pressure gas pipe, branch pipe, cleaning agent jar, outlet pipe and controller, venturi is including the first hole enlargement portion that is located both ends, second hole enlargement portion and the throat portion that is located the centre, the one end of inlet tube is connected the storage water tank, the other end of inlet tube is connected to first hole enlargement portion, the water pump heating device with temperature probe set gradually in on the inlet tube, high-pressure gas union coupling is to first hole enlargement portion, branch connection the throat portion, branch connection the cleaning agent jar, be provided with the aperture control valve on the branch pipe, go out water piping connection second hole enlargement portion. The technical scheme is used for solving the problems of insufficient pressure and low cleaning efficiency of the existing gas turbine washing device.

Description

Water supply pipeline of water washing module of gas turbine
Technical Field
The utility model belongs to the technical field of gas turbine structure, concretely relates to gas turbine washing module supply channel.
Background
The gas turbine is a rotary impeller type heat engine, and uses continuously flowing gas as working medium to drive the impeller to rotate at high speed, so as to convert the energy of fuel into useful work. Because the compressor operates in an open environment and is influenced by environmental factors, impurities can be accumulated on the blades of the compressor to form scale deposit, so that the efficiency of the compressor is reduced, and the blades are easy to generate fatigue cracks. In order to ensure the cleanness of the compressor, the gas turbine is provided with a water washing device, and the hidden danger is eliminated by washing and washing the impurities of the blades of the compressor periodically.
However, the existing gas turbine washing device is connected with a water pipe and a cleaning agent pipeline and then leads the water pipe and the cleaning agent pipeline to a spray head for spray washing, and has two problems, one is that the pressure obtained by water pump pressurization is insufficient, and the washing efficiency is low; secondly, water and the cleaning agent are not fully mixed in the pipeline, and the cleaning effect is also influenced.
SUMMERY OF THE UTILITY MODEL
To the technical problem that above-mentioned exists, the utility model provides a gas turbine washing module supply channel to there is not enough and the problem that cleaning efficiency is low in current gas turbine washing device to solve, this kind of gas turbine washing module supply channel has higher washing pressure and cleaning efficiency.
The utility model provides a gas turbine washing module supply channel, including storage water tank, inlet tube, water pump, heating device, temperature probe, venturi, high-pressure gas pipe, branch pipe, cleaning agent jar, outlet pipe and controller, venturi is including the first hole enlargement portion that is located both ends, second hole enlargement portion and the throat portion that is located the centre, the one end of inlet tube is connected the storage water tank, the other end of inlet tube is connected to first hole enlargement portion, the water pump heating device with temperature probe set gradually in on the inlet tube, high-pressure gas union coupling is to first hole enlargement portion, branch union coupling the throat portion, branch union coupling the cleaning agent jar, be provided with the aperture control valve on the branch pipe, go out water piping connection the second hole enlargement portion, the controller is connected respectively heating device, venturi, high-pressure gas pipe, high-pressure gas union coupling the throat portion, branch union coupling, The temperature probe and the opening control valve.
Further, the high-pressure gas pipe is connected with an air compressor.
Furthermore, the water outlet pipe is connected with a spray head.
This gas turbine washing module supply channel is provided with heating device and temperature probe, accessible on the inlet tube controller control heating device heats the water supply of inlet tube to improve its dissolving effect to the spot, be provided with venturi simultaneously, through venturi inserts high-pressure gas pipe and inlet tube, and the high-pressure gas that the high-pressure gas pipe let in can realize certain pressure boost to supplying water, improves pressure of washing, and on the other hand, the high-pressure gas who lets in has also played better mixing action to water supply and cleaner, has produced more foam, improves clean ability.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, it is obvious that the drawings in the following description are only some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to these drawings without creative efforts.
Fig. 1 is a schematic structural diagram of a water supply pipeline of a water washing module of a combustion engine.
Detailed Description
The utility model discloses a gas turbine washing module supply channel, this kind of gas turbine washing module supply channel have higher washing pressure and cleaning efficiency.
The technical solution of the present invention will be described clearly and completely with reference to the accompanying drawings, and obviously, only some embodiments, not all embodiments, of the present invention are described. Based on the embodiments of the present invention, all other embodiments obtained by a person of ordinary skill in the art without creative efforts belong to the protection scope of the present invention.
Referring to fig. 1, the utility model discloses a water supply pipeline of a water washing module of a combustion engine, which comprises a water storage tank 1, a water inlet pipe 5, a water pump 2, a heating device 4, a temperature probe 6, a venturi tube 8, a high-pressure gas pipe 7, a branch pipe 15, a cleaning agent tank 14, a water outlet pipe 9 and a controller, wherein the venturi tube 8 comprises a first diameter-expanding part 10 and a second diameter-expanding part 12 which are arranged at two ends and a necking part 11 which is arranged in the middle, one end of the water inlet pipe 5 is connected with the water storage tank 1, the other end of the water inlet pipe 5 is connected with the first diameter-expanding part 10, the water pump 2, the heating device 4 and the temperature probe 6 are sequentially arranged on the water inlet pipe 5, the high-pressure gas pipe 7 is connected with the first diameter-expanding part 10, the branch pipe 15 is connected with the necking part 11, the branch pipe 15 is connected with the cleaning agent tank 14, and the branch pipe 15 is provided with an opening control valve 16, the water outlet pipe 9 is connected with the second diameter expanding part 12, and the controller 3 is respectively connected with the heating device 4, the temperature probe 6 and the opening control valve 16.
The high-pressure gas pipe 7 is connected with an air compressor.
The water outlet pipe 9 is connected with a spray head 13.
This gas turbine washing module supply channel is provided with heating device 4 and temperature probe 6, accessible on inlet tube 5 3 control heating device 4 heats the water supply of inlet tube 5 to improve its dissolving effect to the spot, be provided with venturi 8 simultaneously, through venturi 8 inserts high-pressure gas pipe 7 and inlet tube 5, and the high-pressure gas that high-pressure gas pipe 7 let in can realize certain pressure boost to supplying water, improves washing pressure, and on the other hand, the high-pressure gas who lets in has also played better mixed action to supplying water and cleaner, has produced more foam, improves cleaning capacity.
The foregoing is a more detailed description of the present invention, taken in conjunction with the specific preferred embodiments thereof, and it is not intended that the invention be limited to the specific embodiments shown and described. To the utility model belongs to the technical field of ordinary technical personnel, do not deviate from the utility model discloses under the prerequisite of design, can also make a plurality of simple deductions or replacement, all should regard as belonging to the utility model discloses a protection scope.

Claims (3)

1. The utility model provides a combustion engine washing module supply channel, its characterized in that, includes storage water tank, inlet tube, water pump, heating device, temperature probe, venturi, high-pressure gas pipe, branch pipe, cleaning agent jar, outlet pipe and controller, venturi is including the first hole enlargement portion that is located both ends, second hole enlargement portion and the throat portion that is located the centre, the one end of inlet tube is connected the storage water tank, the other end of inlet tube is connected to first hole enlargement portion, the water pump, heating device with temperature probe sets gradually in on the inlet tube, high-pressure gas pipe is connected to first hole enlargement portion, the branch union throat portion, the branch union the cleaning agent jar, be provided with the aperture control valve on the branch pipe, go out water piping connection the second hole enlargement portion, the controller is connected respectively heating device, venturi, high-pressure gas pipe, branch union coupling, The temperature probe and the opening control valve.
2. The water supply line for the water washing module of the combustion engine as claimed in claim 1, wherein the high pressure gas pipe is connected with an air compressor.
3. The water supply line for the water washing module of the combustion engine as claimed in claim 1, wherein the water outlet pipe is connected with a spray head.
CN202220681532.6U 2022-03-28 2022-03-28 Water supply pipeline of water washing module of gas turbine Active CN217491869U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202220681532.6U CN217491869U (en) 2022-03-28 2022-03-28 Water supply pipeline of water washing module of gas turbine

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202220681532.6U CN217491869U (en) 2022-03-28 2022-03-28 Water supply pipeline of water washing module of gas turbine

Publications (1)

Publication Number Publication Date
CN217491869U true CN217491869U (en) 2022-09-27

Family

ID=83347693

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202220681532.6U Active CN217491869U (en) 2022-03-28 2022-03-28 Water supply pipeline of water washing module of gas turbine

Country Status (1)

Country Link
CN (1) CN217491869U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116060387A (en) * 2023-04-06 2023-05-05 山东华灿机械有限公司 Cleaning device for pipe welding part

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116060387A (en) * 2023-04-06 2023-05-05 山东华灿机械有限公司 Cleaning device for pipe welding part

Similar Documents

Publication Publication Date Title
CN106001015B (en) A kind of multi-function washing machine
CN217491869U (en) Water supply pipeline of water washing module of gas turbine
CN202350165U (en) Device for recycling residual heat of exhaust steam of steam turbine by using multi-effect overlapped spraying type heat pump
CN201272697Y (en) Deoxidization apparatus for water used in generator set
CN204227989U (en) On-line cleaner of heat exchanger
CN202746000U (en) Jet flow mixing supercharged engine
CN215049985U (en) Biogas desulfurization aeration heat exchange device
CN205725651U (en) A kind of cooling system of photovoltaic electrification component
CN215109591U (en) Air supply device of wastewater treatment station and wastewater treatment station
CN209604152U (en) A kind of combustion engine water wash system
CN211537280U (en) Self-suction device of nano bubble machine
CN2811912Y (en) Three shock wave sound velocity changing and pressurizing heat exchanger
CN202255081U (en) Cleaning device for surface cooler
CN216241458U (en) Emptying device for fan oil system of thermal power plant
CN110319600A (en) A kind of steam heat pump and photo-thermal heat storage boiler association system
CN201673771U (en) Inner cavity device of independent oil tank single-group flushing finned radiator or cooler
CN209309670U (en) Sewage plant qualification pond waste water pumping system
CN2811909Y (en) Single shock wave sound velocity changing and pressurizing heat exchanger
CN212615371U (en) Cooling system for cooling working fluid of water-ring vacuum pump
CN214330760U (en) Leading natural gas heating device of gas turbine
CN213748086U (en) Multifunctional pump station system for cleaning
CN108507367A (en) A kind of exhaust steam of electric power plant reuse means
CN213021057U (en) Improved condenser
CN219103832U (en) External online circulation cleaning device for heat exchanger driven by internal combustion engine
CN210486558U (en) Vacuum system suitable for gas-steam combined cycle unit

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant