CN217480090U - Wall infiltration leaking stoppage equipment based on power station - Google Patents

Wall infiltration leaking stoppage equipment based on power station Download PDF

Info

Publication number
CN217480090U
CN217480090U CN202221122700.4U CN202221122700U CN217480090U CN 217480090 U CN217480090 U CN 217480090U CN 202221122700 U CN202221122700 U CN 202221122700U CN 217480090 U CN217480090 U CN 217480090U
Authority
CN
China
Prior art keywords
end position
wall surface
plugging device
flexible
device body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202221122700.4U
Other languages
Chinese (zh)
Inventor
张玉
陈森森
陈华煜
王军
张松龙
康成兵
孙益林
顾生丰
张柏龙
张克芬
刘军华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanjing Kangtai Building Grouting Technology Co ltd
Original Assignee
Nanjing Kangtai Building Grouting Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanjing Kangtai Building Grouting Technology Co ltd filed Critical Nanjing Kangtai Building Grouting Technology Co ltd
Priority to CN202221122700.4U priority Critical patent/CN217480090U/en
Application granted granted Critical
Publication of CN217480090U publication Critical patent/CN217480090U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

The utility model discloses a wall surface water seepage and leakage stoppage device based on a hydropower station, which comprises a leakage stoppage device body, a flexible connecting extension tube is arranged at the inner position of the pulp outlet head, a connecting baffle ring is arranged at the left end position of the flexible connecting extension tube, the plugging device body is provided with a connecting sleeve, the lower end of the connecting sleeve is provided with a fastening knob, a connecting column is arranged at the upper end of the connecting sleeve, a connecting baffle plate is arranged at the upper end of the connecting column, a rubber plug is arranged at the tail end of the connecting rod, the connecting baffle plate can effectively avoid the problem that the grout flowing out is solidified and is difficult to clean due to inconvenient cleaning when workers inject the grout, effectively improves the working efficiency, through adding flexible coupling pipe can effectually avoid when the gap of wall is great water, mud hardly enters into the gap depths and causes the not good phenomenon of leaking stoppage effect to take place.

Description

Wall infiltration leaking stoppage equipment based on power station
Technical Field
The utility model belongs to the technical field of the wall infiltration leaking stoppage is relevant, concretely relates to wall infiltration leaking stoppage equipment based on power station.
Background
The hydropower station consists of a hydraulic system, a mechanical system, an electric energy generating device and the like, is a hydro-junction project for converting water energy into electric energy, and the sustainability of electric energy production requires that the utilization of the water energy of the hydropower station is uninterrupted. The hydropower station is realized by a hydro-electrical system in order to effectively convert water energy in the reservoir into electric energy, and the system mainly comprises a pressure water conduit, a water turbine, a generator, a tail water pipe and the like.
The existing wall surface water seepage and leakage stoppage equipment technology based on the hydropower station has the following problems: when cement paste is injected into a wall gap, the cement paste flows down along the wall from the wall gap easily, and the cement paste flowing out is solidified and is difficult to clean due to inconvenient cleaning when workers inject the cement paste.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a wall infiltration leaking stoppage equipment based on power station to solve the current wall infiltration leaking stoppage based on power station that provides in the above-mentioned background art and when going on pouring into the grout into the wall gap, the grout flows down along the wall from the wall gap easily, and the grout solidification problem of difficult clearance that leads to flowing of clearance of being not convenient for clear up when staff pours into the grout into.
In order to achieve the above object, the utility model provides a following technical scheme: a wall infiltration leaking stoppage equipment based on hydropower station comprises a leaking stoppage equipment body, wherein a grout outlet head is arranged at the left end position of the leaking stoppage equipment body, a bendable connecting telescopic pipe is arranged at the inner position of the grout outlet head, a connecting baffle ring is arranged at the left end position of the bendable connecting telescopic pipe, a connecting sleeve is arranged on the leaking stoppage equipment body, a fastening knob is arranged at the lower end position of the connecting sleeve, a connecting column is arranged at the upper end position of the connecting sleeve, a connecting baffle is arranged at the upper end position of the connecting column, a rear cover is arranged at the right end position of the leaking stoppage equipment body, a mobile connecting piece is arranged at the right end position of the rear cover, a pulling ring is arranged at the right end position of the mobile connecting piece, a connecting rod is arranged at the left end intermediate position of the mobile connecting piece, and a rubber plug is arranged at the tail end position of the connecting rod, the leaking stoppage equipment body adopts stainless steel material to make and forms, the centre of the leaking stoppage equipment body is through-hole structure, the leaking stoppage equipment body is close to right side inner wall position department and is provided with the screw thread, the adapter sleeve adopts PVC material to make and forms, the adapter sleeve rotates through the pivot with connecting the sideboard and is connected, it adopts stainless steel material to make and forms to connect the sideboard, it is cuboid platelike structure to connect the sideboard, the inside of rearmounted lid is provided with the helicitic texture, the rearmounted is covered and is provided with the hole, the hole internal diameter that the rearmounted was covered and is set up equals the external diameter of connecting rod, the inside of flexible connection telescopic pipe is made for the silica gel material and is formed, flexible connection telescopic pipe outside is made for rubber materials, the rubber buffer adopts rubber materials to make and forms, the rubber buffer is connected with the removal connection piece through the connecting rod, the pull ring is the cyclic annular structure that adopts the polyethylene material to make and form, the pull ring and the movable connecting piece are of an integrated structure.
Preferably, the leakage stoppage device body is made of stainless steel materials, a through hole structure is arranged in the middle of the leakage stoppage device body, and threads are arranged at the position, close to the right end, of the leakage stoppage device body.
Preferably, the connecting sleeve is made of PVC materials and is rotatably connected with the connecting baffle plate through a rotating shaft.
Preferably, the connecting baffle plates are made of stainless steel materials and are of cuboid plate structures.
Preferably, the inside of the rear cover is provided with a thread structure, the rear cover is provided with a hole, and the inner diameter of the hole formed in the rear cover is equal to the outer diameter of the connecting rod.
Preferably, the flexible pipe of flexible connection inside is the silica gel material preparation and forms, flexible connection outside of tubes is the rubber materials preparation and forms.
Preferably, the rubber buffer adopts rubber materials to make and forms, the rubber buffer is connected with the removal connection piece through the connecting rod.
Preferably, the pull ring is an annular structure made of polyethylene materials, and the pull ring and the movable connecting piece are of an integrated structure.
Compared with the prior art, the beneficial effects of the utility model are that:
1. the utility model discloses a be provided with the adapter sleeve on the leaking stoppage equipment body, the lower extreme position department of adapter sleeve is provided with the fastening knob, the upper end position department of adapter sleeve is provided with the spliced pole, the upper end position department of spliced pole is provided with the connection sideboard, the adapter sleeve adopts PVC material to make and forms, adapter sleeve and connection sideboard rotate through the pivot to be connected, the connection sideboard adopts stainless steel material to make and forms, the connection sideboard is cuboid platelike structure, because current wall infiltration leaking stoppage based on power station is when carrying out the grout injection to the wall gap, the grout flows down along the wall from the wall gap easily, and the grout solidification that leads to flowing out of easy clearance when staff injects the grout is inconvenient, finally lead to the busy work efficiency of follow-up work change influence, through improving, the staff can be connected the sideboard wall when carrying out the grout injection with the connection sideboard rotation to suitable position department, when grout flowed down along the wall from the wall gap, the staff can use and connect the sideboard and scrape and get, collect the grout that flows on connecting the sideboard, connect the sideboard through adding and be not convenient for clear up when can effectually avoiding the staff to pour into grout and lead to the grout that flows to solidify difficult clearance, the effectual work efficiency that has improved.
2. The utility model discloses a position department is provided with flexible connection pipe in the inside of play thick liquid head, the left end position department of flexible connection pipe is provided with connects the fender ring, the flexible connection pipe's of flexible inside is made for the silica gel material, flexible connection pipe outside is made for rubber materials, when the gap of wall is great, the depth of gap also can be relatively dark, when the staff carries out the injection grout in gap department, grout hardly gets into the gap depths, and plugging equipment body department is thicker inconvenient to get into the gap, through improving, when the gap of wall is great, when the gap is darker, the staff can pull out flexible connection pipe, extend it to the gap inside, because flexible connection pipe flexibility is better, flexible connection pipe more suits the environment in the gap, can effectively avoid water when the gap of wall is great through adding flexible connection pipe, the slurry is difficult to enter the deep part of the gap, so that the leaking stoppage effect is poor.
Drawings
Fig. 1 is a schematic view of the overall structure of the wall surface water seepage plugging device based on the hydropower station of the utility model;
fig. 2 is a schematic drawing of the drawing structure of the flexible connecting telescopic pipe of the wall seepage plugging device based on the hydropower station of the utility model;
fig. 3 is a schematic structural view of the wall surface water seepage plugging device based on the hydropower station without plugging device body of the utility model;
fig. 4 is a schematic structural view of the plugging device body pulling-out position of the wall surface water seepage plugging device based on the hydropower station of the utility model;
in the figure: 1. connecting the barrier plates; 2. discharging the pulp head; 3. connecting a baffle ring; 4. fastening a knob; 5. connecting columns; 6. connecting sleeves; 7. a plugging device body; 8. moving the connecting sheet; 9. pulling the ring; 10. a rear cover; 11. the telescopic pipe can be flexibly connected; 12. a rubber plug; 13. a connecting rod.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-4, the present invention provides a technical solution: a wall surface water seepage plugging device based on a hydropower station comprises a plugging device body 7, a grout outlet head 2 is arranged at the left end position of the plugging device body 7, a flexible connecting extension pipe 11 is arranged at the inner position of the grout outlet head 2, the left end position department of flexible connection flexible pipe 11 is provided with connects and keeps off ring 3, be provided with adapter sleeve 6 on the leaking stoppage equipment body 7, the lower extreme position department of adapter sleeve 6 is provided with fastening knob 4, the upper end position department of adapter sleeve 6 is provided with spliced pole 5, the upper end position department of spliced pole 5 is provided with connects sideboard 1, the right-hand member position department of leaking stoppage equipment body 7 is provided with rearmounted lid 10, the right-hand member position department of rearmounted lid 10 is provided with removal connection piece 8, the right-hand member position department of removing connection piece 8 is provided with pulls ring 9, the left end intermediate position department of removing connection piece 8 is provided with connecting rod 13, the end position department of connecting rod 13 is provided with rubber buffer 12.
The leaking stoppage equipment body 7 is made of stainless steel materials, the middle of the leaking stoppage equipment body 7 is of a through hole structure, the leaking stoppage equipment body 7 is provided with threads close to the position of the right end, the inside of the rear cover 10 is provided with a threaded structure, the rear cover 10 is provided with a hole, the inner diameter of the hole formed in the rear cover 10 is equal to the outer diameter of the connecting rod 13, the rubber plug 12 is made of rubber materials, the rubber plug 12 is connected with the movable connecting piece 8 through the connecting rod 13, the pulling ring 9 is an annular structure made of polyethylene materials, and the pulling ring 9 and the movable connecting piece 8 are of an integral structure.
When the plugging device works, a worker pulls the pulling ring 9, and the rubber plug 12 moves, so that air pressure is strong to press cement slurry into the plugging device body 7 to be used.
The connecting sleeve 6 is made of PVC materials, the connecting sleeve 6 is rotationally connected with the connecting baffle plate 1 through a rotating shaft, the connecting baffle plate 1 is made of stainless steel materials, and the connecting baffle plate 1 is of a cuboid plate-shaped structure.
When in work, because the existing hydropower station-based wall seepage plugging is carried out when cement paste is injected into the wall gap, the cement paste is easy to flow down along the wall from the wall gap, and the grout is inconvenient to clean when being injected into the grout by workers, so that the grout flowing out is solidified and is difficult to clean, and the subsequent work is changed busy to influence the work efficiency, after the improvement, a worker can rotate the connecting baffle plate 1 to a proper position so that the worker can attach the connecting baffle plate 1 to the wall surface when injecting cement paste, when the cement paste flows down from the gap of the wall surface along the wall surface, a worker can scrape the cement paste by using the connecting baffle plate 1, collect the flowing cement paste on the connecting baffle plate 1, connecting through adding that sideboard 1 can effectually avoid the staff to pour into the grout into when the clearance of being not convenient for lead to the grout that flows to solidify and be difficult to clear up, effectual work efficiency that has improved.
The flexible connection telescopic pipe 11 is made of silica gel materials inside, and the flexible connection telescopic pipe 11 is made of rubber materials outside.
The during operation, because when the gap of wall is great, the degree of depth in gap also can be for darker, the staff is when the grout is injected in gap department, the grout hardly enters into the gap depths, and 7 departments of leaking stoppage equipment are thick inconvenient gap of getting into, through improving the back, when the gap of wall is great, when the gap is more dark, the staff can pull out flexible pipe 11 of flexible connection, extend it to the gap inside, because flexible pipe 11 pliability of flexible connection is better, so the environment in the flexible pipe 11 more suitable gap of flexible connection, through adding flexible pipe 11 of flexible connection can effectually avoid the great time water in the gap of wall, mud hardly enters into the gap depths and causes the not good phenomenon of leaking stoppage effect to take place.
The utility model discloses a theory of operation and use flow: after the utility model is installed, the worker pulls the ring 9 by pulling, the movement of the rubber plug 12 can lead the air to force the cement paste to be pressed into the plugging device body 7 for standby use, because the existing wall seepage plugging based on the hydropower station is carried out when the cement paste is injected into the wall gap, the cement paste can easily flow down along the wall surface from the wall gap, and the cement paste flowing out is solidified and is difficult to be cleaned when the worker injects the cement paste, and finally the subsequent work is changed to busy to influence the work efficiency, after the improvement, the worker can rotate the connecting baffle plate 1 to a proper position to lead the worker to connect the baffle plate 1 to be close to the wall surface when injecting the cement paste, when the cement paste flows down along the wall surface from the wall gap, the worker can scrape the connecting baffle plate 1 and collect the flowing cement paste on the connecting baffle plate 1, the connecting baffle plate 1 can effectively avoid the phenomenon that when a worker injects cement slurry, the grout is not convenient to clean and is difficult to clean, the work efficiency is effectively improved, when the gap of the wall is large, the depth of the gap is also relatively deep, when the worker injects the cement slurry at the gap, the cement slurry is difficult to enter the deep part of the gap, and the leakage stoppage device body 7 is thicker and is inconvenient to enter the gap, after improvement, when the gap of the wall is large, and the gap is deep, the worker can pull out the flexible connection extension tube 11 to extend the flexible connection extension tube 11 to the inner part of the gap, because the flexible connection extension tube 11 has better flexibility, the flexible connection extension tube 11 is more suitable for the environment in the gap, and the phenomenon that when the gap of the wall is large, the grout is difficult to enter the deep part of the gap to cause poor leakage stoppage effect can be effectively avoided by adding the flexible connection extension tube 11, after the work is finished, the staff extracts clear water and discharges the clear water to repeatedly execute the clear water until the plugging equipment is cleaned and then is collected.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (8)

1. The utility model provides a wall infiltration leaking stoppage equipment based on power station, includes the leaking stoppage equipment body (7), its characterized in that: the left end position of the plugging device body (7) is provided with a slurry outlet head (2), the inner position of the slurry outlet head (2) is provided with a flexible connecting pipe (11), the left end position of the flexible connecting pipe (11) is provided with a connecting baffle ring (3), the plugging device body (7) is provided with a connecting sleeve (6), the lower end position of the connecting sleeve (6) is provided with a fastening knob (4), the upper end position of the connecting sleeve (6) is provided with a connecting column (5), the upper end position of the connecting column (5) is provided with a connecting baffle plate (1), the right end position of the plugging device body (7) is provided with a rear cover (10), the right end position of the rear cover (10) is provided with a movable connecting sheet (8), the right end position of the movable connecting sheet (8) is provided with a movable ring (9), remove the left end intermediate position department of connection piece (8) and be provided with connecting rod (13), the terminal position department of connecting rod (13) is provided with rubber buffer (12).
2. The wall surface water seepage and leakage stoppage equipment based on the hydropower station as claimed in claim 1, which is characterized in that: the leakage stoppage device body (7) is made of stainless steel materials, a through hole structure is arranged in the middle of the leakage stoppage device body (7), and threads are arranged at the position, close to the right end, of the leakage stoppage device body (7).
3. The wall surface water seepage and leakage stoppage equipment based on the hydropower station as claimed in claim 1, which is characterized in that: the connecting sleeve (6) is made of PVC materials, and the connecting sleeve (6) is rotationally connected with the connecting baffle plate (1) through a rotating shaft.
4. The wall surface water seepage and plugging device based on the hydropower station as claimed in claim 1, which is characterized in that: the connecting baffle plate (1) is made of stainless steel materials, and the connecting baffle plate (1) is of a cuboid plate-shaped structure.
5. The wall surface water seepage and plugging device based on the hydropower station as claimed in claim 1, which is characterized in that: the inside of rearmounted lid (10) is provided with helicitic texture, be provided with the hole on rearmounted lid (10), the hole internal diameter that sets up on rearmounted lid (10) equals the external diameter of connecting rod (13).
6. The wall surface water seepage and plugging device based on the hydropower station as claimed in claim 1, which is characterized in that: the flexible inside of connecting flexible pipe (11) forms for the preparation of silica gel material, flexible connecting flexible pipe (11) outside forms for the preparation of rubber materials.
7. The wall surface water seepage and plugging device based on the hydropower station as claimed in claim 1, which is characterized in that: rubber buffer (12) adopt rubber materials to make and form, rubber buffer (12) are connected with removal connection piece (8) through connecting rod (13).
8. The wall surface water seepage and plugging device based on the hydropower station as claimed in claim 1, which is characterized in that: the pull ring (9) is an annular structure made of polyethylene materials, and the pull ring (9) and the movable connecting piece (8) are of an integrated structure.
CN202221122700.4U 2022-05-11 2022-05-11 Wall infiltration leaking stoppage equipment based on power station Active CN217480090U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221122700.4U CN217480090U (en) 2022-05-11 2022-05-11 Wall infiltration leaking stoppage equipment based on power station

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221122700.4U CN217480090U (en) 2022-05-11 2022-05-11 Wall infiltration leaking stoppage equipment based on power station

Publications (1)

Publication Number Publication Date
CN217480090U true CN217480090U (en) 2022-09-23

Family

ID=83309969

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221122700.4U Active CN217480090U (en) 2022-05-11 2022-05-11 Wall infiltration leaking stoppage equipment based on power station

Country Status (1)

Country Link
CN (1) CN217480090U (en)

Similar Documents

Publication Publication Date Title
CN206245384U (en) A kind of energy-conserving and environment-protective water conservancy irrigation device with rainwater-collecting and water filtration function
CN217480090U (en) Wall infiltration leaking stoppage equipment based on power station
CN106034998A (en) Movable irrigator with water diversion driven by multiple power
CN217026751U (en) Slip casting device is used in municipal administration road bridge construction
CN209941685U (en) Curtain slip casting water plugging device in confined water stratum
CN101597954A (en) Caulking device and method for building facing bricks
CN207959726U (en) Reinforced bar sleeve grouting self-closing apparatus
CN110841523A (en) Multifunctional loam matrix spray-seeding equipment for mine restoration
CN209935443U (en) Building pipeline silt cleaning device
CN214683362U (en) Belt cleaning device of polycarboxylate water reducing agent storage tank
CN213639165U (en) Energy-saving irrigation device
CN214532989U (en) Shield constructs quick-witted slip casting pipeline
CN214007117U (en) Oil field water injection well is with scale removal device that has protective structure
CN212733520U (en) Landfill district leachate cyclic utilization device
CN212193621U (en) Water spraying device for building concrete maintenance
CN212317903U (en) Drilling mud guiding device
CN209750872U (en) Water-saving shower capable of adjusting water flow force
CN209114594U (en) A kind of inner wall of the pipe cleaning equipment
CN202954851U (en) Decompression and drainage device of wall
CN217378784U (en) Seepage-proofing reinforcing construction device for dam foundation of hydraulic engineering dam
CN216948147U (en) Water conservancy and hydropower engineering constructs water conservancy diversion drainage structures in hole
CN216741445U (en) Double-layer grouting flange plate pipe fixing device for drilling
CN217663066U (en) Pneumatic mixed flow device of cyclone spray tower
CN218029053U (en) Waterproof device is applied paint with a brush in shutoff of shear force wall hole
CN221193347U (en) Pull rod hole grouting device and culvert grouting system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant