CN217478812U - Host installation mechanism for villa elevator - Google Patents

Host installation mechanism for villa elevator Download PDF

Info

Publication number
CN217478812U
CN217478812U CN202221678780.1U CN202221678780U CN217478812U CN 217478812 U CN217478812 U CN 217478812U CN 202221678780 U CN202221678780 U CN 202221678780U CN 217478812 U CN217478812 U CN 217478812U
Authority
CN
China
Prior art keywords
bearing frame
frame
reinforcing
main frame
main
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202221678780.1U
Other languages
Chinese (zh)
Inventor
杨益峰
程剑
邓康
李跃
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Eysar Elevator Co ltd
Original Assignee
Eysar Elevator Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Eysar Elevator Co ltd filed Critical Eysar Elevator Co ltd
Priority to CN202221678780.1U priority Critical patent/CN217478812U/en
Application granted granted Critical
Publication of CN217478812U publication Critical patent/CN217478812U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Lift-Guide Devices, And Elevator Ropes And Cables (AREA)

Abstract

The utility model relates to a villa is host computer installation mechanism for elevator, its characterized in that: the main frame comprises a first bearing frame connected to the oppositely arranged counterweight guide rails, a second bearing frame connected to the oppositely arranged main guide rails and a main frame for installing a main machine; the first bearing frame and the second bearing frame are connected with a hoistway; the main frame is connected on the first bearing frame and the second bearing frame. The problem of when the well does not have the hole or the hole position is incorrect among the current scheme, need modify the well before the host computer installation, lead to elevator installation technology loaded down with trivial details is solved.

Description

Host installation mechanism for villa elevator
Technical Field
The utility model relates to an elevator field especially relates to a host installation mechanism for villa elevator.
Background
At present, the main machine of the elevator is fixed by adopting a scheme that an installation support of the main machine of the elevator is placed in a reserved hole on a wall of a hoistway. However, due to various reasons, no hole is reserved on the wall of the hoistway or the position of the reserved hole is incorrect, great troubles are brought to the rectification and modification of the hoistway before the elevator is installed, the villa elevator is used as an indoor additional elevator, the opening of the hoistway in the indoor is limited, and therefore, how to install the elevator traction machine (host machine) in the existing hoistway without the opening at the top can be realized in the hoistway which is not suitable for the opening. When no hole is left in the well with the reinforced concrete structure or the position of the hole is incorrect, the well needs to be rectified before the host machine is installed, so that the elevator installation process is complicated. How to solve this problem becomes crucial.
Disclosure of Invention
To above-mentioned prior art's shortcoming, the utility model aims at providing a villa is host installation mechanism for elevator to when the well does not leave the hole or leave the hole position incorrect among the solution prior art, need rectify the well before the host installation, lead to the loaded down with trivial details problem of elevator installation technology.
In order to achieve the above purpose, the technical scheme of the utility model is as follows:
a host installation mechanism for villa elevator;
the device comprises a first bearing frame connected to oppositely arranged counterweight guide rails, a second bearing frame connected to oppositely arranged main guide rails and a main frame for mounting a main machine; the first bearing frame and the second bearing frame are connected with a hoistway; the main frame is connected on the first bearing frame and the second bearing frame.
The further technical scheme is as follows: the first bearing frame and the second bearing frame are arranged on the first bearing frame; the accessory is arranged on the shaft; each group of accessories is respectively connected with the first bearing frame and the second bearing frame.
The further technical scheme is as follows: the reinforcing mechanism is used for supporting the main frame; the reinforcing mechanism comprises reinforcing rods which are arranged in a mutually crossed manner and reinforcing plates for supporting the main frame; the reinforcing plates are arranged at the positions where the reinforcing rods are intersected with each other; the reinforcing rod is respectively connected with the first bearing frame and the second bearing frame.
The further technical scheme is as follows: the reinforcing rod is connected with the first bearing frame and the second bearing frame, and the positions of the first bearing frame and the second bearing frame are higher than the position of the reinforcing plate for supporting the main frame.
The further technical scheme is as follows: the first bearing frame and the second bearing frame are respectively provided with a connecting frame; the reinforcing rod penetrates through the connecting frame; the reinforcing rod is in threaded connection with a first locking piece; the first locking member tensions the reinforcement bar.
The further technical scheme is as follows: flat rods are arranged at two ends of the reinforcing rod; the connecting frame is provided with a flat hole; the flat rod penetrates through the flat hole, and the flat hole limits the flat rod to rotate; the first locking member is in threaded connection with the flat bar.
The further technical scheme is as follows: a reinforcing pipe is arranged on the reinforcing plate along the direction of the reinforcing rod; the reinforcing rod penetrates through the reinforcing pipe.
The further technical scheme is as follows: the main frame is connected with the first bearing frame and the second bearing frame through a stabilizing mechanism; mounting holes are formed in the first bearing frame and the second bearing frame; the stabilizing mechanism comprises a first fixing piece, a second locking piece for fixing the main frame, an elastic device for pressing the main frame and a third locking piece for adjusting the pressing force of the elastic device; the first fixing piece penetrates through the mounting hole and the main frame; the second locking piece is in threaded connection with the first fixing piece; the elastic device is sleeved between the main frame and the third locking piece on the first fixing piece; the third locking member is screwed along the first fixing member.
The further technical scheme is as follows: the elastic device is a spring.
Compared with the prior art, the utility model discloses a beneficial technological effect as follows: (1) the first bearing frame and the second bearing frame are supported and fixed through the accessories, the main frame is fixed in the hoistway through the first bearing frame and the second bearing frame to complete the installation of the main machine, the installation of the main machine can be completed without changing the hoistway structure, and the rectification and improvement of the hoistway civil engineering are reduced; (2) the pressing force of the elastic device on the main frame can be adjusted by screwing the third locking piece, the main machine can vibrate during working, the vibration can be transmitted to the main frame, the vibration of the main frame can be eliminated through the elastic device, and the vibration on the main frame can be completely eliminated by adjusting the third locking piece; (3) the positions of the front end and the rear end of the reinforcing rod are higher than the positions of the reinforcing plates, so that the reinforcing rod forms upward thrust on the reinforcing plates, and the main frame is supported by the reinforcing plates; (4) the reinforcing rods are in a tensioning state by screwing the first locking pieces, so that the structural strength of the reinforcing rods is improved, and the reinforcing plates can stably support the main frame; (5) the reinforcing pipes are welded on the lower surface of the reinforcing plate in the horizontal direction, and penetrate through the reinforcing pipes through the reinforcing rods, so that the reinforcing plate is prevented from displacing, and the reinforcing plate can continuously support the main frame; (6) run through the flat hole through the flat pole for the flat hole restriction flat pole rotating makes the support reinforcing plate that the reinforcing rod can be stable, makes the support body frame that the reinforcing plate can last.
Drawings
Fig. 1 shows the first embodiment of the utility model discloses host installation mechanism for villa elevator overlook the structure chart.
Fig. 2 shows the second embodiment of the utility model discloses host installation mechanism for villa elevator overlook the structure chart.
Fig. 3 is a front view structural view showing a stabilizing mechanism according to a second embodiment of the present invention.
Fig. 4 shows a plan view structure diagram of a host installation mechanism for a villa elevator according to a third embodiment of the present invention.
Fig. 5 is a top view structural view of a reinforcing mechanism according to a third embodiment of the present invention.
Fig. 6 shows a plan view structure diagram of the host installation mechanism for villa elevator in the fourth embodiment of the present invention.
Fig. 7 is a top view structural view of a reinforcing mechanism according to a fourth embodiment of the present invention.
In the drawings, the reference numbers: 1. a first bearing frame; 2. a second bearing frame; 3. a main frame; 4. an accessory; 5. a reinforcing mechanism; 51. a reinforcing bar; 52. a reinforcing plate; 53. a first locking member; 54. a flat bar; 55. a reinforcement tube; 6. a connecting frame; 61. flat holes; 7. a stabilizing mechanism; 71. mounting holes; 72. a first fixing member; 73. a second locking member; 74. an elastic device; 75. and a third locking member.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more clearly understood, the following detailed description of the device according to the present invention is made with reference to the accompanying drawings and the detailed description of the present invention. The advantages and features of the present invention will become more apparent from the following description. It should be noted that the drawings are in a very simplified form and are not to precise scale, and are provided for convenience and clarity in order to assist in describing embodiments of the present invention. To make the objects, features and advantages of the present invention more comprehensible, please refer to the attached drawings. It should be understood that the structure, proportion, size and the like shown in the drawings attached to the present specification are only used for matching with the content disclosed in the specification, so as to be understood and read by those skilled in the art, and are not used for limiting the limitation of the implementation of the present invention, so that the present invention does not have the essential technical meaning, and any modification of the structure, change of the proportion relation or adjustment of the size should still fall within the scope that the technical content disclosed in the present invention can cover without affecting the function and the achievable purpose of the present invention.
Fig. 1 shows the first embodiment of the utility model discloses host installation mechanism for villa elevator overlook the structure chart. As shown in the combined figure 1, the utility model discloses a host installation mechanism for villa elevator. The direction of X in the figure is the front end of the overlooking structure chart of the utility model, and the direction of Y in the figure is the right end of the overlooking structure chart of the utility model.
Host installation mechanism for villa elevator is including connecting first bearing frame 1 on the counter-weight guide rail that sets up relatively, connecting second bearing frame 2 and the body frame 3 of installation host computer on the main guide rail that sets up relatively. The first bearing frame 1 and the second bearing frame 2 are connected with a hoistway. The main frame 3 is connected to the first bearing frame 1 and the second bearing frame 2.
The host installation mechanism for the villa elevator further comprises an accessory 4 for supporting the first bearing frame 1 and the second bearing frame 2. The attachment 4 is provided on the hoistway. Each set of accessories 4 is connected with the first bearing frame 1 and the second bearing frame 2 respectively.
The counterweight guide rail is arranged at the front end in the hoistway in the vertical direction. The counterweight guide rails are oppositely arranged in the left and right directions. The main guide rail is arranged at the left end and the right end in the shaft in the vertical direction. The main guide rail is arranged oppositely in the left and right directions. The first bearing frame 1 is arranged at the front end in the hoistway in the left-right direction. The left end and the right end of the first bearing frame 1 are connected with the upper end of the counterweight guide rail. The second bearing frame 2 is disposed at a middle position in the hoistway in the left-right direction. The left end and the right end of the second bearing frame 2 are connected with the upper end of the main guide rail. The main frame 3 is arranged in the front-rear direction. The front end of the main frame 3 is connected with the first bearing frame 1. The rear end of the main frame 3 is connected with the second bearing frame 2. The main machine is arranged at the upper end of the main frame 3.
First bearing frame 1 is connected to the heavy guide rail through bolt assembly, and bolt assembly runs through first bearing frame 1 through the bolt and to heavy guide rail, through screwing up the nut with first bearing frame 1 with to heavy guide rail fixed connection.
Preferably, the appendages 4 are in two groups. A first set of accessories 4 connects the shaft and the first load bearing frame 1. A second set of accessories 4 connects the hoistway with the second load bearing frame 2. The first set of attachments 4 connect the hoistway and the first load bearing frame 1 by means of expansion bolt assemblies. The expansion bolts penetrate through the first bearing frame 1 and the first group of accessories 4 and then are embedded into the well, and the first bearing frame 1 and the first group of accessories 4 are fixed in the well by tightening nuts. The second set of attachments 4 connect the hoistway and the second load bearing frame 2 by means of expansion bolt assemblies. The expansion bolts penetrate through the second bearing frame 2 and the second group of accessories 4 and then are embedded into the well, and the second bearing frame 2 and the second group of accessories 4 are fixed in the well by tightening nuts.
Support fixed first bearing frame 1 and second bearing frame 2 through annex 4, fix the installation of accomplishing the host computer in the well through first bearing frame 1 and second bearing frame 2 with body frame 3, need not to change the well structure and just can accomplish the installation of host computer, reduced the rectification of well civil engineering.
Second embodiment:
fig. 2 shows the second embodiment of the utility model discloses villa host installation mechanism for elevator overlook structure chart. Fig. 3 is a front view structural view showing a stabilizing mechanism according to a second embodiment of the present invention. As shown in fig. 1, 2 and 3, the second embodiment is different from the first embodiment in that:
the main frame 3 is connected with the first bearing frame 1 and the second bearing frame 2 through a stabilizing mechanism 7. The first bearing frame 1 and the second bearing frame 2 are provided with mounting holes 71. The stabilizing mechanism 7 includes a first fixing member 72, a second locking member 73 that fixes the main frame 3, an elastic device 74 that presses the main frame 3, and a third locking member 75 that adjusts the pressing force of the elastic device 74. The first fixing member 72 penetrates the mounting hole 71 and the main frame 3. The second locker 73 is screw-coupled to the first holder 72. The elastic device 74 is sleeved on the first fixing part 72 between the main frame 3 and the third locking part 75. The third locking member 75 is screwed along the first fixing member 72.
Preferably, the resilient means 74 is a spring.
Preferably, the mounting hole 71 is a kidney-shaped hole.
Preferably, the first fixing member 72 is a bolt. Preferably, the second locking member 73 is a nut. The first fixing member 72 vertically penetrates the mounting hole 71 and the main frame 3. The main frame 3 is fixed on the first bearing frame 1 and the second bearing frame 2 after the second locking piece 73 is screwed down. The elastic device 74 is vertically sleeved on the first fixing member 72.
Preferably, the third locking member 75 is a nut. The third locker 75 is screw-coupled to the upper end of the first holder 72.
The upper end of the resilient means 74 abuts against the third locking member 75. The lower end of the elastic means 74 abuts against the main frame 3.
By screwing the third locking member 75 downward, the third locking member 75 moves downward along the first fixing member 72, and the third locking member 75 presses the resilient means 74 downward, increasing the force with which the resilient means 74 presses the main frame 3 downward.
By twisting the third locking member 75 upward, the third locking member 75 moves upward along the first fixing member 72, and the third locking member 75 no longer presses the resilient means 74, reducing the force with which the resilient means 74 presses the main frame 3 downward.
The magnitude of the pressing force of the elastic means 74 against the main frame 3 can be adjusted by screwing the third locking member 75, and the main machine vibrates during operation, and the vibration is transmitted to the main frame 3, and the vibration of the main frame 3 can be eliminated by the elastic means 74. By adjusting the third locking member 75 it is ensured that vibrations in the main frame 3 can be completely eliminated.
The third embodiment:
fig. 4 shows a plan view structure diagram of a host installation mechanism for a villa elevator according to a third embodiment of the present invention. Fig. 5 shows a top view structural view of a reinforcing mechanism according to a third embodiment of the present invention. As shown in fig. 1, 4 and 5, the third embodiment is different from the first embodiment in that:
the host installation mechanism for the villa elevator further comprises a reinforcing mechanism 5 for supporting the main frame 3. The reinforcing mechanism 5 includes reinforcing rods 51 arranged to cross each other and reinforcing plates 52 supporting the main frame 3. The reinforcing plates 52 are provided at positions where the reinforcing rods 51 cross each other. The reinforcing rods 51 are connected to the first carrier 1 and the second carrier 2, respectively.
Preferably, the stiffeners 51 are in two sets. The reinforcing bars 51 are arranged to cross each other in an X-shape. The reinforcing plates 52 are disposed horizontally at positions where the reinforcing rods 51 cross each other. The front end of the reinforcing rod 51 is connected with the first bearing frame 1. The rear end of the reinforcing bar 51 is connected to the second carrier 2.
The position of the reinforcing rod 51 connecting the first bearing frame 1 and the second bearing frame 2 is higher than the position of the reinforcing plate 52 supporting the main frame 3.
The front and rear ends of the reinforcing bar 51 are positioned higher than the reinforcing plate 52. So that the reinforcing bar 51 exerts an upward urging force on the reinforcing plate 52 and supports the main frame 3 via the reinforcing plate 52.
The first bearing frame 1 and the second bearing frame 2 are respectively provided with a connecting frame 6. The reinforcing rods 51 extend through the connecting frame 6. A first locking member 53 is threadedly coupled to the reinforcing rod 51. The first locking member 53 tightens the reinforcing bar 51.
The connecting frame 6 is arranged on the first carrier 1 and on the second carrier 2, respectively, towards the reinforcing bar 51.
Preferably, the first locking member 53 is a nut. The reinforcing bar 51 is placed in a tensioned state by tightening the first locking member 53, and the structural strength of the reinforcing bar 51 is improved, so that the reinforcing plate 52 can stably support the main frame 3.
The reinforcing plate 52 is provided with a reinforcing tube 55 along the direction of the reinforcing rod 51. The reinforcing rod 51 extends through the reinforcing tube 55.
The reinforcing pipe 55 has a through structure. The reinforcing pipe 55 is welded horizontally to the lower surface of the reinforcing plate 52. The reinforcing rod 51 penetrates the reinforcing tube 55, so that the reinforcing plate 52 is prevented from being displaced, and the reinforcing plate 52 can continuously support the main frame 3.
The fourth embodiment:
fig. 6 shows a plan view structure diagram of the host installation mechanism for villa elevator in the fourth embodiment of the present invention. Fig. 7 is a top view structural view of a reinforcing mechanism according to a fourth embodiment of the present invention. As shown in fig. 1, 4, 5, 6 and 7, the fourth embodiment is different from the third embodiment in that:
flat bars 54 are provided at both ends of the reinforcing bar 51. The connecting frame 6 is provided with a flat hole 61. Flat bar 54 extends through flat hole 61, and flat hole 61 restricts rotation of flat bar 54. The first locking member 53 is threaded onto the flat bar 54.
Flat bars 54 are provided at the front and rear ends of the reinforcing bar 51. The flat hole 61 includes, but is not limited to, a kidney-shaped hole, a square hole. Threads are formed on both sides of the flat rod 54. The flat bar 54 is screw-coupled to the first locking member 53 at both sides. The flat rod 54 penetrates through the flat hole 61, so that the flat hole 61 limits the flat rod 54 to rotate, the reinforcing plate 52 can be stably supported by the reinforcing rod 51, and the main frame 3 can be continuously supported by the reinforcing plate 52.
The technical features of the embodiments described above may be arbitrarily combined, and for the sake of brevity, all possible combinations of the technical features in the embodiments described above are not described, but should be considered as being within the scope of the present specification as long as there is no contradiction between the combinations of the technical features.
The above-mentioned embodiments only represent several embodiments of the present invention, and the description thereof is specific and detailed, but not to be construed as limiting the scope of the invention. It should be noted that, for those skilled in the art, without departing from the spirit of the present invention, several variations and modifications can be made, which are within the scope of the present invention. Therefore, the protection scope of the present invention should be subject to the appended claims.

Claims (9)

1. The utility model provides a host installation mechanism for villa elevator which characterized in that: the main frame comprises a first bearing frame connected to the oppositely arranged counterweight guide rails, a second bearing frame connected to the oppositely arranged main guide rails and a main frame for installing a main machine; the first bearing frame and the second bearing frame are connected with a hoistway; the main frame is connected on the first bearing frame and the second bearing frame.
2. The villa elevator host installation mechanism of claim 1, wherein: the first bearing frame and the second bearing frame are supported by the first bearing frame and the second bearing frame; the accessory is arranged on the shaft; each set of accessories is connected with the first bearing frame and the second bearing frame respectively.
3. The villa elevator host installation mechanism of claim 1, wherein: the main frame also comprises a reinforcing mechanism for supporting the main frame; the reinforcing mechanism comprises reinforcing rods which are arranged in a mutually crossed manner and reinforcing plates which support the main frame; the reinforcing plates are arranged at the positions where the reinforcing rods are crossed with each other; the reinforcing rod is connected with the first bearing frame and the second bearing frame respectively.
4. The villa elevator host installation mechanism of claim 3, wherein: the reinforcing rod is connected with the first bearing frame and the second bearing frame, and the positions of the first bearing frame and the second bearing frame are higher than the positions of the main frame supported by the reinforcing plate.
5. The villa host installation mechanism for elevator of claim 3, characterized in that: the first bearing frame and the second bearing frame are respectively provided with a connecting frame; the reinforcing rod penetrates through the connecting frame; the reinforcing rod is in threaded connection with a first locking piece; the first locking member tensions the reinforcement bar.
6. The villa elevator host installation mechanism of claim 5, wherein: flat rods are arranged at two ends of the reinforcing rod; the connecting frame is provided with a flat hole; the flat rod penetrates through the flat hole, and the flat hole limits the flat rod to rotate; the first locking member is in threaded connection with the flat bar.
7. The villa elevator host installation mechanism of claim 3, wherein: a reinforcing pipe is arranged on the reinforcing plate along the direction of the reinforcing rod; the reinforcing rod penetrates through the reinforcing pipe.
8. The villa host installation mechanism for elevator of claim 1, characterized in that: the main frame is connected with the first bearing frame and the second bearing frame through a stabilizing mechanism; mounting holes are formed in the first bearing frame and the second bearing frame; the stabilizing mechanism comprises a first fixing piece, a second locking piece for fixing the main frame, an elastic device for pressing the main frame and a third locking piece for adjusting the pressing force of the elastic device; the first fixing piece penetrates through the mounting hole and the main frame; the second locking piece is in threaded connection with the first fixing piece; the elastic device is sleeved on the first fixing piece between the main frame and the third locking piece; the third locking member is screwed along the first fixing member.
9. The villa elevator host installation mechanism of claim 8, wherein: the elastic device is a spring.
CN202221678780.1U 2022-06-30 2022-06-30 Host installation mechanism for villa elevator Active CN217478812U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221678780.1U CN217478812U (en) 2022-06-30 2022-06-30 Host installation mechanism for villa elevator

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221678780.1U CN217478812U (en) 2022-06-30 2022-06-30 Host installation mechanism for villa elevator

Publications (1)

Publication Number Publication Date
CN217478812U true CN217478812U (en) 2022-09-23

Family

ID=83317038

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221678780.1U Active CN217478812U (en) 2022-06-30 2022-06-30 Host installation mechanism for villa elevator

Country Status (1)

Country Link
CN (1) CN217478812U (en)

Similar Documents

Publication Publication Date Title
CN217478812U (en) Host installation mechanism for villa elevator
CN209184156U (en) A kind of cable testing bridge installation trailing arm
CN111119461A (en) A operation platform that is used for steel construction elevator well installation top hoisting point
CN219622339U (en) Building beam reinforced structure
CN206987424U (en) A kind of supporting construction and the overlapping harden structure based on the supporting construction
CN2399150Y (en) Crankshaft stress eliminating straightener
CN211681829U (en) Crane part installation auxiliary device convenient to accurate butt joint
CN206957208U (en) A kind of supporting construction for superimposed sheet
CN107130814A (en) A kind of supporting construction and the superimposed sheet structure based on the supporting construction
CN107165409A (en) A kind of supporting construction for superimposed sheet
CN218667899U (en) Steel structure node component for building construction
CN211701665U (en) Firm motor of installation
CN218971731U (en) Vibration reduction supporting mechanism and cloth machine
CN212503524U (en) Elevator host installation structure suitable for reinforced concrete well
CN210767864U (en) Plate bottom support adjusting structure
CN210558774U (en) Elevator air conditioner fixing device
CN214610955U (en) Elevator safety is with overhauing strutting arrangement
CN221075892U (en) Anti-seismic hanging bracket for electromechanical engineering
CN219138371U (en) Novel square timber fixture
CN219887663U (en) House anti-seismic reinforcing device
CN220504618U (en) Reinforcing structure for roof of steel structure factory building
CN209872095U (en) Oblique-pulling elevator door motor
CN220815053U (en) Cantilever beam reinforcing structure
CN219062665U (en) Safety protection device for supporting pipeline
CN217956619U (en) Cable bridge installation hanger

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant