CN217445294U - Combined spiral ground pile for photovoltaic solar installation - Google Patents

Combined spiral ground pile for photovoltaic solar installation Download PDF

Info

Publication number
CN217445294U
CN217445294U CN202221491927.6U CN202221491927U CN217445294U CN 217445294 U CN217445294 U CN 217445294U CN 202221491927 U CN202221491927 U CN 202221491927U CN 217445294 U CN217445294 U CN 217445294U
Authority
CN
China
Prior art keywords
cover
installation
lead screw
spiral
ground
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202221491927.6U
Other languages
Chinese (zh)
Inventor
王宝山
王宝强
辛宗善
贾志英
李凤霞
樊辉勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qingdao Baoqiang Energy Technology Co ltd
Original Assignee
Qingdao Baoqiang Solar Energy Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Qingdao Baoqiang Solar Energy Technology Co ltd filed Critical Qingdao Baoqiang Solar Energy Technology Co ltd
Priority to CN202221491927.6U priority Critical patent/CN217445294U/en
Application granted granted Critical
Publication of CN217445294U publication Critical patent/CN217445294U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/50Photovoltaic [PV] energy

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses a combination formula spiral ground stake for installation of photovoltaic solar energy, twist cover, accommodate the lead screw and lead screw cooperation cover including spiral stake pipe, connecting plate, ground stake installation, the spiral stake pipe is the tubulose, and one end is sealed, other end opening, the connecting plate activity alternates and sets up the inside at the spiral stake pipe, the end position of cover fixed mounting at the connecting plate is twisted in ground stake installation, accommodate the lead screw rotates to be installed in the inside of twisting the cover in connecting plate and ground stake installation, the inside fixed mounting of spiral stake pipe has lead screw cooperation cover, accommodate the lead screw with lead screw cooperation cover spiral cooperation. The utility model discloses an accommodate the lead screw that sets up for the cover is twisted in ground stake installation has the altitude mixture control effect, thereby can touch the end at the spiral pile pipe and can't continue when dark, makes the cover is twisted in ground stake installation to tighten up through accommodate the lead screw and moves down, thereby realizes that the installation of cover is twisted in place in ground stake installation, has greatly improved the adaptability of spiral ground stake to ground environment.

Description

Combined spiral ground pile for photovoltaic solar installation
Technical Field
The utility model relates to a spiral ground stake technical field specifically is a combination formula spiral ground stake for installation of photovoltaic solar energy.
Background
Photovoltaic solar energy can face various open-air ground environment when installing, and traditional spiral ground stake is when twisting into the ground, if touch debris such as underground rock, can make spiral ground stake can't continue to go deep, and the height of twisting the cover with other ground stake inconsistent is twisted in the ground stake installation this moment, can't carry out follow-up installation operation, can only screw out ground stake, changes the installation site to can cause the reduction by a wide margin of installation effectiveness.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a combination formula spiral ground stake for installation of photovoltaic solar energy to solve the problem that proposes among the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a combination formula spiral ground stake for installation of photovoltaic solar energy, twists cover, accommodate the lead screw and lead screw cooperation cover including spiral stake pipe, connecting plate, ground stake installation, the spiral stake pipe is the tubulose, and one end is sealed, other end opening, the connecting plate activity alternates sets up the inside at the spiral stake pipe, the end position of cover fixed mounting at the connecting plate is twisted in ground stake installation, accommodate the lead screw rotates to be installed in the inside of twisting the cover in connecting plate and ground stake installation, the inside fixed mounting of spiral stake pipe has lead screw cooperation cover, accommodate the lead screw with lead screw cooperation cover screw cooperation, ground stake installation twist the cover with be provided with limit structure between the accommodate the lead screw, limit structure makes accommodate the lead screw can only rotate unable axial displacement in the inside of twisting the cover in ground stake installation.
The limiting structure comprises a screw rod positioning block, a positioning ring groove and a positioning chuck.
Screw rod locating piece fixed mounting is in the inside that the cover was twisted in the ground stake installation, the inside at the screw rod locating piece is seted up to the positioning ring groove, positioning chuck fixed mounting is in accommodate the lead screw's surface position, positioning chuck rotates the inside that sets up at the positioning ring groove.
The inner wall surface position of spiral pile pipe is vertical to be seted up the lateral wall spacing groove, the surface position fixed mounting of spiral pile pipe has helical blade.
The outer surface position fixed mounting of connecting plate has spacing bead, spacing bead interlude sets up in the inside of lateral wall spacing groove, the lower extreme surface position fixed mounting of connecting plate has the chassis of stabilizing.
The upper end surface position fixed mounting of cover is twisted in the installation of ground stake has the mounting disc, the surface of cover is twisted in the installation of ground stake runs through and has seted up fixed pinhole.
The upper end surface position fixed mounting of accommodate the lead screw is twisted the cap with rotatory, rotatory cap of twisting is located the inside of ground stake installation twisting cover.
Compared with the prior art, the beneficial effects of the utility model are that: the utility model discloses an accommodate the lead screw that sets up for the cover is twisted in ground pile installation has the altitude mixture control effect, thereby can touch the end at the spiral pile pipe and can't continue when dark, makes the cover is twisted in ground pile installation to tighten up through accommodate the lead screw and moves down, thereby realizes that the installation of cover is twisted in ground pile installation targets in place, has greatly improved the adaptability of spiral ground pile to ground environment.
Drawings
FIG. 1 is a schematic view of the overall structure of the present invention;
FIG. 2 is a schematic view of a half-section structure of the present invention;
FIG. 3 is a schematic view of the present invention;
fig. 4 is a front view of the present invention.
In the figure: 1. a spiral pile pipe; 2. a connecting plate; 3. mounting a screwing sleeve on the ground pile; 4. adjusting the screw rod; 5. a screw rod matching sleeve; 401. a screw rod positioning block; 402. a positioning ring groove; 403. positioning the chuck; 101. a side wall limiting groove; 102. a helical blade; 201. a limiting convex rib; 202. stabilizing the chassis; 301. mounting a disc; 302. a fixing pin hole; 404. the screw cap is rotated.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-4, the present invention provides a technical solution: the utility model provides a combination formula spiral ground stake for installation of photovoltaic solar energy, including spiral stake pipe 1, the connecting plate 2, cover 3 is twisted in ground stake installation, accommodate the lead screw 4 and lead screw cooperation cover 5, spiral stake pipe 1 is the tubulose, one end is sealed, the other end opening, 2 activities of connecting plate alternate the setting in spiral stake pipe 1's inside, 3 fixed mounting are twisted in the tip position of cover 3 fixed mounting at connecting plate 2 in ground stake installation, accommodate the lead screw 4 rotates to be installed in connecting plate 2 and the inside of twisting cover 3 in ground stake installation, the inside fixed mounting of spiral stake pipe 1 has lead screw cooperation cover 5, accommodate the lead screw 4 and 5 spiral cooperations of lead screw cooperation cover, be provided with limit structure between cover 3 and accommodate the lead screw 4 in ground stake installation, limit structure makes accommodate the lead screw 4 can only rotate unable axial displacement in the inside of twisting cover 3 in ground stake installation.
The limiting structure comprises a screw rod positioning block 401, a positioning ring groove 402 and a positioning chuck 403; the screw rod positioning block 401 is fixedly installed inside the ground pile installation screwing sleeve 3, the positioning ring groove 402 is formed in the screw rod positioning block 401, the positioning chuck 403 is fixedly installed on the outer surface of the adjusting screw rod 4, and the positioning chuck 403 is rotatably arranged inside the positioning ring groove 402.
The inner wall surface position of the spiral pile pipe 1 is vertically provided with a side wall limiting groove 101, and the outer surface position of the spiral pile pipe 1 is fixedly provided with a spiral blade 102.
Outer surface fixed position of connecting plate 2 installs spacing bead 201, spacing bead 201 alternates and sets up the inside at lateral wall spacing groove 101, cooperation through spacing bead 201 and lateral wall spacing groove 101, can increase the cooperation stability of connecting plate 2 and spiral pile pipe 1, make connecting plate 2 can only the lifting movement in spiral pile pipe 1's inside, can't rotate, the lower extreme fixed surface position of connecting plate 2 installs and stabilizes chassis 202, stabilize chassis 202 and can strengthen the connection stability between the connecting plate 2, avoid taking place deformation when connecting plate 2 drives spiral pile pipe 1 rotation and gos deep into.
The upper end surface position fixed mounting of cover 3 is twisted in the installation of ground stake has mounting disc 301, and mounting disc 301 is used for the fixed mounting of spiral ground stake and other external equipment, and the surface that cover 3 is twisted in the installation of ground stake runs through and has seted up fixed pinhole 302.
The upper end surface position of the adjusting screw rod 4 is fixedly provided with a rotary screwing cap 404, and the rotary screwing cap 404 is positioned inside the ground pile mounting screwing sleeve 3.
When the utility model is used, the ground pile installation screwing sleeve 3 and the fixed pin hole 302 are connected with the rotation driving equipment, so that the spiral pile pipe 1 is vertical to the ground, pressure is applied and the spiral pile pipe 1 rotates, and the spiral pile pipe 1 is screwed into the ground;
when spiral pile pipe 1 deepens the in-process at the ground end spiral, when touching barriers such as rocks, spiral pile pipe 1 can't continue to stretch out, this moment through the spanner instrument, the cover is in the outside of rotatory cap 404 of twisting, it is rotatory to pull rotatory cap 404 of twisting and drive accommodate the lead screw 4, when accommodate the lead screw 4 rotates, owing to with the spiral cooperation of lead screw cooperation cover 5, can make connecting plate 2 insert to spiral pile pipe 1 inside gradually, thereby make ground pile installation twist cover 3 move down gradually, draw close with ground, thereby reach ground pile installation and twist the tightening up effect of cover 3, can make ground pile installation twist cover 3 keep unified height with the ground pile installation twist cover 3 of other positions, be convenient for follow-up installation, after stopping rotatory cap 404 of twisting, under accommodate lead screw 4 and lead screw cooperation cover 5's spiral cooperation, ground pile installation twist the height of cover 3 and is fixed.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (7)

1. The utility model provides a combination formula spiral ground stake for installation of photovoltaic solar energy, twists cover (3), accommodate the lead screw (4) and lead screw cooperation cover (5), its characterized in that including spiral stake pipe (1), connecting plate (2), ground stake installation: spiral pile pipe (1) is the tubulose, and one end is sealed, other end opening, connecting plate (2) activity alternates and sets up the inside at spiral pile pipe (1), the tip position of cover (3) fixed mounting at connecting plate (2) is twisted in the installation of ground pile, accommodate the lead screw (4) are rotated and are installed and twist the inside of cover (3) in connecting plate (2) and the installation of ground pile, the inside fixed mounting of spiral pile pipe (1) has lead screw cooperation cover (5), accommodate the lead screw (4) with lead screw cooperation cover (5) screw cooperation, the installation of ground pile twist cover (3) with be provided with limit structure between accommodate the lead screw (4), limit structure makes accommodate the lead screw (4) can only rotate unable axial displacement twisting the inside of cover (3) in the installation of ground pile.
2. A modular helical pile for photovoltaic solar installation according to claim 1, characterised in that: the limiting structure comprises a screw rod positioning block (401), a positioning ring groove (402) and a positioning chuck (403).
3. A modular helical pile for photovoltaic solar installation according to claim 2, characterised in that: screw rod locating piece (401) fixed mounting is in the inside of cover (3) is twisted in the installation of ground stake, the inside at screw rod locating piece (401) is seted up in positioning ring groove (402), positioning chuck (403) fixed mounting is in the surface position of accommodate the lead screw (4), positioning chuck (403) rotate the inside of setting at positioning ring groove (402).
4. A modular helical pile for photovoltaic solar installation according to claim 1, characterised in that: the inner wall surface position of spiral pile pipe (1) has vertically seted up lateral wall spacing groove (101), the outer surface position fixed mounting of spiral pile pipe (1) has helical blade (102).
5. A combined helical pile for photovoltaic solar installation according to claim 4, characterised in that: the outer surface position fixed mounting of connecting plate (2) has spacing bead (201), spacing bead (201) alternate the inside that sets up at lateral wall spacing groove (101), the lower extreme surface position fixed mounting of connecting plate (2) has stable chassis (202).
6. A modular helical pile for photovoltaic solar installation according to claim 1, characterised in that: the upper end surface position fixed mounting of cover (3) is twisted in ground stake installation has mounting disc (301), the surface of cover (3) is twisted in ground stake installation runs through and has seted up fixed pinhole (302).
7. A modular helical pile for photovoltaic solar installation according to claim 1, characterised in that: the upper end surface position fixed mounting of accommodate the lead screw (4) is twisted cap (404) rotatoryly, it is twisted cap (404) to rotate to be located the inside of cover (3) is twisted in ground stake installation.
CN202221491927.6U 2022-06-15 2022-06-15 Combined spiral ground pile for photovoltaic solar installation Active CN217445294U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221491927.6U CN217445294U (en) 2022-06-15 2022-06-15 Combined spiral ground pile for photovoltaic solar installation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221491927.6U CN217445294U (en) 2022-06-15 2022-06-15 Combined spiral ground pile for photovoltaic solar installation

Publications (1)

Publication Number Publication Date
CN217445294U true CN217445294U (en) 2022-09-16

Family

ID=83222962

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221491927.6U Active CN217445294U (en) 2022-06-15 2022-06-15 Combined spiral ground pile for photovoltaic solar installation

Country Status (1)

Country Link
CN (1) CN217445294U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117488778A (en) * 2023-12-25 2024-02-02 黄骅市利盈五金制品有限公司 Photovoltaic power generation's ground stake

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117488778A (en) * 2023-12-25 2024-02-02 黄骅市利盈五金制品有限公司 Photovoltaic power generation's ground stake
CN117488778B (en) * 2023-12-25 2024-03-08 黄骅市利盈五金制品有限公司 Photovoltaic power generation's ground stake

Similar Documents

Publication Publication Date Title
CN217445294U (en) Combined spiral ground pile for photovoltaic solar installation
CN208670276U (en) A kind of adjustable natural gas extraction pipeline support frame
CN211370300U (en) Adjustable drill bit for coal mine exploration
CN212002079U (en) Indoor natural light lighting device for green building
CN212563332U (en) Shield tunnel portal sealing device
CN218117737U (en) Engineering geology drilling plugging device
CN208455628U (en) A kind of piling machine positioning device
CN214883681U (en) Building foundation engineering monitoring protector
CN213175590U (en) Fishable bridge plug
CN206608401U (en) A kind of hydraulic support column seal with annular groove attachment structure
CN106122385A (en) A kind of twist bit
CN205532325U (en) Horizontal azimuth adjusting device of track -mounted drill
CN212203337U (en) Novel electric butterfly valve for drainage pipeline
CN218596939U (en) Pier stud template
CN221721741U (en) Deep foundation pit inclinometer pipe protection device
CN214167197U (en) Liftable support for construction engineering construction
CN217950413U (en) Supporting and reinforcing column for mine building channel
CN214658884U (en) Cement pouring equipment for civil engineering
CN211256997U (en) Subway building mortar extrusion formula grouter
CN215926077U (en) Municipal administration public works well lid protective structure
CN212225271U (en) Tunnel engineering top bearing structure
CN216590419U (en) Ball valve convenient to installation
CN211342044U (en) Steel pipe tower rotates cross arm
CN213954739U (en) Remote supervision system for construction site
CN214788346U (en) Hydraulic cylinder barrel end cover for excavator

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 266000 No. 889-1, DAZHUSHAN North Road, Jiaonan sub district office, Huangdao District, Qingdao City, Shandong Province

Patentee after: Qingdao Baoqiang Energy Technology Co.,Ltd.

Address before: 266000 No. 889-1, DAZHUSHAN North Road, Jiaonan sub district office, Huangdao District, Qingdao City, Shandong Province

Patentee before: Qingdao Baoqiang Solar Energy Technology Co.,Ltd.