- Publication number
- CN217420023U CN217420023U CN202220590890.6U CN202220590890U CN217420023U CN 217420023 U CN217420023 U CN 217420023U CN 202220590890 U CN202220590890 U CN 202220590890U CN 217420023 U CN217420023 U CN 217420023U
- Authority
- CN
- China
- Prior art keywords
- installation
- construction hole
- mounting block
- hole
- block
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/20—Hydro energy
Landscapes
- Building Environments (AREA)
Abstract
The utility model relates to an engineering construction equipment field discloses a structure of improving engineering construction hole shutoff mode, including the installation component, the installation component front end is provided with net cloth, the net cloth other end is provided with the grid net, the installation component is including installation plate and fixed subassembly, the installation plate includes first installation piece and second installation piece, first installation piece is 2 respectively with second installation piece quantity, and the shape is the quarter circle. The utility model discloses in will install the plate installation through fixed subassembly and be fixed in the lateral wall in construction hole, lay foaming adhesive, grid net, foaming adhesive, net cloth, putty in proper order again respectively, accomplish the shutoff operation in construction hole, when construction hole inner wall is not regular circle, can install mutual split between piece with first installation piece and the second to be fixed in construction hole inner wall with its installation in proper order, accomplish the fixed of installation plate.
Description
Technical Field
The utility model relates to an engineering construction equipment field specifically is a structure of improving engineering construction hole shutoff mode.
Background
In the prior art, when a construction hole is plugged, if putty is directly coated and hung at the position of the hole opening, cracks or even falling can occur on the surface of the putty for a long time due to uneven stress and different humidity, and the hole walls of most construction holes are uneven and cannot be effectively fixed on the hole walls during installation, so that the final construction effect can be influenced.
The prior Chinese patent discloses a construction hole plugging structure, wherein the publication number is CN215564684U, the publication date is 2022.01.18, the technology of the patent comprises a filler, a fixing screw rod, a grid cloth, a grid net, a grid nut and a long nut, wherein the filler is arranged in a construction hole, the fixing screw rod is arranged in the filler, the grid cloth is used for plugging the construction hole, the grid net is arranged on one side of the grid cloth far away from the fixing screw rod, the area of a mesh hole of the grid net is 50-100 times of that of the mesh hole of the grid cloth, the adjusting screw rod is arranged between the kraft paper grid cloth and the fixing screw rod and is connected with the grid net, the long nut is arranged on the fixing screw rod and the adjusting screw rod, the long nut, the fixing screw rod, the kraft paper grid net and the fixing screw rod are in threaded connection, and the long nut is inserted with a wire, the inserted wire is arranged in the filler and is used for fixing the structure of the grid net, solves the problem that the putty can fall off for a long time. But wherein still there is the inside condition complicacy of construction hole, the inside problem of construction hole can't effectively be fixed in to the clamping screw bottom. In view of the situation, the technical personnel in the field provide a structure for improving the blocking mode of the engineering construction hole.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide an improve structure of engineering construction hole shutoff mode to the construction hole internal conditions that proposes among the above-mentioned background art is complicated to lead to installing inconvenient, insecure problem.
In order to achieve the above object, the utility model provides a following technical scheme:
the utility model provides a structure of engineering construction hole shutoff mode is improved, includes the installation component, the installation component front end is provided with net cloth, the net cloth other end is provided with the grid net, the installation component is including installation plate and fixed subassembly, the installation plate includes first installation piece and second installation piece, first installation piece is 2 respectively with second installation piece quantity, and the shape is the quarter circle.
As a further aspect of the present invention: and a third mounting block is fixed on one side of the first mounting block, which is close to the second mounting block, a groove matched with the third mounting block is formed on one side of the second mounting block, which is close to the first mounting block, and the fixed mounting between the first mounting block and the second mounting block is completed by fixing the third mounting block and the groove with each other.
As a further aspect of the present invention: screw holes are respectively formed in the third mounting block and the groove, a first screw rod is connected with the screw holes in an internal thread mode, the third mounting block is aligned with the screw holes in the groove, and then the first screw rod is screwed in, so that the third mounting block and the groove are fixed with each other.
As a further aspect of the present invention: the fixing assembly comprises a fixing block, one side of the fixing block is fixedly connected to the outer ring side wall of the first mounting block, and the first mounting block is fixedly installed on the side wall of the construction hole through the fixing assembly.
As a further aspect of the present invention: the fixing block is internally provided with a through hole, a second screw rod is arranged in the through hole, the second screw rod penetrates through the through hole and is finally screwed into the side wall of the construction hole at the other end of the through hole, and the fixing assembly is installed and fixed on the side wall of the construction hole.
As a further aspect of the present invention: fixed block one side is provided with the gasket, the gasket cup joints on the second screw rod, and the area of contact between second screw rod and the fixed block can be strengthened to the gasket, reduces pressure, prevents not hard up.
The utility model has the advantages that:
1. compared with the prior art, the structure for improving the plugging mode of the engineering construction hole is characterized in that the second screw penetrates through the through hole in the fixing block, and is finally screwed into the side wall of the construction hole at the other end of the through hole, and the fixing component is installed and fixed on the inner wall of the construction hole, so that the first installation block is installed and fixed on the side wall of the construction hole;
2. compared with the prior art, the structure for improving the plugging mode of the engineering construction hole can separate the first installation block and the second installation block from each other in the wall of the irregular construction hole, so that the installation and fixation between the first installation block and the second installation block on the wall of the hole can be independently completed, and the difficulty of painting later-stage putty due to insecure installation is avoided.
Drawings
The present invention will be further described with reference to the accompanying drawings.
FIG. 1 is a schematic perspective view of a structure for improving a plugging manner of a construction hole;
FIG. 2 is a perspective view of the mounting assembly of FIG. 1;
FIG. 3 is a schematic view of the mounting plate of FIG. 2;
fig. 4 is a schematic structural view of the fixing assembly in fig. 2.
In the figure: 1. mounting the component; 2. mesh cloth; 3. a grid net; 4. mounting a plate; 5. a fixing assembly; 6. A first mounting block; 7. a second mounting block; 8. a groove; 9. a third mounting block; 10. a screw hole; 11. a first screw; 12. a fixed block; 13. a through hole; 14. a second screw; 15. and (7) a gasket.
Detailed Description
The technical solution in the embodiment of the present invention is clearly and completely described below with reference to the accompanying drawings in the embodiment of the present invention, please refer to fig. 1 to 4, and the embodiment of the present invention is as follows:
a structure for improving the plugging mode of engineering construction holes is shown in figures 1 and 2: the grid mesh fixing device comprises a mounting assembly 1, wherein a grid mesh 2 is arranged at the front end of the mounting assembly 1, a grid mesh 3 is arranged at the other end of the grid mesh 2, and the mounting assembly 1 comprises a mounting plate 4 and a fixing assembly 5.
In fig. 2 and 3: the mounting plate 4 comprises a first mounting block 6 and a second mounting block 7, the number of the first mounting block 6 and the number of the second mounting block 7 are respectively 2, the shapes of the first mounting block 6 and the second mounting block 7 are quarter circles, one side, close to the second mounting block 7, of the first mounting block 6 is fixed with a third mounting block 9, one side, close to the first mounting block 6, of the second mounting block 7 is provided with a groove 8 matched with the third mounting block 9, through mutual fixing between the third mounting block 9 and the groove 8, fixed mounting between the first mounting block 6 and the second mounting block 7 is completed, screw holes 10 are respectively formed in the third mounting block 9 and the groove 8, screw holes 10 are in threaded connection with first screw rods 11, through mutual alignment of the third mounting block 9 and the screw holes 10 in the groove 8, the first screw rods 11 are screwed in, and mutual fixing between the third mounting block 9 and the groove 8 is completed.
In fig. 2 and 4: fixed subassembly 5 includes fixed block 12, fixed block 12 one side fixed connection is in the 6 outer lane lateral walls of first installation piece, the lateral wall in the construction hole is fixed in the installation of first installation piece 6 through fixed subassembly 5, through-hole 13 has been seted up in fixed block 12, be provided with second screw rod 14 in the through-hole 13, pass through-hole 13 through second screw rod 14, finally twist the lateral wall in the construction hole of the through-hole 13 other end, the lateral wall in the construction hole is fixed in the installation of fixed subassembly 5, fixed block 12 one side is provided with gasket 15, gasket 15 cup joints on second screw rod 14, area of contact between second screw rod 14 and fixed block 12 can be strengthened to gasket 15, reduce pressure, prevent to become flexible.
The utility model discloses a theory of operation is: the first screw rod 11 can be screwed down in the irregular construction hole wall, the first screw rod 11 is taken out from the screw hole 10, the third installation block 9 and the groove 8 are separated, the mutual separation between the first installation block 6 and the second installation block 7 is completed, the installation and the fixation between the first installation block 6 and the second installation block 7 on the hole wall are independently completed, the later putty smearing difficulty caused by the instable installation is avoided, the fixing component 5 is installed and fixed on the inner wall of the construction hole by penetrating the second screw rod 14 through the through hole 13 in the fixing block 12 and finally screwing the second screw rod into the side wall of the construction hole at the other end of the through hole 13, the first installation block 6 is installed and fixed on the side wall of the construction hole, the second installation block 7 is installed on the side wall of the construction hole through the same operation, the installation plate 4 can be installed on the hole wall without disassembling the first installation block 6 and the second installation block 7 in the regular round construction hole wall, after installation of installation plate 4 is accomplished, the foaming adhesive that will fill slowly coats on installation plate 4, pastes grid 3 in the foaming adhesive after the coating, continues to scribble the foaming adhesive to grid 3, pastes net cloth 2 in the foaming adhesive after the coating, and then scribbles putty to net cloth 2.
The above-mentioned, only be the concrete implementation of the preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art is in the technical scope of the present invention, according to the technical solution of the present invention and the utility model, the concept of which is equivalent to replace or change, should be covered within the protection scope of the present invention.
Claims (6)
1. The utility model provides a structure of engineering construction hole shutoff mode improves, includes installation component (1), its characterized in that, installation component (1) front end is provided with net cloth (2), net cloth (2) other end is provided with grid net (3), installation component (1) is including installation plate (4) and fixed subassembly (5), installation plate (4) are including first installation piece (6) and second installation piece (7), first installation piece (6) are 2 respectively with second installation piece (7) quantity, and the shape is the quarter circle.
2. The structure for improving the plugging mode of an engineering construction hole according to claim 1, wherein a third mounting block (9) is fixed on one side of the first mounting block (6) close to the second mounting block (7), and a groove (8) matched with the third mounting block (9) is formed on one side of the second mounting block (7) close to the first mounting block (6).
3. The structure for improving the plugging mode of an engineering construction hole according to claim 2, wherein a screw hole (10) is respectively formed in the third mounting block (9) and the groove (8), and a first screw rod (11) is connected with the screw hole (10) in an internal thread manner.
4. A structure for improving the sealing mode of an engineering construction hole according to claim 1, wherein the fixing component (5) comprises a fixing block (12), and one side of the fixing block (12) is fixedly connected with the side wall of the outer ring of the first mounting block (6).
5. A structure for improving the plugging mode of an engineering construction hole according to claim 4, wherein a through hole (13) is formed in the fixing block (12), and a second screw (14) is arranged in the through hole (13).
6. A structure for improving a plugging mode of an engineering construction hole according to claim 5, wherein a gasket (15) is arranged on one side of the fixed block (12), and the gasket (15) is sleeved on the second screw rod (14).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202220590890.6U CN217420023U (en) | 2022-03-17 | 2022-03-17 | Structure for improving plugging mode of engineering construction hole |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202220590890.6U CN217420023U (en) | 2022-03-17 | 2022-03-17 | Structure for improving plugging mode of engineering construction hole |
Publications (1)
Publication Number | Publication Date |
---|---|
CN217420023U true CN217420023U (en) | 2022-09-13 |
Family
ID=83181449
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202220590890.6U Active CN217420023U (en) | 2022-03-17 | 2022-03-17 | Structure for improving plugging mode of engineering construction hole |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN217420023U (en) |
-
2022
- 2022-03-17 CN CN202220590890.6U patent/CN217420023U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN211007225U (en) | Curtain wall claw type structure | |
CN217420023U (en) | Structure for improving plugging mode of engineering construction hole | |
CN217353498U (en) | Disc buckle type pull rod structure | |
CN208939493U (en) | Novel cable pipeline plug | |
CN209245019U (en) | A kind of device assisting the close assembly of detachable lid oil | |
CN206893968U (en) | A kind of Wiring nose | |
CN210459569U (en) | Intermediate connecting piece of prefabricated building | |
CN209418788U (en) | A kind of fixation device for the installation grounding-for-lightning device on roofing | |
CN205452657U (en) | Dark dress socket -outlet box of easy dismouting | |
CN209538471U (en) | It is a kind of to facilitate fixed spliced curtain wall | |
CN205863836U (en) | A kind of attachment structure of rosette | |
CN207093753U (en) | Sealing-plug | |
CN207879782U (en) | L type slot type connection structure | |
CN219317881U (en) | Sealed flange piece for ocean current resistant operation bin | |
CN210622197U (en) | Movable mounting structure of assembled wallboard | |
CN219755056U (en) | Hexagonal sealing nut | |
CN205559505U (en) | Gasket | |
CN220633059U (en) | Bubble cap structure of tray | |
CN211174925U (en) | Shield type foundation bolt | |
CN213557945U (en) | Detachable shower pipe installation mechanism | |
CN206865885U (en) | A kind of appliance panel that reduces deformation of structure optimization | |
CN220100784U (en) | Waterproof plugging structure for opposite-pull bolt holes | |
CN210032312U (en) | Energy-conserving wallboard of building of easily installing | |
CN208565212U (en) | A kind of disconnecting prevention structure for installing bolt | |
CN215564684U (en) | Construction hole block structure |