CN217379465U - Assembled large tracts of land aluminum plate furred ceiling project organization - Google Patents

Assembled large tracts of land aluminum plate furred ceiling project organization Download PDF

Info

Publication number
CN217379465U
CN217379465U CN202123110448.3U CN202123110448U CN217379465U CN 217379465 U CN217379465 U CN 217379465U CN 202123110448 U CN202123110448 U CN 202123110448U CN 217379465 U CN217379465 U CN 217379465U
Authority
CN
China
Prior art keywords
piece
plate
bottom plate
cavity
pull rod
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202123110448.3U
Other languages
Chinese (zh)
Inventor
吴宇恒
何康喜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Zhan Yi Construction Group Co ltd
Original Assignee
Shenzhen Zhan Yi Construction Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Zhan Yi Construction Group Co ltd filed Critical Shenzhen Zhan Yi Construction Group Co ltd
Priority to CN202123110448.3U priority Critical patent/CN217379465U/en
Application granted granted Critical
Publication of CN217379465U publication Critical patent/CN217379465U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The utility model discloses a design structure of an assembled large-area aluminum plate suspended ceiling, belonging to the hoisting field, which comprises a pull rod, a hoisting piece and a main keel, the top end of the pull rod is nailed into the top wall of the floor slab, the bottom end of the pull rod is in threaded connection with the hanging piece, the main keel is provided with a triangular clamping piece corresponding to the hanging piece, the bottoms of the triangular clamping pieces are clamped with triangular keels, the hanging piece comprises a left side plate and a right side plate which form an inverted U-shaped plate, hang the bottom movable mounting of piece and have the bottom plate of upwards overturning, the bottom plate is used for the spacing main joist of joint, hangs the piece and is square, and the main joist is installed with the triangle fossil fragments is perpendicular, and it can make constructor need not to cross the hook plate card of U-shaped with the main joist and hang the piece inslot, and direct follow hangs a bottom card and advances the piece inslot, realizes the effect of work progress labour saving and time saving.

Description

Assembled large tracts of land aluminum plate furred ceiling project organization
Technical Field
The utility model relates to a hoist and mount field, more specifically say, relate to an assembled large tracts of land aluminum plate furred ceiling project organization.
Background
The aluminum gusset plate is made of a special material, is light and durable in texture, is widely applied to a household suspended ceiling, has various excellent characteristics, is suitable for kitchens and toilets, can achieve a good decorative effect, has various effects, and is popular among consumers, namely the suspended ceiling of the aluminum gusset plate.
At present, the sharp of integrated furred ceiling trade is pursued, make us walk out narrow and small kitchen guarding space, develop the diversified product that is applicable to different regional multiple functions and usage such as sitting room, the bedroom, the vestibule, the balcony, in the life of family, the material selection of furred ceiling also is vital to the people with master's construction technology, wherein, the piece is hung to the square or Z shape of adoption all to most hanging, the opening that hangs the piece all is ascending, need constructor's the hook plate card that crosses the U-shaped with the main joist in hanging the piece inslot, comparatively waste time and energy.
SUMMERY OF THE UTILITY MODEL
1. Technical problem to be solved
To the problem that exists among the prior art, the utility model aims to provide an assembled large tracts of land aluminum plate furred ceiling project organization, it can make constructor need not to cross the hook plate card of U-shaped with the main joist and hang a inslot, directly from hanging a bottom card and advance a piece inslot, realizes the effect of work progress labour saving and time saving.
2. Technical scheme
In order to solve the above problems, the utility model adopts the following technical proposal.
A design structure of an assembled large-area aluminum plate ceiling comprises a pull rod, a hanging piece and a main keel, wherein the top end of the pull rod is nailed into a top wall of a floor slab, the bottom end of the pull rod is in threaded connection with the hanging piece, triangular clamping pieces are mounted on the main keel corresponding to the hanging piece, triangular keels are clamped at the bottoms of the triangular clamping pieces, each hanging piece comprises a left side plate and a right side plate, the left side plate and the right side plate form an inverted U-shaped plate, an upwards-turned bottom plate is movably mounted at the bottom of the hanging piece, and the bottom plate is used for clamping and limiting the main keel;
the hanging piece is square;
the main keel and the triangular keel are vertically installed.
Further, the bottom of left side board corresponds the bottom plate and has seted up first cavity, the piece that resets is installed to one side that the bottom plate is located first cavity, the dwang is installed to the bottom plate axial, the bottom plate passes through the dwang rotates the inside of installing at first cavity.
Furthermore, the middle of the resetting piece is provided with a semicircular clamping piece, and two ends of the clamping piece extend away from the slope.
Furthermore, the inside of first cavity is installed the spring corresponding to the piece that resets, the one end of spring is fixed in the inside of first cavity, and the other end is fixed at the lateral wall that resets.
Furthermore, a boss which is integrally formed extends from one side of the bottom plate, which is far away from the left side plate, the bottom plate and the boss form two staggered table surfaces, and convex rings are arranged on one side surface of the boss at equal intervals.
Further, the height of the boss is half of the height of the bottom plate.
Furthermore, a bottom end of the right side plate is matched with the bottom plate and provided with a second cavity, the boss is located inside the second cavity, and the convex ring is tightly abutted to the inner side wall of the right side plate.
3. Advantageous effects
Compared with the prior art, the utility model has the advantages of:
(1) in the scheme, the main keel is pushed upwards against the bottom plate until the main keel is pushed into the hanging piece, at the moment, the bottom plate is pressed by the spring, and the outward tension of the reset piece automatically falls, one end of the boss on the bottom plate is clamped and embedded in the second chamber, the main keel is pulled downwards to ensure that the convex ring at the side edge of the bottom plate is tightly pressed against the inner side wall of the right side plate, the stress of the outward expansion of the convex ring and the inner side wall of the right side plate form mutual thrust, the bottom plate is mutually vertical and tightly connected with the left side plate and the right side plate, and the rectangular hanging piece is compared with the semi-closed hanging piece, can better disperse the vertical tension on the pull rod, so that the hoisting whole has more lasting fatigue resistance, and place with traditional lift formula and compare, constructor need not to cross the hook plate card of U-shaped with the main joist and hang a inslot, directly in hanging a bottom card income hanging an inslot, realizes the effect of work progress labour saving and time saving.
Drawings
FIG. 1 is a schematic view of the overall overhead structure of the hoisting device of the present invention;
FIG. 2 is a schematic view of the structure of the hanger of the present invention;
FIG. 3 is a schematic view of the structure of the present invention showing the hanging member separated from the bottom plate;
FIG. 4 is a schematic view of the bottom plate structure of the present invention;
FIG. 5 is a schematic sectional view of the hanger of the present invention;
fig. 6 is a schematic view of the hoisting integral overhead structure of the utility model.
The numbering in the figures illustrates:
1. a pull rod; 2. a hanger; 3. a main keel; 4. a triangular card; 5. a triangular keel; 201. a left side plate; 202. a right side plate; 6. a base plate; 7. a first chamber; 8. a reset member; 9. rotating the rod; 10. a spring; 11. a boss; 12. a convex ring; 13. a second chamber.
Detailed Description
The technical solution in the embodiment of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiment of the present invention; obviously, the described embodiments are only a part of the embodiments of the present invention, and not all embodiments, and all other embodiments obtained by those skilled in the art without any inventive work are within the scope of the present invention based on the embodiments of the present invention.
Please refer to fig. 1-2, a large tracts of land aluminum plate furred ceiling of assembled design structure, including pull rod 1, hang 2 and main joist 3, the top of pull rod 1 is nailed into the floor roof, pull rod 1 bottom with hang 2 threaded connection, correspond on the main joist 3 and hang 2 and install triangle card 4, a plurality of triangle card 4 bottom joint have triangle fossil fragments 5, hang 2 including left side board 201 and right side board 202, the U-shaped board of invering is constituteed with right side board 202 to left side board 201, the bottom movable mounting who hangs 2 has the bottom plate 6 of upwards overturning, bottom plate 6 is used for the spacing main joist 3 of joint.
Wherein, the hanger 2 is square.
Wherein, the main keel 3 and the triangular keel 5 are vertically arranged.
Further, the hanger 2 is rectangular in shape.
Compared with the semi-closed hanging piece 2, the rectangular hanging piece 2 can better disperse the vertical tension on the pull rod 1, so that the whole hanging piece has more lasting fatigue resistance.
Referring to fig. 2-3, a first cavity 7 is opened at the bottom of the left side plate 201 corresponding to the bottom plate 6, a reset element 8 is installed at one side of the bottom plate 6 located in the first cavity 7, a rotating rod 9 is axially installed on the bottom plate 6, and the bottom plate 6 is rotatably installed inside the first cavity 7 through the rotating rod 9.
Further, the height of the first chamber 7 is greater than the length of the bottom plate 6, so that the bottom plate 6 can be accommodated inside the first chamber 7 when it is turned upside down.
Referring to fig. 3-4, the middle of the reset member 8 is provided with a semicircular clip member, and two ends of the clip member extend away from the slope.
Further, under the static state, the extending ends at two sides of the reset piece 8 are expanded outwards in a deviating mode.
Referring to fig. 3-4, a spring 10 is mounted inside the first chamber 7 corresponding to the reset member 8, one end of the spring 10 is fixed inside the first chamber 7, and the other end is fixed on the side wall of the reset member 8.
The spring 10 continuously presses to push the reset piece 8 to be in a pressing state, so that the bottom plate 6 can be automatically reset to be vertical to the two side plates.
Referring to fig. 4-5, a boss 11 integrally formed extends from a side of the bottom plate 6 away from the left side plate 201, the bottom plate 6 and the boss 11 form two staggered table surfaces, and a protruding ring 12 is disposed on a side surface of the boss 11 at an equal interval.
Further, the diameter of the convex ring 12 is gradually increased from the two sides to the middle.
Referring to fig. 4-5, the height of the boss 11 is half the height of the bottom plate 6.
Referring to fig. 5, the bottom end of the right side plate 202 is adapted to the bottom plate 6 and is provided with a second chamber 13, the boss 11 is located inside the second chamber 13, and the protruding ring 12 is tightly abutted to the inner side wall of the right side plate 202.
Referring to fig. 6, the bottom ends of the two side plates protrude from the bottom surface of the bottom plate 6, and the two ends of the bottom plate 6 are respectively located inside the two cavities, so that the bottom plate 6 can only be turned upwards, and the main keel 3 is better limited.
Support main joist 3 and upwards promote bottom plate 6, until pushing the inside of hanging 2, bottom plate 6 is through the pressure of spring 10 this moment, and reset 8 outside tension automatic fall back, the one end inlay card of boss 11 is in the inside of second cavity 13 on bottom plate 6, stimulate main joist 3 downwards, make 6 side bulge loops 12 of bottom plate closely offset with the right side board 202 inside wall, the stress that bulge loop 12 rises outward forms mutual thrust with the right side board 202 inside wall, bottom plate 6 and left side board 201, right side board 202 mutually perpendicular and zonulae occludens.
When in use: the main keel 3 is propped against the bottom plate 6 to be pushed upwards until the inside of the hanging piece 2 is pushed, at the moment, the bottom plate 6 automatically falls back through the pressure of the spring 10 and the outward tension of the reset piece 8, one end of the boss 11 on the bottom plate 6 is clamped and embedded in the second chamber 13, the main keel 3 is pulled downwards to enable the convex ring 12 at the side edge of the bottom plate 6 to be tightly propped against the inner side wall of the right side plate 202, the stress of the outward expansion of the convex ring 12 and the inner side wall of the right side plate 202 form mutual thrust, the bottom plate 6, the left side plate 201 and the right side plate 202 are mutually perpendicular and tightly connected, the rectangular hanging piece 2 can better disperse the perpendicular tension on the pull rod 1 compared with the semi-closed hanging piece 2, the whole hanging piece has more lasting fatigue resistance, and compared with the traditional lifting type placement, a constructor does not need to clamp the main keel 3 in a groove of the hanging piece 2 from the bottom of the U-shaped hook plate, the time-saving and labor-saving effects in the construction process are realized.
The above description is only the preferred embodiment of the present invention; the scope of the present invention is not limited thereto. Any person skilled in the art should also be able to cover the technical scope of the present invention by replacing or changing the technical solution and the improvement concept of the present invention with equivalents and modifications within the technical scope of the present invention.

Claims (7)

1. The utility model provides an assembled large tracts of land aluminum plate furred ceiling project organization, includes pull rod (1), hangs piece (2) and main joist (3), the floor roof is driven into on the top of pull rod (1), pull rod (1) bottom and hang piece (2) threaded connection, it installs triangle card (4), a plurality of to correspond on main joist (3) to hang piece (2) triangle card (4) bottom joint has triangle fossil fragments (5), its characterized in that: the hanging piece (2) comprises a left side plate (201) and a right side plate (202), the left side plate (201) and the right side plate (202) form an inverted U-shaped plate, the bottom of the hanging piece (2) is movably provided with a bottom plate (6) which is turned upwards, and the bottom plate (6) is used for clamping and connecting the limiting main keel (3);
the hanging piece (2) is square;
the main keel (3) and the triangular keel (5) are vertically arranged.
2. The fabricated large area aluminum sheet ceiling design structure of claim 1, wherein: first cavity (7) have been seted up to the bottom of left side board (201) corresponding bottom plate (6), reset piece (8) are installed to one side that bottom plate (6) are located first cavity (7), dwang (9) are installed to bottom plate (6) axial, bottom plate (6) pass through dwang (9) are rotated and are installed the inside at first cavity (7).
3. The fabricated large area aluminum sheet ceiling design structure of claim 2, wherein: the middle of the resetting piece (8) is provided with a semicircular clamping piece, and two ends of the clamping piece extend away from the inclined direction.
4. The fabricated large area aluminum sheet ceiling design structure of claim 2, wherein: the spring (10) is installed corresponding to the reset piece (8) in the first cavity (7), one end of the spring (10) is fixed in the first cavity (7), and the other end of the spring is fixed on the side wall of the reset piece (8).
5. The fabricated large area aluminum sheet ceiling design structure of claim 1, wherein: the side, far away from left side board (201), of bottom plate (6) extends and has boss (11) of integrative formation, bottom plate (6) and boss (11) form two staggered mesa, boss (11) one side equidistant bulge loop (12) that is provided with.
6. The fabricated large area aluminum sheet ceiling design structure of claim 5, wherein: the height of the boss (11) is half of the height of the bottom plate (6).
7. The fabricated large area aluminum sheet ceiling design structure of claim 6, wherein: the bottom end of the right side plate (202) is matched with the bottom plate (6) and is provided with a second cavity (13), the boss (11) is located inside the second cavity (13), and the convex ring (12) is tightly abutted to the inner side wall of the right side plate (202).
CN202123110448.3U 2021-12-07 2021-12-07 Assembled large tracts of land aluminum plate furred ceiling project organization Active CN217379465U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202123110448.3U CN217379465U (en) 2021-12-07 2021-12-07 Assembled large tracts of land aluminum plate furred ceiling project organization

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202123110448.3U CN217379465U (en) 2021-12-07 2021-12-07 Assembled large tracts of land aluminum plate furred ceiling project organization

Publications (1)

Publication Number Publication Date
CN217379465U true CN217379465U (en) 2022-09-06

Family

ID=83094388

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202123110448.3U Active CN217379465U (en) 2021-12-07 2021-12-07 Assembled large tracts of land aluminum plate furred ceiling project organization

Country Status (1)

Country Link
CN (1) CN217379465U (en)

Similar Documents

Publication Publication Date Title
CN217379465U (en) Assembled large tracts of land aluminum plate furred ceiling project organization
CN201564202U (en) Two-purpose clothes hanger
CN202287676U (en) Mosquito net hoisting device
CN218026802U (en) Invisible clothes hanger
CN101538908A (en) Combined installation method of keel and hanging hook
CN215800529U (en) Novel invisible clothes airing device
CN213696482U (en) Wall-mounted suction cup hanging seat
CN202359996U (en) Multifunctional door
CN2828097Y (en) Airer
CN213272316U (en) Novel ceiling lamp with sleep-assisting effect
CN214678749U (en) Wall-mounted multifunctional soap box
CN203162908U (en) Wall-mounted ceramic candleholder
CN208414905U (en) A kind of clothes hanger buckle structure
CN202430923U (en) Tile with hooks
CN2382319Y (en) Cabinet type clothes hanger
CN215457033U (en) Detachable suspends pergola in midair
CN2196990Y (en) Basin hook
CN206616387U (en) Invisible clothes hanger
CN201578004U (en) Hook
CN212938728U (en) Clothes rod hook
CN216042111U (en) Aluminum square tube furred ceiling mounting structure with shape reinforcement design of preapring for an unfavorable turn of events
CN201798475U (en) Convenient clothes rack
CN2376255Y (en) Multi-function hanging board
CN202747170U (en) Kitchen and bathroom lamp
CN211689592U (en) Space-saving indoor clothes hanger

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant