CN217354414U - Large-scale underground cavern country rock supporting construction - Google Patents

Large-scale underground cavern country rock supporting construction Download PDF

Info

Publication number
CN217354414U
CN217354414U CN202220916169.1U CN202220916169U CN217354414U CN 217354414 U CN217354414 U CN 217354414U CN 202220916169 U CN202220916169 U CN 202220916169U CN 217354414 U CN217354414 U CN 217354414U
Authority
CN
China
Prior art keywords
arc
shaped
frame
cavern
buried
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202220916169.1U
Other languages
Chinese (zh)
Inventor
晏和刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yunnan University of Finance and Economics
Original Assignee
Yunnan University of Finance and Economics
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yunnan University of Finance and Economics filed Critical Yunnan University of Finance and Economics
Priority to CN202220916169.1U priority Critical patent/CN217354414U/en
Application granted granted Critical
Publication of CN217354414U publication Critical patent/CN217354414U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

A large underground cavern surrounding rock supporting structure comprises pre-buried frames, wherein the pre-buried frames are fixed on the side wall of an arc-shaped cavern in a bilateral symmetry mode, each pre-buried frame is provided with a sliding groove along the length direction, and two ends of each arc-shaped frame are slidably arranged in the left sliding groove and the right sliding groove and can move back and forth along the sliding grooves; and the top of the arc-shaped frame is provided with a support seat along the arc-shaped track, and the support seat is tightly attached to the arc-shaped inner wall of the arc-shaped chamber and is tightly supported. The utility model provides a pair of large-scale underground cavern country rock supporting construction, stable in structure and supporting effect are better, and the later stage can be convenient for enclose the rock maintenance net.

Description

Large-scale underground cavern country rock supporting construction
Technical Field
The utility model relates to a supporting construction, especially a large-scale underground cavern country rock supporting construction.
Background
The supports of underground works can be classified into pre-supports and post-supports according to the construction time of the support structure. The support which is constructed or partially constructed before the excavation of the cavern is pre-support; the support of construction again after the cavern excavation, for the back is strutted, the phenomenon such as surrounding rock ageing deformation, the obvious diastrophism of side wall crack, rock mass splitting destruction has appeared in the work progress, just need stable and the higher supporting construction of intensity to use this moment, current mode adopts the rock maintenance net to use, though low cost of this mode, but can't play safety protection's effect at all, secondly, the top of cavern has the protrusion because of some rock layer's the reason, the laminating that the rock maintenance net just can not be complete is in its inner wall department, for this reason, we need improve it.
Disclosure of Invention
The utility model aims to solve the technical problem that a large-scale underground cavern country rock supporting construction is provided, arc cavern inner wall can laminate completely, and stable in structure is reliable, satisfies the safety protection needs.
In order to solve the technical problem, the utility model discloses the technical scheme who adopts is:
a large underground cavern surrounding rock supporting structure comprises pre-buried frames, wherein the pre-buried frames are bilaterally symmetrically fixed on the side wall of an arc-shaped cavern, each pre-buried frame is provided with a sliding groove along the length direction, and two ends of each arc-shaped frame are slidably arranged in the left and right sliding grooves and can move back and forth along the sliding grooves; and the top of the arc-shaped frame is provided with a support seat along an arc-shaped track, and the support seat is tightly attached to the arc-shaped inner wall of the arc-shaped chamber and is tightly supported.
The pre-buried frame is fixed on the arc-shaped cavern through pre-buried bolts and nuts.
The inner side of the embedded frame clings to the inner wall of the arc-shaped cavern and is provided with a water storage cavity, the end face of the outer wall of the water storage cavity, which is positioned on one side of the arc-shaped cavern, is an inclined plane, and seepage holes are formed in two ends of the water storage cavity.
A plurality of vertical frames are arranged on the outer side of the embedded frame side by side along the length direction, each vertical frame is provided with a through groove along the length direction, and two adjacent vertical frames are reinforced through reinforcing plates.
The inner wall of the arc-shaped frame is provided with an extension plate, and the extension plate is arc-shaped.
And a plurality of fixing columns are fixed on the vertical frames at the front end and the rear end of the embedded frame.
The utility model relates to a large-scale underground cavern country rock supporting construction has following technological effect:
1) through setting up a plurality of perpendicular frames, can be convenient for promote the stability of pre-buried frame, the firm effect that the later stage was used has also been strengthened simultaneously to a plurality of perpendicular frames, and a plurality of perpendicular frames are in the equidistant distribution in the outside of pre-buried frame, enclose the rock maintenance net of dress when reuniting the later stage and using, make and carry out abundant protection to the cliff of the indoor side of arc hole, stable supporting role that plays in the work progress has ensured the constructor's of construction period safety. Through all installing a plurality of V-arrangement gusset plates between two adjacent vertical frames, the purpose is in order to promote the joint strength between single vertical frame and the pre-buried frame, and a plurality of V-arrangement gusset plates can link to each other two free vertical frames, make when using, the overall structure in the pre-buried frame outside is the higher structure of a bulk joint strength when supporting the use, so far a plurality of V-arrangement gusset plates have played and will erect the connecting link between frame and the pre-buried frame.
2) The utility model discloses a rock drilling machine, including arc grotto top, the arc is put up the fixed column of both ends border is pre-buried, the fixed column of both ends border on the pre-buried frame, the slidable multiunit arc frame through setting up, can adapt to the hard rock layer at arc grotto top and use, when meetting hard bellied rock piece, the arc frame can be when installing in advance, remove the adjustment well position, avoid fixed rock piece, then support at the inboard top of arc grotto, and the extension board of wall mounting in the arc frame, with the fixed column on the pre-buried frame in both ends border, the later stage of can being convenient for is putting up rock maintenance net, thereby what more possessed supports the use to arc grotto rock wall.
3) The water storing cavity is formed in the inner side of the embedded frame close to the upper portion, water drops on the arc-shaped cavity inner wall can be conveniently drained, the water drops on the rock wall can routinely slide along the rock wall, in order to avoid influencing the stability of later use of the embedded bolt, the water drops can fall on the inner side of the water storing cavity arranged on the inclined plane, and then the water drops are drained through the seepage holes at the two ends of the embedded frame in opposite directions.
Drawings
The invention will be further explained with reference to the following figures and examples:
fig. 1 is a schematic structural diagram of the present invention.
Fig. 2 is a partially enlarged schematic view of a portion a in fig. 1.
Fig. 3 is a schematic view of a partial structure of the present invention.
Fig. 4 is a schematic view of a partial structure of the present invention.
Fig. 5 is a partially enlarged view of B in fig. 4.
In the figure: arc cavern 1, pre-buried frame 2, erect frame 3, fixed column 4, V-arrangement gusset plate 5, lead to groove 6, support seat 7, arc frame 8, pre-buried bolt 9, nut 10, extension board 11, spout 12, seepage flow hole 13, inclined plane 14, deposit water cavity 15.
Detailed Description
As shown in fig. 1 to 5, a surrounding rock supporting structure of a large underground cavern comprises reinforcing mechanisms respectively arranged on two side walls of an arc-shaped cavern 1. Every strengthening mechanism all includes two pre-buried framves 2 from top to bottom, and the outside is fixed with a plurality of vertical braces 3 between two pre-buried framves 2, and a plurality of vertical braces 3 are along the equidistant interval arrangement of horizontal direction. V-shaped reinforcing plates 5 are arranged between every two adjacent vertical frames 3 at equal intervals along the vertical direction. 2 tops of pre-buried frame above two reinforcing mechanism all have seted up spout 12 along length direction about, and the equal sliding connection in inboard of spout 12 has a plurality of sliders, controls just right two sliders and be a set of, and all installs arc frame 8 jointly with the slider top of group, and the top of multiunit arc frame 8 is all installed along the arc orbit equidistance and is supported seat 7, supports the inboard arc roof of seat 7 top at arc cavern 1.
Preferably, through grooves 6 are formed in each vertical frame 3, embedded bolts 9 are embedded in the arc-shaped cavern 1, and the positions of the embedded bolts 9 correspond to the positions of the through grooves 6. The outside screw thread cover at pre-buried bolt 9 is equipped with nut 10, the tip of pre-buried bolt 9 extends to the inboard of arc grotto 1, pre-buried bolt 9 through setting up can be convenient for fix pre-buried frame 2, pre-buried bolt 9 is when the in-service use, can use the special toper pre-buried bolt 9 of rock of high strength metal preparation to the rock wall, this pre-buried bolt 9 joint strength is higher, and be applicable to and bore the dress to the rock, the effect of getting up in the use is stronger, and can carry out rust-proof spraying to pre-buried bolt 9 and nut 10 in the later stage use, thereby avoid causing the outside to rust the problem that influences the use in the underground use.
Preferably, a plurality of fixing posts 4 are mounted on the outer sides of the vertical frames 3 at both ends of the left and right reinforcing mechanisms. And a plurality of fixed columns 4 are arranged along vertical direction equidistance, install a plurality of fixed columns 4 in the 3 outsides of the perpendicular frame that are close to both ends border, can be convenient for the later stage to arc cavern 1's lateral wall adding one deck rock maintenance net to avoid causing the stone to drop because phenomenons such as cliff fracture, weigh down the problem that causes accident.
Preferably, hug closely arc cavern 1 lateral wall in the inboard of every pre-buried frame 2 and be provided with drainage mechanism, drainage mechanism is including all seting up the water storage cavity 15 in 2 inboard top positions of pre-buried frame, and 2 side edges of pre-buried frame are terminal surface 14 for the inclined plane, and water storage cavity 15 both ends have seted up seepage hole 13. It is in order to carry out the drainage in the water droplet on the rock wall under the conventional state to set up water storage cavity 15 through the top at pre-buried frame 2, normal underground works is because underground temperature and earth's surface temperature's difference, the rock wall top layer of underground building has a large amount of water droplets to depend on in its rock wall outside, wait to assemble the back according to gravity nature whereabouts, in order to avoid influencing pre-buried frame 2 and the use of many pre-buried bolts 9, wait that the water droplet shaping just falls to water storage cavity 15's inboard along the rock wall, then the seepage hole 13 of seting up through pre-buried frame 2's both ends will persist water, flow out from both ends.
Preferably, be fixed with extension 11 on the 8 inner walls of arc frame, the appearance of extension 11 is the arc setting, the arc frame 8 through setting up can be convenient for carry out the erection bracing that corresponds to the modeling of arc grotto 1 top, thereby strengthen strutting the rock wall at arc grotto top, extension 11 can be in the top rock maintenance net that the 1 top of outer frame dress arc grotto was used, use the rock maintenance net of this and lateral wall department to make up, in the in-service use in later stage, can laminate the face of extension 11 on the 8 inner walls of each arc frame with top rock maintenance net, then make the stable installation of top rock maintenance net on the extension 11 of the 8 positions of corresponding arc frame through the mounting of outside use.
The working principle is as follows: before using, can realize observing the rock layer at the inboard top of arc cavern 1, then when the installation, through the selection of the hard bellied rock piece of avoiding that corresponds, remove and slide at the inboard arc frame 8 of pre-buried frame 2 in top, a plurality of seats 7 of supporting in the arc frame 8 outside support when the inboard top of arc cavern 1, the inboard of pre-buried frame 2 is pegged into to the pre-buried 9 cartridge of corresponding, can install pre-buried frame 2. The installation is fixed the back, at first correspond extension board 11 on the 8 inner walls of arc frame with outside cliff maintenance net again and install it, the cliff maintenance net accessible both ends border department of lateral wall erects the multiunit fixed column 4 in the 3 outsides of frame then with its enclose dress, from this, overall structure obtains improving more step to the protectiveness of cliff, in the later stage use, the water droplet on the cliff can fall to the water chamber 15 department of depositing of 2 inboards setings of pre-buried frame that are close to the top, in order to avoid influencing the stability of 9 later stage uses of pre-buried bolt, fall in the water droplet that deposits water chamber 15 inboards, can follow the seepage flow hole 13 departments of 2 both ends setings of pre-buried frame and flow away.

Claims (6)

1. The utility model provides a large-scale underground cavern country rock supporting construction which characterized in that: the embedded type tunnel cave is characterized by comprising embedded frames (2), wherein the embedded frames (2) are fixed on the side wall of an arc-shaped tunnel (1) in a bilateral symmetry mode, each embedded frame (2) is provided with a sliding groove (12) along the length direction, and two ends of an arc-shaped frame (8) are arranged in the left sliding groove (12) and the right sliding groove (12) in a sliding mode and can move back and forth along the sliding grooves (12); the top of the arc-shaped frame (8) is provided with a support seat (7) along the arc-shaped track, and the support seat (7) is tightly attached to the arc-shaped inner wall of the arc-shaped chamber (1) and is tightly supported.
2. The surrounding rock supporting structure of the large underground cavern as claimed in claim 1, wherein: the pre-buried frame (2) is fixed on the arc-shaped cavern (1) through pre-buried bolts (9) and screw caps (10).
3. The surrounding rock supporting structure of the large underground cavern as claimed in claim 1, wherein: the inner side of the embedded frame (2) clings to the inner wall of the arc-shaped cavern (1) and is provided with a water storage cavity (15), the end face of the outer wall of the water storage cavity (15) on one side of the arc-shaped cavern (1) is an inclined plane (14), and seepage holes (13) are formed in two ends of the water storage cavity (15).
4. The surrounding rock supporting structure of the large underground cavern as claimed in claim 1, wherein: a plurality of vertical frames (3) are installed side by side along length direction in the outer side of the embedded frame (2), a through groove (6) is formed in each vertical frame (3) along the length direction, and two adjacent vertical frames (3) are reinforced through reinforcing plates (5).
5. The surrounding rock supporting structure of the large underground cavern as claimed in claim 1, wherein: the inner wall of the arc-shaped frame (8) is provided with an extension plate (11), and the extension plate (11) is arc-shaped.
6. The surrounding rock supporting structure of the large underground cavern as claimed in claim 1, wherein: a plurality of fixing columns (4) are fixed on the vertical frames (3) at the front end and the rear end of the embedded frame (2).
CN202220916169.1U 2022-04-20 2022-04-20 Large-scale underground cavern country rock supporting construction Expired - Fee Related CN217354414U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202220916169.1U CN217354414U (en) 2022-04-20 2022-04-20 Large-scale underground cavern country rock supporting construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202220916169.1U CN217354414U (en) 2022-04-20 2022-04-20 Large-scale underground cavern country rock supporting construction

Publications (1)

Publication Number Publication Date
CN217354414U true CN217354414U (en) 2022-09-02

Family

ID=83056768

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202220916169.1U Expired - Fee Related CN217354414U (en) 2022-04-20 2022-04-20 Large-scale underground cavern country rock supporting construction

Country Status (1)

Country Link
CN (1) CN217354414U (en)

Similar Documents

Publication Publication Date Title
CN210458948U (en) High pile cap construction support of naked rock face of big inclination
CN217354414U (en) Large-scale underground cavern country rock supporting construction
CN1670323B (en) Bi-fixation planking curtain
CN213926989U (en) Slope roof supporting structure
CN107700655A (en) The fabricated construction and its installation method of a kind of Special-Shaped Column
CN210315980U (en) Door type steel frame structure
CN207499219U (en) Large area moulding aluminium grille decorative wall surface connecting system
CN215594693U (en) Steel pipe pull rod hollow ceramic archaized brick combined wall
CN210685071U (en) Assembled power consumption shear force wall of removable built-in shaped steel bracing
CN210658899U (en) Ceiling conversion layer structure
CN210797987U (en) Horizontal aluminum plate line structure
CN215888767U (en) Unit type glass curtain wall with glass flying wings
CN219864666U (en) Ultra-long double-layer lintel window frame capable of resisting multidirectional load
CN208916557U (en) A kind of modular lift car
CN221119022U (en) Assembled unit component
CN219993381U (en) Noise-reducing protective sound-insulating plate for construction site
CN217896520U (en) Large-span shaped steel integrated configuration that excavation supporting used
CN216108954U (en) Precast beam column building steel structure with antidetonation function
CN217027640U (en) U type stone material decorative column pendant system
CN214460498U (en) Mountain slope protection device module
CN218060717U (en) Install wooden fill beam column structure on steel construction
CN219471745U (en) Construction is with green ecological fender that encloses of planting
CN213087641U (en) Assembled enclosure structure
CN220167240U (en) Oversized plate galvanized steel sheet and heat preservation integrated plate mounting device
CN215108959U (en) Roadway driving supporting device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20220902

CF01 Termination of patent right due to non-payment of annual fee