CN217326378U - Climbing type outer frame real-time protection and winter construction rapid sealing outer frame heat insulation structure - Google Patents

Climbing type outer frame real-time protection and winter construction rapid sealing outer frame heat insulation structure Download PDF

Info

Publication number
CN217326378U
CN217326378U CN202220278117.6U CN202220278117U CN217326378U CN 217326378 U CN217326378 U CN 217326378U CN 202220278117 U CN202220278117 U CN 202220278117U CN 217326378 U CN217326378 U CN 217326378U
Authority
CN
China
Prior art keywords
climbing
outer frame
frame
wall
fixedly connected
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202220278117.6U
Other languages
Chinese (zh)
Inventor
崔寿凯
周志健
裴鸿斌
黎映呈
崔爱珍
张�杰
姚文山
贾宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN202220278117.6U priority Critical patent/CN217326378U/en
Application granted granted Critical
Publication of CN217326378U publication Critical patent/CN217326378U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B30/00Energy efficient heating, ventilation or air conditioning [HVAC]
    • Y02B30/90Passive houses; Double facade technology

Landscapes

  • Building Environments (AREA)

Abstract

The utility model relates to the technical field of building construction safety protection and closed heat preservation, in particular to a climbing type frame real-time protection and winter construction rapid closed frame heat preservation structure, which comprises a frame structure, wherein the frame structure comprises a plurality of climbing frames, and the climbing frames comprise climbing frame guide rails, one side of each climbing frame guide rail is fixedly connected with a climbing frame main stand column, the bottom end of each climbing frame guide rail is provided with a suspension component, the suspension component comprises a stand column suspension arm, the stand column suspension arm is fixedly connected with the bottom ends of the climbing frame guide rails and the climbing frame main stand columns, and one end of the outer wall at the bottom of the stand column suspension arm is fixedly connected with double-channel steel suspension lugs through bolts; the utility model discloses the frame heat preservation tarpaulin that the utilization slideed the zip fastener rings and connect makes things convenient for the installation and subsequent recovery of frame heat preservation tarpaulin, can realize that the outer facade of concrete structure real-time safety protection seals heat preservation maintenance concrete with construction in winter fast, ensures the safety and the quality of construction.

Description

Climbing type outer frame real-time protection and winter construction rapid sealing outer frame heat insulation structure
Technical Field
The utility model relates to a construction safety protection and seal heat preservation technical field specifically are a frame insulation construction is sealed fast in climbing formula frame real-time protection and construction winter.
Background
The super high-rise building construction usually adopts climbing frames, an integral all-steel structure, an integrated device, assists the operation of the outer vertical face of workers, and has the characteristics of climbing along with the structure, real-time full-closed protection, no fire hazard, low comprehensive cost and the like. After the one deck has been under construction to the structure, climb the frame and upwards climb the one deck, climb frame one deck afterwards and should in time install the protection rail, ensure to face limit operation safety.
In the prior art, the following problems exist:
after the climbing frame climbs upwards and accomplishes, because reasons such as the time limit for a project tight, the size is big, perpendicular transportation difficulty, the protection rail fails in time to be installed, prevents the high accident that weighs down, need in time adopt the safety protection measure to the outer facade, and the winter construction need be adopted simultaneously and seal the heat preservation measure, how can construct in real time winter with the help of the climbing frame and seal the problem that heat preservation maintenance concrete still need solve urgently.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a climb formula frame real-time protection and quick closed frame insulation construction of construction winter to solve the problem that proposes among the above-mentioned background art.
The technical scheme of the utility model is that: the utility model provides a climb formula frame real-time protection and quick closed frame insulation construction of construction in winter, includes the frame structure, the frame structure includes a plurality of frames of climbing, and a plurality of frames of climbing all include and climb a guide rail, one side fixedly connected with of frame guide rail climbs a head tree, the bottom of climbing a guide rail is provided with suspension assembly, and suspension assembly includes the stand cantilever arm, the stand cantilever arm and the bottom fixed connection who climbs a guide rail and climb a head tree, and the stand cantilever arm bottom outer wall one end all articulates the hangers through two channel-section steels of bolt fixedly connected with, the bottom that two channel-section steels articulated hangers all has seted up coupling mechanism through bolt fixedly connected with wall hangers, the bottom of wall hangers all is provided with the I-steel circular orbit, and is provided with insulation assembly on the I-steel circular orbit.
Preferably, the heat preservation assembly comprises a plurality of sliding zipper hanging rings connected to the I-shaped steel annular rail in a sliding mode, and the outer frame heat preservation tarpaulin is hung on the sliding zipper hanging rings.
Preferably, coupling mechanism is including offering T-slot, bar groove and the hole groove on the wall hangers, and the T-slot is located the both sides wall of wall hangers respectively, bar groove and hole groove are located all the other both sides walls of wall hangers respectively.
Preferably, the hole groove is fixedly connected with the wall edge or the beam edge through a bolt, the strip-shaped groove is connected with the double-groove steel hanging lugs through bolts, and the T-shaped groove is hung with the I-shaped steel annular track.
Preferably, it is a plurality of climb equal fixedly connected with triangle bracing on the one end outer wall that a main upright is close to the bottom, and the top fixedly connected with scaffold board of triangle bracing, there is the opening flap in one side outer wall of scaffold board through hinged joint.
Preferably, a plurality of I-steel annular rails are connected with each other through pressing plate bolts in a threaded manner.
Preferably, a top hanging lug is adopted as a connecting piece between the double-channel steel hanging lug and the I-shaped steel annular track, and the top hanging lug is also provided with a T-shaped groove and a strip-shaped groove.
The utility model discloses an improve and provide a formula of climbing frame real-time protection and frame insulation construction is sealed fast with construction winter here, compare with prior art, have following improvement and advantage:
one is as follows: the utility model utilizes the outer frame heat-insulating tarpaulin connected with the slide zipper rings, facilitates the installation and subsequent recovery of the outer frame heat-insulating tarpaulin, can realize the real-time safety protection of the outer facade of the concrete structure and the rapid sealing heat-insulating concrete maintenance in winter construction, and ensures the safety and quality of the construction;
the second step is as follows: the utility model provides two types of hangers, one is a top hanger and the other is a wall hanger, and the top hanger needs to hang the hanger and the upright post suspension arm of the climbing frame guide rail by means of double-groove steel; wall hangers accessible bolt setting is climbing the side that the frame faced the wall bottommost, and the below setting that turns over the board is opening on facing the limit and is not attached to and climbs the frame body, only realizes ann with the help of the platform that climbs the frame bottommost and tears the dismouting to increase flexibility, the suitability of this structure.
Drawings
The invention is further explained below with reference to the figures and examples:
FIG. 1 is a schematic sectional structure view of the outer frame structure of the present invention;
FIG. 2 is an enlarged structural diagram of the cross section of the outer frame structure of the present invention;
fig. 3 is a schematic view of the outer frame structure of the present invention;
FIG. 4 is a schematic view of the structure of the outer frame structure of the enlarged node of the present invention;
fig. 5 is a schematic view of the outer frame structure of the present invention;
fig. 6 is a schematic view of the present invention in a partially enlarged structure shown in fig. 5;
FIG. 7 is a schematic view of the structure of the wall hanger in the drawing of the present invention;
fig. 8 is a schematic view of the three-dimensional structure of the top suspension loop in the drawing of the present invention.
Description of reference numerals:
1. an outer frame structure; 101. climbing a frame; 1011. a climbing frame guide rail; 1012. a main upright post of the climbing frame; 102. the outer frame is made of heat-insulating tarpaulin; 103. an I-steel annular track; 2. a slide zipper hanging ring; 3. hanging a lug on a wall; 301. a T-shaped slot; 302. a strip-shaped groove; 303. a hole groove; 304. a top suspension loop; 4. a double-channel steel is connected with a suspension loop; 5. opening the turning plate; 6. a column cantilever arm; 7. a triangular inclined strut; 8. a scaffold board; 9. and (5) a pressure plate bolt.
Detailed Description
The present invention will be described in detail below, and it is apparent that the technical solutions in the embodiments of the present invention are described clearly and completely. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
The utility model discloses an improve and provide a formula of climbing frame real-time protection and frame insulation construction is sealed fast in construction winter here, the technical scheme of the utility model is:
the first embodiment is as follows:
as shown in fig. 1-7, a climbing-type outer frame real-time protection and winter construction rapid closed outer frame heat preservation structure comprises an outer frame structure 1, the outer frame structure 1 comprises a plurality of climbing frames 101, and the plurality of climbing frames 101 comprise climbing frame guide rails 1011, one side of the climbing frame guide rails 1011 is fixedly connected with a climbing frame main upright column 1012, the bottom ends of the climbing frame guide rails 1011 are provided with suspension components, and the suspension component comprises an upright post suspension arm 6, the upright post suspension arm 6 is fixedly connected with the bottom end of the climbing frame guide rail 1011 and the climbing frame main upright post 1012, and one end of the outer wall of the bottom of the upright post cantilever arm 6 is fixedly connected with a double-channel steel hanging lug 4 through a bolt, the bottom end of the double-channel steel hanging lug 4 is fixedly connected with a wall hanging lug 3 through a bolt, and the wall hangers 3 are provided with connecting mechanisms, the bottom ends of the wall hangers 3 are provided with I-shaped steel annular rails 103, and the I-shaped steel annular rails 103 are provided with heat insulation assemblies.
Further, the heat preservation assembly comprises a plurality of sliding zipper hanging rings 2 connected to the I-shaped steel annular rail 103 in a sliding mode, and outer frame heat preservation tarpaulin 102 is hung on the sliding zipper hanging rings 2.
By means of the structure, the outer frame heat-insulation tarpaulin 102 connected with the sliding zipper hanging ring 2 is convenient to install and subsequently recover the outer frame heat-insulation tarpaulin 102, good protection and heat insulation effects are achieved by the outer frame heat-insulation tarpaulin 102, and safety guarantee is provided for winter construction.
Further, coupling mechanism is including offering T-slot 301, bar groove 302 and hole groove 303 on wall hangers 3, and T-slot 301 is located wall hangers 3's both sides wall respectively, and bar groove 302 and hole groove 303 are located wall hangers 3's all the other both sides wall respectively.
Further, the hole groove 303 is fixedly connected with the wall edge or the beam edge through a bolt, the strip-shaped groove 302 is connected with the double-groove steel hanging lug 4 through a bolt, and the T-shaped groove 301 is hung with the I-shaped steel annular rail 103.
By means of the structure, the connecting effect of the wall hanging lug 3 can be improved by the aid of the arranged connecting mechanism.
Further, a plurality of equal fixedly connected with triangle bracing 7 on climbing frame owner stand 1012 is close to the one end outer wall of bottom, and the top fixedly connected with scaffold board 8 of triangle bracing 7, and there is opening through hinged joint and turns over board 5 one side outer wall of scaffold board 8.
By means of the structure, the stable installation of the scaffold board 8 can be realized by the arranged triangular inclined strut 7; the opening turning plate 5 is arranged, so that the whole disassembly and assembly operation is convenient to carry out.
Further, a plurality of I-steel annular rails 103 are connected with a pressing plate bolt 9 through threads.
By means of the structure, the I-shaped steel annular rails 103 can be connected through the arranged pressing plate bolts 9.
The working principle is as follows: when the steel wire rope is used, the upright post cantilever arm 6 is installed on a climbing frame guide rail 1011 at the lowest edge of the climbing frame 101, the upright post cantilever arm 6 is connected with the double-channel steel hanging lug 4 through a bolt, the lower part of the double-channel steel hanging lug 4 is connected with the wall hanging lug 3 or the top hanging lug 304, the I-shaped steel annular track 103 is hung below the wall hanging lug 3 or the top hanging lug 304, the sliding zipper hanging ring 2 is arranged on the I-shaped steel annular track 103, the sliding zipper hanging ring 2 can be hung on the outer frame heat-insulating tarpaulin 102 or a protective steel wire net, in order to ensure the safety of the edge, the steel wire rope and the outer frame heat-insulating tarpaulin 102 or the steel wire net are in a pulling mode through expansion bolts for fixing at the position of the edge of a floor slab.
Example two:
as shown in fig. 8, compared with the first embodiment, the embodiment of the fast frame thermal insulation structure for climbing type frame real-time protection and winter construction has the advantages that the top suspension loop 304 is adopted as a connecting piece between the double-channel steel hanging suspension loop 4 and the i-shaped steel annular rail 103, and the top suspension loop 304 is also provided with the T-shaped groove 301 and the strip-shaped groove 302.
By means of the structure, the utility model provides two hanging lug forms, one is that the top hanging lug 304 is the wall hanging lug 3, and the top hanging lug 304 needs to hang the hanging lug 4 and the upright post cantilever arm 6 of the climbing frame guide rail 1011 by means of double channel steel; wall hangers 3 accessible bolt setting is climbing the side that the frame 101 faces the wall at the bottom, and the below setting of turning over board 5 is opening and is not attached to climbing the frame body facing the limit, only realizes ann with the help of the platform that climbs the frame 101 bottommost and tears open.

Claims (7)

1. The utility model provides a climb formula frame real-time protection and quick closed frame insulation construction of construction in winter which characterized in that: comprises an outer frame structure (1), wherein the outer frame structure (1) comprises a plurality of climbing frames (101), the plurality of climbing frames (101) comprise climbing frame guide rails (1011), one side of each climbing frame guide rail (1011) is fixedly connected with a climbing frame main stand column (1012), the bottom end of each climbing frame guide rail (1011) is provided with a suspension assembly, each suspension assembly comprises a stand column suspension arm (6), each stand column suspension arm (6) is fixedly connected with the bottom end of each climbing frame guide rail (1011) and the bottom end of each climbing frame main stand column (1012), one end of the outer wall at the bottom of each stand column suspension arm (6) is fixedly connected with a double-channel steel hanging lug (4) through a bolt, the bottom end of each double-channel steel hanging lug (4) is fixedly connected with a wall hanging lug (3) through a bolt, a connecting mechanism is arranged on each wall hanging lug (3), and the bottom end of each wall hanging lug (3) is provided with an I-shaped steel annular track (103), and a heat insulation component is arranged on the I-shaped steel annular track (103).
2. The climbing type outer frame real-time protection and winter construction rapid closing outer frame heat insulation structure as claimed in claim 1, characterized in that: the heat preservation assembly comprises a plurality of sliding zipper hanging rings (2) which are connected to the I-shaped steel annular rail (103) in a sliding mode, and outer frame heat preservation tarpaulin (102) is hung on the sliding zipper hanging rings (2).
3. The climbing type outer frame real-time protection and winter construction rapid closed outer frame heat insulation structure as claimed in claim 1, characterized in that: coupling mechanism is including offering T-slot (301), bar groove (302) and hole groove (303) on wall hangers (3), and T-slot (301) are located the both sides wall of wall hangers (3) respectively, bar groove (302) and hole groove (303) are located the all the other both sides walls of wall hangers (3) respectively.
4. The climbing type outer frame real-time protection and winter construction rapid closing outer frame heat insulation structure as claimed in claim 3, characterized in that: hole groove (303) pass through bolt and wall limit or roof beam limit fixed connection, bar groove (302) and double flute steel articulate hangers (4) and pass through bolted connection, T-slot (301) articulate mutually with I-steel circular orbit (103).
5. The climbing type outer frame real-time protection and winter construction rapid closing outer frame heat insulation structure as claimed in claim 1, characterized in that: a plurality of climb equal fixedly connected with triangle bracing (7) on the one end outer wall that a main upright post (1012) is close to the bottom, and the top fixedly connected with scaffold board (8) of triangle bracing (7), there is opening and turning over board (5) one side outer wall of scaffold board (8) through hinged joint.
6. The climbing type outer frame real-time protection and winter construction rapid closed outer frame heat insulation structure as claimed in claim 1, characterized in that: and a plurality of I-shaped steel annular rails (103) are connected with each other through a pressing plate bolt (9) through threads.
7. The climbing type outer frame real-time protection and winter construction rapid closing outer frame heat insulation structure as claimed in claim 1, characterized in that: a top hanging lug (304) is adopted as a connecting piece between the double-channel steel hanging lug (4) and the I-shaped steel annular track (103), and a T-shaped groove (301) and a strip-shaped groove (302) are also formed in the top hanging lug (304).
CN202220278117.6U 2022-02-11 2022-02-11 Climbing type outer frame real-time protection and winter construction rapid sealing outer frame heat insulation structure Active CN217326378U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202220278117.6U CN217326378U (en) 2022-02-11 2022-02-11 Climbing type outer frame real-time protection and winter construction rapid sealing outer frame heat insulation structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202220278117.6U CN217326378U (en) 2022-02-11 2022-02-11 Climbing type outer frame real-time protection and winter construction rapid sealing outer frame heat insulation structure

Publications (1)

Publication Number Publication Date
CN217326378U true CN217326378U (en) 2022-08-30

Family

ID=82997533

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202220278117.6U Active CN217326378U (en) 2022-02-11 2022-02-11 Climbing type outer frame real-time protection and winter construction rapid sealing outer frame heat insulation structure

Country Status (1)

Country Link
CN (1) CN217326378U (en)

Similar Documents

Publication Publication Date Title
CN109629810B (en) Closed type overhanging scaffold and construction method
CN104652670B (en) It is a kind of can indoor location glass curtain wall system
GB2108561A (en) Process for the installation of curtain walls and wall elements
CN217326378U (en) Climbing type outer frame real-time protection and winter construction rapid sealing outer frame heat insulation structure
CN214786179U (en) Instrument formula level safety net of encorbelmenting
CN209521066U (en) A kind of precast beam steam curing canopy
CN209053231U (en) A kind of separate type bracket node structure and Housing Structure System for beam column of steel structure connection
CN206888607U (en) A kind of rail type mobile workshop for the assembling of water-storage formula generator unit
CN109278174A (en) A kind of precast beam steam curing canopy and its construction method
CN114517523A (en) Multi-layer air corridor for high-rise steel structure building and construction method of multi-layer air corridor
CN108412103B (en) Roof center closing device for rotary opening and closing roof and control method thereof
JP2764356B2 (en) Temporary roof and its construction method
CN215166537U (en) Slidable formula safety net stretch-draw support
CN215670073U (en) H-shaped steel connecting structure
CN220014543U (en) Elevator shaft crossing rail guard
CN221053260U (en) Fixing device for constructional engineering steel structure
CN220565758U (en) Shaping overhanging protection shed
CN218623258U (en) Climbing structure of attached scaffold
CN215829715U (en) Curtain wall panel fixing device
CN220642357U (en) Telescopic tower crane safety channel
CN216840816U (en) Shaft ladder cage safety channel
CN218346774U (en) Two-stage turnover plate splicing structure
CN220522077U (en) Top isolation protective film structure for built overhead station
CN219794617U (en) Lower stay bar piece of attached overhanging scaffold
CN212533700U (en) Pin-connected panel staple bolt platform of bent cap construction usefulness

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant