CN217300458U - Drilling platform for pile foundation of soft foundation - Google Patents

Drilling platform for pile foundation of soft foundation Download PDF

Info

Publication number
CN217300458U
CN217300458U CN202122902153.3U CN202122902153U CN217300458U CN 217300458 U CN217300458 U CN 217300458U CN 202122902153 U CN202122902153 U CN 202122902153U CN 217300458 U CN217300458 U CN 217300458U
Authority
CN
China
Prior art keywords
platform
platform body
bolts
pump
foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202122902153.3U
Other languages
Chinese (zh)
Inventor
汪华刚
杜德峰
陆晓峰
杜晓
袁兆巍
伍剑锋
肖佳哲
郭庆
楼俊阳
胡刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANDONG ZHONGHONG ROAD AND BRIDGE CONSTRUCTION CO Ltd
Zhongtian Communications Construction Investment Group Co ltd
Original Assignee
SHANDONG ZHONGHONG ROAD AND BRIDGE CONSTRUCTION CO Ltd
Zhongtian Communications Construction Investment Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANDONG ZHONGHONG ROAD AND BRIDGE CONSTRUCTION CO Ltd, Zhongtian Communications Construction Investment Group Co ltd filed Critical SHANDONG ZHONGHONG ROAD AND BRIDGE CONSTRUCTION CO Ltd
Priority to CN202122902153.3U priority Critical patent/CN217300458U/en
Application granted granted Critical
Publication of CN217300458U publication Critical patent/CN217300458U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The utility model discloses a soft foundation pile foundation drilling platform, including platform body, pump and air cushion, platform body bottom periphery is provided with the air cushion, the mount pad is all installed to platform body bottom four corners department, the mount pad bottom is provided with the track. Has the advantages that: the utility model discloses a platform body, track, air cushion and the air pump that sets up can perfectly be applicable to weak ground, and the platform can not appear the condition that the slope collapsed yet when the construction to improve the convenience when the platform uses, through drilling rod, grid net, blow off pipe and the pump of taking out that sets up, can carry out quick effectual absorption with the sewage mud that its ground contains, thereby improve the work efficiency of platform.

Description

Drilling platform for pile foundation of soft foundation
Technical Field
The utility model relates to a drilling platform technical field, concretely relates to weak ground pile foundation drilling platform.
Background
The soft foundation is mainly composed of silt, mucky soil, filling soil, miscellaneous filling soil or other high-compressibility soil layers. The ground has overlarge natural water content and low bearing capacity, and is easy to slide or solidify and settle under the action of load. Special drilling platforms are required to operate on such foundations.
However, the existing drilling platform for the pile foundation of the soft foundation is heavy, so that the condition of platform inclination and subsidence is caused, the levelness of the flat platform needs to be continuously corrected, thereby reducing the convenience of the platform in use, secondly, when the existing drilling platform for the pile foundation of the soft foundation is used for the condition of more mud and sewage in the ground, the existing drilling platform for the pile foundation of the soft foundation can not quickly and effectively suck the existing drilling platform for the pile foundation of the soft foundation, thereby reducing the working efficiency of the platform, and therefore, the problem is solved by urgently needing a novel drilling platform for the pile foundation of the soft foundation.
SUMMERY OF THE UTILITY MODEL
Technical problem to be solved
In order to overcome prior art not enough, now provide a soft foundation pile foundation drilling platform, solved current soft foundation pile foundation drilling platform when drilling operation, all return the condition that takes place the platform and incline and sink because of the machine is heavier, need constantly to correct the flatbed levelness, thereby convenience when having reduced the platform and using, and when current soft foundation pile foundation drilling platform is to the more condition of ground bed sewage mud, can't effectively absorb it fast, thereby the problem of the work efficiency of platform has been reduced.
(II) technical scheme
The utility model discloses a following technical scheme realizes: the utility model provides a soft foundation pile foundation drilling platform, including platform body, suction pump and air cushion, platform body bottom periphery is provided with the air cushion, platform body bottom four corners department all installs the mount pad, the mount pad bottom is provided with the track, platform body bottom middle part symmetry is provided with two mounts, the mount pad bottom is installed the hydraulic stem, hydraulic stem one end is connected with the limiting plate, platform body upper end one side is installed the air pump, air pump one end is provided with operating panel, the last microprocessor that is provided with of operating panel, platform body upper end middle part is provided with the portal frame, the portal frame bottom is installed the pile driver, the drill rod is connected to the drill pipe bottom, drill rod bottom one side is provided with the grid net, grid net one end is provided with the suction groove, suction groove one end is provided with the blow off pipe, the pump is arranged at one end of the sewage discharge pipe.
Further, the air cushion is connected with the platform body through bolts, the mounting seat is connected with the platform body through bolts, and the crawler belt is connected with the mounting seat through bolts.
Through adopting above-mentioned technical scheme, the air cushion can freely inflate, it is right the platform body supports to can be applicable to the ground of soft foundation, prevent that the platform from sinking, the track can go on comparatively complicated ground.
Further, the fixing frame is connected with the platform body through bolts, the hydraulic rod is connected with the fixing frame through bolts, and the limiting plate is connected with the hydraulic rod through bolts.
By adopting the technical scheme, the hydraulic rod is matched with the limiting plate for use, and the drill rod can be limited.
Furthermore, the air pump is connected with the platform body through bolts, the operating panel is connected with the platform body through bolts, and the microprocessor is electrically connected with the operating panel.
By adopting the technical scheme, the air pump can rapidly inflate the air cushions, and the operation panel can control the operation of each device.
Furthermore, the portal frame is connected with the platform body through bolts, and the pile driver is connected with the portal frame through bolts.
Through adopting above-mentioned technical scheme, the portal frame can be right the pile driver hoists firmly, the pile driver cooperation the drilling rod uses, can carry out the pile drilling operation.
Furthermore, the drill rod is connected with the pile driver clamping groove, the grid net is connected with the drill rod clamping groove, and the suction groove is formed in the drill rod.
Through adopting above-mentioned technical scheme, the grid net can prevent the suction slot blocks up.
Furthermore, the sewage discharge pipe is in threaded connection with the pump, and the pump is in bolted connection with the platform body.
By adopting the technical scheme, the sewage discharge pipe is matched with the pump for use, so that the underground water can be quickly sucked out.
(III) advantageous effects
Compared with the prior art, the utility model, following beneficial effect has:
1. in order to solve the problem that the existing drilling platform for the pile foundation of the soft foundation is inclined and collapsed due to the fact that a machine is heavy, the levelness of the platform needs to be continuously corrected, and therefore the convenience of the platform in use is reduced, the utility model discloses a platform body, a track, an air cushion and an air pump which are arranged can be perfectly suitable for the soft ground, the platform can not be inclined and collapsed in construction, and therefore the convenience of the platform in use is improved;
2. when solving the more condition of current soft foundation pile foundation drilling platform to ground bottom sewage mud, can't carry out quick effective absorption to it to the problem of the work efficiency of platform has been reduced, the utility model discloses a drilling rod, grid net, blow off pipe and the pump of taking out that set up can carry out quick effectual absorption with the sewage mud that its ground bottom contains, thereby improve the work efficiency of platform.
Drawings
Fig. 1 is a front view of a drilling platform for pile foundations of soft foundation according to the present invention;
fig. 2 is an enlarged view of a part a of a drilling platform for a soft foundation pile foundation according to the present invention;
fig. 3 is the utility model discloses a weak ground pile foundation drilling platform's circuit block diagram.
The reference numerals are explained below:
1. a platform body; 2. pumping; 3. an air cushion; 4. a mounting base; 5. a crawler belt; 6. a fixed mount; 7. a hydraulic lever; 8. a limiting plate; 9. an air pump; 10. an operation panel; 11. a microprocessor; 12. a gantry; 13. a pile driver; 14. a blow-off pipe; 15. a drill stem; 16. a suction groove; 17. a grid net.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more clearly understood, the present invention is further described in detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the invention and are not intended to limit the invention.
As shown in fig. 1-3, the drilling platform for pile foundation of soft foundation in this embodiment comprises a platform body 1, a pump 2 and an air cushion 3, the air cushion 3 is arranged on the periphery of the bottom end of the platform body 1, mounting bases 4 are arranged at four corners of the bottom end of the platform body 1, crawler belts 5 are arranged at the bottom ends of the mounting bases 4, two fixing frames 6 are symmetrically arranged in the middle of the bottom end of the platform body 1, hydraulic rods 7 are arranged at the bottom ends of the fixing frames 6, one end of each hydraulic rod 7 is connected with a limiting plate 8, an air pump 9 is arranged on one side of the upper end of the platform body 1, an operating panel 10 is arranged at one end of each air pump 9, a microprocessor 11 is arranged on each operating panel 10, a portal frame 12 is arranged in the middle of the upper end of the platform body 1, a pile driver 13 is arranged at the bottom end of the portal frame 12, a drill rod 15 is connected to the bottom end of the pile driver 13, a grid net 17 is arranged on one side of the bottom end of the drill rod 15, and a suction groove 16 is arranged at one end of the grid net 17, one end of the suction groove 16 is provided with a sewage discharge pipe 14, and one end of the sewage discharge pipe 14 is provided with a suction pump 2.
As shown in fig. 1-3, in this embodiment, the air cushion 3 is connected to the platform body 1 by bolts, the mounting seat 4 is connected to the platform body 1 by bolts, the crawler 5 is connected to the mounting seat 4 by bolts, the air cushion 3 can be inflated freely to support the platform body 1, so as to be suitable for the ground of soft foundation and prevent the platform from sinking, the crawler 5 can run on a relatively complicated ground, the fixing frame 6 is connected to the platform body 1 by bolts, the hydraulic rod 7 is connected to the fixing frame 6 by bolts, the limiting plate 8 is connected to the hydraulic rod 7 by bolts, the hydraulic rod 7 can be used in cooperation with the limiting plate 8 to limit the position of the drill rod 15, the air pump 9 is connected to the platform body 1 by bolts, the operating panel 10 is connected to the platform body 1 by bolts, the microprocessor 11 is electrically connected to the operating panel 10, the air pump 9 can inflate the air cushion 3 rapidly, and the operating panel 10 can control the operation of each device, portal frame 12 and platform body 1 bolted connection, pile driver 13 and portal frame 12 bolted connection, portal frame 12 can stabilize hoist and mount to pile driver 13, pile driver 13 cooperation drilling rod 15 uses, can carry out pile drilling operation, drilling rod 15 is connected with pile driver 13 draw-in groove, grid net 17 is connected with drilling rod 15 draw-in groove, inhale the groove 16 shaping on drilling rod 15, grid net 17 can prevent to inhale the groove 16 and block up, blow off pipe 14 and 2 threaded connection of suction pump, suction pump 2 and platform body 1 bolted connection, blow off pipe 14 cooperation suction pump 2 uses, can be fast with groundwater suction.
The specific implementation process of this embodiment is as follows: when using, at first with each equipment switch on, track 5 transports platform body 1 to the drilling position, then air pump 9 blows fast air cushion 3, make air cushion 3 support platform body 1 completely, platform body 1 can not sink on weak soil, pile driver 13 hoists drilling rod 15 afterwards, carry out drilling operation to ground, when meetting low sewage mud and need getting rid of, the sewage mud of suction groove 16 department is got rid of fast through blow off pipe 14 to suction pump 2, be convenient for subsequent construction operation.
The above-described embodiments are merely illustrative of the preferred embodiments of the present invention, and are not intended to limit the spirit and scope of the present invention. Without departing from the design concept of the present invention, various modifications and improvements made by the technical solution of the present invention by those skilled in the art should fall into the protection scope of the present invention, and the technical contents claimed by the present invention have been fully recorded in the claims.

Claims (7)

1. The utility model provides a weak foundation pile foundation drilling platform which characterized in that: the air cushion type air pumping platform comprises a platform body (1), a pumping pump (2) and an air cushion (3), wherein the air cushion (3) is arranged on the periphery of the bottom end of the platform body (1), mounting seats (4) are mounted at four corners of the bottom end of the platform body (1), a crawler belt (5) is arranged at the bottom end of each mounting seat (4), two fixing frames (6) are symmetrically arranged in the middle of the bottom end of the platform body (1), a hydraulic rod (7) is mounted at the bottom end of each fixing frame (6), one end of each hydraulic rod (7) is connected with a limiting plate (8), an air pump (9) is mounted on one side of the upper end of the platform body (1), an operation panel (10) is arranged at one end of each air pump (9), a microprocessor (11) is arranged on the operation panel (10), a portal frame (12) is arranged in the middle of the upper end of the platform body (1), and a pile driver (13) is mounted at the bottom end of the portal frame (12), the device is characterized in that a drill rod (15) is connected to the bottom end of the pile driver (13), a grid net (17) is arranged on one side of the bottom end of the drill rod (15), an absorption groove (16) is formed in one end of the grid net (17), a sewage discharge pipe (14) is arranged at one end of the absorption groove (16), and the pump (2) is arranged at one end of the sewage discharge pipe (14).
2. The weak foundation pile foundation drilling platform of claim 1, wherein: the air cushion (3) is connected with the platform body (1) through bolts, the mounting seat (4) is connected with the platform body (1) through bolts, and the crawler belt (5) is connected with the mounting seat (4) through bolts.
3. The weak foundation pile foundation drilling platform of claim 1, wherein: the fixing frame (6) is connected with the platform body (1) through bolts, the hydraulic rod (7) is connected with the fixing frame (6) through bolts, and the limiting plate (8) is connected with the hydraulic rod (7) through bolts.
4. The weak foundation pile foundation drilling platform of claim 1, wherein: the air pump (9) is connected with the platform body (1) through bolts, the operation panel (10) is connected with the platform body (1) through bolts, and the microprocessor (11) is electrically connected with the operation panel (10).
5. The drilling platform for the pile foundation of the soft foundation according to claim 1, wherein: the portal frame (12) is connected with the platform body (1) through bolts, and the pile driver (13) is connected with the portal frame (12) through bolts.
6. The weak foundation pile foundation drilling platform of claim 1, wherein: the drill rod (15) is connected with the clamping groove of the pile driver (13), the grid net (17) is connected with the clamping groove of the drill rod (15), and the suction groove (16) is formed in the drill rod (15).
7. The weak foundation pile foundation drilling platform of claim 1, wherein: the sewage discharge pipe (14) is in threaded connection with the pump (2), and the pump (2) is in bolted connection with the platform body (1).
CN202122902153.3U 2021-11-24 2021-11-24 Drilling platform for pile foundation of soft foundation Active CN217300458U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202122902153.3U CN217300458U (en) 2021-11-24 2021-11-24 Drilling platform for pile foundation of soft foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202122902153.3U CN217300458U (en) 2021-11-24 2021-11-24 Drilling platform for pile foundation of soft foundation

Publications (1)

Publication Number Publication Date
CN217300458U true CN217300458U (en) 2022-08-26

Family

ID=82912904

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202122902153.3U Active CN217300458U (en) 2021-11-24 2021-11-24 Drilling platform for pile foundation of soft foundation

Country Status (1)

Country Link
CN (1) CN217300458U (en)

Similar Documents

Publication Publication Date Title
CN104276527B (en) Tower equipment hoisting apparatus and its using method
CN206570662U (en) A kind of construction of the highway concrete paving and leveling all-in-one
CN217300458U (en) Drilling platform for pile foundation of soft foundation
CN111827248A (en) System and method for air bag expansion pressurization and vacuum-electroosmosis composite dewatering and dewatering in hole
CN205604220U (en) Soft clay secondary consolidation drainage device of superweak saturation
CN210571479U (en) Sampling device for soil remediation
CN215595619U (en) Anchor rod transfer unit for seven-arm coal mine
CN113650688A (en) Mining emergency drainage vehicle
CN109137875A (en) A kind of rammer compacter that construction stability is high
CN205858179U (en) A kind of portable exploratory drilling rig
CN208917836U (en) A kind of architectural engineering piling equipment
CN211735383U (en) Constructional engineering pile device
CN207861786U (en) PVC packaging bag jack works
CN210714490U (en) Bottom supporting device of rotary drilling rig special for railway
CN210134414U (en) Small-sized hole drilling and digging machine for detecting compaction degree of highway subgrade
CN201649062U (en) High-frequency hydraulic spiling machine
CN2735001Y (en) Hydraulic roadway support for moving fully-mechanized mining equipment in coal mine
CN212703653U (en) Organic contaminated soil and groundwater normal position prosthetic devices
CN204645655U (en) Rubble for building operations fills out hole car
CN213329200U (en) Excavator cab heightening support
CN214091918U (en) Temporary supporting structure for coal mining
CN220185051U (en) Double-sided drilling and drilling integrated drilling frame
CN214107395U (en) Coal gangue crushing equipment
CN212639207U (en) Movable efficient soil feeding machine
US3373572A (en) Method of driving tunnels

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant