CN217264414U - Detachable building tower crane anchor - Google Patents

Detachable building tower crane anchor Download PDF

Info

Publication number
CN217264414U
CN217264414U CN202220822791.6U CN202220822791U CN217264414U CN 217264414 U CN217264414 U CN 217264414U CN 202220822791 U CN202220822791 U CN 202220822791U CN 217264414 U CN217264414 U CN 217264414U
Authority
CN
China
Prior art keywords
installation
tower crane
mounting
column
seat
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202220822791.6U
Other languages
Chinese (zh)
Inventor
袁啸天
张志强
袁瑞龙
彭家蔓
潘莉
王金行
罗青
毛文文
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Residential Industrialization Group Co ltd
China University of Mining and Technology Beijing CUMTB
Beijing University of Civil Engineering and Architecture
Original Assignee
Beijing Residential Industrialization Group Co ltd
China University of Mining and Technology Beijing CUMTB
Beijing University of Civil Engineering and Architecture
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Residential Industrialization Group Co ltd, China University of Mining and Technology Beijing CUMTB, Beijing University of Civil Engineering and Architecture filed Critical Beijing Residential Industrialization Group Co ltd
Priority to CN202220822791.6U priority Critical patent/CN217264414U/en
Application granted granted Critical
Publication of CN217264414U publication Critical patent/CN217264414U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Jib Cranes (AREA)

Abstract

The utility model discloses a detachable building tower crane anchor, including installation base, installation footstock, erection column and anchor structure, the installation base is established on the floor, the installation footstock is established on the roof, the erection column is established between installation base and installation footstock, the top of erection column is connected on the installation footstock, and the bottom is connected on the installation base, the anchor structure is established on the erection column. The utility model discloses set up installation base and installation footstock and increase the area of contact of anchor and building floor structure, promote the stability of anchor, avoid causing the damage to floor structure, be connected for dismantling between the while and the mount pad, easy to assemble and transport; and the mounting column is adjustably connected with the mounting base and the mounting top seat, so that the anchoring angle is adjustable, the special mounting angle is adapted, and the normal connection of the attachment arm is ensured.

Description

Detachable building tower crane anchor
Technical Field
The utility model relates to a construction technical field, concretely relates to detachable building tower crane anchor.
Background
Need the tower crane to carry out material hoist and mount during construction, it supports the tower crane to generally adopt the adhering to the arm now, the general anchor of anchor device in the building of tower crane adhering to the arm, present anchor device generally adopts steel construction post snap-on to guarantee anchor device's stability and impact resistance on building floor and add the bracing, but because the anchor area of steel construction post is little, lead to floor structure's damage easily when receiving great impact, and the bracing of addding is because space restriction can't be used in specific position department, need rework and reprocess, waste time and energy. The utility model provides a detachable building tower crane anchor solves above-mentioned problem.
SUMMERY OF THE UTILITY MODEL
The utility model provides a detachable building tower crane anchor enlarges the area of contact of anchor and floor, guarantees the stability of anchor structure.
The utility model provides a technical scheme that above-mentioned technical problem adopted is:
a detachable building tower crane anchoring device comprises a mounting base, a mounting top seat, a mounting column and an anchoring structure, wherein the mounting base is arranged on a floor slab, the mounting top seat is arranged on a roof, the mounting column is arranged between the mounting base and the mounting top seat, the top end of the mounting column is connected to the mounting top seat, the bottom end of the mounting column is connected to the mounting base, and the anchoring structure is arranged on the mounting column;
the anchoring structure comprises a sleeve and a connecting seat, the sleeve is sleeved on the mounting column and fixed on the mounting column through a locking bolt, and the connecting seat is arranged on the sleeve and connected with the attachment arm of the tower crane.
Further, the erection column includes cylinder and flange, flange establishes the upper and lower tip at the cylinder.
Furthermore, the installation base and the installation top seat respectively comprise a base body and a flange seat, the flange seats are arranged on the base bodies, and the connecting flanges are connected to the flange seats.
Further, the connecting seat includes connecting plate and strengthening rib, the connecting plate level sets up two, the strengthening rib is established between connecting plate and sleeve, and the end of tower crane attached arm passes through the round pin hub connection between two connecting plates.
Furthermore, connecting holes are formed in the column body at intervals, connecting holes are formed in the sleeve, and locking bolts are arranged in the connecting holes.
Further, the pedestal includes mounting panel and connecting plate, the connecting plate is established between the relative mounting panel that sets up, the flange seat is established on the connecting plate.
Preferably, the mounting plate is connected with the connecting plate in a welding mode, and the flange seat is connected to the connecting plate in a welding mode.
Preferably, the mounting plate and the connecting plate are angle steels, and the column is an I-shaped steel.
The utility model discloses beneficial effect as follows:
the installation base and the installation top seat are arranged to increase the contact area between the anchoring device and the building floor slab structure, the stability of the anchoring device is improved, the floor slab structure is prevented from being damaged, and meanwhile, the installation base and the installation top seat are detachably connected, so that the installation and the transportation are convenient;
the mounting column is adjustably connected with the mounting base and the mounting top seat, so that the anchoring angle is adjustable, the special mounting angle is adapted, and the normal connection of the attachment arm is ensured;
the anchoring structure is adjustably connected with the mounting column, so that the mounting height can be flexibly adjusted to adapt to the mounting of the attachment arm.
Drawings
FIG. 1 is a schematic view of the overall structure of the present invention;
FIG. 2 is a schematic view of the structure of the mounting base of the present invention;
FIG. 3 is a schematic view of the connection between the mounting post and the anchoring structure of the present invention;
fig. 4 is a schematic view of the anchoring structure of the present invention.
Reference numerals are as follows: 1-mounting base, 11-base body, 111-mounting plate, 112-connecting plate, 12-flange base, 2-mounting top base, 3-mounting column, 31-column body, 32-connecting flange, 4-anchoring structure, 41-sleeve and 42-connecting base.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings, and it is to be understood that the described embodiments are only some embodiments of the present invention, rather than all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
In the description of this patent, it is to be understood that the terms "center," "upper," "lower," "front," "rear," "left," "right," "vertical," "horizontal," "top," "bottom," "inner," "outer," and the like are used in the orientations and positional relationships indicated in the drawings for the convenience of describing the patent and for the simplicity of description, and are not intended to indicate or imply that the referenced devices or elements must have a particular orientation, be constructed and operated in a particular orientation, and are not to be considered limiting of the patent.
As shown in FIG. 1, a detachable building tower crane anchoring device, including installation base 1, installation footstock 2, erection column 3 and anchor structure 4, installation base 1 establishes on the floor, installation footstock 2 establishes on the roof, erection column 3 establishes between installation base 1 and installation footstock 2, the top of erection column 3 is connected on installation footstock 2, and the bottom is connected on installation base 1, anchor structure 4 establishes on erection column 3.
When the included angle between the tower crane attachment arm and the wall surface of a building is small, the attachment arm is easy to interfere by the wall when the attachment arm extends into the building through a window, and the angle of the mounting column 3 is adjusted by adjustably connecting the mounting column 3 to the mounting base 1 and the mounting top seat 2, so that the mounting column is more convenient to butt joint with the attachment arm, and anchoring connection at the position where the included angle between the attachment arm and the wall surface is small is realized; and set up installation base 1, installation footstock 2 and be connected with the floor structure, replaced the reinforcing effect of bracing, both avoided the damage to the floor structure, also avoided the bracing to the requirement in big space to the regulation of 3 angles of cooperation erection column can realize installation base 1, the arbitrary angle installation of installation footstock 2, and adaptability is good.
As shown in fig. 1 and 4, the anchoring structure 4 includes a sleeve 41 and a connecting seat 42, the sleeve 41 is sleeved on the mounting column 3, and is fixed on the mounting column 3 through a locking bolt, and the height of the mounting column 3 is adjusted up and down, and the connecting seat 42 is arranged on the sleeve 41 and is connected with the tower crane attachment arm.
As shown in fig. 1 and 3, further, the mounting column 3 includes a column 31 and connecting flanges 32, the connecting flanges 32 are disposed at the upper and lower ends of the column 31, the connecting flanges 32 are connected with the flange seats 12 through bolts, and the adjustment of the mounting angle is achieved by adjusting the relative positions.
Preferably, the mounting post 3 and the anchoring structure 4 are a combined structure.
As shown in fig. 1 and 2, the installation base 1 and the installation top base 2 each include a base body 11 and a flange base 12, the flange base 12 is disposed on the base body 11, the base body 11 is used as an installation base and fixed on a floor by bolts, and the connection flange 32 is connected to the flange base 12.
Further, connecting seat 42 includes connecting plate and strengthening rib, the connecting plate level sets up two, the strengthening rib is established between connecting plate and sleeve 41, and the tip of tower crane attached arm passes through the round pin hub connection between two connecting plates.
Furthermore, the column 31 is provided with connecting holes at intervals, the sleeve 41 is provided with connecting holes, and locking bolts are arranged in the connecting holes.
As shown in fig. 2, further, the base body 11 includes mounting plates 111 and a connecting plate 112, the connecting plate 112 is disposed between the oppositely disposed mounting plates 111, and the flange base 12 is disposed on the connecting plate 112.
Preferably, the mounting plate 111 is connected with the connecting plate 112 by welding, and the flange base 12 is connected with the connecting plate 112 by welding.
Preferably, the mounting plate 111 and the connecting plate 112 are angle steels, and the column 31 is an i-steel.
The utility model discloses a use method as follows: with erection column 3 and anchor structure 4's integrated configuration, installation base 1 and installation footstock 2 transport to the mounted position, then install installation base 1 and installation footstock 2 according to installation space, guarantee the suitable of mounted position, then install erection column 3 between installation base 1 and installation footstock 2, adjustment installation angle during the installation, guarantee connecting seat 42's orientation, the installation is accomplished the back, carry out anchor structure 4 altitude mixture control, the back of finishing adjusting, adhere to the arm with the tower crane and be connected.
It will be evident to those skilled in the art that the invention is not limited to the details of the foregoing illustrative embodiments, and that the present invention may be embodied in other specific forms without departing from the spirit or essential attributes thereof. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein, and any reference signs in the claims are not to be construed as limiting the claim concerned.

Claims (8)

1. The detachable anchoring device for the tower crane for the building is characterized by comprising an installation base (1), an installation top seat (2), an installation column (3) and an anchoring structure (4), wherein the installation base (1) is arranged on a floor slab, the installation top seat (2) is arranged on a roof, the installation column (3) is arranged between the installation base (1) and the installation top seat (2), the top end of the installation column (3) is connected to the installation top seat (2), the bottom end of the installation column is connected to the installation base (1), and the anchoring structure (4) is arranged on the installation column (3);
anchor structure (4) include sleeve (41) and connecting seat (42), sleeve (41) cover is established on erection column (3) to fix on erection column (3) through the lock bolt, establish on sleeve (41) connecting seat (42), adhere to the arm with the tower crane and be connected.
2. The detachable building tower crane anchoring device of claim 1, wherein: the mounting column (3) comprises a column body (31) and a connecting flange (32), wherein the connecting flange (32) is arranged at the upper end part and the lower end part of the column body (31).
3. The detachable building tower crane anchoring device of claim 2, wherein: the mounting base (1) and the mounting top seat (2) both comprise a seat body (11) and a flange seat (12), the flange seat (12) is arranged on the seat body (11), and the connecting flange (32) is connected to the flange seat (12).
4. The detachable building tower crane anchoring device of claim 1, wherein: connecting seat (42) include connecting plate and strengthening rib, the connecting plate level sets up two, the strengthening rib is established between connecting plate and sleeve (41), and the tip of tower crane attached arm is through round pin hub connection between two connecting plates.
5. The detachable building tower crane anchoring device of claim 2, wherein: the cylinder (31) is provided with connecting holes at intervals, the sleeve (41) is provided with connecting holes, and locking bolts are arranged in the connecting holes.
6. The detachable building tower crane anchoring device of claim 3, wherein: the base body (11) comprises mounting plates (111) and connecting plates (112), the connecting plates (112) are arranged between the mounting plates (111) which are arranged oppositely, and the flange bases (12) are arranged on the connecting plates (112).
7. The detachable building tower crane anchoring device of claim 6, wherein: and the mounting plate (111) is connected with the connecting plate (112) in a welding manner, and the flange seat (12) is connected onto the connecting plate (112) in a welding manner.
8. The detachable building tower crane anchoring device of claim 6, wherein: the mounting plate (111) and the connecting plate (112) are angle steels, and the column body (31) is I-shaped steel.
CN202220822791.6U 2022-04-11 2022-04-11 Detachable building tower crane anchor Active CN217264414U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202220822791.6U CN217264414U (en) 2022-04-11 2022-04-11 Detachable building tower crane anchor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202220822791.6U CN217264414U (en) 2022-04-11 2022-04-11 Detachable building tower crane anchor

Publications (1)

Publication Number Publication Date
CN217264414U true CN217264414U (en) 2022-08-23

Family

ID=82874771

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202220822791.6U Active CN217264414U (en) 2022-04-11 2022-04-11 Detachable building tower crane anchor

Country Status (1)

Country Link
CN (1) CN217264414U (en)

Similar Documents

Publication Publication Date Title
CN217264414U (en) Detachable building tower crane anchor
CN214498388U (en) Assembled overhanging formwork support bent
CN211470603U (en) Telescopic tower crane passageway
CN217326624U (en) Split type adjustable turnover slope roofing structure reentrant corner reinforcing apparatus
CN116081454A (en) Clamping mechanism for hanging steel beam
CN212053664U (en) Scaffold upright rod base
CN212802459U (en) Mechanism is set up to inclined plane flower frame roof beam curtain hanging flower basket
CN211849438U (en) Device for pile connection and perpendicularity adjustment
CN208087094U (en) A kind of inclined-plane cell cube Lift-on/Lift-off System
CN112127620A (en) Silo conical shell formwork support platform and erection method thereof
CN217500995U (en) Anti-tilting device for building side column protection platform
CN111663772A (en) Aluminum alloy template boundary beam triangle bracing reinforcing apparatus
CN220058781U (en) Adjustable cantilever outer frame support
CN216007787U (en) Template system is pour to double-deck shear force wall unilateral
CN110725704A (en) Steel structure supporting structure
CN219754009U (en) T roof beam prevents adjustable steel support that overturns
CN218371433U (en) Eight-brace rod structure of tower crane lower support
CN219118807U (en) Construction structure is built to slope steel column
CN217580583U (en) Supporting structure and shock strut of spherical steel support
CN219527354U (en) Pouring template system of oblique leg steel structure bridge
CN218522611U (en) Support for assisting in mounting and transporting lifting hook
CN215830503U (en) Steel ring both sides bracing reinforcing apparatus
CN217768725U (en) Multipurpose mounting structure of satellite communication system
CN216304913U (en) Supporting steel structure for installing large display screen
CN216110004U (en) Iron tower rest platform with antenna boom

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant