CN217232599U - Full hall frame of putting up fast - Google Patents

Full hall frame of putting up fast Download PDF

Info

Publication number
CN217232599U
CN217232599U CN202123275191.7U CN202123275191U CN217232599U CN 217232599 U CN217232599 U CN 217232599U CN 202123275191 U CN202123275191 U CN 202123275191U CN 217232599 U CN217232599 U CN 217232599U
Authority
CN
China
Prior art keywords
diagonal brace
full hall
rod
inclined strut
slider
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN202123275191.7U
Other languages
Chinese (zh)
Inventor
田亚林
王松
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Divion Southern Construction Co Ltd
Original Assignee
China Construction Eighth Engineering Divion Southern Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Divion Southern Construction Co Ltd filed Critical China Construction Eighth Engineering Divion Southern Construction Co Ltd
Priority to CN202123275191.7U priority Critical patent/CN217232599U/en
Application granted granted Critical
Publication of CN217232599U publication Critical patent/CN217232599U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Mutual Connection Of Rods And Tubes (AREA)

Abstract

The utility model provides a full hall frame of putting up fast relates to scaffold technical field, including at least two upper and lower parallel and range upon range of prefabricated module that links to each other, wherein, prefabricated module includes that diagonal brace and equipartition link to each other through vertical round pin axle rotation in the horizontal pole and the vertical pole of this diagonal brace both sides and three's one end, the diagonal brace the horizontal pole with overlap respectively on the vertical pole and establish and sliding connection has the slider, be located on the diagonal brace the slider with two in addition rotate respectively between the slider and be connected with the connecting rod, be equipped with on the diagonal brace and be used for the locking the slider with diagonal brace relative position's locking subassembly works as when the position lock of slider, two connecting rods with the horizontal pole with the vertical pole encloses into rectangular frame. It has solved among the prior art full hall frame dismouting convenient problem fast inadequately.

Description

Full hall frame of putting up fast
Technical Field
The utility model belongs to the technical field of scaffold frame technique and specifically relates to a full hall frame of buildding fast is related to.
Background
The full framing is a common scaffold in building construction; the full hall frame mainly comprises upright rods and horizontal rods, wherein the upright rods and the horizontal rods are usually formed by steel pipes, the horizontal rods are divided into transverse horizontal rods and longitudinal horizontal rods, and the full hall frame is more stable relative to other scaffolds; but because among the prior art between pole setting and the horizontal pole and horizontal pole and vertical horizontal pole between all bind through corresponding fastener and be connected, a large amount of fasteners lead to installing and removing not fast convenient enough.
SUMMERY OF THE UTILITY MODEL
Not enough to exist among the prior art, the utility model provides a full hall frame of buildding fast, it has solved among the prior art problem that full hall frame dismouting is convenient fast inadequately.
According to the embodiment of the utility model, a full hall frame of buildding fast, including at least two upper and lower parallel and range upon range of continuous prefabricated module, wherein, prefabricated module includes that diagonal brace and equipartition link to each other through vertical round pin axle in the horizontal pole and the vertical pole of this diagonal brace both sides and three's one end, the diagonal brace the horizontal pole with overlap respectively on the vertical pole and establish and sliding connection has the slider, be located on the diagonal brace the slider with two in addition rotate respectively between the slider and be connected with the connecting rod, be equipped with on the diagonal brace and be used for the locking the slider with diagonal brace relative position's locking subassembly works as when the position lock of slider, two connecting rods with the horizontal pole with the vertical pole encloses into rectangular frame jointly.
Compared with the prior art, the utility model discloses following beneficial effect has: by adopting the scheme, an operator stirs the two connecting rods to enable the two connecting rods to be perpendicular to the transverse rod and the longitudinal rod respectively, the positions of the sliding blocks on the diagonal braces are locked by the locking assemblies, the transverse rod, the longitudinal rod and the two connecting rods surround a stable rectangular frame, and the diagonal braces are distributed along the diagonal lines of the rectangular frame to further enhance the stability of the prefabricated module; the utility model provides a full hall frame utilizes prefabricated good prefabricated module, only need the slider position on the locking diagonal brace to make prefabricated module form stable rectangular frame during the use, a plurality of prefabricated modules are arranged from top to bottom and range upon range of linking to each other can build full hall frame, and the buildding of full hall frame is convenient fast.
Drawings
Fig. 1 is a schematic structural diagram of a double-layer prefabricated module in an embodiment of the present invention;
fig. 2 is a schematic structural diagram of a single-layer prefabricated module in an embodiment of the present invention.
In the above drawings: 1. a diagonal brace; 2. a cross bar; 3. a longitudinal bar; 4. a pin shaft; 5. a slider; 6. a connecting rod; 7. a first nut; 8. a column; 9. a second nut; 10. a support pillar; 11. a sleeve.
Detailed Description
The technical solution of the present invention will be further explained with reference to the accompanying drawings and embodiments.
As shown in fig. 1 and 2, a full hall frame which is built quickly comprises at least two prefabricated modules which are parallel up and down and are connected in a stacked manner, the number of the prefabricated modules depends on the actual requirement, and in order to better explain the invention content of the utility model, two layers of prefabricated modules are taken as an example in the embodiment; each layer of prefabricated module comprises an inclined strut 1, a cross rod 2 and a longitudinal rod 3 which are uniformly distributed on two sides of the inclined strut 1, wherein one ends of the cross rod 2 and the longitudinal rod 3 are connected through a vertical pin shaft 4, preferably, the pin shaft 4 can be connected with the inclined strut 1, the cross rod 2 and the longitudinal rod 3 in a key mode, so that the cross rod 2 and the longitudinal rod 3 are perpendicular, and the included angle between the inclined strut 1 and the cross rod 2 is 45 degrees; the inclined strut 1, the cross bar 2 and the longitudinal bar 3 are respectively sleeved and slidably connected with a sliding block 5, wherein a connecting rod 6 is respectively rotatably connected between the sliding block 5 on the inclined strut 1 and the other two sliding blocks 5, two ends of the connecting rod 6 are respectively rotatably connected to the corresponding sliding blocks 5 through vertical connecting shafts, and the two connecting rods 6 are distributed on the upper side and the lower side of the inclined strut 1 so as to be conveniently spatially arranged; the inclined strut 1 is provided with a locking assembly for locking the relative positions of the sliding block 5 and the inclined strut 1, and when the sliding block 5 is locked, the two connecting rods 6, the cross rod 2 and the longitudinal rod 3 jointly enclose a rectangular frame.
By adopting the scheme, an operator stirs the two connecting rods 6 to enable the two connecting rods to be perpendicular to the transverse rod 2 and the longitudinal rod 3 respectively, the positions of the sliding blocks 5 on the diagonal brace 1 are locked by the locking assemblies, the transverse rod 2, the longitudinal rod 3 and the two connecting rods 6 enclose a stable rectangular frame, and the diagonal brace 1 is distributed along the diagonal line of the rectangular frame to further enhance the stability of the full hall shelf; the utility model provides a full hall frame utilizes prefabricated module, only needs 5 positions of slider on the locking diagonal brace 1 to make prefabricated module form stable rectangular frame during the use, and a plurality of prefabricated modules are arranged from top to bottom and range upon range of linking to each other and can be built full hall frame, and the quick convenience of putting up of full hall frame.
As shown in fig. 1 and fig. 2, the present invention provides another embodiment, the free end of the diagonal brace 1 (i.e. the end away from the pin 4) is provided with an external thread, the locking assembly includes two first nuts 7 symmetrically disposed on two sides of the slider 5, the two first nuts 7 are sleeved and screwed on the diagonal brace 1, and the two first nuts 7 are used to lock the position of the slider 5 on the diagonal brace 1; the locking assembly can also be formed by arranging two clamping grooves in the diagonal brace 1, and clamping rings (not shown in the figure) are embedded into the two clamping grooves so as to lock the sliding block 5 to slide along the diagonal brace 1; the locking assembly can also be that a lock hole is arranged on the diagonal brace 1, and the slide block 5 is locked at the lock hole by using a bolt (not shown in the figure); and adopt above-mentioned first nut 7's locking mode except can stabilizing the locking, can also finely tune according to actual demand, make two connecting rods 6 and horizontal pole 2 or the contained angle of vertical pole 3 be acute angle or obtuse angle respectively.
As shown in fig. 1 and fig. 2, the present invention provides another embodiment, the inclined strut 1, the horizontal rod 2 and the vertical rod 3 are rectangular blocks and the three are stacked up and down, the height of the inclined strut 1, the horizontal rod 2 and the vertical rod 3 is reduced by setting the inclined strut 1, the horizontal rod 2 and the vertical rod 3 into rectangular blocks, the three can be folded by rotating the three relatively, it should be noted that the bar key of the pin shaft 4 needs to be pulled out before the inclined strut 1, the horizontal rod 2 and the vertical rod 3 are rotated, so as to ensure the relative rotation among the inclined strut 1, the horizontal rod 2 and the vertical rod 3; in addition, the rectangular block shape is more beneficial to the connection arrangement of the pin shaft 4 than the round tube shape.
As shown in fig. 1 and fig. 2, the present invention provides another embodiment, two adjacent prefabricated modules have opposite upright posts 8 fixed at four corners respectively, each upright post 8 is sleeved with a sleeve 11, and the sleeves can move relatively, wherein two sleeves 11 distributed along the diagonal of the prefabricated modules are provided with internal threads, and two upright posts 8 on the prefabricated modules above are in threaded connection with two sleeves 11; an operator can simultaneously rotate the two sleeves 11 with the internal threads to drive the upright post 8 to move upwards or downwards, so that the distance between the two prefabricated modules in the height direction can be adjusted; furthermore, in order to facilitate the rotation of the sleeve 11 by an operator, the sleeve 11 is provided with two internal threads, the second nut 9 is sleeved and fixed on the sleeve 11, and the sleeve 11 can be conveniently rotated by the operator by clamping the second nut 9 with tools such as a wrench.
As shown in fig. 1 to 2, support columns 10 with a diameter larger than that of the sleeve 11 are fixedly arranged at the bottom ends of the prefabricated modules at the bottommost layer, and the bottom ends of the support columns 10 are located on the same horizontal plane; the contact area between the supporting column 10 with the larger diameter and the ground is larger, so that the supporting is more stable; in addition, support columns 10 of different heights are utilized to stably support the bottom ends of the prefabricated modules on the same plane.
Finally, although the present invention has been described in detail with reference to the preferred embodiments, it should be understood by those skilled in the art that the present invention can be modified or replaced by other means without departing from the spirit and scope of the present invention, which should be construed as limited only by the appended claims.

Claims (6)

1. The utility model provides a full hall frame of putting up fast which characterized in that: comprises at least two prefabricated modules which are parallel up and down and are connected in a stacked manner, wherein each prefabricated module comprises an inclined strut (1), a cross rod (2) and a longitudinal rod (3) which are uniformly distributed on two sides of the inclined strut (1), one ends of the cross rod and the longitudinal rod are connected through a vertical pin shaft (4), the inclined strut (1), the cross rod (2) and the longitudinal rod (3) are respectively sleeved and connected with a sliding block (5) in a sliding way, a connecting rod (6) is respectively and rotatably connected between the sliding block (5) on the inclined strut (1) and the other two sliding blocks (5), a locking component for locking the relative position of the sliding block (5) and the diagonal brace (1) is arranged on the diagonal brace (1), when the slide block (5) is locked, the two connecting rods (6), the cross rod (2) and the longitudinal rod (3) jointly form a rectangular frame.
2. A quickly erected full hall shelf according to claim 1, characterised in that: the free end of the inclined strut (1) is provided with an external thread, the locking assembly comprises two first nuts (7) symmetrically arranged on two sides of the sliding block (5), and the two first nuts (7) are sleeved and connected on the inclined strut (1) in a threaded mode.
3. A quickly erected full hall shelf according to claim 2, characterised in that: the inclined support rods (1), the cross rods (2) and the longitudinal rods (3) are all rectangular blocks and are arranged in an up-and-down stacked mode.
4. A rapid-build full hall stand according to any one of claims 1 to 3, characterised in that: adjacent two relative stand (8) have set firmly respectively in the four corners of prefabricated module, but each stand (8) all overlaps outward and is equipped with sleeve (11) and the two relative movement, wherein, follows two of prefabricated module's diagonal distribution sleeve (11) are equipped with the internal thread, are located the top two stand (8) and two on the prefabricated module sleeve (11) threaded connection.
5. A full hall frame of building fast of claim 4, characterized by: two sleeves (11) provided with internal threads are sleeved and fixed with second nuts (9).
6. A full hall frame of building fast of claim 5, characterized by: the bottom ends of the prefabricated modules positioned at the bottommost layer are fixedly provided with supporting columns (10) with diameters larger than those of the sleeves (11), and the bottom ends of the supporting columns (10) are positioned on the same horizontal plane.
CN202123275191.7U 2021-12-23 2021-12-23 Full hall frame of putting up fast Withdrawn - After Issue CN217232599U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202123275191.7U CN217232599U (en) 2021-12-23 2021-12-23 Full hall frame of putting up fast

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202123275191.7U CN217232599U (en) 2021-12-23 2021-12-23 Full hall frame of putting up fast

Publications (1)

Publication Number Publication Date
CN217232599U true CN217232599U (en) 2022-08-19

Family

ID=82825948

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202123275191.7U Withdrawn - After Issue CN217232599U (en) 2021-12-23 2021-12-23 Full hall frame of putting up fast

Country Status (1)

Country Link
CN (1) CN217232599U (en)

Similar Documents

Publication Publication Date Title
CN207553652U (en) A kind of assembled architecture wallboard combines support device
CN217232599U (en) Full hall frame of putting up fast
CN102191851B (en) Novel support system
CN115142654B (en) Lifting folding foot rest system applied to capital construction
CN217522768U (en) Sectional type photovoltaic support
CN206428986U (en) A kind of detachable turnover type support jig
CN114182646B (en) Assembled ladder cage buttress with adjustable length
CN214834659U (en) Attached supporting steel frame
CN2529945Y (en) Mobile scaffold
CN212583181U (en) Inclined lever type movable cantilever platform
CN211642947U (en) Detachable stack extraction platform shelf
CN109403668B (en) Truss and method for constructing multi-form exhibition stand
CN215889277U (en) Steel structure platform support frame
CN215443011U (en) Support frame for construction
CN219731666U (en) Engineering building construction frame
CN218407260U (en) Manual one-way rotary brake
CN220414791U (en) High-stability support frame for building technology construction
CN220412693U (en) Tower body frame structure of tower crane
CN220972354U (en) Civil engineering pipe fitting rack
CN210598419U (en) Assembled penetrating fender that encloses
CN211047971U (en) Warmhouse booth aluminum alloy support
CN213063174U (en) Building isolated column
CN216428978U (en) High green construction scaffold of security
CN214462916U (en) Temporary supporting device for steel net rack
CN215290657U (en) Be used for building structure to assemble and use telescopic bracket

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
AV01 Patent right actively abandoned

Granted publication date: 20220819

Effective date of abandoning: 20230608

AV01 Patent right actively abandoned

Granted publication date: 20220819

Effective date of abandoning: 20230608

AV01 Patent right actively abandoned
AV01 Patent right actively abandoned